20-0003 SOW.pdf
PDF 431 KB Posted
- Attached to
- Building AS702 & AS704 Spalling Repairs
- Solicitation number
- N6247020R6011
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amnd 0001 20R6011 FINAL.pdf | ||
| Master PPI Form - AS702 and AS704.xls | XLS spreadsheet | |
| 20-0003 AppendixD.pdf | ||
| RFP 20-0003 - AS702 and AS704 Spalling Repairs.pdf | ||
| N4008520B0003 Dwgs.pdf | ||
| N4008520B0003 Specs.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT DESCRIPTION:
The contractor shall provide all material, labor, equipment and supervision required to accomplish demolish the existing 4 (four) concrete stairwells at buildings AS702 and AS704 and to replace them with new units as shown in the construction documents. And incidental related work.
SPECIAL SCHEDULING:
The facility/activity will remain in operation during the entire construction period. The Contractor shall conduct his operations so as to cause the least possible interference with normal operations of the facility/activity.
Within the overall project schedule, commence and complete the work in one phase.
SPECIAL CONDITIONS:
None
HAZARDOUS MATERIALS:
None
ENVIRONMENTAL:
None
SUPERVISION:
One person may fill the roles of Superintendent, Quality Control Manager, and Safety & Health Officer, if duly qualified for all three positions as defined in the project specification.
File details come from the government source that posted it. Updated .