2-EAJSA WWTP Sludge Canopy Repairs IFB Specifications.pdf
PDF 12 MB Posted
- Attached to
- Sludge Canopy Repairs
- Solicitation number
- US.263475
- Issued by
- Northampton County, Pennsylvania
About this file
This is an Invitation for Bid (IFB) specifications document issued by the Easton Area Joint Sewer Authority (EAJSA) in Pennsylvania for structural repairs to the sludge canopy at the Easton Wastewater Treatment Plant (WWTP). The project scope includes roof framing demolition, parapet rehabilitation, installation of new roof panels and gutters, drainage system improvements, structural steel cleaning and recoating, roof framing leveling, and associated repairs to canopy support components. The project has an expected duration of 140 days. A non-mandatory pre-bid meeting is scheduled for 10:00 AM on Tuesday, December 1, 2026, at the Administration Building located at the WWTP. Site visits are available by appointment only until 3:00 PM on Tuesday, December 15, 2026, at 50 South Delaware Drive, Easton, PA 18042. Prospective bidders are urged to register as plan holders on the designated bidding website at https://pennbid.bonfirehub.com, where all official notifications, addenda, and bidding documents will be posted. This is a General Contract award.
The specifications document does not contain explicit information regarding pricing terms, set-asides, incumbent contractors, funding sources, or contract amounts. All official bidding documents, addenda, and updates will be made available exclusively through the designated Bonfire Hub portal, and bidders are advised that neither the Owner nor Engineer will be responsible for documents obtained from alternative sources.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1-EAJSA WWTP Sludge Canopy Repairs IFB Drawings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BIDDING DOCUMENTS
WASTEWATER TREATMENT PLANT
SLUDGE CANOPY REPAIRS
ISSUED FOR BIDDING
CHA CONSULTING, Inc.
ONE EAST BROAD STREET, SUITE 310
BETHLEHEM, PA 18018
TELEPHONE 610.865.3000
FAX 610.861.0181
CHA PROJECT NO. 103023
11/19/2026
[THIS PAGE INTENTIONALLY LEFT BLANK]
EASTON AREA JOINT SEWER AUTHORITY
TABLE OF CONTENTS 000110-1
TABLE OF CONTENTS
PROCUREMENT AND CONTRACTING REQUIREMENTS
001116 Advertisement for Bids .......................................................................................................... 2 pages 002113 Instructions to Bidders ........................................................................................................ 19 pages
PROCUREMENT FORMS AND SUPPLEMENTS
004113 Bid Form ................................................................................................................................ 5 pages 004117 Agreement of Surety .............................................................................................................. 1 page 004313 Bid Bond ................................................................................................................................ 2 pages 004336 List of Proposed Subcontractors ............................................................................................. 1 page 004513 Experience Questionnaire ..................................................................................................... 3 pages 004519 Affidavit of Non-Collusion ................................................................................................... 1 page
CONTRACTING AND PROJECT FORMS AND SUPPLEMENTS
005200 Agreement ............................................................................................................................. 7 pages 006000 Contractor’s Affidavit of Payment of Debts and Claims ....................................................... 1 page 006010 Contractor’s Affidavit of Release of Liens ........................................................................... 2 pages 006100 Performance Bond ............................................................................................................... 4 pages 006150 Payment Bond ........................................................................................................................ 4 pages 006172 Waiver Of Liens .................................................................................................................... 3 pages 006216 Sample Certificate of Insurance ............................................................................................ 1 page
CONDITIONS OF THE CONTRACT
007200 General Conditions ............................................................................................................. 71 pages 007343 Pennsylvania Prevailing Wage Rate Requirements ............................................................. 2 pages
007346.1 PA L&I Form LLC-25 Blank ............................................................................................... 2 pages
007346.13 PA Prevailing Wage Determination Schedule
007346.2 Public Works Employment Verification Act ......................................................................... 1 page
007346.3 Public Works Employment Verification Form....................................................................... 1 page 007300 Supplementary Conditions ................................................................................................. 12 pages
DIVISION 01 – GENERAL REQUIREMENTS
011000 Summary of Work ................................................................................................................. 3 pages 012000 Measurement and Payment ................................................................................................... 2 pages 012100 Allowances ............................................................................................................................. 2 pages 012300 Alternates ............................................................................................................................... 2 pages 012600 Contract Modifications Procedures ....................................................................................... 3 pages 012900 Payment Procedures ............................................................................................................... 4 pages 013000 Project Meetings .................................................................................................................... 2 pages 013200 Construction Progress Documentation .................................................................................. 5 pages 013300 Submittal Procedures ............................................................................................................. 5 pages 014000 Quality Requirements ............................................................................................................ 6 pages 014200 References .............................................................................................................................. 2 pages 015000 Temporary Facilities and Controls ....................................................................................... 9 pages 016600 Product Storage and Handling Requirements ....................................................................... 3 pages 017300 Execution Requirements ........................................................................................................ 5 pages 017329 Cutting and Patching ............................................................................................................. 4 pages 017423 Final Cleaning ........................................................................................................................ 3 pages 017700 Closeout Procedures.............................................................................................................. 5 pages 017836 Warranties .............................................................................................................................. 3 pages 017839 Project Record Documents .................................................................................................... 4 pages
TABLE OF CONTENTS 000110-2
DIVISION 05 – METALS
051200 Structural Steel Framing ........................................................................................................ 3 pages
DIVISION 09 – FINISHES
099600 High-Performance Coatings .................................................................................................. 5 pages
END OF SECTION
ADVERTISEMENT FOR BIDS
EASTON, PENNSYLVANIA SLUDGE CANOPY REPAIRS
The Easton Area Joint Sewer Authority (Owner) is requesting Bids for the construction of the following Project:
The Project includes the following Work:
Structural repairs to the sludge canopy including, but not limited to, roof framing demolition, parapet rehabilitation, installation of new roof panels and gutters, drainage system improvements, structural steel cleaning and recoating, roof framing leveling, and associated repairs to canopy support components at the Easton WWTP. The WWTP is owned by the City of Easton and is leased to the Easton Area Joint Sewer Authority.
