2-NOI 448-2024-016902.pdf

PDF 198 KB Posted

Attached to
WL/SS/SSM/Paving and Incidental Drainage Improvements to serve Bridger Pawnee Addition - Phase 2 & Main
Solicitation number
260307
Issued by
Sedgwick County, Kansas

About this file

This document is a Notice of Intent (NOI) for discharge of stormwater runoff from construction activities submitted to the Kansas Department of Health and Environment under the National Pollutant Discharge Elimination System (NPDES) for the Wichita - Bridger Pawnee Addition project. The project owner/operator is Bridger on Pawnee LLC, with Carter Wells as the primary contact located in Dallas, Texas. The construction project involves grading, paving, drainage, sanitary sewer, storm water, waterline, and water main improvements in Wichita, Kansas, located approximately one-half mile south of 119th Street and Pawnee in Sedgwick County. The site encompasses 79 acres total with 84 acres of anticipated soil disturbance. The project is anticipated to commence on January 1, 2025, and be completed by January 1, 2035. The NOI was submitted on November 21, 2024, and received authorization on December 23, 2024, with permit expiration on July 31, 2027. The Kansas Permit Number is S-AR94-1936 and the Federal Permit Number is KSR122863.

The erosion and sediment control plan includes installation of perimeter silt fence barriers, temporary sediment storage basin at the detention area outfall, permanent drainage structures with erosion control measures, utility improvements, and pavement improvements with permanent seeding. A sedimentation basin will be installed in the common drainage area where more than ten acres will be disturbed, with design calculations prepared by Hunter Wiles, a licensed engineer (License #29849). The first annual permit fee is $60.00, payable through the KEIMS system, with continued annual invoicing required until a Notice of Termination is submitted. Stormwater runoff from the site will discharge to the Arkansas River within the Lower Arkansas River Basin. No historic or archeological sites, threatened or endangered species habitat, contaminated soils, or critical water quality management areas were identified within or near the project site boundary.

View the file

Other files

File Type Posted
3-BP 448-2024-016902.pdf PDF
1-260307 Bid Table.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Effective: August 1, 2022 Notice of Intent (NOI) for Discharge of Stormwater Runoff from Construction Activites Page 1 of 4

NOTICE OF INTENT (NOI)

For Authorization to Discharge Stormwater Runoff from Construction Activities In accordance with the Kansas Water Pollution Control General Permit Under the National Pollutant Discharge Elimination System (NPDES)

Submission of this Notice of Intent constitutes notice that the party identified in Section I of this form requests authorization for coverage under the Kansas Water Pollution Control general permit, or KDHE issued successor permits, issued for stormwater runoff from construction activities in the State of Kansas. Becoming a permittee obligates the discharger to comply with the terms and conditions of the general permit. A complete request for Authorization for coverage under the general permit must be submitted or the request will not be processed. KDHE will notify owners or operators whose Notice of Intent (NOI) and supporting documentation for Authorization of stormwater runoff associated with construction activities are incomplete, deficient, or denied.

I. OWNER OR OPERATOR ADDRESS, BILLING, CONTACT & RECORDS LOCATION INFORMATION

Owner/Operator Carter Wells Mailing Address: 4514 Cole Ave Ste 800 Company Name: Bridger on Pawnee LLC City, State Zip: Dallas, TX 75205 Phone: (316) 262-2691 Email: Carter@bridgercos.com

Contact Name: Carter Wells Mailing Address: 4514 Cole Ave Ste 800 Company Name: Bridger on Pawnee LLC City, State Zip: Dallas, TX 75205 Phone: (316) 262-2691 E-mail: Carter@bridgercos.com

PERMIT FEE BILLING INFORMATION

Billing Contact: Carter Wells Billing Address: 4514 Cole Ave Ste 800 Dallas, TX 75205

Phone: (316) 262-2691 E-mail: Carter@bridgercos.com

II. SITE INFORMATION

Project Name: Wichita - Bridger Pawnee Addition Street Address: 1/2 mile south of 119th & Pawnee

Wichita, KS 67215 County: Sedgwick

Legal Site Description:

Qtr: Qtr: NW Qtr: SW Section: 06 Township: 28S Range: 01W

Decimal Degrees Latitude: 37.641111 Decimal Degrees Longitude: -97.475833

AUTHORIZED:Submission Received: 11/21/2024 Submission Number:

HQ8-A6TS-H0DGA YES X NO

Reviewer: Is Authorization Conditional

YES NO X

(if yes, see Section V for conditions)

Larry Hook Are there any Considerations

YES NO X

(if yes, see Section V for considerationsAuthorized By:

Secretary, Kansas Department of Health and Environment KS Permit No.: S-AR94-1936

Issued: December 23,2024 Federal Permit No.: KSR122863

KEIMS Watermark KSR122863 v1.0

Approved Issued On:12/23/2024

Expires On:07/31/2027

Project Name: Wichita - Bridger Pawnee Addition Notice of Intent (NOI)

Effective: August 1, 2022 Notice of Intent (NOI) for Discharge of Stormwater Runoff from Construction Activites Page 2 of 4

B. Existing Conditions/Uses

1) Is any part of the project located on Indian Country Land?

No

2) If stormwater runoff drains to or through a Municipal Separate Storm sewer System (MS4): MS4 Name:

3) Name of the first receiving water, stream, or lake Arkansas R (110300011), River Basin AR -

LOWER ARKANSAS

4) Are contaminated soils present on the site or is there groundwater contamination located within the site boundary?

No

5) Are there any contaminated soils that will be disturbed or any contaminated groundwater that will be pumped by the proposed construction activity?

