2-MPGC 2025 Sand Bunker Technical Specifications.pdf

PDF 207 KB Posted

Attached to
Sand Bunker Renovation MacDonald Golf Course
Solicitation number
250290
Issued by
Sedgwick County, Kansas

About this file

This document is a Request for Bid (RFB) from the City of Wichita for a Sand Bunker Renovation project at MacDonald Golf Course. The project involves renovating sand bunkers with a completion date of April 30, 2026. The contractor must be certified with Better Billy Bunker for sand bunker construction and will be responsible for renovating bunkers according to the Golf Course Architect's specifications. Interested contractors are required to contact Ron Reese for a course tour and can submit questions through the City's Procurement Portal. The project involves comprehensive bunker renovation, including drainage installation, liner application, gravel layering, polymer binding, and sand placement.

The bid specifies detailed requirements for materials and installation, including using mason sand from Central Sand Company and a specific gravel from Cornejo & Sons. The contractor must follow strict installation procedures, including precise drainage trenching, gravel layering with ST410 POLYMER binder, and sand placement techniques. The project requires hand placement of materials, careful edge shaping, and quality control sampling. Payment will be made per square foot of sand bunker construction, with the contractor responsible for all initial establishment costs, including sodding and initial irrigation. The bid emphasizes precision in construction methods and adherence to the Better Billy Bunker installation specifications.

View the file

Other files

File Type Posted
3-MGC Sand Bunker Renovation - CDs.pdf PDF
1-RFB 250290 Solicitation Documents.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MacDonald Golf Course RFB 250290

Sand Bunker Renovation 1 October 2025

SECTION 1 - GENERAL SPECIFICATIONS

1.1 SCOPE OF WORK

1.1.1 The City of Wichita is seeking bids for Sand Bunker Renovation MacDonald Golf Course from qualified contractors for construction services. The contractor must be certified with Better Billy Bunker for the construction of the sand bunkers.

1.1.2 The contractor shall contact Ron Reese for a course tour to review the scope of work being considered.

There will not be a pre-bid meeting for this project. The contractor may submit questions during the bidding process. Questions will be answered through an addendum posted on the City’s Procurement Portal, https://wichita.gov/procurementportal

1.1.3 The completion date for the Sand Bunker Renovation is April 30, 2026.

1.2 PROJECT CONTACT PERSON

1.2.1 Direct all bidding questions to the Golf Course Architect and to schedule a course tour contact the Golf

Course Superintendent:

Golf Course Architect:

Todd Clark CE Golf Design 14105 Noland Street Overland Park, KS 66221 Cell Number: (913) 233-9279 Email: todd@cegolfdesign.com

Golf Course Superintendent:

Ron Reese MacDonald Golf Course 840 N Yale Ave.

Wichita, KS 67208 Cell Number: (316) 215-2700 Email: RReese@wichita.gov

END OF SECTION

https://wichita.gov/procurementportal mailto:todd@cegolfdesign.com mailto:RReese@wichita.gov

Sand Bunker Renovation 2 October 2025

SECTION 2 - DEFINITION OF TERMS

2.1 DEFINITIONS

2.1.1 Approved Equal: Approved by the Golf Course Architect.

2.1.2 Contractor: The word “Contractor” or “Builder” or “Golf Course Builder” applies with equal meaning to the General Contractor and all other Contractors having a contract with the Owner for other divisions of the work.

2.1.3 Engineer: The Engineer as designated as representative of the Owner.

2.1.4 General Contractor: The Contractor for all parts of the work except those for which separate provision is made in the Form of Proposal.

2.1.5 Golf Course Architect: The professional employed by the Owner to plan and administer Detailed

Drawings and Specifications for renovating a golf course, including overseeing of the golf course during construction.

2.1.6 Irrigation Design Consultant: The professional employed by the Owner to plan and administer Detailed

Drawings and Specifications for designing the irrigation system.

2.1.7 Owner: City of Wichita, Kansas.

2.1.8 Work: Labor and/or materials.

2.2 ABBREVIATIONS

2.2.1 AAN: American Association of Nurserymen

2.2.2 AASHTO: American Association of State Highway and Transportation Officials

2.2.3 AISI: American Iron and Steel Institute

2.2.4 ANSI: American National Standards Institute

2.2.5 ASCE: American Society of Civil Engineers

2.2.6 ASTM: American Society for Testing and Materials

2.2.7 AWG: American Wire Gauge

Sand Bunker Renovation 3 October 2025

SECTION 3 - GENERAL REQUIREMENTS

3.1 SCOPE

3.1.1 The Contractor will provide the essential labor, materials, equipment and services required to complete this work as set forth in the Specifications and indicated on the Plans.

3.2 MATERIAL INVOICES

3.2.1 The Contractor will be provided the Golf Course Architect and Owner a copy of their material invoices at the time of bidding for all specified materials used during the construction activities. These invoices will be used to determine if there are any additional cost that may need to be paid for due to a change in market conditions from the time of bidding and actual delivery time.

