IFB No. 6134-26C: FY2026 Trenchless Pipe Repairs
Solicitation number
6134-26C
Issued by
Charleston County, South Carolina

About this file

This document is an Invitation for Bid (IFB No. 6134-25C) issued by Charleston County, South Carolina for a Cured-In-Place-Pipe (CIPP) rehabilitation project spanning five separate subdivision locations. The project involves repairing approximately 13,795 total linear feet of drainage pipes, including Corrugated Metal Pipe (CMP) and Reinforced Concrete Pipe (RCP), across Woodside Manor, Heaton Place, Oak Island, Glendale, and Forest Lakes Subdivisions. The work is intended to prevent sinkholes, potential pipe collapse, and extend the life of existing drainage infrastructure. The project is scheduled to be substantially completed within 270 calendar days from the Notice to Proceed, with final completion required within 30 calendar days after substantial completion.

The contract will be constructed utilizing South Carolina Department of Transportation (SCDOT) standard specifications and will conform to various technical standards and guidelines. Either individual projects or a combination of projects may be awarded. The work includes accessing drainage easements between residential properties, pipe cleaning, inspection, and dewatering. Contractors are responsible for traffic control, erosion prevention, utility protection, and maintaining access for property owners throughout the construction process. The project will be funded through standard municipal infrastructure improvement channels, with specific funding sources not explicitly detailed in the document. Bidders must comply with various state and federal regulations, including provisions related to work authorization, subcontractor payments, and environmental protections.

View the file

Other files

File Type Posted
4-Appendix B Addtl CIPP Specifications.pdf PDF
5-Appendix A Projects Map Exhibit.pdf PDF
3-Bid Form.xlsx XLSX spreadsheet
1-6134 IFB.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IFB NO. 6134-25C

SCOPE OF WORK

SPECIFICATIONS – SPECIAL PROVISIONS

I. GENERAL

A. WORK DESCRIPTION

Project A- Woodside Manor Subdivision CIPP

The project is located in Woodside Manor subdivision in Charleston County off Highway 78 and consists of repairing approximately 2,310 feet of Corrugated Metal Pipe (CMP) using Cured-In-

Place-Pipe (CIPP). The CIPP repairs located under roadway and grassed areas are intended to prevent sinkholes and the potential collapse of the CMP, which could pose safety hazards to residents. The repairs are also intended to extend the life of the drainage pipes. This work may include accessing between residential homes through Public drainage easements, pipe cleaning, inspection, and dewatering. Project A is approximately 1.6 miles driving distance from Project B.

Project B-Heaton Place Subdivision CIPP

This project is located in Heaton Place Subdivision in Charleston County off Highway 78 and consists of repairing approximately 1,795 feet of Corrugated Metal Pipe (CMP) using Cured-In-

Place-Pipe (CIPP). The CIPP repairs located under roadway and grassed areas are intended to prevent sinkholes and the potential collapse of the CMP, which could pose safety hazards to residents. The repairs are also intended to extend the life of the drainage pipes. This work may inspection, and dewatering. Project B is approximately 1.6 miles driving distance from Project A.

Project C-Oak Island CIPP

This project is located off various roads connected to Oak Island Drive near Folly Beach in

Charleston County and consists of repairing approximately 1,500 feet of Reinforced Concrete

Pipe (RCP) using Cured-In-Place-Pipe (CIPP). The CIPP repairs located under roadway and grassed areas are intended to prevent sinkholes and the potential collapse of the CMP, which could pose safety hazards to residents. The repairs are also intended to extend the life of the drainage pipes. This work may include accessing between residential homes through Public drainage easements, pipe cleaning, inspection, and dewatering. Project C is approximately 15.4 miles driving distance from Project E.

Project D-Glendale Subdivision CIPP

This project is located in the Glendale Subdivision in Charleston County off Ashley River Road

(Highway 61) and consists of repairing approximately 6,425 feet of Corrugated Metal Pipe

(CMP) using Cured-In-Place-Pipe (CIPP). The CIPP repairs located under roadway and grassed areas are intended to prevent sinkholes and the potential collapse of the CMP, which could pose safety hazards to residents. The repairs are also intended to extend the life of the drainage pipes.

This work may include accessing between residential homes through Public drainage easements, pipe cleaning, inspection, and dewatering. Project D is approximately 2.8 miles driving distance from Project E.

Project E-Forest Lakes Subdivision CIPP

This project is located in the Forest Lakes Subdivision in Charleston County off Dogwood Road and consists of repairing approximately 6,765 feet of Corrugated Metal Pipe (CMP) using Cured-

In-Place-Pipe (CIPP). The CIPP repairs located under roadway and grassed areas are intended to prevent sinkholes and the potential collapse of the CMP, which could pose safety hazards to residents. The repairs are also intended to extend the life of the drainage pipes. This work may inspection, and dewatering. Project E is approximately 2.8 miles driving distance from Project D.

The project will be constructed utilizing the items listed on the Project A, B, C, D, and E bid tab forms in the solicitation. Either Project A, B, C, D, or E may be awarded independently, or any combination of some or all of the Projects may be awarded.

B. MISCELLANEOUS

1. This project is scheduled to be substantially completed within two-hundred and seventy (270) calendar days from the issuance of a Notice to Proceed, and achieve final completion within thirty

(30) calendar days after substantial completion date.