Bids are requested for the following Contract: General Contract
The Project has an expected duration of 140 days.
Information and Bidding Documents for the Project can be found at the following designated website:
https://pennbid.bonfirehub.com
Bidding Documents may be downloaded from the designated website. Prospective Bidders are urged to register with the designated website as a plan holder, even if Bidding Documents are obtained from a plan room or source other than the designated website in either electronic or paper format. The designated website will be updated periodically with addenda, lists of registered plan holders, reports, and other information relevant to submitting a Bid for the Project. All official notifications, addenda, and other Bidding Documents will be offered only through the designated website. Neither Owner nor Engineer will be responsible for Bidding Documents, including addenda, if any, obtained from sources other than the designated website.
A non-mandatory Pre-Bid meeting will be held at 10:00 AM on Tuesday, December 1, 2026 in the Administration Building at the WWTP. If you do not attend the Pre-Bid meeting, a site visit is strongly encouraged.
Site visits will be held by Appointment Only, at 50 South Delaware Drive, Easton, PA 18042 until 3:00 PM on Tuesday, December 15, 2026. Contact: Jeffrey J. Morgan, P.E., SC Engineers/EAJSA Engineer at 484-347-1336 or
JJMSCENGRS@AOL.COM.
Questions will be accepted until 3:00 PM on Tuesday, December 15, 2026; All questions must be submitted through PennBid.
This project is subject to the Pennsylvania Prevailing Wage Act, approved August 15, 1961, P.L. 987 (Act No. 442), as amended and supplemented, and reference is made to the prevailing minimum wage rates applicable to this project which have been promulgated by the Secretary of Labor and Industry. Bidders shall prepare their Bids after giving consideration to the applicability of said Pennsylvania Wage Act to the work involved and all other laws and regulations, state or federal, applicable to such projects.
Each Bid must be accompanied by Bid security in the form of a certified check, bank check, irrevocable letter of credit, or Bid bond (on the form included with the Bidding Documents) in an amount equal to ten (10%) percent of the Bid total.
It is a requirement of this Contract that Bidder shall have a minimum five (5) year, five (5) project documented experience in the type of Work required by this Project.
Bidders, subcontractors, their workers and any persons providing labor and products to the Project shall be persons lawfully permitted to work in the United States and the Commonwealth of Pennsylvania.
Bids will be received online via the PennBid Program until 10:00 AM prevailing time on Tuesday, December 22, 2026 at which time they will be opened.
Bids may be modified or withdrawn at any time prior to the opening of Bids.
An Authority representative will open the Bids through the PennBid Program at the Authority’s offices at the address listed above, upon the expiration of the Bid deadline at 10:00 AM prevailing time on Tuesday, December 22, 2026, and read aloud the Bid results. Bidders, other interested persons, and the public may attend the opening of the Bids. After the Bid opening, the results will be available for viewing at the PennBid website.
After the Bid opening, Bids may be withdrawn only by complying with Commonwealth of Pennsylvania laws and regulations. A summary of such laws and regulations is given in the Instructions to Bidders (Document 00100).
The apparent low Bidder and the next two lowest Bidders must submit, to the Engineer, originals of the Bidding Documents within two (2) business days from the date of the Bid opening.
Successful Bidder will be selected by Owner at a later date. The Authority Board will first consider the award of the contract, at its regular meeting scheduled for Tuesday, January 19, 2027 at 5:00 PM at the above EAJSA address, or any public meeting of the Board thereafter.
Bids shall remain open for a period of 60 days from the date of Bid opening unless award is delayed by a required approval from a governmental agency, the sale of bonds, or the award of a grant or grants, in which event the Bids shall remain open for a period of 120 days from the date of Bid opening. See Instructions to Bidders for other provisions on the time available for acceptance of Bids.
As a precondition of being awarded a Contract, Successful Bidder, and its subcontractor(s) are required, to provide confirmation of compliance with Act 141 of 2022, the “Public Works Employment Verification Act”.
The OWNER hereby reserves the right, which is understood and agreed to by all Bidders, to reject any or all Bids and to waive any omissions, errors, defects, or irregularities in any Bid.