3.2.2 In preparation for the Final Payment, a thorough rechecking of the total quantities of materials used will be made against the total bid, and if minimum quantities have not been satisfactorily met, the Contractor will take whatever steps deemed necessary by the Golf Course Architect to balance and correct these deficiencies.

3.3 DISMISSAL

3.3.1 The Contractor, agents and employees will conduct the construction project without inappropriate behavior to patrons (including harassment, profanity, etc.) The Owner will have the absolute rights for personnel dismissal.

3.4 ESTIMATES

3.4.1 All estimates of quantities are "estimates." It is the exclusive responsibility of the Contractor to perform their own take-offs and quantity estimates on which to price and submit their bid. The Contractor's estimates will be viewed as a measure of comparison against those which the Golf Course Architect can check his calculations.

3.4.2 If any significant discrepancies between these quantity estimates are found, the Contractor will notify the Golf Course Architect by writing concerning any such discrepancies. The Golf Course Architect will in turn, answer in writing and document an adjustment to reflect any unusual findings.

3.5 MOBILIZATION

3.5.1 All moving in of equipment and materials will be coordinated with the Owner and will take place only in the areas approved by the Owner. Complete establishment of a construction office and necessary utilities and services shall be fully operational within one (1) weeks of notice to begin work from the Owner.

3.5.2 It will be the responsibility of the Contractor to secure and pay for any and all transport permits to relocate their equipment on site and to keep the street clean from mud from construction vehicles.

3.6 WARRANTY

3.6.1 The Contractor shall provide the Owner a warranty for a period of one (1) year after the golf course project is accepted by the Owner. All necessary repairs shall be the responsibility of the Contractor.

3.7 GPS AS-BUILT PLANS

3.7.1 The Contractor shall provide the Owner GPS “As-Built” Plans of the golf course improvements. It shall include the size of all final bunkers built, disturbed areas, bunker drainage, and any other improvements with each monthly pay request. The Golf Course Architect will not approve any payment without these “As-Built” documents.

Sand Bunker Renovation 4 October 2025

3.7.2 These plans shall be delivered to the Owner and Architect on a CD in a AutoCadd 2000 dwg or Microstation dwg format before final payment is considered.

3.8 RESTORATION OF GOLF COURSE

3.8.1 Any portion of the golf course property outside the scope of work shall be restored as nearly as possible to its original condition at the Contractor's expense. The Owner and Golf Course Architect will decide the restoration method for any damaged areas that need repaired or replaced.

3.8.2 The Contractor will responsible for any damage caused to the existing cart paths. The Owner understands that some construction traffic will have to use the cart paths to cross creeks throughout the golf course. The Contractor shall take special care to protect these paths. The Owner and Golf Course Architect will determine if any paths need to be replaced by the Contractor at the Contractor’s expense.

3.9 PERMITS

3.9.1 The Contractor will be responsible for securing and paying for any licenses or business fees with the

City of Wichita if required.

3.10 BASIS OF PAYMENT

3.10.1 MOBILIZATION shall be paid for at bid unit price per lump sum and such price shall include all labor, materials, equipment and permits to mobilize on the job site.

3.10.2 STORED MATERIALS contractor shall submit with their pay applications the cost for purchasing and storing materials such as sand prior to commencing or during construction activities.

Sand Bunker Renovation 5 October 2025

SECTION 4 - UNDERGROUND UTILITIES

4.1 LOCATION

4.1.1 The Contractor is responsible for contacting all utilities to confirm the presence, absence, and location of buried or proposed underground utilities.

4.2 NOTIFICATION

4.2.1 The Contractor is responsible for preparing an "as built" map indicating the location and type of all underground utilities that are not already located.

4.2.2 The Contractor shall immediately notify the Golf Course Architect with the utilities information.

4.2.3 The Contractor is required to protect any known underground utilities by whatever means necessary to insure no disruption of service, unless coordinated with the agency responsible for that utility.

4.2.4 The Contractor will need to coordinate with utility contractors during the installation of utilities so that interferences are not encountered. No golf course features are to be located over any utilities unless written notification is given by the Golf Course Architect or Owner.

4.3 BASIS OF PAYMENT

4.3.1 Underground utilities are considered incidental to the work and separate payment for these items shall not be made to the contractor.

Sand Bunker Renovation 6 October 2025

SECTION 5 - EROSION AND SEDIMENT CONTROL

5.1 METHODS TO BE EMPLOYED:

5.1.1 Due to the nature of the project, there is no silt fence specified for this sand bunker renovation project.

A sand bunker renovation project is considered more a maintenance improvement and not a total new construction project. We have several small disturbed areas that total less than 0.50 acres per area.