2. All work shall be performed and completed in accordance with South Carolina Department of

Transportation (hereinafter “SCDOT”) Standard Specifications for Highway Construction, 2007, or latest edition, including revisions (hereinafter “Standard Specifications”), the SCDOT

Supplemental Specifications in effect at the time of letting, the SCDOT Construction Manual, 2004 Edition (hereinafter “Construction Manual”), the SCDOT Standard Drawings for Roadway

Construction, the American Association of the State Highway and Transportation Officials

Standard Specifications for Highway Bridges, 17th Edition, 2002 (including the latest interim specifications thereto) and A Policy on Geometric Design of Highways and Streets, 7th Edition, 2018 (the last two hereinafter referred to collectively as “AASHTO”), the Manual on Uniform

Traffic Control Devices, 2009 Edition, (hereinafter “MUTCD”) or latest version, and all other specifications and special provisions included in the specifications and plans of this document, and any modification which may be recommended and approved by the SCDOT, the County, and the Federal Highway Administration (hereinafter “FHWA”).

Charleston County (hereinafter the “County”) has adopted many SCDOT specifications and provisions, and it shall be understood that all interaction during the execution of this contract work shall be between the Contractor and the County and not SCDOT.

The terms and definitions in SCDOT Standard Specification Section 100 shall be used to interpret the intent and meaning as such definition necessitates, unless otherwise specified in this document.

3. Charleston County personnel such as Project Manager, Construction Manager and Construction

Inspector will be identified at the preconstruction meeting.

4. The Contractor shall submit invoices no later than the 5th day of the following month. The

Contractor and the Construction Manager, or designated County representative, on or before the last day of each month shall review and agree on the quantities detailed on an invoice being submitted for payment.

5. This project is subject to compliance with the National Pollution Discharge Elimination Systems

(NPDES) and in accordance with the NPDES General Permit for Stormwater Discharges from

Construction Activities, Permit No.: SCR100000. Permit SCR 100000 can be downloaded from the following website: https://www.scdhec.gov/sites/default/files/docs/Environment/docs/CGP-permit.pdf. The Contractor is to ensure compliance with the approved Stormwater Pollution

Prevention Plan (hereinafter “SWPPP”) and the requirements of NPDES Permit SCR 100000.

https://www.scdhec.gov/sites/default/files/docs/Environment/docs/CGP-permit.pdf https://www.scdhec.gov/sites/default/files/docs/Environment/docs/CGP-permit.pdf

The Contractor must complete a project specific Contractor Certification Form, meeting the requirements set forth in the NPDES General Permit, and provide it to the County before the pre-construction meeting. The Contractor Certification Form can be found at https://www.scdhec.gov/sites/default/files/Library/D-0437.pdf.

The County’s Certified Erosion and Sediment Control Inspector and the Contractor’s representative shall inspect all stormwater management, and erosion and sediment control practices as specified under current South Carolina Department of Health and Environmental

Control (hereinafter “SCDHEC”) requirements until final stabilization is reached on all areas of the construction site. An inspection is recommended within 24 hours of the end of a storm event of 0.5 inches or greater. The Contractor shall promptly correct any deficiencies noted within the inspection report.

Laydown and concrete truck washout areas are the responsibility of the Contractor. The

Contractor will be responsible for all costs associated with the laydown and concrete truck washout areas, for obtaining all permits and/or permit amendments, and for receiving property owner concurrence should these areas extend outside the existing right-of-way limits.

6. The Contractor shall arrange to protect all utility facilities above and below ground, or other utility properties from damage before commencing work. The Contractor shall refer to the

SCDOT Standard Specifications Subsection 107.22, for additional information.

The Contractor is required to coordinate with utility companies to obtain riser rings and any other items necessary to ensure that the new surface matches the elevation of utility structures within the project limits.

It shall be the responsibility of the Contractor to inspect the site for potential utility conflicts and abide by the South Carolina Underground Facility Damage Prevention Act. It is the responsibility of the Contractor to contact South Carolina 811 as per South Carolina State Law at least 3 full working days’ notice at 11:59 p.m. (not including the day of the call) prior to digging. Call SC

811 by dialing 811 or (888) 721-7877.

If the Contractor finds that the field conditions differ from the information provided in the plans and/or the utility relocations, the Contractor shall submit a notice to the Project Manager before performing additional work resulting from the alleged differing site conditions. The Contractor shall be responsible for coordinating all related utility relocation and/or adjustments of the impacted utility owners within the contract duration. No additional compensation will be made for delays associated with utility relocations. The Contractor shall refer to SCDOT Standard

Specifications Subsection 105.6, for additional information.

7. The Contractor shall submit a copy of its South Carolina Contractor’s License and be responsible for maintaining the necessary license to perform the proposed work in accordance with S.C. Code of Laws, Title 40, Professions and Occupations, Chapter 11, Contractors. Failure to submit a copy of the necessary license to perform the work may result in the disqualification of the bid. A

Contractor may be disqualified as a bidder in accordance with the provisions of the South

Carolina Code of Regulations, Section 63-304 through 306, and through SCDOT Standard

Specifications Subsection 102.12.

8. On all projects, when acting as the Prime Contractor, perform with your own organization and with the assistance of workers under your immediate supervision work amounting to not less than

30% of the combined value of all items of work embraced in the Contract, exclusive of any items https://www.scdhec.gov/sites/default/files/Library/D-0437.pdf of work under the Contract that require highly specialized knowledge, craftsmanship, or equipment not ordinarily available in contracting organizations qualified to bid on the project.

The Contractor shall refer to SCDOT Standard Specifications Section 108, for additional information.

9. The Contractor will be responsible for reproduction of the plans, and the County shall provide only an electronic copy.

