Notice of Intent/Requirement Synopsis – WWYK200131
This is a Notice of Intent and Requirement Synopsis for the repair of a chilled water system in Building 2280 at Tinker Air Force Base, Oklahoma. The requirement is a 100% construction-only contract with a total small business set-aside using a two-step sealed bidding process. The magnitude of construction exceeds $10,000,000, with NAICS Code 236220 (Commercial and Institutional Building Construction) and a corresponding size standard of $45,000,000 in annual receipts. The work encompasses furnishing all materials, labor, plant, tools, transportation, equipment, testing services, quality control, and incidentals necessary to repair the chilled water system and deliver a complete, fully operational system ready for government use. The contractor is responsible for identifying all necessary logistical, architectural, and structural work elements and field-verifying all provided information, including floor plans, structural and mechanical data, and utility locations. All contractor personnel must receive Foreign Object Debris (FOD) awareness training in accordance with Tinker Air Force Base Instruction 21-100 due to work on flight lines, runways, taxiways, parking ramps, aircraft hangars, and maintenance areas.
The acquisition process comprises two steps evaluated using separate criteria. Step One requires site visit attendance (mandatory for proposal eligibility) and technical proposal submission evaluated on Capability & Management and Schedule & Planning subfactors, with evaluation of correction potential and acceptability of any required revisions. Step Two considers only bids from technically acceptable proposals, with award made to the responsible bidder with the lowest conforming price. Step Two pricing bids are evaluated for reasonableness, balanced pricing, and cost realism, with unreasonable or unbalanced pricing subject to rejection. All offerors must complete System for Award Management (SAM) registration to be eligible for contract award. The contracting officer is Sharla Flowers (sharla.flowers_brandon.1@us.af.mil) and the contracting specialist is Michael Johnson (michael.johnson.404@us.af.mil).
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Notice of Intent/Requirement Synopsis
WWYK200131 – Repair Chilled Water System, Bldg. 2280
This notice is for all registered Small Businesses interested in providing for the Repair of the Chilled Water System in Bldg. 2280 on Tinker Air Force Base (TAFB). This requirement will be a 100% construction-only contract.
The competitive acquisition approach will be a total small business set-aside, Request for Proposal (RFP) with a magnitude of construction greater than $10,000,000 in accordance with FAR 36.204(h). The North American Industry Classification System (NAICS) Code is 236220 - Commercial and Institutional Building Construction with a corresponding size standard of $45,000,000 in annual receipts.
As identified in the Sources Sought, TAFB will procure the Repair of the Chilled Water System utilizing Two-Step Sealed Bidding procedures in accordance with FAR 14.5. The process is outlined below:
Note: The Government will first post the site visit information to SAM.gov. Site visit attendance is mandatory to be eligible to submit proposals/bids for this requirement.
Step One: Only site visit attendees will be eligible to submit Step One technical proposals in response to the Request for Proposal after all Requests for Information (RFIs) have been answered and disseminated to all site visit attendees. The Government will consider the correction potential of any technical proposal. If a Mistake in Bid is not considered correctable IAW FAR 14.407-3 or if the amount and/or complexity of the corrections needed to meet the Government requirement requires a major proposal revision, the Bidder will be categorized as unacceptable and may be eliminated from the competition.
Step Two: Only bids based upon technical proposals determined to be acceptable, either initially or as a result of acceptable revision, will be considered for award. In Step Two, award will be made to the responsible bidder whose bid, conforming to the solicitation, will be most advantageous to the Government, considering only price and the price-related factors specified elsewhere in the solicitation IAW FAR 52.214-10 - Contract Award-Sealed Bidding.
The Step One technical proposals will be evaluated according to two subfactors, and the subsequent Step Two pricing bid will be evaluated according to three metrics. The Evaluation Methodology is outlined below:
Step One Technical Offer Evaluation Subfactor 1 – Capability & Management: This subfactor is met when the offeror sufficiently demonstrates and describes how the offeror will meet the capability and management requirements to complete the construction and administrative requirements with little potential for disruption of schedule, increased price, or degradation of performance.
Step One Technical Offer Evaluation Subfactor 2 – Schedule & Planning: This subfactor is met when the offeror sufficiently demonstrates and describes how the offeror can schedule and plan the construction project that will meet or improve the mandatory completion date with little potential for disruption of schedule, increased price, or degradation of performance. The evaluation will include the offeror’s proposal to meet the following requirement specification IAW all of Section 3.3 of the SOW.
Step Two Pricing Bid Evaluation Metrics: Price bids will be evaluated for (1) reasonableness to reach completeness, (2) balanced pricing, and (3) cost realism. Offerors whose price is determined to be unreasonable will not be considered for award. Additionally, an offeror’s price may be rejected if it contains unbalanced pricing to the extent that it poses an unacceptable risk to the Government.
Important Notice: Offerors are required to complete their registration in the System for Award Management (SAM) database via the website https://www.sam.gov. Offerors are strongly recommended to review their information in SAM to validate that it is current and up to date. Failure to register in SAM makes an offeror ineligible for award of DoD contracts
IAW FAR 4.1102.
Disclaimer: The information being requested does not constitute a commitment on the part of the government to award a contract, nor to pay for any costs incurred as a result in replying to this notice. This notice should not be construed as a commitment by the government for any purpose.
WWYK200131 – Repair of Chilled Water System in Bldg. 2280 Synopsis:
The work to be performed under the terms of this contract consists of furnishing all materials, labor, plant, tools, transportation, equipment, testing services, quality control and incidentals required to accomplish the repair of the chilled water system at B2280 at Tinker Air Force Base (AFB), Oklahoma.
The Contractor shall be responsible for identifying the necessary logistical, architectural, and structural work elements required to perform the work as described herein.
Assemblies, framework, fixtures, or apparatus not readily identified on the project drawings, specifications, or the Statement of Work (SOW) shall be provided by the
Contractor as required for a complete, fully operating, and functioning system or systems ready for use by the Government.
Information such as floor plan layouts and dimensions; structural, mechanical, and electrical data; and location of underground utilities provided by the Government for existing and new construction are based on available as-built documentation, field observation, and equipment selected as design basis by the Government. This information is to be considered approximate and shall be field verified by the Contractor.
This project will require contractor personnel to perform work and/or operate vehicles on flight lines, runways, taxiways, parking ramps or in aircraft hangers or maintenance areas.
Thus, all contractor personnel will be required to receive FOD awareness training in accordance with Tinker Air Force Base Instruction (Tinker AFBI) 21-100.
Please reach out to the Contracting Officer Sharla Flowers (sharla.flowers_brandon.1@us.af.mil) or the Contracting Specialist Michael Johnson (michael.johnson.404@us.af.mil) with any additional questions you may have.