2-Memorial Elementary School Parking Lot Sketch.pdf
PDF 340 KB Posted
- Solicitation number
- Not on record
- Issued by
- Pennsylvania
About this file
This sketch plan document pertains to parking lot improvements at Memorial Elementary School in Bloomsburg, Pennsylvania, under the Bloomsburg Area School District. The project encompasses asphalt base repair, milling, asphalt overlay, line striping, and fence relocation. The parking lot is located at the intersection of West 5th Street and Jefferson Street. The sketch indicates full-depth new pavement work totaling approximately 618 linear feet with a width of 22 feet, along with sub-base widening of one foot and asphalt wearing course overlay. The plan shows ADA stall locations with slope requirements of less than two percent, fence relocation to a new position, and a three-foot-wide base repair area. The design specifies Superpave asphalt mixture with PG 64S-22 wearing course and a 1.5-inch mill depth.
The sketch plan uses a horizontal scale of one inch equals ten feet and was prepared on July 20, 2026 by Livi Civil Engineering, with contact information at 888-987-1993. The document identifies the specific pavement notch requirements at four inches white waterborne material and establishes repair limits and material specifications for the contractor. No specific contract pricing, timeline, or response date information is contained within this sketch plan document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1-Memorial Elementary Project Manual 7.27.26.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
X X
X X
X X
X X
X X X
X X
X X
X X
X
XXXXXXXXXXXXXXXXXXXXXXXXXXX
X X X
X X
X
XXX
X X
X
X X X
X X
X X
X X
X
OH
OH
OH
OH
OH
OH
OH
OH
OH
OH
OH
OH
OH
OH
OH
OH
OH
OH
OH
OH
OH
OH
OH
OH
X X
X X
9'
18'
9'
18'
26'
50'
JEFFERSON ST.
W
T H
S T
R E
E T
147'
63'
26'
22'
30'
1'
FENCE TO BE
RELOCATED TO
THIS LOCATION
4'' WHITE WATERBORNE
4' MILL PAVEMENT
NOTCH
FULL DEPTH
NEW PAVEMENT
FULL DEPTH
NEW PAVEMENT
618'
9'
22'
PREPARED FOR
LOCATION
2 9 E . M A I N S T R E E T B L O O M S B U R G , P A 1 7 8 1 5 P H O N E : 8 8 8 . 9 8 7 . 1 9 9 3 w w w . l i v i c c i v i l . c o m
SKETCH PLAN
07.20.2026
W 5TH STREET AND JEFFERSON STREET
BLOOMSBURG AREA SCHOOL DISTRICT
MEMORIAL ELEMENTARY SCHOOL PARKING LOT
N
10 10 20 FT0
HORIZONTAL SCALE: 1 INCH = 10 FEET
APPROXIMATE BASE REPAIR LIMITS - 3' WIDE
FULL DEPTH PAVEMENT
FENCE RELOCATION
ASPHALT WEARING COURSE (OVERLAY)
ADA STALL LOCATION (< 2%)
SUB BASE WIDENING (1')
1.5" MILL
LEGEND
X X
SUPERPAVE ASPHALT MIXTURE DESIGN
WEARING COURSE
PG 64S-22, <0.3 MILLION ESAL'S
9.5MM MIX, 1.5" DEPTH, SRL-L
SUPERPAVE ASPHALT MIXTURE DESIGN
BASE COURSE
PG 64S-22, <0.3 MILLION ESAL'S
25.0MM MIX, 4.5" DEPTH
NO 2A SUBBASE, 6" DEPTHCOMPACTED SUBBGRADE
STANDARD ASPHALT PAVEMENT
NOT TO SCALE
File details come from the government source that posted it. Updated .