DAVID HOPKINS, CHAIRMAN
INSTRUCTIONS TO BIDDERS 00 21 13-i
SECTION 00 21 13
INSTRUCTIONS TO BIDDERS
TABLE OF CONTENTS
ARTICLE 1 - DEFINED TERMS
ARTICLE 2 - COPIES OF BIDDING DOCUMENTS
ARTICLE 3 - QUALIFICATIONS OF BIDDERS
ARTICLE 4 - EXAMINATION OF BIDDING DOCUMENTS, OTHER RELATED DATA, AND
SITE
ARTICLE 5 - PRE-BID CONFERENCE
ARTICLE 6 - SITE AND OTHER AREAS
ARTICLE 7 - INTERPRETATIONS AND ADDENDA
ARTICLE 8 - BID SECURITY
ARTICLE 9 - CONTRACT TIMES
ARTICLE 10 - LIQUIDATED DAMAGES
ARTICLE 11 - SUBSTITUTE AND “OR-EQUAL” ITEMS
ARTICLE 12 - SUBCONTRACTORS, SUPPLIERS, AND OTHERS
ARTICLE 13 - PREPARATION OF BID
ARTICLE 14 - BASIS OF BID; COMPARISON OF BIDS
ARTICLE 15 - SUBMITTAL OF BID
ARTICLE 16 - MODIFICATION AND WITHDRAWAL OF BID
ARTICLE 17 - OPENING OF BIDS
ARTICLE 18 - BIDS TO REMAIN SUBJECT TO ACCEPTANCE
ARTICLE 19 – EVALUATION OF BIDS AND AWARD OF CONTRACT
ARTICLE 20 - CONTRACT SECURITY AND INSURANCE
ARTICLE 21 - SIGNING OF AGREEMENT
ARTICLE 22 - SALES AND USE TAXES
ARTICLE 23 - NONDISCRIMINATION IN EMPLOYMENT
ARTICLE 24 - LAWS AND REGULATIONS
INSTRUCTIONS TO BIDDERS 00 21 13-ii
TABLE OF ARTICLES (Alphabetical by Subject)
Subject Article
Award of Contract
Basis of Bid; Comparison of Bids
Bid Security
Bids to Remain Subject to Acceptance
Contract Security and Insurance
Contract Times
Copies of Bidding Documents
Defined Terms
Evaluation of Bids and Award of Contract
Examination of Bidding Documents, Other Related Data, and Site
Interpretations and Addenda
Laws and Regulations
Liquidated Damages
Modification and Withdrawal of Bid
Nondiscrimination in Employment
Opening of Bids
Pre-Bid Conference
Preparation of Bid
Qualifications of Bidders
Sales and Use Taxes
Signing of Agreement
Site and Other Areas
Subcontractors, Suppliers and Others
Submittal of Bid
Substitute and “Or-Equal” Items
INSTRUCTIONS TO BIDDERS 00 21 13-1
ARTICLE 1 - DEFINED TERMS
1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:
A. Issuing Office--The Owner’s office/operations center located at 50-A South Delaware Drive, Easton, Pennsylvania, 18042, which will be the location from which the Bidding Documents are to be issued and where the bidding procedures are to be administered.
ARTICLE 2 - COPIES OF BIDDING DOCUMENTS
2.01 Complete sets of the Bidding Documents in the number and for the deposit sum, if any, stated in the Advertisement or Invitation to Bid may be obtained from the Issuing Office. The deposit will not be refunded.
2.02 Complete sets of Bidding Documents shall be used in preparing Bids; neither Owner nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.
2.03 Owner and Engineer, in making copies of Bidding Documents available on the above terms, do so only for the purpose of obtaining Bids for the Work and do not confer a license or grant for any other use.
ARTICLE 3 - QUALIFICATIONS OF BIDDERS
3.01 To demonstrate Bidder’s qualifications to perform the Work, within five (5) days of Owner’s request, Bidder shall submit written evidence such as financial data, previous experience, present commitments, and such other data as may be called for below.
A. Financial data
B. Previous experience with name of contact and project name.
C. Project superintendent resume.
D. Current contracts.
E. List of proposed subcontractors.
INSTRUCTIONS TO BIDDERS 00 21 13-2
ARTICLE 4 - EXAMINATION OF BIDDING DOCUMENTS, OTHER RELATED DATA, AND
SITE
4.01 Subsurface and Physical Conditions
A. The Project Manual identifies:
1. Those reports of explorations and tests of subsurface conditions at or contiguous to the Site that Engineer has used in preparing the Bidding Documents.
2. Those drawings of physical conditions in or relating to existing surface and subsurface structures at or contiguous to the Site (except Underground Facilities) that Engineer has used in preparing the Bidding Documents.
B. Copies of reports and drawings referenced in Paragraph 4.01.A will be made available by Owner to any Bidder on request. Those reports and drawings are not part of the Contract Documents, but the “technical data” contained therein upon which Bidder is entitled to rely as provided in Paragraph 4.02 of the General Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any “technical data” or any other data, interpretations, opinions or information contained in such reports or shown or indicated in such drawings.
4.02 Underground Facilities
A. Information and data shown or indicated in the Bidding Documents with respect to existing Underground Facilities at or contiguous to the Site is based upon information and data furnished to Owner and Engineer by owners of such Underground Facilities, including Owner, or others.
4.03 Hazardous Environmental Condition
A. The Project Manual identifies those reports and drawings relating to a Hazardous Environmental Condition identified at the Site, if any, that Engineer has used in preparing the Bidding Documents.
