About this file
This document is a Procurement Solicitation issued by the Great Lakes Water Authority (GLWA) for Systems Control Center Support Services. The solicitation seeks experienced and qualified vendors to provide personnel to augment GLWA staff and support the operations and maintenance of equipment for the GLWA System Control Group. The solicitation meeting is optional and scheduled for Friday, November 14, 2025, at 11:00 AM EST via Microsoft Teams, with no site tour available. Questions are due by Friday, November 21, 2025, at 12:00 PM EST, and vendor responses are due by Friday, December 12, 2025, at 12:00 PM EST. The contract start date is to be determined, and the services will involve providing qualified personnel for various operational roles including team leads, systems technicians, operators, and support engineers.
The solicitation includes specific minimum qualifications for vendors, such as demonstrating at least five comparable projects in the last ten years, having a local office, and providing personnel capable of working on-site daily and on-call 24/7. The evaluation criteria heavily weight the lowest cost/responsive/responsible bid at 97%, with a 3% allocation for Business Inclusion and Diversity (B.I.D.) Economic Equity. Vendors must submit a diversity plan and certification, and those with a validated one-year aggregate vendor performance score less than 70% will be deemed non-responsible. No specific funding source is mentioned, and no bonds are required for this solicitation. The contract terms and conditions, including insurance requirements, are detailed in Attachment No. 1 of the document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GLWA Procurement Solicitation
Advertisement Date:
Monday, November 3, Requisition/Contract No.:
0003185
Issuing Buyer and E-Mail Address:
Gerald Moore/Gerald.Moore@glwater.org
Project/Contract Title: Systems Control Center Support Services Solicitation Cover/Instructions to Vendors
Solicitation Cover/Instruction to Vendors (FSA_PRO_TPL_0003) Rev. #4 06.11.2025 Page 1 of 8
Solicitation
This solicitation issued by the Great Lakes Water Authority (GLWA) is seeking submittals from experienced and qualified vendors to provide Systems Control Center Support Services. The Services will function to augment GLWA staff and include providing qualified personnel to perform work to support the operations and maintenance of equipment for the GLWA System Control Group.
The fees from the successful bid shall be included in the Contract executed by the parties. The Contract can be found in Attachment No. 1. Capitalized terms used in this solicitation, if not otherwise defined herein, shall have the meaning ascribed in the Contract.
Solicitation Meeting
Attendance: Optional Date: Friday, November 14, 2025 Time: 11:00AM EST Location: Microsoft Teams Site Tour: Not Applicable
Access to the site tour, if any, requires pre-approval through GLWA Security and Integrity.
RSVP: By Monday, November 10, 2025, 12:00 PM EST via e-mail to Gerald.Moore@glwater.org
Questions All questions must be sent through https://glwater.bonfirehub.com/portal Question Due Date/Time: Friday, November 21, 2025, 12:00 PM EST
Due Date
Date: Friday, December 12, 2025 Time: 12:00 PM EST
Note: For construction projects only, addendums will be included in the final contract document.
Late submittals will not be accepted.
Contract Details The terms and conditions of the Contract, including insurance requirements, are set forth in Attachment No. 1. The estimated start Work date is TBD.
Specialized Funding N/A
Business Inclusion and Diversity (B.I.D.)
The B.I.D. Requirement Applies The GLWA B.I.D. requirements can be found at:
www.glwater.org/vendors/doing-business-with-glwa/
Required Bonds
☒ N/A
☐ Bid Bond – 5% of Bid Price
☐ Performance Bond – 100% of Contract Price
☐ Payment Bond – 100% of Contract Price https://glwater.bonfirehub.com/portal http://www.glwater.org/vendors/doing-business-with-glwa/
Monday, November 3, Requisition/Contract No.:
0003185
Solicitation Cover/Instruction to Vendors (FSA_PRO_TPL_0003) Rev. #4 06.11.2025 Page 2 of 8
Section 1. Project Overview/Background
The Services are required to augment GLWA staff and include providing qualified personnel to perform work to support the operations and maintenance of equipment of the GLWA System Control Group.
