This document is a Statement of Work for a federal contract opportunity to replace the existing aged and broken asphalt on Pine Creek Road in the Cleveland National Forest in California. The purpose is to improve public traffic safety, access for fire management, and recreation use.
The work includes pulverization and road reconditioning, compaction, installation of an aggregate base and new asphalt, and installation of a sign system. The contract period of performance is 30 calendar days from the Notice to Proceed, with an optional 45 calendar days total. The estimated contract value is between $1,000,000 and $5,000,000. The contract is set aside for 100% small business concerns under NAICS code 237310 for Highway, Street, and Bridge Construction. The Forest Service recommends site visits prior to bidding. Contractor responsibilities include securing any necessary permits, repairing damage to roads, properly disposing of debris, and adhering to the Fire Plan requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 12970224R0059 00002.pdf | ||
| 12970224R0059 00001.pdf | ||
| RFI Log.xlsx | XLSX spreadsheet | |
| 1. Schedule of Items.pdf | ||
| 5. E - Fire Plan_14S05 -PAL Area 675.doc | DOC document | |
| 4. FSSS.docx | DOCX document | |
| 12970224R0059.pdf | ||
| 3. Pine Creek Road RESURFACING.pdf | ||
| 6. CA20240007 07262024.txt | TXT text file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION C
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
SCOPE OF CONTRACT
The purpose of this contract is to replace existing aged and broken HMA of Pine Creek Road (System Road 14S05 on the Descanso Ranger District (DRD) of the Cleveland National Forest to improve public traffic safety, access for fire management and recreation use This contract provides for the equipment, labor, materials, services and permits necessary to perform work ordered by the Government, in compliance with its terms, specifications, drawings and provisions, for pulverization and road reconditioning per FP-14 Sec. 304, compaction FSSS method D, with optional Caltrans AB Class 2 aggregate base 1-1/2 in. max. followed by HMA CalTrans 1/2 in. max. Type A, PG 64 – 16 (Low Mountain Region) and installation of sign system.
All associated work not listed under Pay Items but necessary and directly related to listed pay items are incidental.
Project Location
This project is located in Pine Valley, San Diego County, CA, off Sunrise Highway near Mount Laguna.
From Descanso Ranger Station at 3348 Alpine Blvd, Alpine, CA 91901, head east on Alpine Blvd for 0.5 mi., look for sign of I-8 and merge onto I-8E, stay on I-8E for 13 mi., take exit 47 toward Sunrise Hwy, turn left on Old Hwy I-80 and continue on Sunrise Hwy for 14.2 mi., Pine Creek road is on the left.
The Forest Service highly recommends site visit prior to bidding to ensure complete knowledge of site conditions and the difficulty of operations.
Period of Performance
Projected start date: late 2024
Restricted work: Limit construction activities within road prism. Sensitive areas require specialist monitoring during or approved clearance prior to construction activities.
Time for completion: 30 calendar days from the issuance of the “Notice to Proceed”. 45 calendar days including options.
Requirements
The Contractor shall furnish the necessary personnel, material, equipment, services and facilities to perform the Statement of Work/Specifications referenced below (see Specifications in Section C).
It is the Contractor responsibility to secure special permit(s) as required for mobilization of heavy equipment/heavy load on public roads, mobilization of heavy equipment/heavy load on Pine Creek road or Pine Creek Bridge is subject to approval of the CO in advance. Heavy loads that require permit on highway will need separate permit from FS with 2 week processing time.
The Contractor shall repair all associated damage on established roads caused by their operations or equipment prior to partial or final payment.
The Contractor shall legally dispose of all project related trash, debris and excess as it accumulates on site.
The Contractor shall adhere to the pertinent requirements addressed in the Fire Plan (see Attachment). Fire Plan restrictions may require work to cease at 1:00 pm or not be initiated at all on a high fire activity day.
The Contractor is responsible for traffic control and equipment requirements in work areas when working on National Forest System Lands and at intersection(s) with county road(s).
All ground disturbing equipment shall be thoroughly cleaned of debris and dirt before mobilizing onto Forest lands and between project areas in order to prevent the introduction of invasive weeds into those areas. No separate measurement and payment will be included for this item.
Specifications
Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-03, U.S. Customary Units and Forest Service Supplemental Specifications (FSSS). FP-14 electronic copy can be downloaded at: https://flh.fhwa.dot.gov/resources/specs/fp-14/fp14.pdf
If state of California specifications or typical are referred to, download is available at http://www.dot.ca.gov/hq/esc/oe/construction_contract_standards/std_specs/2015_StdSpecs/2015_StdSpecs.pdf and http://www.dot.ca.gov/hq/esc/oe/project_plans/HTM/stdplns-US-customary-units-new15.htm
BMPs, fiber rolls soil and sediment control information:
http://www.dot.ca.gov/hq/construc/stormwater/CSBMP-May-2017-Final.pdf
Temporary traffic control shall be in accordance with the manual on uniform traffic control devices (mutcd) 2009 version, electronic copy is available at https://mutcd.fhwa.dot.gov/pdfs/2009r1r2/mutcd2009r1r2edition.pdf
FSSS (Attached)
Drawing Sheets (Attached)
Fire Plan (Attached)