This is a Lead-Based Paint Specification document prepared by Terracon Consultants, Inc. for Opportunity Home San Antonio (the Owner) regarding lead hazard removal at Alazan Apache Courts, a 685-unit multi-family residential community in San Antonio, Texas originally constructed in 1939. The project involves abatement of lead-based paint hazards identified at concentrations at or above the EPA definition of 1.0 mg/cm² across various interior and exterior components of the residential facility. Lead-based paint inspections were conducted between May and September 2025, with findings documented in separate inspection and risk assessment reports. The specification establishes comprehensive requirements for qualified contractors, including mandatory pre-bid and preconstruction meetings prior to project commencement. The Owner reserves the right to determine the final total of components to be abated based on project budget and feasibility considerations, and all bidders must provide unit pricing for each work task or component to facilitate potential change order requests should final quantities differ from estimates.

The specification requires contractors to hold current State of Texas licensing as general contractors and certification as EPA-licensed Lead Renovation Firms with certified Lead Renovators. All work must comply with EPA, OSHA, and applicable state and local regulations, including respiratory protection protocols, worker medical examinations, and comprehensive decontamination and clearance procedures. Contractors are responsible for all project costs including mobilization, labor, materials, hazardous waste disposal, permit fees, and containment preparation. The project includes provisions for interim control work and component removal and replacement, with off-site paint stripping preferred where feasible. Final clearance is contingent upon passing visual inspections and EPA-compliant dust wipe sampling with results compared to the EPA's November 2024 Final Rule standards (5 micrograms per square foot for floors, 40 micrograms per square foot for interior windowsills, and 100 micrograms per square foot for window troughs). The specification also references a Limited Asbestos Survey Report identifying asbestos-containing materials, including exterior CMU texture and door caulking, which workers must be trained to handle though disturbance of these materials is excluded from the lead abatement scope.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Lead-Based Paint Specification Alazan-Apache Courts 1011 S. Brazos San Antonio, Texas December 23, 2025 Terracon Project No. 9025P137

Prepared for:

Opportunity Home San Antonio San Antonio, Texas

Jeff A. Delise Jason M. Maloney

Senior Project Manager Authorized Project Reviewer

Lead Abatement Project Designer

#2090105

6000 Northwest Parkway, Suite 100 San Antonio, Texas 78249 P 210.641.2112

TABLE OF CONTENTS

INTRODUCTION

SCOPE OF WORK AND PROJECT COORDINATION

Scope of Work

2.1.1 Lead-Based Paint

General Personnel Meetings Pre-Job Submittals Post-Job Submittals Special Reports Contingency Plan

REGULATORY OVERVIEW

TEMPORARY FACILITIES

General Electrical Service First Aid Fire Extinguishers Toilet Facilities Building Security Storage

WORKER PROTECTION

General Worker Training Medical Examinations Protective Clothing Additional Protective Equipment Washing Facilities Eyewash Station

RESPIRATORY PROTECTION

Description of Work General

WORK AREA PREPARATION AND CONTAINMENT

General

COMPONENT REMOVAL AND REPLACEMENT

General

PAINT REMOVAL

General

PROJECT DECONTAMINATION

General

WORK AREA CLEARANCE

General Clearance

DISPOSAL OF WASTE MATERIAL

General

Attachments:

Positive Lead-Based Paint Results and Locations

Limited Asbestos Survey Report dated November 4, 2025

Alazan-Apache Courts■ San Antonio, Texas December 23, 2025 ■ Terracon Project No. 9025P137

INTRODUCTION

Terracon Consultants, Inc. has prepared this Specification, which addresses the previously identified lead-based paint hazards at the subject property. The subject property is a multi-family, residential community with multiple housing structures encompassing 685 individual dwelling units originally constructed in 1939. The structures were slab-on-grade, concrete-framed construction with concrete veneer and metal roof systems. Interior finishes consisted of a combination of drywall or woodwalls, drywall ceilings, and various vinyl/ceramic floor tile/carpeted flooring finishes.

Terracon performed lead-based paint inspections and risk assessment activities between May 6 and May 17, 2024. Findings are summarized in Terracon’s Lead-Based Paint Inspection and Risk Assessment Report dated July 2024. Subsequently, Terracon performed a Lead-Based Paint Inspection of the remaining 623 residential units and associated building exteriors between August 4 and September 13, 2025. Findings are summarized in Terracon’s Lead- Based Paint Inspection Report dated September 16, 2025.

Terracon and the Owner will not be responsible for the contractor’s means or methods used during the proposed work activities. The listing or mention of any method of installation, erection, fabrication, or workmanship shall not operate to make Terracon an agent of the Owner or contractor but shall be for the sole purpose of setting a standard of quality for the finished work.

SCOPE OF WORK AND PROJECT COORDINATION

The following information is the scope of work to be bid and completed as part of this project.

The Owner reserves the right to reject any and all bids from Abatement Contractors. The Owner reserves the right to waive any irregularities in the bids or bidding process if it is in the best interest of the Owner to do so. The Owner reserves the right to award this project to the lowest responsible bidder therefore, this project may not necessarily be awarded to the bidder with the lowest price.

The scope of work (choice of abatement option) shall be at the discretion of Opportunity Home San Antonio (Owner). The Contractor shall consult with Terracon and the Owner prior to commencing LBP work activities. The abatement contractor shall be responsible for completing and submitting the Occupant Protection Plan.

The abatement contractor shall be responsible for completing and submitting the Occupant Protection Plan prior to the start of abatement activities. A written occupant protection plan shall be unique to each residential dwelling or child-occupied facility and be developed prior to abatement.

The occupant protection plan shall describe the measures and management procedures that will be taken during the abatement.

The occupant protection plan must be prepared and signed by a certified supervisor or project designer and must be kept at the worksite by the certified lead abatement firm at all times during any abatement activity.

December 23, 2025 ■ Terracon Project No. 9025P137

Scope of Work

Lead was identified at a concentration at or above the EPA LBP definition of 1.0 mg/cm2 and/or classified as LBP per the XRF device Performance Characteristic Sheet at various locations within the residential facility. The locations and components identified with LBP are presented as an attachment to this design.

Individual components that are classified positive should be considered as being LBP and managed or abated appropriately. Abatement of these components are an option for the owner; however, Owner reserves the right to consider project budget and feasibility as factors when determining final total of components included in the project.

The Owner shall have the right to request bids in a format of their choosing. Along with the bid, it is recommended unit pricing for each work task/component be provided. Change orders will be limited in approval by the Owner.

If the final quantity of abated materials differs from estimated quantity, a change order may be requested from the owner at the indicated unit rate. The Owner reserves the right to reject any and all change orders from the Abatement Contractor.

Bidders shall inform themselves of the conditions under which the work is to be performed at the worksite and all obstacles which may be encountered during the work. Bidders shall also inform themselves of all other relevant matters concerning the work to be performed, and, the bidder, if awarded the contract, shall not be allowed any extra compensation by reason of any matter or thing concerning which the bidder might have fully informed themselves, but failed to do so prior to bidding.

The contractor agrees that their bid will cover all abatement activities and expenses necessary to complete this project. Therefore, the bid shall include all charges for mobilization, labor, materials, hazardous materials removal/disposal expenses, reimbursables, etc., as needed to complete this project.

General

The term “Contractor” will be used throughout and refers to the contractor performing lead-based paint hazard control work. “Terracon,” “Project Designer,” and “Project Monitor” shall be considered synonymous in this specification. “Opportunity Home” and “Owner” shall be considered synonymous.

The Contractor will be a licensed general contractor by the State of Texas. In addition, the Contractor shall also be certified and licensed as a Lead Renovation Firm with certified Lead Renovators by the EPA and the State of Texas.

The Contractor shall be responsible for inspecting the site prior to pricing the project to confirm the scope of the work. Any quantities listed by the Project Designer in the lead hazard specifications, LBP inspection and risk assessment, or other related documents are provided as estimations. The Contractor is responsible for measurements and quantifying the LBP work.

December 23, 2025 ■ Terracon Project No. 9025P137

The Contractor shall furnish and is responsible for all costs including, but not limited to: permit fees, containment preparation, scaffolding, labor, materials, services, insurance, and equipment necessary to carry out the scope of work. All work including impacting LBP-affected material will be in accordance with this specification, applicable Environmental Protection Agency (EPA), Occupational Safety and Health Administration (OSHA) regulations, and any other applicable state and local government regulations.

Abatement activities, where planned, shall be performed under proper notification and timelines in accordance with state and local regulation.

Work schedules shall be submitted and approved by the Owner prior to the start of any abatement activities.

The Contractor has and assumes the responsibility of proceeding in such a manner that he/she offers his/her employees a workplace free of recognized hazards causing or likely to cause death or serious injury. The Contractor shall be responsible for performing the work and disposal so that lead dust/fume levels do not exceed the established levels of the personal protective equipment provided to employees.

The Contractor will be responsible for all costs associated with employee monitoring to meet all applicable OSHA requirements.

The Contractor is responsible for all costs, including additional visits, should the Project Designer and/or the Project Monitor determine that the Contractor failed a final inspection. Notification and scheduling of the final inspection during the project is the responsibility of the Contractor. The Contractor will allow a minimum notice of twenty-four

(24) hours unless the Project Monitor and/or Project Designer and the Contractor agree upon a different time frame.

Contractor shall coordinate all LBP activities including lead work, clearances, potential re-cleaning, re-testing, build back, and re-occupation of residents with the Owner and Project Monitor. Use of areas within identified units by occupants shall be determined by the Owner.

The Contractor shall be responsible to adhere to all security requirements imposed by the Owner.

The Contractor shall be aware of the findings associated with Terracon’s Limited Asbestos Survey Report included as an Attachment to these specifications. The limited asbestos survey identified asbestos-containing exterior concrete masonry unit block fill and exterior door caulking throughout the property. The abatement (i.e. disturbance) of these materials is not included in the scope of work for LBP abatement but may be located adjacent to LBP-impacted components. However, training of workers working around ACM’s would be required.

December 23, 2025 ■ Terracon Project No. 9025P137

Personnel

A. Personnel

1. Personnel performing interim control work: The workers and supervisor(s) must be EPA-certified renovators. If the workers are not EPA-certified renovators, the supervisor must be accredited in addition to being a certified renovator. A documented training must then be performed by the supervisor for the workers.

2. Personnel performing component removal and replacement (abatement): The workers and supervisor(s) must be accredited.

B. Competent Person

1. A competent person, as defined in the OSHA lead in construction standard 29 CFR 1926.62, employed by the Contractor must be outside each work area during LBP activities to monitor activity, ensure containment security, provide information to visitors, and provide access to the work area.

2. The competent person must be an EPA-certified renovator and have experience with projects of similar type and size.

3. The competent person, employed by the Contractor, shall be bilingual in the appropriate languages when employing workers who do not speak fluent English.

C. Employees

1. The Contractor is responsible for the behavior of workers within his/her employment. If at any time during the contracted work, any of his/her employees are judged to exhibit behavior unfitting for the area or judged to be a nuisance by the Owner or the Project Designer, the Contractor shall remove such employee(s) immediately from the project.

2. The Contractor shall be responsible for compliance with the following concerning employee behavior:

a. Under no circumstances are alcohol, drugs, or any other type of controlled substances permitted on the property.

b. Firearms are not permitted on the property.

c. All workers are restricted to the construction project site only.

d. All workers must conform to the following basic dress code when in public areas of the project confines: long pants, shirts, no tank tops, no shorts, no bare backs.

December 23, 2025 ■ Terracon Project No. 9025P137

e. The Contractor is responsible for disposal of all trash brought on the property by his/her employees; including drink cans, bottles or other food containers and wrappers.

f. Eating, drinking, and smoking are not allowed in the containment area(s).

3. Failure to adhere to these rules could result in criminal prosecution and/or removal from the property.

Meetings

A. Mandatory Preconstruction Meeting

1. A mandatory pre-bid meeting shall be held prior to bidding the project. The purpose of the pre-bid meeting is to finalize the scope of work review the requirements of the job and confirm and agree on the on the exact number, location, and choice of abatement option. The Contractor’s representative at this meeting must be able to commit to the exact number, location, and choice of abatement options that will be addressed at this meeting.

2. A mandatory preconstruction meeting shall be held prior to starting the project.

The purpose of the preconstruction meeting is to finalize the work schedule and review the requirements of the job. The Contractor’s representative at this meeting must be able to commit to schedule and project requirements that will be addressed at this meeting.

Pre-Job Submittals

A. The Owner reserves the right to review and approve product, equipment, materials, and procedural submittals.

B. Submit one (1) complete, bound set of pre-job submittals to the Owner at least five

(5) working days prior to start of work. Work is prohibited until the submittal package has been reviewed and approved by the Owner. A copy of the submittals shall be kept in a three-ring binder (project log) by the Contractor at the project site.

1. Employee List: Provide copies of lists of supervisors and workers, along with their LBP accreditations, to be utilized on the project.

2. Medical Surveillance: Include individually signed forms by each worker to be utilized on the project documenting that each is actively involved in a company employee medical surveillance program.

3. Respirator Training: Copies of most recent fit testing records, individually signed for each worker to be utilized on the project. Include individually signed statements from each employee that they have received training in compliance with 29 CFR 1910.134.

4. Project Schedule: Time schedule for the project, outlining the proposed start, setup, clearances, etc. for the various phases of the project.

December 23, 2025 ■ Terracon Project No. 9025P137

5. Initial Exposure Assessment: As required by the OSHA lead in construction standard

29 CFR 1926. 62.

6. Any other programs or training as outlined by the OSHA and EPA standards.

Post-Job Submittals

Submit One (1) complete, bound set of post-job submittals to the Owner following the final completion of the work. Requests for final payment will not be approved until the submittal package has been reviewed and approved by the Owner.

1. Affidavits: The Contractor’s affidavit of payment of debts and claims, affidavit of release of liens, and consent of surety company to final payment.

2. Waste Manifest: Waste shipment record receipt of utilized landfill which acknowledges the Contractor’s delivery(s) of waste material. Include date, quantity of material delivered, and signature of authorized representative of landfill. Also, include name of waste transporter and all other requirements per instructions the waste manifest form.

3. Daily Supervisor Log: A copy of all daily logs showing the following: name, date, entering and leaving time, company or agency represented, reason for entry for all persons entering the work area, employee's daily air monitoring data as required by the OSHA standards, and written comments by inspectors, industrial hygienists, Designers and visitors.

4. Workers: Copies of lead-based paint accreditation cards and respirator training and fit test documentation of all new employees hired during the project.

5. Special Reports: All documents generated under Section 2.7.

Special Reports

General: Except as otherwise indicated, submit special reports to the Project Monitor or Project Designer within one (1) day of occurrence requiring the special report, with copies to others affected by occurrence. Also keep a copy in the project logbook.

A. Reporting Unusual Events: When an event of unusual and significant nature occurs at site (examples: failure of negative pressure system, rupture of temporary enclosures), prepare and submit a special report to the Project Designer immediately, listing chain of events, persons participating, response by Contractor's personnel, evaluation of results or effects, and similar pertinent information. When such events are known or predictable in advance, advise the Project Designer in advance at earliest possible date.

December 23, 2025 ■ Terracon Project No. 9025P137

B. Reporting Accidents: Prepare and submit reports of significant accidents, at site and anywhere else work is in progress. A complete copy of the accident report shall be provided to the Owner and the Project Designer within 24-hours of the accident occurrence. Record and document date and actions; comply with industry standards for reporting accidents. For this purpose, a significant accident is defined to include events where personal injury is sustained, or property loss of substance is sustained, or where the event posed a significant threat of loss or personal injury.

Contingency Plan

Contingency Plan: The Contractor shall prepare a site-specific contingency plan for emergencies including fire, accident, power failure, negative pressure system failure, supplied air system failure (if applicable), evacuation of injured persons for both life threatening and non-life threatening, or any other event that may require modification or abridgment of decontamination or work area isolation procedures. Include in this plan specific procedures for decontamination or work area isolation. Note that nothing in this specification should impede safe exiting or providing adequate medical attention in the event of an emergency. The plan will be completed prior to beginning any on-site work and shall be kept on-site at all times.

REGULATORY OVERVIEW

The Contractor shall assume full responsibility and liability for compliance with all applicable federal, state and local regulations pertaining to work practices, hauling, disposal, and protection of workers, visitors to the site, and persons occupying areas adjacent to the site.

A. The following regulations published by the Environmental Protection Agency (EPA):

1. “Lead-Based Paint Activities: Training, Certification, and Work Practice Requirements,” 40 CFR Part 745

2. “Resource Conservation and Recovery Act (RCRA),” 40 CFR Part 260, 261, 262, 263, 264

B. The following regulations published by the U.S. Department of Labor, OSHA:

1. “Respiratory Protection,” Title 29, Part 1910, Section 134 of the Code of Federal Regulations.

2. Construction Industry, Title 29, Part 1926, of the Code of Federal Regulations.

3. “Access to Employee Exposure and Medical Records,” Title 29, Part 1910, Section 20 of the Code of Federal Regulations.

4. “Hazard Communication,” Title 29, Part 1926, Section 59 of the Code of Federal Regulations.

5. “Specifications for Accident Prevention Signs and Tags,” Title 29, Part 1910, Section 145 of the Code of Federal Regulations.

6. “Lead in Construction Standard,” 20 CFR 1926.62.

December 23, 2025 ■ Terracon Project No. 9025P137

7. Fall Protection Standard, 29 CFR 1926 subpart M.

C. The following documents published by the American National Standards Institute:

1. "Fundamentals Governing the Design and Operation of Local Exhaust Systems," Z9.2 1979.

2. "American National Standard for Respiratory Protection ¬Respiratory Use Physical Qualifications for Personnel," Z88.6 1984.

3. "Practices for Respiratory Protection," Z88.21992.

D. The following guidelines published by the U.S. Department of Housing and Urban Development (HUD):

1. “Guidelines for the Evaluation and Control of Lead-Based Paint Hazards in Housing,” Second Edition, July 2012. Specifically Chapters 8 through 15.

E. The following regulations published by the State of Texas:

1. Texas Administrative Code title 25 Part 1 Chapter 295 Subchapter I – Texas Environmental Lead Reduction

TEMPORARY FACILITIES

General

A. Provide temporary facilities as required herein or as necessary to carry out the work.

B. Use qualified tradesmen for installation of temporary services and facilities. Locate, modify and extend temporary services and facilities where they will serve the project adequately and result in minimum interference with the performance of the work.

C. The Contractor is responsible for the lock and tag out of all power sources.

Electrical Service

A. It is assumed electricity will be available at the structure.

B. Ground Fault Protection: The contractor shall use outlets equipped with ground fault circuit interrupters (GFCI), reset button and pilot light, for plug-in connection of power tools and equipment. All GFCI shall be located outside of the containment areas. All powered equipment shall be connected to a GFCI.

C. If necessary, the Contractor will be responsible for installing temporary lighting adequate to provide sufficient illumination for safe work and traffic conditions in every area of work.

December 23, 2025 ■ Terracon Project No. 9025P137

First Aid

A. A minimum of one first aid kit shall be located in the clean rooms. Additional first aid kits may be required at the discretion of the Contractor or as required by law shall be located throughout the work areas.

Fire Extinguishers

A. Comply with the applicable recommendations of NFPA Standard 10 - "Standard for Portable Fire Extinguishers." Locate fire extinguishers where they are most convenient and effective for their intended purpose, however, provide not less than one extinguisher in each work area equipment room and one in the clean rooms of the personnel decontamination units.

Toilet Facilities

A. The Contractor must provide toilet facilities and toiletries (i.e., toilet paper). No toilet facilities or toiletries are available at the site.

Building Security

A. The Contractor is responsible for constructing and maintaining secure containment areas including the entry/exit areas. The regulated areas shall be restricted to authorized, trained, and protected personnel. These may include the Contractor’s employees, employees of approved subcontractors, state representatives, and any other designated individuals. The Contractor shall establish a list of authorized personnel prior to job start and post this list in the clean rooms of the decontamination facilities. Work locations will be appropriately identified utilizing warning signs as required by OSHA and all city, state, and federal regulations. The Contractor is responsible for creating and maintaining a secure work area during the entire project.

B. The Contractor is responsible for maintaining secure entry/exit locations at the facility while work is being completed. The Contractor is responsible for coordinating building security issues with the Owner.

C. Access to the work area shall be through a single decontamination system (if a negative pressure enclosure is needed) or an airlock. All other means of access (doors, windows, hallways, etc.) shall be blocked or locked so as to prevent entry to or exit from the work area. The only exceptions to this rule are the waste pass-out air lock, which shall be sealed except during the removal of bagged lead waste from the work area, and emergency exits in case of fire or accident.

Emergency exits within the work area shall not be locked from the inside; however, they shall be sealed with pre-scored polyethylene sheeting and high-visibility tape until needed. Keep a razor knife taped to the polyethylene sheeting for emergency egress.

Storage

A. Supply temporary storage required for storage of equipment and materials for duration of project. Trailer and storage dumpsters will be maintained in areas designated by the Owner.

December 23, 2025 ■ Terracon Project No. 9025P137

WORKER PROTECTION

General

A. Provide worker protection as required by OSHA, state, and local standards applicable to the work. The Contractor is solely responsible for enforcing worker protection requirements at least equal to those specified in this section.