Each area is surrounded by maintained turf which helps keep any soil from washing outside of the disturbed area. The Contractor shall not disturbed areas that have a sum total that is greater than one

(1) acre at any one given time. This keeps our disturbed area below the state of Kansas requirements of one (1) acre of disturbance before a permit is required. All disturbed areas will be sodded for instant turfgrass coverage and playability of the golf course.

5.2 BASIS OF PAYMENT

5.2.1 Erosion and Sediment Control are considered incidental to the work and separate payment for these items shall not be made to the contractor.

Sand Bunker Renovation 7 October 2025

SECTION 6 - LAYOUT AND STAKING

6.1 SCOPE

6.1.1 The Contractor will provide the essential labor, materials, equipment and services required to complete this part of the work as set forth in the Specifications and indicated on the Plans.

6.2 BUNKER LOCATIONS

6.2.1 The Golf Course Architect will locate all of the proposed sand bunkers on the golf course with the

Contractor prior to stripping sod or shaping these bunkers. The Contractor will maintain these paint lines with flags until the bunker is ready to be built.

6.3 PROPERTY LINES

6.3.1 The property lines will be located by the Owner if necessary. The contractor is responsible for any damages located outside of the surveyed property lines.

6.4 FLAGS AND RIBBON

6.4.1 Flags shall be two inches (2") square polyethylene, have a metal stem, and a twelve inch (12") minimum length. A minimum of three (3) different colors is required.

6.5 PAINT

6.5.1 Paint shall be water base marking paint in sixteen ounce (16 oz) cans. A minimum of three (3) different colors are required, one (1) of which shall be fluorescent. A paint gun will also be on-site for use by the Golf Course Architect.

6.6 BASIS OF PAYMENT

6.6.1 Wooden stakes, paint and secured gate are considered incidental to the work and separate payment for these items shall not be made to the contractor.

Sand Bunker Renovation 8 October 2025

SECTION 7 - SITE CLEARING

7.1 GENERAL

7.1.1 There will be no tree removal or site demolition required for this project by the Contractor. The Owner will be responsible for any site clearing if it is deemed necessary.

Sand Bunker Renovation 9 October 2025

SECTION 8 - EARTHWORK

8.1 SOURCES OF FILL MATERIAL

8.1.1 The source of fill material for the proposed construction is generally shown on the Grading Plan.

However, this plan should in no way be construed as anything but approximate. Unless otherwise stated, the Contractor shall assume that no fill material will need to be purchased and that the fill requirements will be balanced by available cuts on site at each disturbed area or designated borrow area..

8.1.2 It is solely the Contractor's responsibility to determine the quantity of cut and fill required to complete the work. The source of fill material will come from designated borrow areas and the Contractor is responsible for cost associated with this work.

8.2 EXISTING CONDITIONS

8.2.1 The Golf Course Architect reserves the right to adjust any proposed grades to meet field conditions or to enhance the character of the golf course or to expedite construction.

8.2.2 Haul distances and routes within the work area are the responsibility of the Contractor as long as they are coordinated and approved by the Golf Course Architect.

8.2.3 All existing sand shall be removed from the bunker floor and the bunker faces to ensure that we have good subgrade material in the bunker floor and topsoil on the faces. The contractor shall bury the sand within the disturbed area with a minimum of 18” of cover over the sand or haul the excavated sand to disposal areas designated by the Golf Course Architect. All existing drainage shall be removed from the bunker and the exit drain line inspected for proper flows.

8.3 TOPSOIL

8.3.1 The Contractor shall remove all grass or vegetation over the areas before stripping topsoil. The Golf

Course Superintendent will spray the limits of disturbance prior to tilling and stripping the topsoil.

8.3.2 Topsoil, where in the judgment of the Golf Course Architect is suitable for saving, shall be removed from all areas to be graded to a depth of at least eight inches (8") and shall be re-spread to a depth of six inches (6") over the subgrade of all areas where grade is altered.

8.3.3 The full depth of topsoil shall be stripped from areas that are to be cut, filled or shaped.

8.3.4 The stockpiles of topsoil shall be made in such a manner to build the bunkers while remaining with the limits of disturbance.

8.4 EARTHWORK

8.4.1 Suitable fill material is any soil that is non-compressible and lends itself to the raising of subgrade to specified level.

8.4.2 Fill material should be reasonably free of organic matter and have a moisture content that lends itself to compaction.

8.4.3 Fill material will be placed in layers not to exceed eight inches (8") and each layer will be compacted by tracking each layer with this the dozer before the next fill layer is laid upon it. All fill areas should be compacted and approved prior to spreading topsoil.

8.5 SHAPING

8.5.1 The Golf Course Architect shall approve the Golf Course Shaper for the project. If, the Contractor’s

Shaper cannot achieve the desired bunker shapes, the Contractor will be required to find a different

Sand Bunker Renovation 10 October 2025 shaper to achieve the desired bunker shape. The Shaper will follow the grading plans with the Golf Course Architect reserving the right to adjust any grades to enhance the character of the golf course.