C. APPENDICES AND RELATED DOCUMENTS

The following are enclosed as Appendices to the Scope of Work and are part of the Scope of

Work and the Contract:

Appendix A: Project Map Exhibits

Appendix B: Additional CIPP Specifications

D. CONSTRUCTION SCHEDULE

1. The Contractor shall prior to commencement of the work, provide to the Project Manager a four-week look ahead schedule identifying planned weekly work activities. The Contractor shall update the schedule every two weeks, or as specified by the Project Manager. The County will not be responsible for delays, which may be caused by the Contractor’s failure to abide by the schedule. Failure to submit the look ahead schedule as specified may result in the withholding of partial payments or stoppage of work.

The County reserves the right to determine the priority of scheduled items. The Contractor shall also be responsible demonstrating actual and planned progress, in such detail as required by the

County.

2. The Contractor shall notify the County in writing as early as possible as to the time and date at which work is expected to begin, but, in all cases, at least 7 days before beginning work, unless otherwise specified by the Project Manager.

E. COORDINATION AND MEETINGS

Project meetings between the County and the Contractor will be held weekly or as designated by the Project Manager, for the duration of the Contract to discuss the progress of the work and provide scheduled updates. There shall be representation at each meeting by every party involved in coordination or planning for the work. The meetings shall be conducted in a manner that will resolve coordination problems, should those arise. The Document Control Technician shall record minutes and results of the meeting and distribute copies to everyone in attendance, and to others affected by decisions or actions resulting from each meeting.

The Contractor shall, if requested by the County, prepare a written memorandum on required coordination activities to include such items as required notices and reports. The Contractor shall distribute this memorandum to each entity performing work, and prepare a similar memorandum for separate Contractors where interfacing of their work may be required.

F. CONTROL OF WORK/COOPERATION BY CONTRACTOR

1. The Contractor shall designate a competent superintendent who shall be present on site at all times. The superintendent shall be capable of reading and thoroughly understanding the plans and specifications, and thoroughly experienced in the type of work being performed.

2. The Project Manager will be the spokesperson for final acceptance of the project with respect to decisions regarding the quality and acceptability of the work, materials and rate of progress, all interpretations of the Contract Plans and Specifications, and the acceptability of the progress toward completion of the contract.

3. The Contractor shall perform the work in conformity with the plans and specifications as outlined in SCDOT Standard Specifications Subsection 105.

Unless and until a Change Order is executed and issued by the County, the Contractor remains obligated to perform the work in accordance with the terms of the existing contract. Such change order must be executed prior to the work being performed. No change order will be issued for work already performed outside of the scope of the original project, without prior authorization by the Project Manager.

4. The Project Manager shall coordinate any interaction between the Contractor and the Design

Engineer that may be required by this Scope of Work. To the extent that any document, data, information, other material or items are required by this Scope of Work to be furnished to the

Design Engineer, they shall instead be furnished to the Project Manager who shall then furnish them, if necessary, to the Design Engineer.

G. AUTHORITY OF PROJECT MANAGER AND CONSTRUCTION INSPECTOR

The Project Manager or Construction Manager has the authority to suspend the work, wholly or in part, or to withhold further payments to the Contractor for failure to correct unsafe conditions for its workers or the general public; for failure to carry out provisions of the contract; for periods as deemed necessary due to unsuitable weather; for conditions considered unsuitable for the prosecution of the work; or for any other conditions or reasons deemed to be in the public interest. No additional compensation shall be paid to the Contractor because of such suspensions of work.

The County’s Construction Inspector may inspect all work done and all materials furnished. Such inspection may extend to all or part of the work and to the preparation, fabrication, or manufacture of the material to be used. Such inspection does not relieve the Contractor of any responsibility or obligation to perform the work strictly in accordance with the requirements of the contract. The Construction Inspector has the authority to reject defective material and to suspend any work that is being improperly performed subject to the final decision of the Project

Manager.

The Construction Inspector is not authorized to alter or waive the provisions of the contract, to approve or accept any portion of the work, or to issue instructions contrary to the plans and the specifications. In no case will the Construction Inspector act as superintendent or perform other duties for the Contractor, or interfere with the management of the work by the Contractor’s superintendent. Advice given by the Construction Inspector is not binding and does not release the Contractor from fulfillment of the terms of the contract.

H. WARRANTY AND ACCEPTANCE

1. Substantial completion is that point at which, as certified in writing by the Construction Manager, the Work, or a designated portion thereof, has been constructed per the plans over the entire length of the project, including tie-ins to adjacent projects or existing roads, all travel lanes are to be open to the public, all safety features are installed and are being properly maintained, no lanes will have to be closed to complete any remaining work and citizens can enjoy beneficial use and legally occupy, use or operate it in all respects, for its intended purpose. Except for a project where the major item of work is installation of pavement markings or markers, the final pavement-marking scheme must be in place with at least temporary markings, but the final pavement markings do not have to be in place for the work to be substantially complete.

2. When the Construction Manager deems that the project or segment of the project has reached substantial completion, the Project Manager, Construction Manager, and Construction Inspector will promptly make an inspection. If all construction provided for and contemplated by the contract is found to be completed to the Project Manager’s satisfaction, that inspection shall constitute as the final inspection, and the Project Manager shall notify the Contractor, in writing, of final acceptance.

3. If the work is not acceptable to the Project Manager at the time of such inspection, the Contractor shall be advised as to the particular corrective work to be performed and timeline for which work shall be completed before final acceptance.

The Contractor shall not request final payment for the work until such time as the Project

Manager deems the project is complete.

4. Excluding any manufacturer’s warranties, all work and components must be warranted to be free from defects for a “reasonable man’s standard” of time as accepted by the trade, provided however, a “reasonable man’s standard” shall not be construed to be less than 24 months after the date of final payment by the County.