B. Each time the work area is entered the Contractor shall require all persons to put on new disposable coveralls, new head cover, and a clean respirator. Protective clothing may be worn over street clothes. Proceed through shower room to equipment room and put on work boots.

C. Workers shall not eat, drink, smoke, chew gum or chew tobacco in the work areas, the equipment rooms, the load out areas, or the clean rooms.

D. Lighters and matches are not allowed in the work areas, the equipment rooms, the load out areas, or the clean rooms.

E. Whenever personnel exit the work area(s), they shall perform the following procedures and shall not leave the workplace wearing any clothing or equipment worn during the work day:

a. Vacuum themselves off using a HEPA vacuum.

b. Remove protective clothing in the contaminated change room and place them in an approved impermeable disposal bag.

c. Wash hands and face at the site, don appropriate disposable or uncontaminated reusable clothing; move to an appropriate facility;

shower.

d. Change to clean clothes prior to leaving the physical boundary designated around the lead control area.

Worker Training

A. Train all workers in accordance with 29 CFR 1926 and Texas state regulations regarding the dangers inherent in handling lead paint, breathing lead dust and fume, proper work procedures and personal and area protective measures.

Medical Examinations

A. Provide medical examinations for all workers. Examination shall at, a minimum, meet OSHA requirements as set forth in 29 CFR 1926.

Protective Clothing

A. Provide disposable full-body coveralls and disposable head covers, and require that they be worn by all workers in the work area. Provide a sufficient number for all required changes, for all workers in the work area.

December 23, 2025 ■ Terracon Project No. 9025P137

B. Boots: Provide sturdy, over the ankle work boots with non-skid soles and, where required by OSHA, foot protection for all workers. Do not allow boots to be removed from the work area for any reason, after being contaminated with lead dust.

C. Gloves: Provide work gloves to all workers and require that they be worn at the appropriate times. Do not remove gloves from work area. Dispose of work gloves as contaminated waste at the completion of the project. Chemical resistant gloves must be provided when using chemical strippers to remove lead-based paint.

D. Safety Glasses: Provide OSHA approved safety glasses with side shields to be worn at all times in all construction areas. Thoroughly clean and decontaminate before removing them from work area at the end of the project.

E. Hard Hats: Provide OSHA approved hard hats for the duration of the project. Hard hats should be worn at all times when on the project site. Thoroughly clean and decontaminate hats before removing them from work area at the end of the project.

Additional Protective Equipment

A. The appropriate level of respiratory protection (i.e. half-face air purifying respirators with replaceable HEPA filters) disposable coveralls, head covers and footwear covers shall be provided by the Contractor for the Owner, the Project Designer, Project Monitor and other authorized representatives who may inspect the job site.

Washing Facilities

A. Provide washing facilities to be used by all workers when exiting the work area.

a. Provide temporary sink with hot and cold water supply. Supply a sufficient quantity of soap and towels for the workers and authorized visitors.

Eyewash Station

A. Where the eyes of employees may be exposed to injurious corrosive materials, suitable facilities for flushing of the eyes shall be provided within the work area for immediate emergency use.

RESPIRATORY PROTECTION

Description of Work

A. Instruct and train each worker involved in lead-based paint disturbance work in proper respirator use and require that each worker always wear a respirator, properly fitted on the face, in the work area from the start of any operation which may cause airborne lead dust until the work area is completely decontaminated. Use respiratory protection appropriate for the fiber level encountered in the workplace or as required for other toxic or oxygen-deficient situations encountered.

December 23, 2025 ■ Terracon Project No. 9025P137

General

A. Provide workers with personally issued and marked respiratory equipment approved by the National Institute for Occupational Safety and Health (NIOSH) and suitable for the lead exposure levels in the work areas according to OSHA Standard 29 CFR

1926.62 and other possible contaminants employees might be exposed to during the project.

B. Provide respiratory protection from the time the first operation involved in the project requires contact with lead-based paint (including construction of decontamination units, construction of airtight barriers/barricades, and placing of plastic sheeting on walls) until acceptance of final clearance test results by the Project Monitor.

C. The minimum respiratory protection for this project shall be half-face air purifying respirators (APRs) with HEPA filters. For using the half-face, negative pressure APRs, supply a sufficient quantity of respirator HEPA filters (P100), so that workers can change filters as necessary. Require that respirators be wet-rinsed, and filters discarded or covered with duct tape, each time a worker leaves the Work Area. Store respirators and filters at the job site in the changing room and protect totally from exposure to lead prior to their use. Respirator cartridges must be replaced whenever a worker experiences increased breathing resistance.

D. Respirator fit testing shall be performed as a minimum at the beginning of the project, at any change in respiratory protection equipment, and at any time during the project if requested by the employee.

E. Do not allow the use of single-use, disposable or quarter-face respirators for any purpose.

WORK AREA PREPARATION AND CONTAINMENT

General

A. Completely isolate each work area from other parts of the building so as to prevent contamination beyond the isolated area.

B. Appropriate signage per 29 CFR 1926.62 shall be posted at entrances, critical barriers, and barrier tape for each work area.

C. Boundary Requirements: Provide physical boundaries around the lead control area by roping off the area designated in the specification or providing curtains, portable partitions or other enclosures to ensure that airborne concentrations of lead will not reach 30 micrograms per cubic meter of air outside of the lead control area.

D. Perform work without damage or contamination of adjacent areas. Where existing work is damaged or contaminated, restore work to its original condition or better.