8.5.2 This phase is also considered the “artistic” part of golf course construction that requires artistry in operating grading equipment. Changes should be expected in the form, shape, and size of golf features during this phase. The Shaper will work to meet the satisfaction of the Golf Course Architect and Owner.

8.6 FINISH GRADING

8.6.1 Finish grading before planting shall be done when the condition of the soil is not too wet so as to allow tracking, or too dry so that the seedbed is “fluffy” and not reasonably compacted. Any areas on the property that have been compacted by construction equipment, trucks, tractors, or storage of materials shall be tilled, fine graded and planted in accordance with the Specifications for the area within which it is located.

8.6.3 All areas to be planted shall be smoothed prior to seeding or sodding. This will require hand rake around each bunker and adjacent to greens. The Contractor shall keep the greens free from any debris or soil that may fall outside the disturbed areas. The Contractor is responsible for repairing any damage to the adjacent green, fairway or rough due to erosion and construction activities.

8.6.4 Any debris, sticks, roots or stones one inch (1") or more in diameter, or any other foreign material coming within the boundaries of the disturbed area shall be removed from the soil surface to a burial site designated by the Golf Course Architect.

8.7 ROCK

8.7.1 The exact texture, depth, hardness and extent of any consolidated rock layers that may be encountered is unknown. Therefore, in the interest of fairness to both the Contractor and the Owner the following definitions and conditions shall be accepted by both as part of this Contract.

1. Consolidated rock layers shall be defined as rock that cannot be removed with an excavator or be ripped by a bulldozer with a ripper shank.

2. Any rock layer that can be excavated or ripped shall be considered as earthwork. All other rock which requires drilling and blasting, hammering or unusual machines shall be compensated for by paying the Contractor for his direct cost plus fifteen percent (15%) for indirect costs or at a negotiated cubic yard price before rock removal commences.

8.8 FILLED BUNKERS

8.7.1 In all filled bunkers the Contractor shall either remove the existing sand or bury 2’ below finish grade.

The Contractor can dispose of sod and spoils in these bunkers being filled in. The Owner will be responsible for providing any fill material and transporting it to the bunkers as needed to accomplish the final shape of the filled in bunkers. The Contractor will be responsible for finish grading and sodding these bunkers.

8.9 BASIS OF PAYMENT

8.9.1 SHAPING shall be paid for as one lump sum price and such price shall include all labor, materials, and equipment necessary to furnish and install as indicated on the drawings and as specified.

8.9.2 FINISH GRADING shall be paid for at bid unit price per acre and such price shall include all labor, materials, and equipment necessary to furnish and install as indicated on the drawings and as specified.

Sand Bunker Renovation 11 October 2025

SECTION 9 – DRAINAGE & IRRIGATION

9.1 SCOPE

9.1.1 It shall be the Contractor’s responsibility to ascertain the sizes, amount, and location of existing drain lines exist prior to construction. It shall be the Contractors responsibility to preserve, repair, or keep functioning all existing drainage on the site.

9.1.2 It shall be the Contractor’s responsibility to ascertain the sizes, amount, and location of existing irrigation sprinkler heads, piping and wiring prior to construction. It shall be the Contractors responsibility to preserve, repair and keep the irrigation systems functioning during construction activities.

9.2 DRAIN PIPE

9.2.1 Corrugated rigid polyethylene plastic sewer pipe – SMOOTH WALL

1. All pipe shall have a smooth walled interior and a corrugated exterior. The sewer pipe shall be manufactured with a minimum pipe stiffness (tested in accordance with ASTM F667) of 50 psi.

Joints shall be gasketed and the seals (gaskets) shall meet the requirements of ASTM Specification F477. ADS, HANCORE or PRINSCO are all acceptable manufacturers for all pipe.

9.3 EXCAVATION

9.3.1 In all drain pipe installations, the ground shall be excavated in open trenches in such directions as required to the depth and width as may be necessary for the proper installation of the drainage system.

The Contractor shall use surveying equipment to verify the pipe has proper fall before beginning the backfill operation.

9.4 INSTALLATION

9.4.1 The backfill bedding for pipe shall consist of suitable soil which shall be placed and tamped solidly under and around the pipe. The backfill shall have a minimum depth of twelve inches (12") above the top of the pipe and shall be carefully compacted into the trench. This part of the backfill shall not contain stones larger than four inches (4") in diameter.

9.5 DRAIN INLETS AND CATCH BASINS

9.5.1 All drain basins (size as noted on drawings) will be located as shown on the Drainage Plans. Rim elevation will be set in the field and approved by the Golf Course Architect. The catch basins will be a perforated drain pipe (size as noted on drawings) positioned vertically with a concrete bottom at a minimum depth of six inches (6”) in the bottom. The cast iron grate will be East Jordan Iron Works, Inc.