The plant establishment period is the 12-month period following the initial construction inspection.

Any and all manufacturer’s warranties on any equipment or materials will be passed on to the

County, and the Contractor shall furnish copies of said warranties to the County upon completion and final acceptance of the work.

II. CHARLESTON COUNTY ADDITIONAL SPECIFICATIONS

A. GENERAL

The enclosed plans and/or detail sheets show dimensions for the proposed work to be constructed.

The limits of the work shall be confined to the project limits shown except by prior contact in writing by both the Contractor and the County.

B. BEGINNING OF WORK/COMPLETION/LIQUIDATED DAMAGES

The Contractor will be permitted to start work after the signing of the contract and Contractor’s receipt of the Notice to Proceed from the County. All work shall be completed within the time frame as indicated in the contract.

The following supersedes SCDOT Standard Specifications Subsection 108.9.

SHOULD THE CONTRACTOR FAIL TO COMPLETE THE WORK WITHIN THE

ALLOWED TIME, AND BY THE CONTRACT SPECIFIED SUBSTANTIAL COMPLETION

DATE, THE CONTRACTOR SHALL BE LIABLE TO THE COUNTY IN THE AMOUNT(S)

SPECIFIED AS LIQUIDATED DAMAGES IN THE CONTRACT FOR EACH AND EVERY

CALENDAR DAY (INCLUDING SUNDAYS AND HOLIDAYS) THAT THE COMPLETION

OF THIS PROJECT IS DELAYED BEYOND THE TIME PROVIDED IN THIS CONTRACT,

AS FIXED AND AGREED LIQUID DAMAGES AND NOT AS A PENALTY; THE COUNTY

SHALL HAVE THE RIGHT TO DEDUCT FROM AND RETAIN OUT OF MONIES WHICH

MAY BE THEN DUE, OR WHICH MAY BECOME DUE AND PAYABLE TO THE

CONTRACTOR, THE AMOUNT OF SUCH LIQUIDATED DAMAGE. IF THE AMOUNT SO

RETAINED BY THE COUNTY IS NOT SUFFICIENT TO PAY IN FULL SUCH

LIQUIDATED DAMAGES, THE CONTRACTOR SHALL PAY THE COUNTY THE

AMOUNT NECESSARY TO EFFECT PAYMENT IN FULL OF SUCH LIQUIDATED

DAMAGES.

The date of substantial completion shall be determined by the Construction Manager.

The punch list must be completed to achieve final completion within the time frame as specified in the contract, unless another time frame is agreed upon by the Project Manager. Seasonal restrictions and temperatures may be considered for individual items. Failure to attain final completion will result in liquidated damages at the specified rate for any punch list item remaining incomplete beyond the allotted time frame. Liquidated damages will be charged daily until all punch list items are complete.

C. LIMITATION ON USE OF THE SITE

1. Any waste materials shall be disposed of by the Contractor as approved by the County at no cost to the County, unless specified in Special Provision No. 1 hereof.

2. Hazardous or Toxic Waste: Refer to Special Provision No 1 hereof.

3. The Contractor shall be responsible for coordinating construction related activities which affect access to adjacent properties with representatives from surrounding commercial, residential, and governmental properties along the project/within the project limits.

D. AVAILABILITY OF RIGHT-OF-WAY/PROJECT ACCESS

The County is responsible for the securing of all right-of-way that it deems necessary in advance of construction. All right-of-way areas necessary for the performance of the work are available for occupancy by the Contractor. Any additional right-of-way required for the Contractor’s operation, plant, equipment, storage of materials, etc., should be obtained and paid for by the

Contractor.

Work under other contracts with the County for grading and drainage construction, roadway pavement construction, bridge construction, erection of guardrail, installation of right-of-way fence and area lighting systems, sign erection and other work may be in progress along the length of the project simultaneously with the work to be done hereunder. The Contractor must coordinate its work accordingly and as specified herein or as directed by the Project Manager.

The Contractor shall permit access to other Contractors if and when such access may be necessary for other work in progress.

ANY DAMAGE DUE TO OPERATIONS BY THE PRIME CONTRACTOR OR HIS

SUBCONTRACTOR(S) TO OTHER CONTRACTOR’S WORK IN THE PROJECT LIMITS,

INCLUDING BUT NOT LIMITED TO, EMBANKMENT CONSTRUCTION, PAVEMENT,

SHOULDERS, TOP-SOILING AND SEEDING AND AREA LIGHTING SHALL BE

REPAIRED BY THE CONTRACTOR ENTIRELY AT THEIR OWN EXPENSE, AND TO

THE SATISFACTION OF THE PROJECT MANAGER.

E. EXISTING APPURTENANCES

1. The Contractor shall be solely responsible for the continuity of services and shall maintain a safe and satisfactory operating condition for all overhead surface or subsurface utilities affected by its operations.

2. The Contractor shall coordinate removal and replacement of all existing utilities, i.e., sewer, water, underground power, and communication cables and conduits that are required to be removed, relocated, and/or replaced during construction. Before starting construction, the

Contractor shall contact all applicable utilities within the limits of construction and shall coordinate with the County Utility Coordinator. Each utility shall be located, marked, and verified as necessary to prevent damage and/or determine the extent of relocation required. The

Contractor shall be solely responsible for coordination of the foregoing within its scheduling.

The identification and location of utilities shown in the plans are based on limited, above ground surveys only and must not be relied upon as accurate for bidding and construction purposes. It shall be the Contractor’s responsibility to verify the nature and location of all utilities prior to bidding and construction. It shall also be the Contractor’s responsibility to anticipate and account for the impact of possible utility conflicts on construction means and methods.

