2. SOW-PPW Piping Repairs.pdf
PDF 141 KB Posted
- Attached to
- PPW Piping Repairs Federal contract opportunity
- Solicitation number
- 12505B23R0008
About this file
This document is a solicitation for PPW piping repairs at a USDA facility in Ames, Iowa. The solicitation requests proposals for repairing leaks in three sections of pumped pretreatment waste piping buried underground. Repairs include excavating piping, locating and patching leaks, and restoring disturbed areas. The small business set-aside contract value is estimated between $100,000 to $250,000, with a 90-day period of performance. A pre-bid site visit is scheduled for May 3rd and 4th, with registration required by May 1st. Questions are due by May 9th, with responses posted as amendments. Proposals are due through SAM.gov. The selected contractor must use biobased products where available and reasonably priced.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 12505B23R0008-0001 - Amendment 1.pdf | ||
| 9. 12505B23R0008 - 2023_PPW repair project drawings.pdf | ||
| 1. 12505B23R0008 - Repair PPW Lines_4.18.23.pdf | ||
| 6. ARS-371.pdf | ||
| 8. Past Performance Questionnaire.pdf | ||
| 7. ARS-372.pdf | ||
| 5. Material Submittal Form (002).pdf | ||
| 4. Wage Determination.pdf | ||
| 3. PPW piping Specs.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
2023 PPW Piping Repair Project
USDA, Ames
3-1-2023
Project Requirements:
This project will include repair work to 3 separate sections of pumped pretreatment waste (PPW) piping buried in the ground in 3 separate areas on the USDA campus in Ames, Iowa.
The first section is the PPW piping that runs from Building 155 to PPW101A. This piping has been determined to have a leak somewhere in its secondary containment allowing ground water to infiltrate the interstitial space of the dual wall piping.
The second section is inside the vault on the east side of Building 156. This secondary piping in this vault has a leak around the secondary containment of an existing wye fitting. Details on the drawings.
The third section is the PPW piping that runs between PPW vault 104 and PPW 103.
The newly installed redundant, dual wall PPW piping has a leak in the secondary containment allowing ground water to infiltrate the interstitial space of the dual wall piping.
SECTION 1: PPW piping between old wastewater treatment plant (Bldg. 155) and PPW vault 101A.
Contractor shall excavate by HydroVac-ing and completely uncovering the existing PPW lines noted in this section (and noted on attached drawings) from building 155 to PPW vault 101A. Once the PPW lines are exposed completely, the USDA will pressure test the section of PPW piping to locate the leak in the outer, secondary containment piping.
Once the leak location has been determined, the Contractor will be responsible for making one patch on the exterior pipe, approximately one foot of piping length entirely around the pipe within the bounds of this section. After the repairs to the dual wall PPW piping is complete, the contractor and USDA personnel will work together to pressure test the piping to verify the integrity of the repairs to the outer wall of the dual wall piping.
Once the piping passes the pressure tests, the Contractor will then be responsible for backfilling the trench and repairing/restoring any disturbed portions of the surrounding area back to its original condition.
Contractor shall be responsible for removing and replacing any of the concrete/asphalt driveway that is removed to expose these PPW pipes back to its original or better condition.
SECTION 2: Buildings 3 and 4 PPW piping repair
Contractor shall be responsible for repairing leak inside vault on the east side of Building
156. The leak is located on the wye fitting and is around one of the joints. Contractor shall be responsible for any excavating that may need done for accessibility to the fitting inside the vault. See drawings for more details. After the repairs to the dual wall PPW piping is complete, the contractor and USDA personnel will work together to pressure test the piping to verify the integrity of the repairs to the outer wall of the dual wall piping.
Once the piping passes the pressure tests, the Contractor will then be responsible for backfilling the trench and repairing/restoring any disturbed portions of the surrounding area back to its original condition. This includes placing sand back inside the vault.
SECTION 3: PPW vault 104 to PPW 103 piping repair
Contractor shall excavate by HydroVac-ing and completely uncovering the existing PPW lines noted in this section (and noted on attached drawings) from PPW 103 to PPW 104 located on the west side of Building 9. Once the PPW lines are exposed completely, the USDA will pressure test the exterior wall of the dual wall piping and locate leak in outer piping. Contractor will be responsible for making one repair to the exterior pipe, approximately one foot of piping length within the bounds of this section. After the repairs to the dual wall PPW piping is complete, the contractor and USDA personnel will work together to pressure test the piping to verify the integrity of the repairs to the outer wall of the dual wall piping. Once the piping passes the pressure tests, the Contractor will then be responsible for backfilling the trench and repairing/restoring any disturbed portions of the surrounding area back to its original condition.
Contractor shall be responsible for removing and replacing any of the fencing that needs to be removed to expose these PPW pipes back to original condition.
Contractor shall be responsible for removing and replacing any of the concrete driveway that is removed to expose these PPW pipes back to its original condition.
Additional Notes for work noted above:
In all areas noted above, the contractor MUST TAKE extreme caution while excavating to not disturb any of the other existing PPW piping and/or any other existing utilities in the area of work. As noted below, the contractor will be responsible for performing or subcontracting the work for utility locates in the area of work prior to any work happening, however, the USDA Personnel will assist in any way possible to help identify potential hazards and their locations. These systems are critical in nature to NCAH operations and must not be disturbed in their operation unless it is a scheduled activity.