B. Copies of reports and drawings referenced in Paragraph 4.03.A will be made available by Owner to any Bidder on request. Those reports and drawings are not part of the Contract Documents, but the “technical data” contained therein upon which Bidder is entitled to rely as provided in Paragraph 4.06 of the General Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any “technical data” or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.
4.04 Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to subsurface conditions, other physical conditions and Underground Facilities, and possible changes in the Bidding Documents due to differing or unanticipated conditions appear in Paragraphs 4.02, 4.03, and 4.04 of the General Conditions. Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to a Hazardous Environmental Condition at the Site, if any, and possible changes in the Contract Documents due to any Hazardous Environmental Condition uncovered or revealed at the Site which was not shown or indicated in the Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work appear in Paragraph 4.06 of the General Conditions.
INSTRUCTIONS TO BIDDERS 00 21 13-3
4.05 On request, Owner will provide Bidder access to the Site to conduct such examinations, investigations, explorations, tests, and studies as Bidder deems necessary for submission of a Bid. Bidder shall fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies. Bidder shall comply with all applicable Laws and Regulations relative to excavation and utility locates.
4.06 Following is a list of other work that is to be performed at the Site by Owner or others (such as utilities and other prime contractors) that relates to the Work contemplated by these Bidding Documents.
On request, Owner will provide to each Bidder for examination access to or copies of Contract Documents (other than portions thereof related to price) for such other work.
A. Refer to the Contract Drawings and Summary of Work.
4.07 It is the responsibility of each Bidder before submitting a Bid to:
A. examine and carefully study the Bidding Documents, the other related data identified in the Bidding Documents, and any Addenda;
B. visit the Site and become familiar with and satisfy Bidder as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work;
C. become familiar with and satisfy Bidder as to all federal, state, and local Laws and Regulations that may affect cost, progress, and performance of the Work;
D. carefully study all: (1) reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the Site (except Underground Facilities) which have been identified in §4.02 of the General Conditions, and (2) reports and drawings of Hazardous Environmental Conditions at the Site which have been identified in §4.06 of the General Conditions;
E. obtain and carefully study (or accept consequences of not doing so) all additional or supplementary examinations, investigations, explorations, tests, studies, and data concerning conditions (surface, subsurface, and Underground Facilities) at or contiguous to the Site which may affect cost, progress, or performance of the Work or which relate to any aspect of the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, including applying any specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents, and safety precautions and programs incident thereto;
F. agree at the time of submitting its Bid that no further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of its Bid for performance of the Work at the price(s) bid and within the times and in accordance with the other terms and conditions of the Bidding Documents;
G. become aware of the general nature of the work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents;
H. correlate the information known to Bidder, information and observations obtained from visits to the Site, reports and drawings identified in the Bidding Documents, and all additional examinations, investigations, explorations, tests, studies, and data with the Bidding Documents;
INSTRUCTIONS TO BIDDERS 00 21 13-4
I. promptly give Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder discovers in the Bidding Documents and confirm that the written resolution thereof by Engineer is acceptable to Bidder; and
J. determine that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work.
4.08 The submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of this Article 4, that without exception the Bid is premised upon performing and furnishing the Work required by the Bidding Documents and applying any specific means, methods, techniques, sequences, and procedures of construction that may be shown or indicated or expressly required by the Bidding Documents, that Bidder has given Engineer written notice of all conflicts, errors, ambiguities, and discrepancies that Bidder has discovered in the Bidding Documents and the written resolutions thereof by Engineer are acceptable to Bidder, and that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performing and furnishing the Work.
ARTICLE 5 - PRE-BID CONFERENCE
5.01 A pre-Bid conference will be held as stated in the Advertisement and Notice to Bidders.
Representatives of Owner and Engineer will be present to discuss the Project. Bidders are encouraged to attend and participate in the conference. Non-attendees will be permitted to bid. Engineer will transmit to all prospective Bidders such Addenda as Engineer considers necessary in response to questions arising at the conference. Oral statements may not be relied upon and will not be binding or legally effective.
ARTICLE 6 - SITE AND OTHER AREAS
6.01 The Site is identified in the Bidding Documents. Easements for permanent structures or permanent changes in existing facilities are to be obtained and paid for by Owner unless otherwise provided in the Bidding Documents. All additional lands and access thereto required for temporary construction facilities, construction equipment, or storage of materials and equipment to be incorporated in the Work are to be obtained and paid for by Contractor.
ARTICLE 7 - INTERPRETATIONS AND ADDENDA
7.01 All questions about the meaning or intent of the Bidding Documents are to be submitted to Engineer in writing via PennBid’s “Public Q&A” tab. Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda and posted within PennBid’s “Public Notice’s” and “Files” tab. An email notification will be sent to all planholders. Questions received after the deadline for questions as indicated in the Advertisement, Notice to Bidders and PennBid may not be answered. Only questions answered by Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect.
INSTRUCTIONS TO BIDDERS 00 21 13-5
7.02 Addenda may be issued to clarify, correct, or change the Bidding Documents as deemed advisable by Owner or Engineer.