The Contractor shall exercise every precaution to avoid damage to existing highway installations including, but not limited to, inlets, storm drains, roadway and shoulder pavements, existing sidewalks and paths, grassed areas, fences, and monuments. Any damage to existing utilities as a result of the construction activities shall be the responsibility of the Contractor. The Contractor is responsible for verifying and notifying the Construction Manager, in writing, that final utility relocation does not conflict with the proposed work.

3. Utility valves and manholes shall be adjusted by the Contractor (raised or lowered) to match the roadway or sidewalk profile. No additional payment will be made for adjusting valves or manholes, unless specified in the bid items, or as directed by the Project Manager. The work shall be considered incidental and shall include all workmanship and materials necessary to complete this item.

4. THE CONTRACTOR WILL, AT ITS OWN EXPENSE, MAKE GOOD ANY DIRECT OR

INDIRECT DAMAGE THAT SHALL BE DONE IN THE COURSE OF CONSTRUCTION TO

ANY UTILITY STRUCTURE, OTHER INSTALLATION OF PROPERTY THROUGH OR BY

REASON OF THE PROSECUTION OF THIS WORK. THE LIABILITY OF THE

CONTRACTOR UNDER THIS COVENANT IS ABSOLUTE AND IS NOT DEPENDENT

UPON ANY QUESTION OF NEGLEGENCE ON ITS PART OR ON THE PART OF ITS

AGENT’S SERVANTS, EMPLOYEES, OR SUBCONTRACTORS, AND THE NEGLECT OF

THE COUNTY TO DIRECT THE CONTRACTOR TO TAKE ANY PARTICULAR

PRECAUTION OR TO REFRAIN FROM DOING ANY PARTICULAR THING SHALL NOT

EXCUSE THE CONTRACTOR IN CASE OF ANY SUCH DAMAGE.

5. The Contractor shall be required to adhere to the County’s Standard Operating Procedure to ensure good rideability over utility facilities and other structures located in the pavement.

F. LAYOUT OF THE WORK

The Contractor shall be responsible for establishing all lines, elevations, reference marks, etc., required during the progress of the work. The County shall be permitted at all times to check lines, elevations, reference marks, etc., set by the Contractor, who shall correct any errors in lines, elevations, reference marks, etc., disclosed by such checks. Such checks shall not be construed to be an approval of the Contractor’s work and shall not relieve or diminish in any way the responsibility of the Contractor for the accurate and satisfactory construction and completion of the work.

G. AS-BUILT DRAWINGS

The Contractor shall produce and deliver to the County one electronic copy (PDF) for this contract. This set of as-built plans is not intended to document final quantities, but is intended to show approved revisions to the contract design including, but not limited to, revised roadway profiles and cross sections, revised typical sections, revised drainage installations, any changes to the demolition and removal items, and any other changes to the original design.

If any design changes occur during construction, the plan sheets (or any other “job site record document” with a seal) revised after award of the contract shall include a complete accounting and detail of the revisions and design changes. The Contractor shall coordinate and obtain approval from the Project Manager, in writing, any design changes prior to substantial completion of the work. This documented information is to be part of the as-built plan requirements.

The as-built plans shall be neat, legible, and of the correct size. All revisions to the original plans shall be delineated in red ink, located properly on the drawing, and shall be legible and true to scale. Every as-built plan, profile, and cross-section sheets shall be designated as such by note or stamp “As-Built” in red.

The as-built plans shall be delivered to the County upon completion and acceptance of the work.

Final payment for the work will not be made until as-built plans have been completed, delivered, and accepted by the County.

H. FIELD QUALITY CONTROL

The policy and procedures for field sampling and testing materials shall conform to the requirements of the SCDOT Construction Manual Section 106.3. No additional payment will be made for Quality Control and Quality Assurance testing.

The Contractor shall supply the County with all required materials certifications and manufacturers test reports for items to be permanently incorporated into this project. The County will supply the Contractor with a list of required certifications and manufacturers tests based on the pay items and special provisions included in the submittals. These material certifications and tests shall be provided by the Contractor prior to the materials use in this project. The County must approve these certifications and reports before payment can be made to the Contractor for these items.

I. EARTHWORK

The Contractor shall furnish all labor, equipment, and materials necessary to complete any and all earthwork operations. The work covered under this section shall conform to the appropriate requirements of SCDOT Standard Specifications Section 200 and any additional specifications that may be indicated on the construction drawings or as contained below.

1. CLEARING AND GRUBBING

The Contractor shall dispose of all removed vegetation off-site unless otherwise directed by the

Construction Inspector.

2. REMOVAL OF STRUCTURES AND OBSTRUCTIONS

The Contractor is advised that SCDHEC regulations require that anytime a facility is razed, a permit must be secured due to health hazards should the building or structure contain asbestos prior to bidding the contract. The Contractor is further advised that it will be their responsibility to inspect the facility and comply with SCDHEC procedures specified in Regulation 61-86.1 VI

D. The inspection must be performed by a trained and licensed Asbestos Building Inspector or management planner in accordance with SCDHEC training and licensing requirements. If asbestos is located, the terms of Special Provision No. 1 shall apply.

If the structural components designated for removal and disposal contain lead-based paints, comply with all applicable federal, state, and municipal requirements for lead as waste; for lead in the air, water, and soil; and for worker health and safety.