Resumes of the Consultant’s proposed personnel shall be provided and GLWA shall interview each to assess their individual qualifications to fulfill the requirements of the Services. Upon GLWA’s approval of Consultant’s personnel, GLWA shall assign to each person a position and work location on an as-needed, hourly basis. Each of Consultant’s personnel shall be able to work in all conditions, in an office or field environment, at remote locations within the GLWA service area. The Services may expose Consultant’s personnel to outside elements and seasonal weather. Consultant shall provide its personnel with all equipment necessary to complete the Services and vehicles for transporting Consultant’s personnel to their assigned work locations. Except in cases of emergency, GLWA shall contact the Consultant’s Project Manager one (1) to seven (7) days in advance to request Services.
The full scope of Services is described in Exhibit A of Attachment No. 1.
Section 2. Minimum Qualifications
1. Minimum Qualifications
a. Consultant shall demonstrate it has performed at least five (5) projects in the last ten (10) years that are comparable to the size and scope of the Services required by this solicitation.
b. Consultant must have a local office.
c. Consultant shall demonstrate it has sufficient numbers and classifications of personnel, or has access to such personnel, with experience in a wide range of operational staffing positions including operators, apprentices, supervisors, and operational support engineers which can be on-site daily and on call 24 hours per day, 7 days per week.
d. Consultant’s Project Manager shall have a minimum of ten (10) years’ experience in managing work similar to the Services required by this solicitation which includes at least five (5) projects.
e. Consultant shall demonstrate its and its Project Manager’s and personnel’s familiarity with large industrial plant environments and facilities.
f. Consultant shall demonstrate its ability to complete the Services required by this solicitation by providing resumes for its proposed Project Manager and personnel for the skill sets listed below including any relevant certifications or licenses for the positions listed.
i. Operations - Team Lead/Supervisor
ii. Operations - Systems Technician
iii. Operations - Systems Operator Trainee
iv. Operations - Systems Operational Support Engineer
v. Confined Space Certification
vi. Project Manager
2. The required B.I.D. Program documents shall be submitted as follows:
Monday, November 3, Requisition/Contract No.:
0003185
Solicitation Cover/Instruction to Vendors (FSA_PRO_TPL_0003) Rev. #4 06.11.2025 Page 3 of 8
(a) Diversity Plan – Interested vendors shall submit an executive summary detailing key points of its diversity plan in no more than three (3) pages at an 11-point font size. The executive summary must specify vendor’s method for maximizing opportunities for inclusion and diversity participation for this solicitation.
(b) Diversity Certification Review and Assessment – Along with the executive summary, vendors must submit a copy of their diversity certification. In addition, if vendor has diversity-certified subcontractors, vendor shall submit the subcontractor’s certification. The following diversity certifications, from a federal agency, the state of Michigan, or a Michigan local unit of government, including certifications upon which those entities might rely, will be accepted and must be submitted with vendor’s Diversity Plan. The following list is not exhaustive, and vendor may include other types of certified disadvantaged groups.
Disadvantaged Business Enterprise (DBE) Minority Business Enterprise (MBE) Small Business Enterprise (SBE) Woman Business Enterprise (WBE)
3. GLWA Vendor Performance Score – Vendors with a validated one (1) year aggregate score of less than 70% will be deemed non-responsible pursuant to the GLWA Procurement Policy.
Section 3. Attachments
All documents are found in Bonfire and should be reviewed to aid in responding to this solicitation. Failure to complete and submit required documents may result in vendor’s response being deemed nonresponsive.