#GR6212-M2 or equivalent. During construction a three-foot minimum perforated extension with gravel backfill will be installed for erosion control methods until the grassing operation takes place. During the grassing operations the extension will be removed and the cast iron grate will be installed. All catch basins will either be sodded or have erosion control blanket placed around the inlet as directed by the

9.5.2 Drain basins that are located in a concrete cart path as shown on the Drainage Plans shall be a 12” x

12” square Nyloplast hinged cast iron grate. Rim elevation will be set in the field and approved by the

9.6 PERFORATED DRAIN PIPE

9.6.1 If occasional areas cannot be surface drained properly, due to underground source of water, they shall be drained with a perforated pipe. Pipe shall be “rigid” plastic, 2-wall construction with smooth interior and corrugated exterior and shall conform to a crushing strength not less than one thousand (1,000)

Sand Bunker Renovation 12 October 2025 pounds per linear foot. Washed pea gravel of one-quarter to three-eighths inch (1/4"-3/8") shall be evenly spread two (2”) inches deep in the bottom of all trenches. Upon the gravel layer the drain pipe shall be laid and covered with one-quarter to three-eighths inch (1/4"-3/8") gravel to subgrade surface.

9.7 IRRIGATION MODIFICATIONS

9.7.1 The Contractor is responsible for relocating all lateral lines that are discovered in the field to accommodate the new sand bunkers and proposed improvements. This includes all signal and power wire that is located with the pipe. The pipe and wire shall be installed within the industry standards for golf course irrigation systems.

9.7.2 Impacted irrigation heads adjacent to the new sand bunkers shall be raised or lowered or re-located in the field to accommodate the new sand bunkers and proposed improvements. This includes all signal wire, swing joints and fittings that is required to make sure the irrigation head functions properly. The Contractor shall re-use the existing irrigation head and if the head is damaged it shall be the Contractor’s responsibility to purchase a new irrigation head. The irrigation head and wire shall be installed within the industry standards for golf course irrigation systems.

9.8 BASIS OF PAYMENT

9.8.1 DRAIN PIPE shall be paid for at bid unit price per lineal foot and such price shall include all labor,

9.8.2 CATCH BASINS shall be paid for at bid unit price per each unit and such price shall include all labor,

9.8.3 IRRIGATION MODIFICATIONS are considered incidental to the work and separate payment for these items shall not be made to the contractor.

Sand Bunker Renovation 13 October 2025

SECTION 10 - TRENCHING, BACKFILLING & COMPACTING

10.1 SHEETING & SHORING

10.1.1 Except where banks are cut back on a stable slope, excavation for structures and trenches shall be properly and substantially sheeted, braced, and shored as necessary to prevent caving or sliding, to provide protection for workers and the work, and to provide protection for existing structures and facilities.

10.2 STABILIZATION

10.2.1 Subgrade for catch basins and trench bottoms shall be firm, dense and thoroughly compacted and shall be sufficiently stable to remain firm and intact under the feet of the workers.

10.2.2 Subgrade for catch basins and trench bottoms which are otherwise solid, but which become mucky on top due to construction operations, shall be reinforced with one or more layers of crushed stone or gravel.

10.2.3 All stabilization work shall be performed by and at the expense of the Contractor.

10.3 TRENCH EXCAVATION

10.3.1 The Contractor shall not open more trench in advance of pipe laying than is necessary to expedite the work. All trench shall be closed at the end of the day or properly marked as an open trench in accordance to the local codes.

10.3.2 The alignment and grade or elevation of each pipe line shall be fixed and determined by means of offset stakes. Vertical and horizontal alignment of pipes shall be in conformity with the project requirements.

10.3.8 Pipe embedment materials both below and above the bottom of the pipe shall conform to the requirements shown on the plans, unless otherwise approved by the Golf Course Architect.

10.3.9 After each pipe has been graded, aligned and placed in final position on the bedding material sufficient pipe embedment material shall be deposited and compacted under and around each side of the pipe to hold the pipe in proper position and alignment during subsequent backfilling. Tamped backfill materials shall be placed in uniform layers of not more than six inches (6"), and shall have a moisture content that will insure that maximum density will be obtained when compacted to ninety-five percent (95%) density.

10.4 TRENCH BACKFILL

10.4.1 All trench backfill above pipe embedment shall conform to the requirements the City requirements for

Standard HDPE Installation Detail or at the direction of the Golf Course Architect.

10.4.2 When beneath pavements, hard surfaces, driveways, curbs, gutters, walks, around wet wells or other surface construction or structures, tamped backfill will be require for the full depth of the trench above the granular fill. Tamped backfill materials shall be placed in uniform layers of not more than six inches (6"), and shall have a moisture content that will insure that maximum density will be obtained when compacted to ninety-five percent (95%) density.

10.5 CRUSHED ROCK OR GRAVEL FILLS

10.5.1 Crushed rock or gravel fills shall be placed on suitably prepared sub grades and compacted by vibration or roller.

