About this file

This is a General Contracting Pricing Sheet (Attachment A) for RFP 20-0147, which appears to be issued by a school district or educational institution managing multiple facilities including White Academy, Ludington Magnet Middle School, and Adult Education East. The pricing sheet establishes unit pricing structures for both facility-specific lump sum costs and itemized work categories across the three named locations. The document outlines pricing requirements for materials and services including painting, flooring, doors, hardware, lighting fixtures, lockers, and toilet fixtures, along with various demolition and refinishing work measured in square feet or by individual unit counts.

The pricing sheet also establishes hourly labor rates for multiple trade classifications including carpenters, masons, painters, demolition laborers, general laborers, cleaning labor, plumbers, pipe fitters, and electricians. Bidders are required to submit unit prices for both material items and labor rates per hour, which will serve as the basis for contract pricing across the three facility locations. The document does not specify contract duration, renewal options, funding sources, or set-aside categories, as it functions solely as a pricing template for bid submission rather than containing those contractual terms.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1 General Contracting RFP 20-0147 Attachment A Pricing Sheet

FacilityLump Sum Cost
White Academy$
Ludington Magnet Middle School$
Adult Education East$
Unit ItemsUnit PricesPer measure
Painting/sq. ft.
Electrostatic painting/sq. ft.
ACT and grid/sq. ft.
VCT (R&R)/sq. ft.
3070 Door & Hardware w/ liteeach
6' VDB (white)each
8' VDB (white)each
LED light fixture (2x4)each
Electric Water Coolereach
Wood flooring refinish/patching/sq. ft.
Caulking (latex)/lft.
Locker (12" x 69" x 15")each
Toilet w/ flush valve (R&R)each
4' VDB (white)each
Exit lighteach
Fire Extinguisher cabineteach
LED light fixture (1x4)each
Labor ItemsLabor RatesPer measure
Carpenter/per hour
Mason (brick, block)/per hour
Painter/per hour
Demolition (laborer)/per hour
General laborer/per hour
Labor (final cleaning)/per hour
Plumber/per hour
Pipe Fitter/per hour
Electrician/per hour