This is a Statement of Work (SOW) for U.S. Customs and Border Protection's Mariposa Land Port of Entry in Nogales, Arizona, detailing installation of remote control touchscreen technology for a narcotics destruction incinerator.
The contractor shall install a remote touchscreen meeting or exceeding specifications of the Keller Manufacturing KMB-2400 model, mounted inside the vault's sally port. The scope includes providing and installing 3/4" minimum conduits for DC and CAT 6A wiring with innerduct protection, positioned underground where feasible, to connect the incinerator to the touchscreen. An approximately 18' x 24' cantilevered metal shade structure must be installed to protect incinerator controls and extend over existing fencing. The contractor shall deliver a complete working system and coordinate all work with CBP to maintain port security and minimize interruption to normal operations. A minimum two-year warranty is required for all labor and materials from substantial completion. All materials must be commercially available first-line products meeting recognized testing facility standards. Work shall comply with current versions of the International Building Code, International Mechanical Code, Uniform Plumbing Code, and National Electrical Code, as well as the 2023 LPOE Design Standard. Work hours are 6:00 a.m. to 5:00 p.m., Monday through Friday, and daytime hours on weekends as permitted by the Contracting Officer/CBP Project Manager. Deliverables include a work schedule prior to project start, product and shop drawing submittals, weekly meeting updates, and Material Safety Data Sheets. The prime contractor must maintain a competent superintendent on-site with HSPD-12 clearance who is satisfactory to the Contracting Officer and authorized to represent the contractor. No changes to the SOW or cost increases are permitted without written prior approval from the Contracting Officer coordinated through the COTR.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 1 - 20157464
STATEMENT OF WORK (SOW)
U.S. Customs and Border Protection
Mariposa Land Port of Entry, Nogales, Arizona Install Remote Control Touchscreen for the Narcotics Destruction
Incinerator DOA
BACKGROUND:
The Customs and Border Protection (CBP), Office of Field Operations (OFO) Mariposa Land Port of Entry in Nogales, Arizona is responsible for guarding America’s borders, welcoming lawful visitors, and facilitating legitimate trade.
1. SCOPE:
Per the enclosed Statement of Work, the Contractor shall provide all supervision, labor, materials, supplies, and equipment, necessary to:
1. Install a Remote Touchscreen, that must meet or exceed one provided by Keller Manufacturing for the KMB-2400. The touchscreen shall be mounted inside of the sally port of the vault as located on the attached plan.
2. Provide and install conduits (3/4” minimum) for DC and CAT 6A wiring/cable necessary to connect the incinerator to the touchscreen. CAT 6A cable shall have innerduct protection. The installation shall be underground as much as possible.
3. Provide and install an approximately 18’ x 24’ cantilevered metal shade structure to protect the incinerator controls. The shade structure shall extend over the existing fencing.
4. The project shall provide a complete working system.
5. The work shall be coordinated with U.S. Customs and Border Protection so that port security is not compromised and the work interrupts normal port operations minimally.
6. The General Contractor shall provide a minimum of a two (2) year warranty for all labor and materials associated with the project from date of substantial completion, unless a longer term is stated elsewhere.
All material shall be commercially available first line products that meet or exceed the requirements of associated recognized testing facility.
2. APPLICABLE DOCUMENTS and CODE COMPLIANCE:
All local, state and federal codes must be followed including the current versions of the International Building Code, International Mechanical Code, Uniform Plumbing Code, National Electrical Code.
2023 LPOE Design Standard Commercial standards shall be used wherever practicable.
3. Work Location: Mariposa Land Port of Entry 120 North Mariposa Road, Nogales, AZ. 85621
4. DELIVERABLES AND DELIVERY SCHEDULE:
4.1 Deliverables:
a. Work schedule prior to start of the project.
Attachment 1
b. Product and shop drawing submittals.
c. Weekly updates at scheduled meetings.
d. Material Safety Data Sheets (MSDS)
5. GOVERNMENT-FURNISHED EQUIPMENT AND INFORMATION:
NA
6. Hours of Work.
Work will be accomplished during normal working hours (M-F - 6:00 a.m. – 5:00 p.m.) and/or daytime hours on Saturday and Sundays, unless otherwise permitted by the Contracting Officer/CBP Project Manager.
7. SECURITY CLEARANCE AND SITE ACCESS:
7.1 The contractor is required to comply with CBP policies and directives related to confidentiality and privacy. The contractor is prohibited from gathering or sharing any information with third parties and is required to protect all data they may observe or overhear while operating on federal premises.
7.2 At all times during performance of this contract and until the work is completed and accepted, the Prime Contractor shall have on the worksite a competent superintendent who is satisfactory to the Contracting Officer/CBP Project Manager and has authority to act for the Contractor. This person shall have an HSPD-12 clearance.
8.3 US Customs and Border Protection personnel will directly monitor the work site security;
however they are not responsible for the security of the project’s equipment or materials.
8. SPECIAL CONSIDERATIONS:
8.1 Changes to the SOW
No changes to this SOW or cost increases shall be incurred without written prior approval of the Contracting Officer as coordinated by the COTR. Any changes or cost increases will not take effect until the Contracting Officer executes a written modification.
9. POINTS OF CONTACT: