SOW.pdf
PDF 3 MB Posted
- Solicitation number
- 20150PR270000020
- Issued by
- Not on record
About this file
This is a Scope of Work for carpet replacement services at USCG Air Station Clearwater in Clearwater, Florida (Project 33643384). The contractor shall provide all labor, supervision, tools, equipment, materials, delivery, furniture moving, removal, disposal, surface preparation, installation, protection, and cleanup for replacement of all existing carpet and associated cove base throughout the FACENG building, including Supply spaces. The base bid scope covers approximately 2,820 square feet of carpet replacement and 775 linear feet of cove base installation across identified carpeted areas including Rooms 102, 103, 104, 107, 108, 109, 110, 115, 116, 119, 122, the former Room 114 envelope (conference room and adjoining office), and carpeted internal passages. Contractor must field-verify quantities before ordering materials. Work must be performed on weekends with all displaced areas, including furniture, restored for normal use by 7:00 a.m. Monday. The period of performance is 45 days. Contractor shall hold a pre-construction conference before work begins and coordinate all work scheduling with designated Coast Guard Points of Contact.
The contractor must comply with CRI 104 standards for commercial carpet installation, provide commercial-grade carpet tiles suitable for heavy-use administrative and supply spaces, and install new commercial resilient cove base with a minimum nominal height of 4 inches unless otherwise approved. The Contracting Officer's Representative will select final carpet tile and cove-base colors from manufacturer standard options. All materials must come from consistent production runs or dye lots within each continuous area. Contractor must remove existing carpet, pad, tack strips, adhesive residue, and cove base, with bulk carpet waste disposed of off-site in accordance with applicable regulations. Subfloor preparation shall include inspection, loose adhesive removal, cleaning, patching, and minor leveling, with moisture and pH testing performed per manufacturer requirements. The contractor warrants workmanship shall be free from defects for one year from final acceptance, with manufacturer warranties transferred to the Coast Guard. Final acceptance occurs when the Contracting Officer's Representative verifies completion after all noted discrepancies have been corrected within five business days. Security requirements include providing a consolidated personnel list one week prior to work for background checks (full name, date of birth, last four Social Security Number digits), limiting personnel to U.S. citizens and permanent resident aliens, and prohibiting firearms and weapons on base.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Combined_Synopsis_Solicitation_-_USCG_Air_Station_Clearwater_Carpet_Replacement.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of Work
For
Project 33643384
USCG Air Station Clearwater
CARPET REPLACEMENT - FACENG AND SUPPLY
OFFICES
Air Station Clearwater 15100 Rescue Way
Clearwater, FL 33762
GENERAL REQUIREMENTS
General:
United States Coast Guard Air Station Clearwater requires replacement of all existing carpet and associated cove base throughout the FACENG building, including Supply spaces. The Contractor shall move and reset all furniture needed to perform the work. Installation and furniture moves shall occur on weekends, with every displaced area restored for normal use by Monday. Reference drawings A-18 and A-19 are provided for orientation. Offerors may arrange a site visit through the Coast Guard Points of Contact to verify the current carpeted areas, dimensions, furniture, and existing conditions. Hold a pre-construction conference before work begins.
Location:
U.S. Coast Guard Air Station Clearwater 15100 Rescue Way Clearwater, Florida 33762
1. Continuity of Facilities Operation:
Perform the work on weekends. Restore every area displaced by the work, including furniture, for normal use by 7:00 a.m. Monday. Coordinate the work schedule with the Coast Guard Points of Contact.
2. Period of Performance and Work Schedule:
The period of performance shall be 45 days. The Contractor shall provide a simple and general schedule stating when work will begin, its expected duration, and when it will be complete.
3. Coast Guard Points of Contact:
Coordinate facility access and weekend turnover with the personnel below, listed in order of preference.
Point of Contact Email / notes Phone Number
CWO Joe Calderon Jose.A.Calderon@uscg.mil 727-423-7586 (cell phone)
LCDR Scott Kellerman scott.n.kellerman@uscg.mil 571-499-0711 (cell phone)
MKC Mike Hemmingway Jonathan.M.Hemmingway@uscg.mil 727-535-1437 x1573
Engineer of the Watch Duty watch-stander (24/7 available) 352-362-1918 (cell phone)
4. Recycling and Disposal of Refuse:
Minor refuse and waste materials resulting from operations may be disposed of in Air Station Clearwater dumpsters. All disposals shall be done in accordance with federal, state, and local laws and regulations. No Hazardous Waste or bulk waste may be disposed of in Air Station Clearwater dumpsters.
5. Safety:
During the execution of this contract, the Contractor shall conform to the rules and regulations as set forth by OSHA State and Federal regulations. Immediate notification to the Contracting Officer’s Representative of lost time due to accidents is required. Provide two copies of workman’s compensation accident reports by noon of the day following the accident. The Coast Guard reserves the right to bar any workers or supervisors from the premises should they be documented as violating set safety standards and regulations.
6. Inspection:
The Contracting Officer’s Representative has the right to reject defective workmanship or materials or work not performed as per the contract specifications.
7. Operations and Storage:
The Coast Guard has no responsibility for receipt, storage, or protection of contractor’s materials. The Coast Guard will not accept shipments and no materials may be stored on site by the contractor. The contractor is responsible for the protection of existing structures, utilities and vegetation. Any damage shall be repaired at the contractor’s expense.
8. Utilities:
Contractor is authorized to use Air Station Clearwater power and water while conducting the work efforts outlined in this document. Any other use of power is not authorized. The unit POC’s listed above will designate available utility connection points if necessary.
9. General Regulations while onboard Coast Guard Air Station Clearwater:
1. Daily colors and the raising/lowering of the American flag will take place every morning at 0800 and every evening at sunset. All personnel on Base will face the main flagpole & maintain silence and all vehicles & equipment will halt during these brief events.
2. Contractors are welcome to eat breakfast & lunch on Base in the base galley at published meal rates. Breakfast is served from 0600-0730 daily & lunch will be served from 1100- 1230 daily in the galley. All personnel desiring meal service shall be in clean, non-soiled clothing. The Coast guard reserves the right to refuse service to anyone it deems dirty.
3. Contractors are welcome to utilize the Base’s Exchange store; however, contracted personnel are prohibited from purchasing any uniform, alcohol or tobacco products in it.
4. Traffic Regulations:
a. 10 mph speed limit
b. No use of cell phones is permitted while driving vehicles or operating heavy machinery.
c. All personnel shall obey all marked traffic signals including stop signs & stoplights.
5. Notice shall be given to the Coast Guard representative one week in advance of any planned utility outage or facility impact, including its expected duration.
6. Contractors are welcome to utilize the restrooms in the area they are currently working in providing they are clean and do not track mud, dirt or any other debris into the restrooms.
7. No personnel other than the Contracting Officer has the authority to alter the terms of any contract or to issue any change orders. Accordingly, the contractor shall not complete any work that would incur additional cost to the government without written approval from the Contracting Officer.
10. SECURITY REQUIREMENTS:
1. The contractor shall provide a consolidated list of all contractor personnel who will be working on Air Station Clearwater Facilities at least 1 week prior to work. This is for routine/ standard background checks of all personnel entering the base. Information required is: full name, date of birth, and last 4 digits only of Social Security Number.
2. Only American citizens and permanent resident aliens are allowed onboard Air Station Clearwater Facilities. Other foreign nationals are not permitted. Appropriate identification shall be provided at the front gate to attain base entry.
3. All contractor vehicles, equipment and gear onboard Coast Guard properties are subject to search at all times. Additionally at all times due to security and operational needs, the contractor is subject to orders to evacuate the property at any time.
4. Absolutely no firearms or weapons of any kind are allowed onboard Air Station Clearwater.
5. The contractor and subcontractor personnel shall at all times wear company identification and carry photo identification on their person. Personnel shall not stray from the immediate area of work nor direct avenues of ingress and egress unless authorized in advance.
11. SCOPE OF WORK:
The Contractor shall provide all labor, supervision, tools, equipment, materials, delivery, furniture moving, removal, disposal, surface preparation, installation, protection, and cleanup for replacement of all existing carpet and associated cove base throughout the FACENG building. Include all furniture moves and resets in the base price. All work shall comply with the selected manufacturer's written instructions, CRI 104, and applicable codes and standards.
Bid Schedule and Areas of Work
Bid Item Type Included Areas Quantity / Pricing Basis
Base Bid Lump sum
Replace all existing carpet and associated cove base throughout the FACENG building, including Supply offices. Include contractor furniture moving and reset.
Include Rooms 108, 109, 110, 119 and 122 and carpeted internal office passages. Exclude hard-floor warehouse, public halls, lobby, and shop floors.
One complete price for all work, including weekend phasing and Monday restoration. Approximately 2,820 SF from scaled drawings and photo review; field-verify quantities before ordering.
Approximate Quantities
FACENG and conference areas, including the adjoining office, carpeted internal passage, and Rooms 115, 116, 119 and 122: approximately 1,150 square feet from the drawing-based takeoff.
Supply office areas, including Rooms 102, 103, 104, 107, 108, 109 and 110: approximately 1,670 square feet from the drawing-based takeoff. Exclude the hard-floor supply warehouse.
Combined planning quantity: approximately 2,820 square feet of carpet and 775 linear feet of cove base.
Quantities are scaled from drawings A-18 and A-19 and reconciled with existing-condition photographs.
The former Room 114 envelope includes the conference room, adjoining office and carpeted internal passage once. Field-verify current dimensions, partitions, base lengths and transitions before ordering.
The identified rooms and carpeted internal circulation areas constitute the carpet replacement scope. All other areas and existing hard-surface flooring are excluded.
All quantities are approximate and subject to verification within the identified carpeted areas. The existing-condition photographs and room schedule identify the work areas. Room 103 is included based on facility personnel confirmation; it was locked and its interior was not photographed. All other areas are excluded. Drawings show historical layouts and may not reflect current partitions. Offerors may schedule a site visit through the Coast Guard Points of Contact to verify quantities. Reconcile discrepancies with the Contracting Officer before submitting a quote.
Reference Documents
Drawing A-18, CG Air Station Clearwater, 4615 Facility Engineering & Supply Building, Architectural Floor Plan, Sheet 19 of 22, scale 1/8 inch = 1 foot.
Drawing A-19, CG Air Station Clearwater, 4615 Facility Engineering & Supply Building, Architectural Floor Plan, Sheet 20 of 22, scale 1/8 inch = 1 foot.
Carpet and Rug Institute (CRI) 104, Standard for Installation of Commercial Carpet, current edition at the time of solicitation.
Submittals and Material Approval Submit carpet product data, color and pattern options, adhesive data, cove-base data, transition details, and manufacturer warranty information before ordering materials.
Provide commercial-grade carpet tiles suitable for heavy-use administrative and supply spaces and equal to or better than the existing carpet in durability and intended use.
The Contracting Officer's Representative (COR) will select the final carpet tile and cove-base colors from the manufacturer's standard available options.
Use materials from consistent production runs or dye lots within each continuous area.
Furniture Moving and Protection
The Contractor shall move all furniture necessary to perform the carpet replacement and reset it in its original location after the carpet is installed and ready for use.
Coordinate furniture moves and room sequencing with the COR. Protect furniture, walls, doors, finishes, equipment, and adjacent areas from damage.
The Coast Guard will remove personal items, secure sensitive records, and disconnect or remove computers, telephones, and other electronic equipment before the scheduled work in each room.
If the offeror or Contractor proposes cyber/IT-related hardware, software, or services not previously approved by the USCG CIO, notify the COR and Contracting Officer before purchase, use, or implementation. No Government network access is authorized by this flooring requirement.
Removal and Disposal Remove existing carpet, pad where present, tack strips where present, adhesive residue, transitions being replaced, and existing cove base in the awarded areas.
Remove carpet and bulk flooring debris from the installation. Do not place bulk carpet waste in Coast
Guard dumpsters.
Dispose of waste off site in accordance with applicable federal, state, and local requirements.
Subfloor Preparation
Inspect exposed substrates and report concealed conditions that could affect installation before covering the area.
Remove loose adhesive and debris and perform normal scraping, cleaning, patching, and minor leveling required for a smooth and serviceable installation.
Perform moisture, pH, or other substrate testing required by the selected flooring and adhesive manufacturers. Do not install over a substrate that does not meet the manufacturer's requirements.
Obtain written direction before performing extensive substrate repair that is beyond normal flooring preparation and would change the contract price.
Carpet and Accessory Installation
Remove and dispose of existing carpet; furnish and install commercial-grade carpet tile rated for severe/high-traffic use in accordance with the manufacturer’s written recommendations, including required floor preparation, adhesives, transitions, and cleanup. Provide carpet-tile color samples to the U.S. Coast Guard for approval before ordering materials.
Install new commercial resilient cove base throughout the awarded carpeted areas. Match the existing height, with a minimum nominal height of 4 inches, unless otherwise approved by the COR.
Provide secure, smooth transitions at doorways and where new carpet meets other flooring materials.
Transitions shall not create a trip hazard or obstruct door operation.
Maintain consistent carpet orientation and pattern within each room and align exposed edges neatly with walls, thresholds, casework, and fixed construction.
Work Sequencing and Facility Operations
Develop a room-by-room work sequence with the COR before mobilization and provide the general work schedule required under Section 2.