E. All LBP work areas shall be pre-cleaned using HEPA vacuums.

December 23, 2025 ■ Terracon Project No. 9025P137

F. The Contractor must post signs clearly defining the work area and warning occupants and other persons not involved in LBP activities to remain outside of the work area. To the extent practicable, these signs must be in the primary language of the occupants.

These signs must be posted before beginning the project and must remain in place and readable until project completion.

G. Before beginning work, the Contractor must isolate the work area utilizing 6-mil poly sheeting so that no dust or debris leaves the work area while the work is being performed. In addition, the Contractor must maintain the integrity of the containment by ensuring that any plastic or other impermeable materials are not torn or displaced, and taking any other steps necessary to ensure that no dust or debris leaves the work area while the renovation is being performed. The Contractor must also ensure that the work area is installed in such a manner that it does not interfere with occupant and worker egress in an emergency.

H. Children are not to be in areas where 6-mil poly is being used due to suffocation hazards.

I. Work Areas

1. Interior work areas:

a. The Owner or Tenant shall remove all personal, moveable objects from the work area, including furniture, rugs, and window coverings, etc. If they cannot be moved, the Contractor shall cover them with 6-mil polyethylene sheeting with all seams and edges taped or otherwise sealed.

b. The Contractor shall close and cover all ducts opening in the work area with taped-down 6-mil polyethylene sheeting.

c. Close windows and doors in the work area. Doors must be covered with 6-mil polyethylene sheeting. Doors used as an entrance to the work area must be covered with at least two flaps of 6-mil polyethylene sheeting in a manner that allows workers to pass through while confining dust and debris to the work area (Z-flaps).

d. Fans and HVAC system should be turned off.

e. Cover the floor surface, including installed carpet, with taped-down 6-mil polyethylene sheeting in the work area 10 feet beyond the perimeter of surfaces undergoing renovation, repair, and/or painting or a sufficient distance to contain the dust, whichever is greater. Floor containment measures may stop at the edge of the vertical barrier when using a vertical containment system consisting of impermeable barriers that extend from the floor to the ceiling and are tightly sealed at joints with the floor, ceiling and walls.

f. Use precautions to ensure that all personnel, tools, and other items, including the exteriors of containers of waste, are free of dust and debris before leaving the work area.

December 23, 2025 ■ Terracon Project No. 9025P137

2. Exterior work areas:

a. Close all doors and windows within 20 feet of the renovation and repair.

b. Ensure that doors within the work area that will be used while the job is being performed are covered with 6-mil polyethylene sheeting in a manner that allows workers to pass through while confining dust and debris to the work area.

c. Daily cleanup of horizontal surfaces within 20 feet of disturbed surfaces is required.

d. Cover the ground with 6-mil polyethylene sheeting extending 10 feet beyond the perimeter of surfaces undergoing renovation and repair or a sufficient distance to collect falling paint debris, whichever is greater, unless the property line prevents 10 feet of such ground covering. Ground containment measures may stop at the edge of the vertical barrier when using a vertical containment system. If work is above the ground floor, sheeting should extend 20 feet.

e. Remove all movable items (playground equipment, toys, sandboxes, outdoor and furniture) to at least a 20-foot distance from working surfaces. Items that cannot be readily moved to a 20-foot distance must be sealed with taped protective sheeting.

f. Do not conduct exterior work if the wind speeds are greater than 20 miles per hour of if dust and debris cannot be adequately contained.

g. Post warning signs on the building and at the 20-foot perimeter around the building.

COMPONENT REMOVAL AND REPLACEMENT

General

A. If listed in the attachment, the Contractor shall perform the following. This section applies to any LBP affected component removal and replacement. Contractor must submit manufacturer information for all like materials utilized for component replacement for approval.

1. Prepare Work Area

a. Prepare work area in accordance with Section 7.0 of this specification.

b. Avoid high-dust jobs and procedures.

c. Plan how the new component will be installed.

i. Whenever possible, use new, energy efficient window, door, and insulating systems.

December 23, 2025 ■ Terracon Project No. 9025P137

2. Mist Component

a. Lightly mist component with water (unless nearby electrical systems).

2. Score Seams

a. Score all painted seams with a sharp knife

b. Remove or Bend Back Fasteners

c. Remove screws, nails, staples, etc. as necessary with hand tools

3. Pry Components

a. Use a flat pry instrument and hammer to pry the component from substrate

4. Wrap Components

a. Wrap and seal bulk components in poly and take to a secured waste storage area along pathways covered in plastic.

6. HEPA Vacuum

a. Vacuum any dust or chips in the area where the component was located

7. Replace Component

a. Replace with new components per manufacturer instructions as approved by the Owner.

b. Replacements components will be in like-in-kind

PAINT REMOVAL

General

A. If listed in the attachment, the Contractor shall perform the following. This section applies to any LBP removal. Off-site paint removal is preferred, where feasible.

1. Prepare Work Area

a. Prepare work area in accordance with Section 7.0 of this specification.

b. Avoid high-dust jobs and procedures.

c. Plan how the component will be removed.

December 23, 2025 ■ Terracon Project No. 9025P137

2. Remove component

a. Score all painted seams with a sharp knife

b. Remove or Bend Back Fasteners

c. Remove screws, nails, staples, etc. as necessary with hand tools

d. Include any affected hardware to be stripped of LBP

3. Use of off-site stripping facilities

a. Wrap and seal bulk components in poly and take to a secured waste storage area along pathways covered in plastic.

b. Tag the component with identifying information that will direct its eventual reinstallation at its original location.

c. If a 3rd party paint stripping entity is performing stripping work, inform them that the components are LBP affected.