10.5.2 Crushed rock or gravel shall be free from dust, clay, or trash, and shall be graded one and one-half inch

(1-1/2") to No. 4 as defined in ASTM C33.

Sand Bunker Renovation 14 October 2025

10.6 STRUCTURAL BACKFILL

10.6.1 All backfill material shall consist of loose, damp (not wet) earth having a moisture content such that maximum density of the compacted soil will be obtained. Moisture content shall be distributed uniformly, and water for correction of moisture content shall be added sufficiently in advance that proper moisture distribution and compaction will be obtained.

10.7 DRAINAGE MAINTENANCE

10.7.1 Backfilling shall be done so that water will not accumulate in unfilled or partially filled trenches.

10.8 PROTECTION OF TRENCH BACKFILL IN DRAINAGE COURSES

10.8.1 Where trenches are constructed in ditches or other water courses, backfill shall be protected from surface erosion.

10.8.2 Where the grade of the ditch exceeds three percent (3%), ditch checks shall be installed.

1. Unless otherwise shown on the Plans or directed by the Golf Course Architect, ditch checks shall be rip-rap according to the City standard details.

10.9 DISPOSAL OF EXCESS EXCAVATED MATERIALS

10.9.1 Excavated soil or rock in excess of the amount permitted to be actually installed in trench backfill and debris encountered in excavation work shall be disposed on the work site in areas designated for such material by the Golf Course Architect.

10.10 BACKFILL SETTLEMENT

10.10.1The Contractor shall be responsible for all settlement of backfill that may occur within one (1) year after final completion of the contract in which the backfilling work was performed.

10.10.2The Contractor shall make, or cause to be made, all necessary backfill replacements and repairs or replacements within thirty (30) days after notice by the Golf Course Architect or Owner.

10.11 MEASUREMENT AND PAYMENT

10.11.1Trenching, backfilling and compacting shall be considered with the unit price of drain pipe and a separate payment to the contractor shall not be made.

Sand Bunker Renovation 15 October 2025

SECTION 11 - SAND BUNKERS

11.1 PREPARATION

11.1.1 All bunkers shall follow the Golf Course Architect’s design in size, shape and depth as delineated on the plans or laid out in the field by the Golf Course Architect.

11.2 DRAINAGE

11.2.1 Trenches shall extend a minimum of ten feet (10') into each low area of the bunkers. The trench shall be eight inches (8") wide by a minimum of twelve inches (12") deep. The bottom shall produce a constant grade of not less than one-half percent (.5%). The trenches shall exit to adjacent lakes, streams, or sumps in non-play areas, or as directed in the field by the Golf Course Architect.

11.2.2 Washed gravel of one-quarter to three eighths inch (1/4"-3/8") diameter shall be evenly spread two inch

(2") deep in the bottom of all trenches. Upon the gravel shall be laid the same pipe used in Section 12 - Green Construction. The trenches shall then be backfilled to one inch (1") above grade with the gravel so as to prevent soil erosion onto the gravel. The portion outside the bunker shall be backfilled with gravel.

11.2.3 Drainage pipe shall be “rigid” plastic, 2-wall construction with smooth interior and corrugated exterior and shall conform to a crushing strength not less than one thousand (1,000) pounds per linear foot.

Washed pea gravel of one-quarter to three-eighths inch (1/4"-3/8") shall be evenly spread two (2”) inches deep in the bottom of all trenches. Upon the gravel layer the drain pipe shall be laid and covered with one-quarter to three-eighths inch (1/4"-3/8") gravel to subgrade surface.

11.2.4 All drain pipes shall have a 14 gauge tracer wire included in the trenches with any drain pipe installed outside of the sand bunker shape.

11.3 BUNKER LINER INSTALLATION

11.3.1 CERTIFIED INSTALLER: The Contractor shall be a certified installer of Better Billy Bunker and will not be allowed to deviate from the Better Billy Bunker specifications. The Contractor must not cause any portion of the Better Billy Bunker warranty to be voided or disallowed due to construction means and methods utilized by the Contractor.

11.3.2 BUNKER CAVITY PREPERATION: The Better Billy Bunker System must be installed in an approved bunker cavity. The area to be covered with the specified liner shall be water settled and mechanically compacted with a hand operated compacting machine to a minimum dry density of ninety-five percent (95%). Absolutely no loose soil shall remain in the bunker cavity prior to liner placement. No liner material will be placed in bunker until Golf Course Architect has approved the bunker shape, depth and compaction of the bunker cavity.

11.3.3 BUNKER EDGE: The bunker edge will be protected with Zoysiagrass sod that is rolled over the upper edge of the bunker shaped.