ARTICLE 8 - BID SECURITY
8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of ten (10%) percent of Bidder’s maximum Bid price and in the form of a cashier’s check or a Bid bond (on the form attached) issued by a surety meeting the requirements of §6.01 and §6.02 of the General Conditions.
8.02 The Bid security of the Successful Bidder will be retained until such Bidder has executed the Contract Documents, furnished the required contract security and met the other conditions of the Notice of Award, whereupon the Bid security will be returned. If the Successful Bidder fails to execute and deliver the Contract Documents and furnish the required contract security within fifteen (15) days after the Notice of Award, Owner may annul the Notice of Award and the Bid security of that Bidder will be forfeited. The Bid security of the three apparent lowest Bidders will be returned upon the signing of the Agreement and furnishing of acceptable bonds and other documents by the successful Bidder.
8.03 Bid security of all Bidders except the three apparent lowest Bidders will be returned within thirty (30) days after the Bid opening.
ARTICLE 9 - CONTRACT TIMES
9.01 The number of days within which, or the dates by which the Work is to be substantially completed and ready for final payment are set forth in the Agreement.
ARTICLE 10 - LIQUIDATED DAMAGES
10.01 Provisions for liquidated damages, if any, are set forth in the Agreement.
ARTICLE 11 - SUBSTITUTE AND “OR-EQUAL” ITEMS
11.01 The Contract, if awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents without consideration of possible substitute or “or-equal” items. Whenever it is specified or described in the Bidding Documents that a substitute or “or-equal” item of material or equipment may be furnished or used by Contractor if acceptable to Engineer, application for such acceptance will not be considered by Engineer until after the Effective Date of the Agreement. Refer to General Conditions Paragraph 6.05 for requirements on substitute and “or equal”.
INSTRUCTIONS TO BIDDERS 00 21 13-6
ARTICLE 12 - SUBCONTRACTORS, SUPPLIERS, AND OTHERS
12.01 A list of proposed Subcontractors and Suppliers is required to be submitted to Owner with the bid.
Such list shall be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor and Suppliers. Contractor shall also submit evidence that Subcontractors and Suppliers are qualified to do business in the Commonwealth of Pennsylvania or covenant to obtain such qualification prior to and as a condition of award of a Contract. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor or Supplier, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit a substitute, without an increase in the Bid.
No substitutions for Subcontractors shown on the list shall be made by Contractor without prior written approval of Owner or Engineer.
12.02 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors or Suppliers. Declining to make requested substitutions will not constitute grounds for forfeiture of the Bid security of any Bidder.
Any Subcontractor or Supplier so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to revocation of such acceptance after the Effective Date of the Agreement as provided in Paragraph 6.06 of the General Conditions.
12.03 Contractor shall not be required to employ any Subcontractor or Supplier against whom Contractor has reasonable objection.
12.04 Note that Contractor is responsible to assure compliance by its subcontractors with various provisions within the Contract Documents and may have to present certifications and documents from the subcontractors to show compliance.
ARTICLE 13 - PREPARATION OF BID
13.01 The Bid Form and required supplements are included with the Bidding Documents. Bids must be submitted online via PennBid’s “Submissions” tabs. Scanned copies of the Bid Form will not be considered.
13.02 A Bid price shall be indicated for each Bid item, alternative, and unit price item listed therein, or the words “No Bid,” “No Change,” or “Not Applicable” entered within the Comment field adjacent to the line item.
13.03 A Bid by a corporation shall be executed in the corporate name by the president or a vice-president or other corporate officer accompanied by evidence of authority to sign and attested by the secretary or an assistant secretary.
13.04 A Bid by a partnership shall be executed in the partnership name and signed by a partner accompanied by evidence of authority to sign.
13.05 A Bid by a limited liability company shall be executed in the name of the firm by a member and accompanied by evidence of authority to sign.
INSTRUCTIONS TO BIDDERS 00 21 13-7
13.06 A Bid by an individual shall show the Bidder’s name and official address.
13.07 A Bid by a joint venture shall be executed by each joint venturer and accompanied by evidence of each venturer’s authority to sign.
13.08 Proof of a partner’s, or agent’s, authority to obligate the Contractor must be attached to the Bid.
13.09 The Bid shall contain an acknowledgment of receipt of all Addenda, the numbers of which shall be filled in on the Bid Form.
13.10 The address and telephone number for communications regarding the Bid shall be shown.
13.11 The Bid shall contain evidence of Bidder’s authority and qualification to do business in the Commonwealth of Pennsylvania or covenant to obtain such qualification prior to award of the Contract.
Bidder’s state contractor license number, if any, shall also be shown on the Bid Form.
13.12 Unless specifically provided in the Contract Documents, bids containing substitutions or combinations of alternates will not be considered unless such substitutions or combinations are specifically authorized by the Owner.
ARTICLE 14 - BASIS OF BID; COMPARISON OF BIDS
14.01 Lump Sums
A. Bidders shall submit a Bid on a lump sum basis for each Lump Sum Bid Item listed in the Bid Form.
B. The Bid for all Lump Sum Bid Items shall be included in the Total Base Bid.
14.02 Project Allowances
A. Bidders shall submit a Bid on a unit price or lump sum basis for each Allowance Bid Item listed in the Bid Form.
B. For unit price allowances, the total of each Allowance Bid Item will be the product of the estimated quantity of each item and the corresponding unit price. The final quantities and Contract Price will be determined in accordance with Paragraph 11.03 of the General Conditions.