3. ROADWAY AND DRAINAGE EXCAVATION

a. SITE EXCAVATION

Site excavation consists of all excavation necessary to construct the project to the typical section in the plans.

b. MUCK EXCAVATION

The amount of muck excavation will be provided in the plans or as directed by the Project

Manager or Construction Manager. The final depth shall not exceed 5 feet, unless otherwise specified in the plans and/or specifications. This item shall include removal of material and the replacement with borrow material approved by the Construction Inspector.

c. STRIPPING

Stripping shall be defined as the removal of up to a maximum of 1 foot of soil after clearing and grubbing operations have been completed. The Contractor shall stockpile the stripping for use later as fill outside of the paved areas, and/or behind curbs and sidewalks.

If it has been determined that the roadway has insufficient room or other criteria that would inhibit placement of the shoulder excavation adjacent to the proposed pavement section, the excavated material shall be hauled off, stored, or disposed of at the discretion of the

Contractor. The excavated material shall be placed in a dump truck at which point it becomes borrow material. The Contractor will be responsible for all costs associated with storage or cleanup of this material, including pulverizing, prior to placement on shoulder. The material may be considered suitable for borrow material to use on the project. If being hauled off is deemed necessary, it will be shown with the number of stations required for the entire roadway shoulder length.

d. BORROW EXCAVATION/FILL

The use of off-site borrow material shall be approved by the Construction Inspector prior to use. Borrow Excavation shall comply with the South Carolina Mining Act. Refer to Special

Provision No. 2 hereof.

4. OVERHAUL

There shall be no additional compensation for hauling of excavated materials unless specifically approved.

J. BASES AND SUBBASES

The Contractor shall furnish all labor, equipment, and materials necessary for installation of bases and subbases. The work covered under this section shall conform to the appropriate requirements of SCDOT Standard Specifications Section 300 and any additional specifications that may be indicated on the construction drawings or as contained below.

1. GRADED AGGREGATE BASE/MAINTENANCE STONE

Maintenance stone used on this project shall conform to the gradation requirements set forth in

SCDOT Standard Specifications Section 305, or to the gradation specified for Aggregate No. CR-

14. The Contractor shall use aggregates obtained from approved sources as listed on the most recent edition of SCDOT Qualified Products Listing 2.

M. MAINTENANCE AND CONTROL OF TRAFFIC

The Contractor shall furnish all labor, equipment, and materials necessary for traffic control and maintenance. The work covered under this section shall conform to the appropriate requirements of SCDOT Standard Specifications Section 600 and any additional specifications that may be

Property owners must have access to their properties at all times.

1. WORK ZONE TRAFFIC CONTROL

a. RESTRICTIONS

Lane closures will be limited per the SCDOT Lane Closures Restrictions’ list for District 6 and/or per restrictions specified in the Encroachment Permit.

CONTRACTOR’S RESPONSIBILITY

The Contractor shall designate a responsible member of its organization with sufficient qualifications whose duty shall be the prevention of accidents. This person shall have successfully completed an advanced or supervisor work zone traffic control training program conducted by an SCDOT approved work zone traffic control training provider. This person shall be responsible for assuring that all necessary precautions are taken for the protection of the public, and all workers, and for assuring that the provisions of the SCDOT Standard

Specifications, MUTCD, SCDOT Standard Drawings, these specifications, and the Design

Engineer are followed. The Contractor’s representative shall be present onsite anytime work is being performed by the Contractor or subcontractor.

The County’s Project Manager, Construction Manager, or Construction Inspector may issue a

Stop Work Directive if unsafe conditions are observed.

N. STRUCTURES

The Contractor shall furnish all labor, equipment, and materials necessary for installation and construction of structures. The work covered under this section shall conform to the appropriate requirements of SCDOT Standard Specifications Section 700 and any additional specifications that may be indicated on the construction drawings or as contained below.

1. PERMANENT PIPE CULVERTS

Permanent pipe culverts shall adhere to the current SCDOT Supplemental Technical

Specification SC-M-714 at the time of bidding. Reinforced Concrete Pipe shall be installed per

AASHTO C 443. Where existing pipe is being removed and replaced, removal of existing pipe shall be incidental to the placement of new pipe.

O. INCIDENTAL CONSTRUCTION

The Contractor shall furnish all labor, equipment, and materials necessary for incidental construction. The work covered under this section shall conform to the appropriate requirements of SCDOT Standard Specifications Section 800 and any additional specifications that may be

1. EROSION CONTROL

The Contractor shall provide erosion control measures, where necessary, to prevent excess quantities of material and debris from washing into existing water courses, ditches, gutters, drains, pipes, drip inlets, catch basins, and other structures. Such material and debris shall be removed and disposed of during the progress of the construction work and upon completion of the work. These conduits shall be in a clean condition.

The Contractor shall ensure that all drainage structures within the work zone are protected from intrusion of asphalt millings, silt, or other construction debris. All storm drainage inlets shall be temporarily covered by the use of silt fence, inlet structure filters, or any other method approved by the County. The Contractor may select a suitable alternative material or device; however, hay bales shall not be considered a suitable alternative.

A chute rinse off, a.k.a. concrete washout, facility or container shall be used to contain concrete and liquids when the chutes of concrete mixers and hoppers of concrete pumps are rinsed out after delivery. The washout facility or prefabricated container is required to consolidate soils for easier disposal and prevent runoff of liquids. If space allows, the washout facility (silt fence or hay bale and plastic washout pit) will be located and detailed on the plans. The facility shall be maintained to prevent leaks on the jobsite. If sufficient space is not available, a prefabricated washout container (washout bag, metal container/mortar pan, high-density plastic tub/kiddie pool) shall be used and must be watertight. The approximate location of the prefabricated washout container shall be identified at the preconstruction meeting, if not already shown on the plans.