11.3.4 GRAVEL LAYER BLANKET: The crushed 3/8” limestone gravel will be from Cornejo & Sons, Wichita, KS with a contact number of (316) 522-5100. A layer of approved gravel (3/16”-1/4”) (4.5mm-6mm) shall be placed over the entire floor of the bunker at a depth of 2” (51mm) deep. This gravel shall be brought up to the edge of the bunker. Contractor will not be allowed to use any machines of any type to spread the gravel within the bunker cavity. Gravel must be spread by hand to ensure no damage occurs to the prepared cavity or bunker edges. Contractor must protect the vertical bunker edges at all times when dumping gravel along the bunker edges. The gravel selected will be sent by the Contractor to Turf Diagnostics and Design, 613 1st Street, Linwood Kansas 6602, phone: (913) 723-3700 soils lab or other approved lab for testing of the sand and gravel to ensure both materials meet the minimum “bridging” standard. This common standard is based on engineering principles that rely on the largest 15% of the sand particles "bridging" with the smallest 15% of the gravel particles. The gravel must be placed evenly and raked smooth.

Sand Bunker Renovation 16 October 2025

Prior to placement of the pea gravel blanket or approved crushed limestone aggregate the Contractor will provide the Golf Course Architect with a record drawing (As-built) of the installed drainage. In addition to the record drawing Contractor will provide to Golf Course Architect digital photos, on CD Media, showing the complete drainage system prior to the gravel layer being installed and approved by Golf Course Architect or Owner.

11.3.5 ST410 POLYMER BINDER APPLICATION: ST410 POLYMER shall be sprayed by a certified and trained Better Billy Bunker installer. Using proper pressure spray equipment, a uniform layer of ST410 POLYMER shall be applied to the gravel in the bunker at a rate 1 gallon of ST410 POLYMER per 30- 35 square feet. The gravel must be dry (less than 15% as tested by the certified installer) at application time. The treated bunker shall be allowed to cure for approximately 24 hours prior to sand installation. NOTE: ST410 POLYMER will penetrate approximately ½ - 1” (12mm - 25mm) depth of the gravel. A sturdy pliable layer of glued gravel will be the result.

11.3.6 INSPECTION AND QUALITY CONTROL: After 12-24 hours, the initial ST410 POLYMER application will have cured. Contractor will walk and inspect every square foot (meter) of each bunker at the end of the curing process. Any areas not to have received the specified rate of polymer will be marked with turf paint and re-sprayed prior to calling for a final inspection by Golf Course Architect. Improper application or omitting the inspection process and follow up polymer application will leave areas weak and the pea gravel loose. It is installer’s responsibility to inspect and maintain the highest standards on when installing the Better Billy Bunker.

11.4 SAND

11.4.1 The bunker sand will be a mason sand from Central Sand Company, Inc, Valley Center, KS with a contact number of (316) 721-3230. The sand will be spread evenly throughout the bunker at a depth of not less than five inches (5") uncompacted and should settle out to not less than four inches (4") compacted. All sand samples must be approved by the Golf Course Architect before they are delivered.

11.4.2 After entire bunker is lined using the above procedures, sodding has been completed and written approval given, the Contractor will clean the cavity with a hand blower to remove all foreign debris.

Absolutely no loose soil shall remain in the bunker cavity prior to sand placement.

11.4.3 After approval, the sand shall be spread evenly throughout at a minimum compacted depth of four (4”) inches on slopes, four (4”) inches on the bottom of the cavity. Contractor will spread the sand against the bunker edges upon completing the installation of the sand in the specific bunker. Contractor will not be allowed to use any machines of any type to spread the sand within the bunker cavity. Sand must be spread by hand to ensure no damage occurs to the prepared cavity or bunker edges. Contractor must protect the vertical bunker edges at all times when dumping sand along the bunker edges. After spreading, all sand shall be water settled and compacted with a hand operated compaction machine. If any sand bunker has less than four (4”) inches of sand, the Contractor shall be responsible for installing additional sand to meet specifications on sand depth.

11.5 SAND PLACEMENT

11.5.1 The sand will be spread evenly throughout the bunker at a depth of not less than five inches (5") uncompacted and should settle out to not less than four inches (4"). The sand will be kept free of debris until the course is turned over to the Owner at the completion of the project.

11.5.2 No sand shall be hauled to or deposited in the bunkers if damage to the course will result from such hauling. All sand shall be hauled to the bunkers when the ground is dry and solid to a depth sufficient to support the hauling vehicle.

11.5.3 No sand shall be hauled to any bunker until it has been approved by the Golf Course Architect as ready to receive sand.

Sand Bunker Renovation 17 October 2025

11.6 EDGING

11.6.1 The edging of the bunkers is the responsibility of the Contractor and will be coordinated with the Golf

Course Architect.

11.6.2 Prior to edging, the Golf Course Architect will determine which bunkers are ready for edging and he will mark the perimeter of the sand with paint provided by the Contractor as specified.

11.6.3 The Contractor shall edge the bunkers to provide for an eight inch (8") vertical face at the sand edge and then work the bottom to a concave shape. The base shall be compacted until it is smooth and firm.