C. The Bid for all Allowance Bid Items shall be included in the Total Base Bid.
D. The Bid price shall include such amounts as the Bidder deems proper for overhead and profit on account of allowances, if any, named in the Contract Documents as provided in Paragraph 11.02 of the General Conditions.
14.03 Alternates
A. When Alternate Bid Items are included in the Project, Bidders shall include a separate lump sum or unit price allowance price for each Alternate Bid Item described in the Bidding Documents as provided for
INSTRUCTIONS TO BIDDERS 00 21 13-8
in the Bid Form. The price for each alternate will be the amount added to or deleted from the Total Base Bid if Owner selects the alternate.
14.04 Comparison of Bids
A. For determination of the apparent low Bidder, Bids will be compared on the basis of the Total Base Bid, plus, in the order of priority listed on the Bid Form, the additive/deductive alternate Bid prices for determination of the apparent low Bidder.
ARTICLE 15 - SUBMITTAL OF BID
15.01 Sealed bids shall be submitted online via the PennBid Program, https://pennbid.bonfirehub.com/
15.02 A Bid shall be submitted no later than the date and time prescribed in the Advertisement, Notice to Bidders and on PennBid.
ARTICLE 16 - MODIFICATION AND WITHDRAWAL OF BID
16.01 A Bidder may withdraw his Bid from consideration after the Bid opening without forfeiture of the cashier's check, surety bid bond or other security filed with the Bid if the price bid was submitted in good faith, and the Bidder submits credible evidence that the reason for the price bid being substantially lower was a clerical mistake as opposed to a judgment mistake, and was actually due to an unintentional and substantial arithmetical error or an unintentional omission of a substantial quantity of work, labor, material or services made directly in the compilation of the Bid. Withdrawal is allowed only if (i) notice of a claim of the right to withdraw such Bid is made in writing with the Owner within two (2) business days after the opening of Bids; and (ii) the withdrawal of the Bid would not result in the awarding of the contract on another Bid of the same Bidder, his partner, or to a corporation or business venture owned by or in which he has a substantial interest. No Bidder who is permitted to withdraw a Bid shall supply any material or labor to, or perform any subcontract or other work agreement for any person to whom a contract or subcontract is awarded in the performance of the contract for which the withdrawn Bid was submitted, without the written approval of the Owner.
16.02 If a Bid is withdrawn in accordance with the provisions of §16.01, the Owner may award the contract to the next lowest Bidder or reject all Bids and resubmit the project for bidding. In the event the Owner resubmits the project for bidding the withdrawing Bidder shall pay the costs, in connection with the resubmission, of printing new contract document, required advertising, and printing and mailing notices to prospective Bidders, if the Owner finds that such costs would not have been incurred but for such withdrawal. In no event shall the withdrawing Bidder be permitted to resubmit a Bid for the Project.
16.03 Prior to the Bid opening date and time a Bidder may modify or withdraw its Bid at anytime via PennBid’s “Submissions” tabs.
INSTRUCTIONS TO BIDDERS 00 21 13-9
ARTICLE 17 - OPENING OF BIDS
17.01 Bids will not be opened and read aloud publicly. An abstract of the amounts of the Total Base Bid and major alternates, if any, will be made available to Bidders after the opening of Bids using PennBid’s “Public Notices” tab.
ARTICLE 18 - BIDS TO REMAIN SUBJECT TO ACCEPTANCE
18.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.
ARTICLE 19 – EVALUATION OF BIDS AND AWARD OF CONTRACT
19.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner further reserves the right to reject the Bid of any Bidder whom it finds, after reasonable inquiry and evaluation, to not be responsible or responsive. Owner may also reject the Bid of any Bidder if Owner believes that it would not be in the best interest of the Project to make an award to that Bidder. Owner also reserves the right to waive all informalities not involving price, time, or changes in the Work and to negotiate contract terms with the Successful Bidder.
19.02 More than one Bid for the same Work from an individual or entity under the same or different names will not be considered. Reasonable grounds for believing that any Bidder has an interest in more than one Bid for the Work may be cause for disqualification of that Bidder and the rejection of all Bids in which that Bidder has an interest.
19.03 In evaluating Bids, Owner will consider whether or not the Bids comply with the prescribed requirements, and such alternates, unit prices and other data, as may be requested in the Bid Form or prior to the Notice of Award.
19.04 In evaluating Bidders, Owner will consider the qualifications of Bidders and may consider the qualifications and experience of Subcontractors, Suppliers, and other individuals or entities proposed for those portions of the Work for which the identity of Subcontractors and Suppliers must be submitted as provided in §12.01.
19.05 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders, proposed Subcontractors and Suppliers to perform the Work in accordance with the Contract Documents.
19.06 If the Contract is to be awarded, Owner will award the Contract to the Bidder whose Bid is in the best interests of the Project.
19.07 Owner reserves the right to cancel the award of any Contract at any time prior to its execution of the Agreement by Owner without incurring any liability to any of the Bidders.