The Contractor must receive written approval for the relocation of the facility or container. The concrete waste within the facility or container shall be properly disposed of per all applicable regulations.

2. CLEAN UP

It shall be the Contractor’s responsibility to keep the site neat and clean as construction progresses. All rubbish, waste materials, and unnecessary construction equipment shall be removed from the site except as otherwise specified. All construction shall be accomplished so that the public and adjacent property owners will be inconvenienced as little as possible.

The Contractor shall restore or replace any damage to public or private properties to a condition at least equal to that of the existing lands prior to site construction work. To this end, the

Contractor shall do as required all necessary highway, driveway, sidewalk, or landscape work to restore properties to their preexisting conditions.

The Contractor shall remove from the construction site all temporary buildings or structures, equipment, and excess materials utilized during the progress of the work.

P. MEASUREMENT AND PAYMENT

The method of measurement and the basis of payment shall be as called for in the SCDOT

Standard Specifications, except as shown on the unit prices in the Contractor’s bid.

It is the Contractor’s responsibility to inspect the site and determine the quantities of material necessary to construct the project. The contractor is responsible for field verifying all pipe diameters prior to ordering liners. The Contractor shall notify the Project Manager, in writing, if the quantities in the bid schedule or change order are insufficient. Compensation for Underrun or

Overrun of Quantities shall be made as specified in SCDOT Standard Specifications Subsection

109.4.

1. CONSTRUCTION STAKES, LINES, AND GRADES

The quantity for the item Construction Stakes, Lines, and Grades is measured by each project site where the work is complete. This item shall adhere to SCDOT Standard Specifications

Subsection 105.8.2. Payment for the work shall be made according to the following schedule:

Percent Contract Complete Percent of Stakes, Lines, and

Grades Bid Amount to be Paid

1 – 5 20

6 – 15 40

16 – 29 60

30 – 49 70

50 – 69 80

70 – 89 90

90 – 100 100

2. BORROW/FILL MATERIAL

A weight ticket shall be provided for all borrow material delivered to the project. For shoulders, a full dump truck will be measured to determine the volume and a ton to cubic yard conversion factor will be established for use on the project to make payment.

3. CLEANING EXISTING PIPE

Measurement for payment for the cleaning existing pipe bid item shall be the actual linear feet of existing pipe satisfactorily cleaned, regardless of size.

4. TRAFFIC CONTROL

The lump sum price bid item for Traffic Control includes payment for providing, installing, relocating, removing, and maintaining all necessary traffic control devices including all necessary signing, permanent construction signs, all necessary temporary pavement markings, and all necessary equipment. Necessary equipment includes, but is not limited to, truck mounted attenuator, trailer-mounted advance warning arrow panel, changeable message signs, etc.

5. TRAFFIC LIGHT TIMING LOOPS

Traffic light timing loops, motorcycle sensitive, shall be measured by the installation of each complete system, and payment shall be by the lump sum bid unit price for each complete unit.

This work shall include, but is not limited to, installing the required conduit runs, making the pavement saw cut, placing the required number of turns of loop wire in the saw cut, creating a twisted pigtail, splicing the pigtail to the shielded-twisted pair lead-in cable, connecting the lead-in cable to the back panel terminals at the controller cabinet, verifying proper detection of traffic, and sealing the saw cut.

6. PERMANENT VEGETATION

The cost for all fertilizers and lime shall be considered incidental to the cost of permanent vegetation and sodding.

III. SPECIAL PROVISIONS

A. SPECIAL PROVISION NO. 1

HAZARDOUS AND/OR TOXIC WASTE

If the Contractor shall encounter or expose during construction operation any abnormal condition, which may indicate the presence of hazardous and/or toxic waste, work in this area shall be immediately discontinued, and the Project Manager shall be notified. The Contractor shall refer to

SCDOT Standard Specifications Subsection 107.27 for more information.

B. SPECIAL PROVISION NO. 2

THE SOUTH CAROLINA MINING ACT

The South Carolina Mining Act enacted by the General Assembly in 1973 requires that the Department adopt reclamation standards to govern activities of the Department and any person acting under contract with the Department, on highway rights-of-way or material pits maintained solely in connection with the construction, repair and maintenance of the public road systems in South Carolina.

STANDARD PLAN FOR THE RECLAMATION OF EXCAVATED AREAS ADOPTED BY

THE SOUTH CAROLINA DEPARTMENT OF TRANSPORTATION

Reclamation Plans as stated herein shall include all areas disturbed in excavations of borrow and material pits, except planned inundated areas.

The final side slopes of areas excavated for borrow and material pits shall be left at such an angle so as to minimize erosion and the possibility of slides. The minimum slope in every case shall be no less than 3:1.

Small pools of water should not be allow that are, or are likely to become noxious, odious, or foul to collect or remain on the borrow pit. Suitable drainage ditches, conduits, or surface gradient shall be constructed to avoid collection of noxious, odious, or foul pools of water unless the borrow pit is to be reclaimed into a lake or pond.

Borrow pits reclaimed to a lake or pond must have an adequate supply of water to maintain a water sufficient level to maintain a minimum water depth of four (4) feet on at least fifty (50) percent of the surface area of the lake or pond.

Excavated areas will be drained where feasible unless otherwise requested by the property owner where, in such instances, the property owner may wish to develop the excavated area for recreational purposes or for the raising of fish, or for other uses, in compliance with the South Carolina Mining Act.