Attachments Description Required Submittal Attachment No. 1 GLWA Contract/Agreement Attachment No. 2 Vendor Certifications (FSA_PRO_SUP_0002) X Attachment No. 3 B.I.D. Requirements (FSA_PRO_SUP_0005)
Section 4. Evaluation Criteria RFB
(End Solicitation Cover - Instructions to Vendors begin on next page)
RFB Evaluation Criteria Weight B.I.D. - Economic Equity 3% Lowest Cost/Responsive/Responsible 97%
TOTAL 100%
Monday, November 3, Requisition/Contract No.:
0003185
Solicitation Cover/Instruction to Vendors (FSA_PRO_TPL_0003) Rev. #3 – 06.11.2025 Page 4 of 8
Instructions to Vendors
1. GENERAL INFORMATION
1.1. Any vendor interested in submitting a response to this solicitation is required to be registered with Bonfire at https://glwater.bonfirehub.com. Registration is FREE. By responding to this solicitation, vendor is agreeing to comply with GLWA’s Procurement Policy, available on the GLWA website at https://www.glwater.org/vendors/doing-business-with-glwa/.
1.2. All communications pertaining to this solicitation are to be directed solely to the GLWA procurement staff designated in “Solicitation Cover”.
2. ADDENDA
2.1. It is the responsibility of Vendor’s to check for any addenda posted on Bonfire and to make inquiry as to any changes issued thereby. Vendors are advised that no oral interpretation, information, or instruction by any officer, employee, or representative of GLWA shall be binding upon GLWA.
2.2. Any interpretations, corrections, and additional provisions that GLWA may make to this solicitation shall be made only by addendum. Should a Vendor (i) be in doubt as to the true meaning of any portion of this solicitation, (ii) find any ambiguity, inconsistency, or omission herein, or (iii) intend to take exception to any requirement of the solicitation, the Vendor must make a written request for an official interpretation or correction on or before the close of the question-and-answer period established in the Solicitation Cover.
2.3. Any addenda issued by GLWA shall become part of this solicitation and shall be reflected by vendor in its response to this solicitation. Vendors shall submit the latest revision of any form or attachment issued by an addendum with its response.
2.4. If this solicitation is a Request for Bid resulting in a construction agreement, then all addenda issued by GLWA shall be fully incorporated by reference as a part of the contract documents.
3. PREPARATION OF RESPONSE
3.1. GLWA shall have no responsibility and shall not reimburse any Vendor for any costs incurred, however caused, in the process of responding to this solicitation including, without limitation
(i) preparing and submitting its response, (ii) attending solicitation meetings, site tours or oral interviews, (iii) withdrawing its response, (iv) objecting to an award, (v) receiving a “Non-Award Determination”, or (vi) negotiating a contract resulting from this solicitation.
3.2. Vendors are advised that the scope of work is intended to define the minimum standard of quality necessary to complete the work. By submitting a response to this solicitation, vendor affirms that except for assumptions and exceptions explicitly stated, vendor considers its response accurate and sufficient to complete the work.
3.3. Documents included with this solicitation are for vendor’s information and convenience only. If a vendor requires any information beyond what is contained in this solicitation, vendor may be required, in GLWA’s sole discretion, to first provide evidence of a security clearance from the U.S. Department of Homeland Security for each person that may have access to the requested https://glwater.bonfirehub.com/ https://www.glwater.org/vendors/doing-business-with-glwa/
Monday, November 3, Requisition/Contract No.:
0003185
Solicitation Cover/Instruction to Vendors (FSA_PRO_TPL_0003) Rev. #3 – 06.11.2025 Page 5 of 8 information. Providing evidence of the security clearance does not guarantee the vendor access to the requested information.
4. PREVAILING WAGES ON FEDERALLY FUNDED CONSTRUCTION PROJECTS
If the work under this solicitation is for a federally funded construction project the vendor shall be required to pay prevailing wage rates in compliance with the Davis-Bacon Act.
5. SECURITY FOR SOLICITATION
5.1. If security is required for this solicitation, the security shall be in the form of a bid bond. The bid bond shall (i) be submitted on GLWA’s bid bond form, (ii) name the vendor as principal, (iii) be executed by a surety, either licensed to do business in the State of Michigan or which has an A.M. Best’s rating of A-/VIII or greater and (iv) be properly executed and accompanied by a certified power of attorney. Vendor’s bid security shall be retained by GLWA until the latter of
(i) the end of the period during which bids shall remain open or (ii) seven (7) business days after contract award.