INSTRUCTIONS TO BIDDERS 00 21 13-10
ARTICLE 20 - CONTRACT SECURITY AND INSURANCE
20.01 Article 5 of the General Conditions, as modified by the Supplementary Conditions, sets forth Owner’s requirements as to performance and payment bonds and insurance. When the Successful Bidder delivers the executed Agreement to Owner, it shall be accompanied by such bonds and appropriate insurance certificates.
ARTICLE 21 - SIGNING OF AGREEMENT
21.01 When Owner gives a Notice of Award to the Successful Bidder, it shall be accompanied by the required number of unsigned counterparts of the Agreement with the other Contract Documents which are identified in the Agreement as attached thereto. Within fifteen (15) days thereafter, Successful Bidder shall sign and deliver the required number of counterparts of the Agreement and attached documents to Owner.
Within ten (10) days thereafter, Owner shall deliver one fully signed counterpart to Successful Bidder with a complete set of the Drawings with appropriate identification.
ARTICLE 22 - SALES AND USE TAXES
22.01 Owner, as a municipal authority, is exempt from the Pennsylvania Sales and Use Tax.
Certificates of Exemption will be furnished to the Contractor for its purchase of materials for which the Authority’s exemption is transferable, upon Contractor’s request; however, it is Contractor's responsibility to determine for which materials the tax exemption is applicable prior to submitting its Bid.
Said taxes shall not be included in the Bid. Contractor shall pay all other sales, consumer, use and other similar taxes required to be paid by Contractor in accordance with the Laws and Regulations of the Commonwealth of Pennsylvania which are applicable during the performance of the Work. Said taxes shall not be included in the Bid. Refer to Paragraph 6.10 of the General Conditions for additional information, if any.
ARTICLE 23 - NONDISCRIMINATION IN EMPLOYMENT
23.01 Contractor agrees that:
A. Neither it nor any subcontractor that Contractor uses for the Contract will discriminate against any employee or applicant for employment because of race, color, religion, sex, gender identity, sexual orientation, veteran’s status, political opinions or affiliations, lawful activity in any employee organization, national origin, age, disability or marital status. Contractor and subcontractors will take affirmative action to ensure that applicants and employees are treated fairly during employment without regard to race, color, religion, sex, gender identity, sexual orientation, veteran's status, political opinions or affiliations, lawful activity in any employee organization, national origin, age, disability or marital status. Such action shall include, but not be limited to the following: employment, upgrading, demotion, or transfer, recruitment, or recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training, including apprenticeship.
INSTRUCTIONS TO BIDDERS 00 21 13-11
(1) Contractor/subcontractor shall comply with all applicable federal, state and local laws regarding non-discrimination, including: (a) the Civil Rights Act of 1964, 42 U.S.C. §2000 et seq. (1981); (b) the Civil Rights Act of 1991, P.L. 102-166; (c) Executive Order Number 11246, 30 Fed. Reg.
12,319 (1965), reprinted in 42 U.S.C. §2000(e) note, as amended by Executive Order Number 11375, 32 Fed. Reg. 14,303 (1967) and by Executive Order Number 12086, 43 Fed. Reg. 46,501 (1978); (d) the Age Discrimination Act, 42 U.S.C. §§6101-6106 (1981); (e) the Age Discrimination in Employment Act, 29 U.S.C. §§621-34 (1967); (f) the Rehabilitation Act of 1973, 29 U.S.C.
§§793-794 (1981); (g) the Americans with Disabilities Act, 42 U.S.C. §12101 et seq. (1990); and
(h) the Pennsylvania Human Relations Act, Act of October 27, 1955 (P.L. 744, No. 222) as amended, 43 P.S. §§951-963.
(2) Contractor/subcontractor shall establish and maintain a written sexual harassment policy and shall inform its employees of the policy. The policy must contain a notice that sexual harassment will not be tolerated and employees who practice it will be disciplined.
(3) Contractor/subcontractor shall not discriminate for any of the reasons set forth above against any subcontractor or supplier who is qualified to perform the work to which the contract relates.
B. The Contract may be canceled or terminated by the Owner, and all money due or to become due under the Contract may be forfeited, for a violation of the terms or conditions of these nondiscrimination provisions.
23.02 Contracts for Work under this Bid will obligate the Contractor and Subcontractor to be non-discriminatory in employment practices. Bidders, if requested, must submit with their Bid any information or documents required by state, federal or local statutes or regulations applicable to non-discrimination in employment; including, if necessary, a compliance report concerning their employment practices and policies in order to maintain their eligibility to receive the award of the Contract.
A. To the extent allowed by law the Contractor/subcontractor shall furnish all necessary employment documents and records to and permit access to its books, records, and accounts by Owner, the City or their agents for purposes of investigation to ascertain compliance with these equal opportunity and non-discrimination provisions. If the Contractor does not possess documents or records reflecting the necessary information requested, it shall furnish such information on reporting forms supplied by Owner or the City.
23.03 Bidders must submit a list of all Subcontractors who will perform work on the Project and written signed statements from authorized agents of the labor pools with which it will or may deal for employees on this Work, together with supporting information to the effect that these labor pools will affirmatively cooperate in or offer no hindrance to the recruitment, employment and equal treatment of employees who are seeking employment and are performing work under the Contract. If such agents or labor pools have failed or refused to furnish the necessary statements prior to the award of the Contract, Bidder shall provide certification as to what efforts have been made to secure such statements.