4. When chemically removing LBP on-site, the contractor shall:

a. Utilize Enviro Klean® Safety Peel 1 and OverCoat chemical stripping agents, or an approved equal, in accordance with the recommendations of the manufacturer.

b. Final Cleaning of Surfaces: Prepare wet detergent wash.

Workers must wear eye shields and chemically resistant gloves when working with this solution. Thoroughly scrub stripped surface to remove as much remaining lead residue as possible. Following wet detergent wash, perform a final wash with clear water to remove any traces of detergent. Sponges used in the clean-up process may not be reused and must be placed in double 4 mil or single 6 mil plastic bags, which will be sealed, labeled, and placed in the secure waste storage area.

Surfaces must be allowed to dry thoroughly before repainting.

c. Painting/sealing: After complete drying, prepare the substrate and seal all surfaces where lead-based paint was removed with a primer or encapsulant which is compatible with the substrate or as specified by the Owner and/or Architect.

December 23, 2025 ■ Terracon Project No. 9025P137

5. If the specified methods above are not feasible, the following shall apply:

a. Any Chemical Stripping Agents and neutralizers shall be applied in accordance with the recommendations of the manufacturer.

b. Caustic Stripper Neutralization: Caustic strippers shall be neutralized in accordance with manufacturer's recommendations. Provide workers with proper protective equipment, including but not limited to;

protective clothing (non-paper), chemically resistant gloves, eye protection and respiratory protection with filters selected for the hazards to be encountered.

c. Remove Stripper Sludge: Place lead containing stripper sludge in corrosion-proof containers and place in a secure waste storage area. The surface from which lead-based paint has been removed shall be thoroughly scrubbed, while still damp from the stripper, in accordance with the manufacturer's recommendation.

Monitor pH of the neutralizing solution to ensure it has not become neutralized in the process.

d. If the pH exceeds 6.5, or the solution becomes overly soiled, change solution. The surface shall be tested with litmus paper following this process. If the litmus paper turns pink, the acid has effectively neutralized the alkali.

If litmus turns blue continue scrubbing until satisfactory results are achieved.

e. Final Cleaning of Surfaces: Prepare wet detergent wash.

Workers must wear eye shields and chemically resistant gloves when working with this solution. Thoroughly scrub stripped surface to remove as much remaining lead residue as possible. Following wet detergent wash, perform a final wash with clear water to remove any traces of detergent. Sponges used in the clean-up process may not be reused and must be placed in double 4 mil or single 6 mil plastic bags, which will be sealed, labeled, and placed in the secure waste storage area.

Surfaces must be allowed to dry thoroughly before repainting. A grayish film indicates that significant lead residues remain and the cleaning process must be repeated. If a white powder appears, the surface is Alkaline and requires further neutralization.

December 23, 2025 ■ Terracon Project No. 9025P137

f. Painting/sealing: After complete drying, prepare the substrate and seal all surfaces where lead-based paint was removed with a primer or encapsulant which is compatible with the substrate or as specified by the Owner.

6. Painting/sealing: After complete drying, prepare the substrate and seal all surfaces where lead-based paint was removed with a primer or encapsulant which is compatible with the substrate or as specified by the Owner.

B. See note in Section 2.2 General for further information on asbestos-containing materials located adjacent to components scheduled for impact as part of the scope of work.

PROJECT DECONTAMINATION

General

A. Final Cleaning:

1. HEPA Vacuum: All surfaces in work area. Start at point farthest from main entrance and finish vacuuming back at that point. Begin at top of each room and work down.

Sequence to avoid passing through rooms already cleaned.

2. Mist critical barriers sheeting and remove.

3. HEPA vacuum area previously covered by critical barrier sheeting.

4. Perform wet detergent wash of all surfaces. Begin at point farthest from main entrance, work from top to bottom. Take care not to damage existing finishes and surfaces. Change cleaning mixture in accordance with manufacturer's recommendations or minimum after each room.

5. Wiping Work Area

a. The work area should be cleaned using a three-container method. Fill two buckets with clean water and place them in the work area with the container of cleaning solution.

b. Pour cleaning solution onto a clean cloth. Wring excess solution into one of the buckets without placing the cloth into the bucket. Wipe the work surface with the cloth. Add more cleaning solution to the cloth and continue wiping until the entire surface area has been covered. Discard all cloths used in this procedure in the disposal bag.

c. Dip and wring out a clean cloth in the first rinse bucket. Wipe off the work area. Rinse the cloth in the first bucket again and wring out thoroughly. Rinse the cloth in the second bucket and wring out thoroughly again.

December 23, 2025 ■ Terracon Project No. 9025P137

d. Continue to clean the work surface with the cloth and rinse using this procedure until the entire work surface has been cleaned. Wipe off all tools to remove any dust.

e. NOTE: The rinse water in the bucket should be changed periodically. The frequency will vary depending on the level of contamination.

6. Perform clear water wash of all surfaces in same manner as wet detergent wash.

7. After all surfaces in work area are allowed to dry, complete final HEPA vacuuming of all surfaces in same manner as first HEPA vacuuming.

8. After final cleaning perform a complete visual inspection of the entire work area including: all surfaces, ceiling, walls, floor, doorways, windows, surfaces previously covered with critical barrier sheeting, and other openings; look for debris from any source, residue on surfaces, dust or other matter. If any debris, residue, dust or other matter is found repeat final cleaning and continue decontamination procedure from that point. When the area is visually clean, complete the certification at the end of this section. Visual inspection is not complete until confirmed in writing, on the certification, by Project Monitor.