5.2. The bid security of the vendor that is awarded the contract shall be retained until that vendor has (i) submitted all required information, (ii) delivered evidence of insurance, (iii) furnished the required performance and payment bonds, and (iv) executed the contract.
5.3. If the awarded vendor fails to execute the contract as requested, GLWA may annul the award notification and, if so, the bid bond shall be forfeited to GLWA. If GLWA incurs any costs in the forfeiture of the bid bond, vendor and vendor's surety jointly and severally agree to reimburse all of GLWA's costs of collection thereon, including reasonable attorneys’ fees and court costs incurred, with or without suit and interest.
6. SUBCONTRACTORS
6.1. Vendors shall be prepared to retain specific subcontractors and/or suppliers for the performance of the work if required by the solicitation documents to do so. If vendor objects to retaining any specified subcontractor and/or supplier and the concern is not addressed by an addendum, then vendor should refrain from submitting a response to this solicitation.
6.2. GLWA may request the removal and/or replacement of any subcontractor nominated by a vendor prior to awarding the contract. In such event, the vendor shall promptly nominate a qualified substitute or state that it shall self-perform the work involved, if qualified to do so. If a vendor declines to act on either option or otherwise fails to act by the date specified by GLWA, GLWA may, in its sole discretion, elect not to recommend vendor for the award.
6.3. Subsequent to the vendor’s submission of its response to this solicitation, the vendor shall not add or replace any designated subcontractor unless vendor (i) gives written notice to GLWA within ten (10) business days of receipt of an “Award Determination Letter” and (ii) provides all information requested by GLWA. If vendor fails to abide by these terms, GLWA may, in its sole discretion, elect not to recommend vendor for the award.
Monday, November 3, Requisition/Contract No.:
0003185
Solicitation Cover/Instruction to Vendors (FSA_PRO_TPL_0003) Rev. #3 – 06.11.2025 Page 6 of 8
7. MATERIAL/EQUIPMENT SUBSTITUTES AND “OR-EQUAL” ITEMS
7.1. Contracts shall be awarded on the basis of materials and equipment specified or described in the solicitation documents and any “or-equal” or substitute materials and equipment subsequently approved by GLWA. Requests by vendor for “or-equal” or substitute materials and/or equipment shall be submitted on or before the close of the question-and-answer period.
The request shall provide a detailed description of the “or-equal” or substitute material and/or equipment and its impact on the work, including time. The burden of proof of the merit of the proposed “or-equal” or substitute item shall be on the vendor. GLWA’s decision to accept or reject any “or-equal” or substitute materials and/or equipment shall be final and set forth in an addendum. Vendor shall not rely upon approvals made in any other manner.
7.2. All prices that a vendor sets forth in its response shall be based on the presumption that vendor will furnish the materials and equipment specified or described in the solicitation documents.
Any assumptions regarding the possibility of post-response approvals of “or-equal” or substitution requests shall be made at vendor’s sole risk.
7.3. This section shall not create or impose any express or implied duty on GLWA to exercise the authority granted herein.
8. OPENING OF RESPONSE
Responses to this solicitation shall be downloaded and opened by GLWA within one (1) business day of the advertised due date and time.
9. MODIFICATION OF RESPONSE
No modification, alteration or revision to vendor's response will be accepted after the solicitation closing time and date.
10. WITHDRAWAL OF RESPONSE
A Vendor’s response may be withdrawn subject to and in accordance with the following rules:
10.1. A Vendor’s response shall not be withdrawn unless the vendor, within one (1) business day after the solicitation response opening, files a written claim with GLWA substantiating a mathematical or clerical error in its response. The claim shall include a signed affidavit stating the facts of the error and a request that vendor’s response be withdrawn. The claim shall be e-mailed to Procurement@glwater.org with a subject line that states, “Response Withdrawal Request” and includes the solicitation number and title.
10.2. If a claim to withdraw a response due to an alleged mathematical or clerical error is timely filed, GLWA shall review the claim within ten (10) business days after its receipt.