No

6) Are there any surface water intakes for public drinking water supplies located within ½ mile of the site discharge points?

No

7) Are there any known historical or archeological sites present within the site boundary or any historic structures located within 1000 feet of the project site?

No

Note: Include documentation of project-specific coordination with the Kansas Historical Society in making this determination

8) Is any threatened or endangered species habitat located within the site boundary or in the receiving water body?

No

Note: Include documentation of project-specific coordination with the Kansas Department of Wildlife, Parks & Tourism in making this determination.

9) Will the project impact the line or grade of a stream or does it include dredge or fill of a potential jurisdictional water body or wetlands?

No

10) Are any Critical Water Quality Management Areas, Special Aquatic Life Use Waters, or Outstanding National Resource Waters located within ½ mile of the facility boundary?

No

C. Project Description

1) Project Description:

Construction of Bridger Pawnee Addition including grading, paving, drainage, sanitary sewer, storm water, waterline, and water main.

Does this NOI include all proposed soil disturbing activities associated with the entire common plan of development? Yes

2) Anticipated project Start Date: January 1, 2025 and Completion Date: January 1, 2035

3) Estimated total area to be disturbed: 84.00 Acres

4) Total area of the site: 79.00 Acres

5) Do you plan to disturb ten or more acres that are within a common drainage area? Yes

Will a sedimentation basin be installed in that drainage area? Yes

(Attach design calculations for each sedimentation basin.) If a sediment basin is not feasible, on a separate sheet describe similarly effective erosion and sediment control measures to be implemented in lieu of a sedimentation basin.

KEIMS Watermark KSR122863 v1.0

Approved

Project Name: Wichita - Bridger Pawnee Addition Notice of Intent (NOI)

Effective: August 1, 2022 Notice of Intent (NOI) for Discharge of Stormwater Runoff from Construction Activites Page 3 of 4

D. Maps

Include an area map showing the outline of the construction site and the topographic features of the area at least one mile beyond the project site.

E. Erosion Control Plan and Best Management Practices

1) Provide a summary of the sequence of major soil disturbing activities including installation of the corresponding stormwater management and pollution control features.

1) Install perimeter silt fence barrier. Sediment barriers will be installed at drainage ways and areas where water flows away from the site. All disturbed areas will have temporary seeding applied.

2) Install temporary sediment storage basin. Temporary sediment storage basin will be installed at outfall of detention area.

3) Install permanent drainage structures at locations specified in the plans with erosion control measures as indicated on plan sheets and erosion control plan (sediment barriers, inlet protection, etc.)

4) Construct utility improvements. Install erosion control measures as indicated on the Erosion Control plan. All disturbed areas will have either temporary or permanent seeding applied.

5) Construct pavement improvements. Install silt fence at locations indicated on the Erosion Control Plan and permanent seeding in easements, right-of-way, and all other areas disturbed by construction.

6) Record all deviations from initial Erosion Control Plan.

2) Provide one or more site plans covering the anticipated soil disturbing activities showing the limits of disturbance, the existing and proposed elevation contours, the types and locations of erosion/sediment control measures and stormwater management/pollution control features during each phase of construction and the locations where stormwater runoff leaves the construction site.

3) Provide a description of the best management practices to be utilized to control erosion and the discharge of sediment and other pollutants in stormwater runoff throughout construction and the design calculations for each sediment basin including total drainage area and storage capacity below the elevation of the mass volume flow outlet device.

See attached file named 6 Sed Basin

4) Provide the name and License or Certification Number of the engineer, geologist, architect, landscape architect, or Certified Professional in Erosion and Sediment Control (CPESC) under which the construction stormwater pollution prevention plan has been developed.

Hunter Wiles 29849 Engineer Name License or Certification Number Profession or Field

III. ANNUAL FEES

The first year of the annual permit fee specified in K.A.R 28-16-56 et seq. as amended is currently $60.00 and can be paid through the KEIMS system at time of submittal. The fee must be paid before this NOI will be processed. An invoice for the annual permit fee will be sent to the contact person requesting a permit until such time as the permittee submits a Notice of Termination (NOT).

Failure to pay the annual fee timely may result in termination of the construction stormwater discharge Authorization.

KEIMS Watermark KSR122863 v1.0

Approved

Project Name: Wichita - Bridger Pawnee Addition Notice of Intent (NOI)

Effective: August 1, 2022 Notice of Intent (NOI) for Discharge of Stormwater Runoff from Construction Activites Page 4 of 4

IV. OWNER OR OPERATOR CERTIFICATIONS

I, the undersigned, certify that a Stormwater Pollution Prevention Plan (SWP2 Plan) will be or has been developed for the construction site described in this NOI and supporting documentation. I further certify that the plan will be implemented at the time construction begins, and, as required by the NPDES general permit for Stormwater Runoff from Construction Activity, will revise the SWP2 plan if necessary.

I understand that continued coverage under the NPDES general permit for Stormwater Runoff from Construction Activities is contingent upon maintaining eligibility as provided for in the requirements and conditions of the general permit, and paying the annual fee.

I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gather and evaluate the information submitted.

Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment.

Carter Wells 11/21/2024 9:02:32 AM Signature (owner or operator) Date

Official Title

V. CONDITIONS AND/OR CONSIDERATIONS OF APPROVAL

Conditions of Authorization - For Official Use Only:

When indicated, Conditions of Authorization are as follows:

NONE

Notes on Consideration – For Official Use Only:

NONE

KEIMS Watermark KSR122863 v1.0

Approved

File details come from the government source that posted it. Updated .