WORK AREA CLEARANCE

General

Notification and scheduling of the final inspection during the project is the responsibility of the Contractor. If abatement was performed, the contractor shall notify the regulating entity 24 hours before the project’s completion. It is recommended that the contractor assumes the potential of an initial failure of clearance sampling into the projected schedule. Additional cleaning, sample re-collection, and sample re-analysis should be considered prior to build-back activities and re-occupation of residents.

Contractor shall coordinate all LBP activities including lead work, clearances, potential re-cleaning, re-testing, build back, and re-occupation of residents with the Owner and Project Monitor. Use of areas within identified units by occupants shall be determined by the Owner.

Clearance

A. No sooner than one hour after the final cleaning and after the work area is completely dry, the following test procedure shall be performed:

1. A final visual inspection shall be conducted by the Project Monitor who is also an EPA and Texas certified lead-based paint inspector/risk assessor (i.e., clearance examiner). When applicable, an interior clearance area should have no evidence of settled dust or paint chips or paint-related debris following a cleanup effort. If dust, paint chips, or paint-related debris are observed, the Contractor will be required to reclean the work area(s) at their expense.

December 23, 2025 ■ Terracon Project No. 9025P137

2. Once the visual inspection has passed, clearance dust sampling shall be performed for interior work areas in accordance with EPA and Texas regulations. Samples should be collected in accordance with Appendix 13.1 and Chapter 15 of the HUD Guidelines and ASTM E 1728.

3. Clearance wipe samples must be analyzed for lead by a laboratory recognized by the EPA under the National Lead Laboratory Accreditation Program (NLLAP) for analysis of lead in dust.

4. Composite sampling is not allowed for clearance dust wipe samples.

5. Wipe samples should be collected after any application of a sealant on a rough, unfinished, horizontal surface, such as a floor or windowsill, not before.

6. Compare the laboratory results to the EPA's Final Rule, issued on November 12, 2024, effective January 13, 2025, with compliance after January 12, 2026 clearance standards for residual lead dust provided below:

Lead Hazards: Any Reportable Level Clearance (Floors): 5 micrograms per square foot (µg/ft2) Clearance (Interior windowsills): 40 µg/ft2 Clearance (Window troughs): 100 µg/ft2

7. Where applicable, the project monitor shall ensure that the work has been properly completed and that no deteriorated paint identified as part of the scope of work remains in the work area(s).

8. Where exterior interim control measures are performed: Exterior clearance following exterior paint work consists of a visual assessment for visible surface dust, debris and residue.

9. Where exterior abatement is performed: Soil and exterior dust sampling is required. Sampling shall consist of at least one sample taken from an adjacent exterior horizontal surface including, but not limited to, a patio, deck, porch, stoop, or common area and composite soil samples taken next to the foundation or from the dripline and any applicable bare soil areas adjacent to the exterior abatement that children, age 6 years and under, frequent. Clearance soil lead concentrations will be required to be less than 1,200 ppm in non-play areas and less than 400 ppm in play areas.

10. The Project Monitor shall immediately report the final clearance dust wipe sampling results to the Project Designer. Clearance results will be provided within 24 hours following receipt by the analytical laboratory.

December 23, 2025 ■ Terracon Project No. 9025P137

11. If clearance dust sampling fails, the work areas will need to be re-cleaned and re-tested at the Contractor’s expense.

It is recommended that the contractor assumes the potential of an initial failure of clearance sampling into the projected schedule. Additional cleaning, sample re-collection, and sample re-analysis should be considered prior to build-back activities and re-occupation of residents.

DISPOSAL OF WASTE MATERIAL

General

A. Per EPA, waste generated as part of LBP activities conducted at residences (which include single family homes, apartment buildings, public housing, and military barracks) is also household waste, and such wastes are excluded from RCRA’s hazardous waste management and disposal regulations. Generators of residential LBP waste do not have to make a RCRA hazardous waste determination.

B. Large waste material should be wrapped in heavy-duty sheeting (6-mil polyethylene or equivalent), and all seams should be sealed with tape during storage and transported to the appropriate landfill.

C. Small waste material (including lead-contaminated protective clothing) should be placed in heavy-duty bags (double 6-mil or 4-mil polyethylene or equivalent). The bags should be securely taped shut with gooseneck closure.

D. The waste should be stored in a designated secure (locked) area. Dumpsters should have lids and be padlocked.

E. An enclosed dumpster will be used to haul waste material to the disposal site. No rental vehicles or trailers shall be used. Vehicle selection, vehicle covers, and work practices shall assure that no lead is dispersed into the environment during the loading, transport and unloading activity, and that material is placed in the waste site without breaking any seals.

F. The Contractor shall transport the bags of waste material to the appropriate landfill.

The sealed plastic bags shall be placed into the burial site unless the bags have been broken or damaged.

APPENDIX A

Attachments

Limited Asbestos Survey Report Alazan-Apache Courts | San Antonio, Texas November 04, 2025 | Terracon Project No. 90257494

Facilities | Environmental | Geotechnical | Materials

APPENDIX A

ASBESTOS SURVEY SAMPLE SUMMARY

November 04, 2025 | Terracon Project No. 90257494

Facilities | Environmental | Geotechnical | Materials

APPENDIX A - ASBESTOS SURVEY SAMPLE SUMMARY

Sample

ID

Material Material Location

Asbestos Containing

A-01, 02, 03, 04, 05, 06, 07 Interior Plaster – Off-White

Utilized as…