10.3. GLWA shall review the claim for evidence as to whether:
10.3.1. A Vendor’s response contains an obvious mathematical or clerical error that does not involve a lack of good faith or fair dealing; and
10.3.2. The error is subject to objective certification and is of such grave consequences that to enforce the response by way of a contract would be unconscionable; and mailto:Procurement@glwater.org
Monday, November 3, Requisition/Contract No.:
0003185
Solicitation Cover/Instruction to Vendors (FSA_PRO_TPL_0003) Rev. #3 – 06.11.2025 Page 7 of 8
10.3.1. The error is of a material nature; and
10.3.2. The error was not caused in any way by a vendor's violation of an affirmative legal duty or culpable negligence.
10.4. Upon completion of the review, GLWA shall notify the vendor within five (5) business days of its decision to allow or not allow vendor to withdraw its response.
10.5. If GLWA suffers no serious prejudice, except loss of bargain, then GLWA shall allow a vendor to withdraw its response and, if applicable, GLWA shall return vendor's bid security within a reasonable time. Upon withdrawal of its response, vendor shall not be allowed to submit another response to the solicitation. The decision of GLWA shall be final and binding on vendor.
11. EVALUATION OF RESPONSE
11.1. For “Requests for Bids” and “Invitations to Quote”, the award shall be made to the responsible vendor submitting the lowest responsive response. GLWA shall review and validate responses for responsibility and responsiveness and prepare a bid tabulation. Bid tabulation information shall not be made available to vendor until GLWA has validated all responses for responsibility and responsiveness.
11.2. For “Requests for Proposals”, “Requests for Qualifications” and “Requests for Information”, the award shall be made to the responsible vendor with the highest ranked score pending successful negotiations. GLWA shall review and validate responses for responsiveness prior to evaluating and scoring the response. Vendors are advised that an award for “Requests for Information” and “Requests for Qualifications” will not be made unless explicitly stated in the solicitation.
11.3. GLWA reserves the right to waive any minor deviations, irregularities and informalities in the response.
11.4. GLWA reserves the right to reject any and all responses to this solicitation for reasons including, without limitation, responses that GLWA determines are nonconforming, nonresponsive, or unbalanced; responses where vendor purports to add terms or conditions, take exception to any provision of the solicitation documents, alter any template provided by GLWA for vendor’s response, or be otherwise conditional in nature; and/or a finding of vendor non-responsibility as set forth in the GLWA Procurement Policy located at GLWA-Procurement-Policy- 10.26.22.pdf.
11.5. If any grounds for the rejection of a response from the vendor under consideration for award are found, a “Non-Award Determination” shall be made by GLWA, and no further consideration shall be given to that vendor’s response. GLWA shall give written notice thereof to such vendor, including the reasons therefor.
12. CONDITIONS TO FINAL AWARD
Vendor’s response shall not be considered responsible in accordance with the requirements of the solicitation unless vendor, within ten (10) business days after receiving an “Award Determination Letter”, submits all documents that GLWA, in its sole discretion, considers necessary to complete the execution of the contract including, without limitation, the contract and certificates of insurance https://glwa.wpenginepowered.com/wp-content/uploads/2018/06/GLWA-Procurement-Policy-10.26.22.pdf https://glwa.wpenginepowered.com/wp-content/uploads/2018/06/GLWA-Procurement-Policy-10.26.22.pdf
Monday, November 3, Requisition/Contract No.:
0003185
Solicitation Cover/Instruction to Vendors (FSA_PRO_TPL_0003) Rev. #3 – 06.11.2025 Page 8 of 8 meeting the contract requirements and any required bonds.
13. POST-AWARD
13.1. Vendor shall be e-mailed a fully executed copy of the contract once completed. For some solicitations, a purchase order will constitute the fully executed contract.
13.2. GLWA may periodically evaluate the performance of vendor under any contract resulting from this solicitation. Information gained during this evaluation process may be used by GLWA to evaluate vendor's capabilities to perform future work for GLWA. The criteria by which vendor will be evaluated can be found at https://www.glwater.org/vendors/doing-business-with-glwa/.
(End Instructions to Vendors)