ARTICLE 24 - LAWS AND REGULATIONS
24.01 The Bidder’s attention is directed to the fact that all applicable laws, ordinances, and rules and regulations having jurisdiction over construction of the Project shall apply to the Contract throughout; are the Bidder’s/Contractor’s responsibility to ascertain; and will be deemed to be included in the Contract the same as though herein written in full, whether or not specified in the Contract Documents.
INSTRUCTIONS TO BIDDERS 00 21 13-12
24.02 PREVAILING WAGE ACT. The Pennsylvania Prevailing Wage Act applies to the work to be performed under the Contract; therefore, the Contractor must pay to its workers the minimum wage rate established by the Secretary of Labor and Industry and specified in the Contract Document - Prevailing Wage Act and Predetermination - and further the Contractor must assure that its Subcontractors also pay the Subcontractor’s workers these same minimum wage rates.
24.03 STEEL PRODUCTS PROCUREMENT ACT. Special attention is drawn to the provisions of Pennsylvania’s Steel Products Procurement Act, which includes cast iron in the definition of steel products. The Contractor is advised that only steel products as defined in said Act shall be used or supplied in the performance of the Contract The Act defines Steel Products as "Products rolled, formed, shaped, drawn, extruded, forged, cast, fabricated or otherwise similarly processed, or processed by a combination of two or more of such operations, from steel made in the United States by the open hearth, basic oxygen, electric furnace, Bessemer or other steel making process and shall include cast iron products and shall include machinery and equipment listed in United States Department of Commerce Standard Industrial Classification 25 (furniture and fixture), 35 (machinery, except electrical) and 37 (transportation equipment) and made of, fabricated from, or containing steel components. If a product contains both foreign and United States steel, such product shall be determined to be a United States steel product only if at least seventy-five (75%) percent of the cost of the articles, materials and supplies have been mined, produced or manufactured, as the case may be, in the United States. Transportation equipment shall be determined to be a United States steel product if it complies with section 165 of Public Law 97-424 (96 Stat. 2136)".
Contractor shall provide steel origin certifications of compliance in conjunction with shop drawing submittals, which certification shall be on forms to be provided by the Owner.
24.04 PUBLIC WORKS EMPLOYMENT ACT. Pennsylvania’s Public Works Employment Act requires contractors and subcontractors performing work on public works projects in this Commonwealth to comply with the Federal E-Verify program (the EVP) to ensure employees are authorized to work in the United States. The EVP is a free Internet-based program operated by the United States Department of Homeland Security that compares information from an employee's Form I-9, Employment Eligibility Verification, to data from the United States Department of Homeland Security and Social Security Administration records to confirm employment eligibility. As a result, every contractor and subcontractor performing work under a public works contract shall utilize the EVP system to verify the employment eligibility of each new employee hired after January 1, 2013; shall submit the official Public Employment Verification Form to the Authority to ensure compliance with the act; and shall maintain documentation of continued compliance with the act by utilizing the EVP for new employees hired throughout the duration of the public work contract. The Pennsylvania Department of General Services is responsible for administering the program and information, as well as establishing the official Public Works Employment Verification Form that needs to be completed by contractors and subcontractors, can be obtained on their website. This has been the appropriate link to that website, although the Authority does not warrant its current accuracy -http://www.dgs.state.pa.us/portal/server.pt/community/construction_and_public_works/1235/public_work s_employment_verification/1357211.
24.05 ENVIRONMENTAL LAWS. According to the Commonwealth Procurement Code, Act of May 15, 1998, P.L. 358, No. 57, 62 Pa.C.S.A. §3301, all invitations for bids and requests for proposals for construction projects issued by any government agency shall set forth any provision of federal and state statutes, rules and regulations dealing with the prevention of environmental pollution and the preservation of public natural resources that affect the projects. This is the list entitled Environmental Statement as prepared by the Commonwealth of Pennsylvania, Department of General Services, 1999 Edition, for its
INSTRUCTIONS TO BIDDERS 00 21 13-13
standard contract forms, although revised to eliminate acts which don’t apply because of geographic location.
The Bidder is hereby notified that this project is subject to those statutes, rules and regulations shown on the following list, and the work must be carried out in compliance with these statutes, rules and regulations.
STATE LAW
I. Purdon's Statutes - Title 3 (Agriculture)
Pennsylvania Fertilizer Law of 1956, Act of May 29, 1956 (P.L. (1955) 1795, §1), as amended, 3 P.S.
68.1 et seq.
Pennsylvania Pesticide Control Act of 1973, Act of March 1, 1974 (P.L. 90, No. 24), as amended, 3 P.S. 111.21 et seq.
Agricultural Liming Materials Act, Act of March 17, 1978 (P.L. 15, No. 9), as amended, 3 P.S.
132-1 et seq.
The Pennsylvania Plant Pest Act of 1992, Act of December 16, 1992 (P.L. 1228, No. 162, §1), as amended, 3 P.S. 258.1 et seq.
Noxious Weed Control Law, Act of April 7, 1982 (P.L. 228, No. 74), as amended, 3 P.S. 255.1 et seq.
Soil Conservation Law, Act of May 15, 1945 (P.L.