Where material is stripped from the ground surface in relatively thin layers, the area, after excavation has been completed, will be thoroughly scarified and terraced and planted to establish satisfactory vegetation necessary to control erosion. Vegetative cover should be established on a continuing basis to ensure soil stability appropriate to the area. Conservation practices essential for controlling both on-site and off-site erosion and siltation must be established. A minimum of seventy-five (75) percent vegetative ground cover, with no substantial bare spots, must be established and maintained into the second growing season.

Excavated areas that are drained will be seeded to obtain a satisfactory vegetative cover. The side slopes of excavated area will be planted to vegetation.

The Deputy Secretary for Engineering, or his duly appointed representative, will make a final inspection of the reclaimed area and keep a permanent record of his approval thereof. A map or sketch providing the location and approximate acreage of each pit used on the project will be provided to the Resident

Construction Engineer for inclusion in the final plans.

All applicable regulations of agencies and statutes relating to the prevention and abatement of pollution shall be complied with by the Contractor in the performance of the contract.

The Contractor shall comply with the provisions of the plan that are applicable to the project as determined by the Engineer. Seeding or other work necessary to comply with the plan on pits furnished by the Contractor shall be at the expense of the Contractor, and in accordance with SC-M-810.

C. SPECIAL PROVISION NO. 3

STANDARDS AND REFERENCES

This project is to be constructed under the specifications and provisions listed herein in effect at the time of the letting.

1. The referenced SCDOT publications are available on the internet as follows, or may be obtained from the SCDOT Engineering Publications office at (803) 737-4533 or via e-mail at

PlanStorage@scdot.org.

a. The latest updated errata to the 2007 Standard Specifications for Highway Construction can be found at https://www.scdot.org/business/road-supplemental-specs.aspx.

b. The latest Construction Manual and Revisions can be found at https://www.scdot.org/business/scdot-construction-manual.aspx.

c. Standard Drawings are available for download at https://www.scdot.org/business/standard-drawings.aspx. These drawings depict standard design features commonly used and the

Standard Drawings constitute contract documents in accordance with SCDOT Standard

Specifications Subsection 101.3.67

2. The FHWA MUTCD and current revisions can be found at https://mutcd.fhwa.dot.gov/kno_2009r1r2.htm.

D. SPECIAL PROVISION NO. 4

CONTRACT PROVISION TO REQUIRE CERTIFICATION AND COMPLIANCE

CONCERNING ILLEGAL ALIENS

By submission of this bid, the bidder as the Prime Contractor does hereby agree:

1. to certify its compliance with the requirements of Chapter 14 of Title 8 of the S.C. Code of Laws regarding Unauthorized Aliens and Public Employment;

2. to provide the County with any documents required to establish such compliance upon request;

and

3. to register, participate, and require agreement from subcontractors and sub-subcontractors to register and participate in the federal work authorization program to verify the employment authorization of all new employees, or to employ only workers who supply the documents required pursuant to S.C. Code 8-14-20.

E. SPECIAL PROVISION NO. 5

SUBLETTING OF CONTRACTS (SPECIALTY ITEMS)

The following items of work, when not performed by the Prime Contractor, will be designated as

Specialty Items in all contracts in which the item does not constitute 30% or more of the original contract value:

Pavement Markings Permanent Roadway Signs

Guardrail Signalization

Milling Asphalt Pavement Electrical/Lighting

Grassing Specialized Retaining Walls mailto:PlanStorage@scdot.org https://www.scdot.org/business/road-supplemental-specs.aspx https://www.scdot.org/business/scdot-construction-manual.aspx https://www.scdot.org/business/standard-drawings.aspx https://www.scdot.org/business/standard-drawings.aspx https://mutcd.fhwa.dot.gov/kno_2009r1r2.htm

Landscaping Fencing

Erosion Control Right-of-Way Surveying

Permanent Construction Signs Railroad Track Work

Utilities Jacking and Boring

Contaminated Soil and Tank Removal Bridge Floor Grooving

Bridge Barrier Walls Milled Rumble Strips

Traffic Count Stations Buildings

Drilled Shafts and Casings Navigational Lighting

Pier Fender Systems Sound Barrier Walls

F. SPECIAL PROVISION NO. 6

PROMPT PAYMENT CLAUSE

1. Subject to the provisions on retainage provided in Paragraph 2 below, when a subcontractor has satisfactorily performed a work item of the subcontract, the Contractor must pay the subcontractor for the work item within 7 calendar days of the Contractor’s receipt of payment from the County. A subcontractor shall be considered to have “satisfactorily performed a work item of the subcontract” when the County pays the Contractor for that work item. In the case of a second or third tier subcontractor, the 7-day time period begins to run when the first tier

Subcontractor receives payment from the Contractor or when the second tier subcontractor receives payment from the 1st tier subcontractor.

2. The Contractor may withhold as retainage up to 5% percent of a subcontractor’s payment until satisfactory completion of all work items of the subcontract. “Satisfactory completion of all work items of the subcontract” shall mean when the County accepts the last work item of the subcontract. The Contractor must release to the subcontractor any retainage withheld within 7 calendar days from the date the Contractor receives payment from the County for the last work item of the subcontract or within 7 days from the County’s acceptance of the last work item of the subcontract, whichever is the latest to occur. However, upon documentation of good cause provided by the Contractor and written concurrence by the Project Manager, the Contractor may continue to withhold the 5% retainage.

3. Prior to receiving payment of each monthly estimate, the Contractor shall (a) certify to the

County that the construction estimate is complete and that its subcontractors have been paid for work covered by previous estimates, for which they are entitled to be paid, in accordance with paragraphs (1) and (2) above, and (b) submit verification that Contractor has received similar certifications or evidence from its subcontractors that lower tier subcontractors have been…