Maintain safe access to occupied portions of the facility. Barricade active work areas and keep corridors and exits clear.
Complete installation, cleanup, and furniture reset in every area displaced over the weekend so that it is ready for normal use by 7:00 a.m. Monday.
Coordinate any adhesive cure time or room closure with the COR so the affected space is not returned to service prematurely.
Cleanup and Closeout
Remove installation debris, excess materials, containers, and protective coverings from the work area daily and at completion.
Vacuum the completed carpet using commercial equipment and clean marks, adhesive, and residue from adjacent surfaces.
Provide the COR with final product data, cleaning and maintenance instructions, and applicable manufacturer warranty documentation.
Warranty
The Contractor warrants that workmanship shall be free from defects for one year from the date of final acceptance.
Manufacturer warranties shall be transferred to the Coast Guard. Warranty corrections shall include all labor, materials, removal, disposal, and restoration necessary to correct the defective work at no additional cost to the Government.
12. ACCEPTANCE OF WORK
When all awarded work is complete, the Contractor shall provide the COR at least 24 hours' notice for final inspection. Work that is incomplete, damaged, defective, poorly aligned, loose, stained, or inconsistent with the approved materials or installation requirements shall be corrected within five business days unless another period is approved by the Contracting Officer. The work will be accepted when all noted discrepancies have been corrected and the COR verifies completion. After acceptance, the Contractor shall submit the final invoice as directed by the Contracting Officer.
FACENG and Supply offices - existing conditions September 28, 2026 | 16 selected photographs | Identified carpeted areas only; all other flooring excluded
Photo 01 - Room 102 - Supply office Numbered entrance, carpeted internal aisle and hard-floor boundary.
Photo 02 - Room 104 Room number, existing carpet and office furnishings.
Photo 03 - Room 107 Room number and patterned carpet tiles.
Photo 04 - Room 108 Room number, carpet and office furnishings.
Room 103 was locked and inaccessible. Carpet confirmed by facility personnel; interior not photographed.
Original photographs retained locally. Photo views do not establish measured floor quantities. 1 / 4
September 28, 2026 | 16 selected photographs | Identified carpeted areas only; all other flooring excluded
Photo 05 - Room 109 Room number, carpet tiles and furniture to be moved.
Photo 06 - Room 110 - SK1 office Existing carpet and office furnishings.
Photo 07 - Room 115 Room number, carpet and office furnishings.
Photo 08 - Room 116 Room number, carpet and office furnishings.
Room 103 was locked and inaccessible. Carpet confirmed by facility personnel; interior not photographed.
Original photographs retained locally. Photo views do not establish measured floor quantities. 2 / 4
September 28, 2026 | 16 selected photographs | Identified carpeted areas only; all other flooring excluded
Photo 09 - Conference room - former 114 area Conference furnishings and carpet. Location confirmed by facility personnel.
Photo 10 - Office adjoining conference room adjoining office; included within the combined former 114 footprint.
Photo 11 - Carpeted passage to Rooms 115/116 Include this internal passage; public hard-floor halls are excluded.
Photo 12 - Room 119 - drawing/storage office Existing carpet, file cabinets and drawing racks.
Room 103 was locked and inaccessible. Carpet confirmed by facility personnel; interior not photographed.
Original photographs retained locally. Photo views do not establish measured floor quantities. 3 / 4
September 28, 2026 | 16 selected photographs | Identified carpeted areas only; all other flooring excluded
Photo 13 - Room 122 - office off shop Room number, carpet, furnishings and shop-side threshold.
Photo 14 - Conference entrance transition Carpet meets hard hallway flooring at the doorway.
Photo 15 - Room 119 rear transition Carpet meets hard shop flooring at an edge strip.
Photo 16 - Existing cove base height Approximately 4 inches at this photographed location.
Room 103 was locked and inaccessible. Carpet confirmed by facility personnel; interior not photographed.
Original photographs retained locally. Photo views do not establish measured floor quantities. 4 / 4
A-18 included carpet footprints September 28, 2026 | Drawing-based estimate | Contractor to field-verify before ordering
Sources: supplied A-18 / A-19 and existing-condition photographs. Highlighted envelopes are approximate. 2
910 SF
150 SF
120 SF
140 SF
150 SF
70 SF
130 SF 114 area
570 SF
130 SF
90 SF
180 SF
A-19 included carpet footprints September 28, 2026 | Drawing-based estimate | Contractor to field-verify before ordering
Sources: supplied A-18 / A-19 and existing-condition photographs. Highlighted envelopes are approximate. 3
180 SF