11.6.4 All loose materials will be removed by the Contractor prior to providing a smooth firm bottom ready to receive sand.

11.6.5 Any damages caused by the edging or filling operations shall be repaired by the Contractor to a smooth and harmonious grade and either seeded or sodded as determined by the Golf Course Architect.

11.6.6 No sand shall be placed in the bunker prior to the completion of the above steps. Sand may be placed immediately before sodding to reduce damage to new turf. Sand can be spread at a later date. All sand should be placed over the drain lines to prevent siltation of drains.

11.7 QUALITY CONTROL

11.7.1 Quality control sampling is very important for insuring consistent material throughout the project. Prior to commence with the project the Contractor shall submit a particle test from a Certified Laboratory of the specified sand as a base line to compare with sand delivered throughout construction activities.

One quality control sample, that is representative of the sand should be taken at the fifty (50%) percent mark of delivered material to the site. The sample must be sent to the same Certified Laboratory for testing to compare with the original test result.

11.8 BASIS OF PAYMENT

11.8.1 SAND BUNKER CONSTRUCTION shall be paid for at bid unit price per square foot and shall include all labor, materials, and equipment necessary to furnish and install as indicated on the drawings and as

Sand Bunker Renovation 18 October 2025

SECTION 12 - GRASSING

12.1 SCOPE OF WORK

12.1.1 The intent of this section is to insure that the golf course is planted correctly in the opinion of the Golf

Course Architect.

12.1.2 It shall be the Contractor's responsibility to ascertain the sizes, amount and extent of materials necessary for proper execution of this section of work.

12.1.3 After areas to be planted have been prepared, graded smooth, and approved by the Golf Course

Architect, they shall be grassed during the period designated below or unless otherwise directed in writing by the Golf Course Architect.

12.1.4 Final inspection and acceptance will be at the end of the construction activities. Acceptance will be based upon a satisfactory stand of turf, which is determined by the Golf Course Architect.

12.2 GRASS SOURCES

12.2.1 All seed and sod sources must be approved by the Golf Course Architect prior to purchase and delivery to the project site.

12.2.2 The Golf Course Architect shall have the right to inspect all turfgrass delivered and planted, and the right to reject any loads of sod delivered that are deemed unsuitable for planting or that has been planted.

12.3 FERTILIZER

12.3.1 Fertilizer will be applied by the Golf Course Superintendent at his discretion.

12.4 SOD

12.4.1 All Fescue Sod shall be 100% Turf Type Tall Fescue from with the source being approved by Golf

Course Architect.

12.4.2 All Zoysiagrass sod will be the variety of Meyers or approved by Golf Course Architect. It shall be free from Bermuda grass and noxious weeds. It shall have a soil layer no less than one-half inch (1/2") and no more than three-quarters of an inch (3/4") in thickness and shall have enough moisture to allow for proper rolling and handling. It is assumed that the sod shall be delivered in big rolls and pads.

Variation of this standard must be approved by the Golf Course Architect prior to delivery of the sod to the site.

12.4.3 All sod will be commercially grown within four hundred (400) miles of the golf course. It shall be cut and delivered within twenty-four (24) hours. It shall be free from noxious weeds and grasses. It shall have a soil layer no less than one-half inch (1/2") and no more than three-quarters of an inch (3/4") in thickness and shall have enough moisture to allow for proper rolling and handling. It is assumed that the sod shall be cut eighteen inches (18”) wide and be rolled in six foot (6') length. Variation of this standard roll must be approved by the Golf Course Architect prior to delivery of the sod to the site.

12.4.4 The contractor will be responsible for all initial irrigation procedures associated with the establishment and rooting of the sod.

12.4.5 No sod shall be laid in place until the area to be sodded has been approved by the Golf Course

Architect as being ready to receive sod.

12.4.6 Sod will be laid and staked as described above and may need to be rolled after soaking to smooth the surface.

12.5 PROTECTION AND ESTABLISHMENT

Sand Bunker Renovation 19 October 2025

12.5.1 After seeding or sodding the area shall be protected against traffic or other use by erecting barricades as needed, and by placing approved warning signs at appropriate intervals.

12.5.2 Immediately after all areas have been planted, the Contractor will water to saturation the planted areas.

After this initial watering and approval of the golf hole by the Owner, it shall be the Owner's responsibility to maintain the planted areas.

12.5.3 Satisfactory establishment is when the sod has rooted down and has survived the winter conditions.

Any areas that do not grow or green up in the spring shall be replaced by at the Contractor’s expense.

12.6 BASIS OF PAYMENT:

12.6.1 FESCUE SOD shall be paid for at bid price per square yard and such price shall include all labor,

12.6.2 ZOYSIAGRASS SOD shall be paid for at bid price per square yard and such price shall include all labor, materials, and equipment necessary to furnish and install as indicated on the drawings and as