For all piping materials (in the ground and in the vaults), the contractor shall match the existing construction, finish, and installation requirements as the existing piping.
Specifications and drawings for the existing installations have been included.
All fencing material needing to be removed to perform piping work must be replaced by contractor with like material and construction once the piping work and groundwork is complete.
Any grounds disturbed (grass, gravel, paving, etc..) in order to expose piping to be worked on, must be returned to original or better conditions after piping work has been completed. Contractor will be responsible for replacing any pavement work that has been removed, reseeding any grassy areas, etc.
Any ground that is disturbed and returned to better or normal conditions due to excavating, equipment access, refilling, etc. must be free of debris, large rocks, construction materials etc.
General Requirements
1.01 Work Restrictions & Conditions
A. Site Security Access
1. Access to the construction site is controlled by a security fence and visitor/contractor check-in/check-out system. All contractor/sub-contractor employees shall sign in and out at the main site entrance gate and wear a contractor/visitor identification badge at all times while on the site. The ID badges will be turned in at the end of the workday. A current government-issued identification with a picture ID is required for entry. Vehicle badges shall be displayed at all times while the contractor is on site.
2. Access to each individual site shall be arranged by the Contracting Officer's Representative according to the schedule submitted by the contractor and approved by the Contracting Officer’s Representative. The contractor shall coordinate and schedule his/her work under this contract to cause the least interference with the normal flow of visitor and employee traffic.
3. Construction vehicles will be allowed access adjacent to the work; contractor employee’s personal vehicles shall be parked in the facility parking lots.
4. The Contractor shall use only the service roads and access routes approved by the Contracting Officer’s Representative.
5. Work shall be confined to the areas identified on the Drawings. Unless accompanied by a NCAH/USDA employee, the Contractor, subcontractors, and their employees shall not enter buildings or facilities not specifically part of this project. Reasons included, but are not limited to, disease control and health requirements.
6. Additional security requirements may be imposed when the Federal Government raises the Homeland Security Alert Level. Additional directions will be provided if the situation occurs.
7. Failure to comply with access requirements shall be adequate grounds for removal of the Contractor/subcontractor employees from the site and barring further site access to individuals.
B. Work Hours: Regular work hours for the site are 7:00 AM to 3:30PM, Monday through Friday, excluding Government holidays. Requests for exceptions to this schedule shall be made in writing forty-eight (48) hours in advance and approved by the Contracting Officer's Representative.
C. Work Outside Regular Work Hours: Work scheduled outside regular work hours including late hours, Saturdays, Sundays, and Government holidays requires Contracting Officer’s Representative (COR) approval in advance. Make application to the COR at least 5 calendar days prior to such work to allow arrangements to be made by the Government for access to the work area and inspection & monitoring arrangements. Requests shall include the exact dates, hours, location, and purpose of the exception. If approved, the COR will coordinate access with the site security office.
D. Construct Work in stages to accommodate Owner’s use of premises during construction period. Coordinate construction schedule and operations with Contracting Office’s Representative (COR).
1. Schedule Work to minimize use of street barricades and detours.
E. Coordinate use of premises under direction of the COR. Contractor shall confine construction equipment, storage of materials and equipment and operations of workers to areas permitted by law, ordinances, permits, or requirements of Contract Documents, and shall not unreasonably encumber premises with construction equipment or other material or equipment. Contractor shall:
1. Assume full responsibility for protection and safekeeping of items under this
Agreement, stored on site.
2. Move any stored items, under Contractor’s control, which interfere with operations of Owner or separate contractor.
3. Obtain and pay for use of additional storage or Work areas needed for operations.
4. Ensure that any materials that are delivered by FedEx, UPS, etc. are delivered to the jobsite and NOT to the USDA warehouse dock at Building 24 or to the north warehouse, Building 11. The USDA and/or the COR will not be responsible for receiving any materials destined for the project. USDA reserves the right to refuse any unscheduled deliveries that arrive at either warehouse or at the main gate. Special considerations shall be made with the COR in advance of the delivery.
5. Notify the COR of any scheduled deliveries. The COR will add the carrier or company to the visitor’s schedule. Contractor will meet the delivery and escort them to the jobsite.
F. Owner will occupy premises during entire period of construction for conduct of its normal operations. Coordinate with Owner’s Representative/COR in all construction operations to minimize conflict, and to facilitate Owner usage. Contractor shall at all times conduct its operations as to ensure least inconvenience to Owner.
1.02 Security Clearance Requirements
A. Use of Premises
1. Limit use of premises to work in areas indicated. Do not disturb portions of site beyond areas in which the work is approved.
2. Keep driveways and entrances serving premises clear and available to the Government, employees, visitors and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
3. Limited parking may be available on the site away from each facility.
4. The contractor shall provide a list of all staff employees that will be working on the project to the Contracting Officer’s Representative (COR) a minimum of three days in advance. The contractors that will be onsite will be required to provide a valid driver’s license and be a valid United States Citizen to be able to access campus.
5. Once onsite, contractors will be escorted by a USDA employee to the location of the work and will be escorted at all times while onsite.
a. The contractor shall provide a list of intended employees to the Contracting
Officer’s Representative within three (3) calendar days of task order award.
b. The contractor shall keep the list of employees up to date throughout the project in the event of employee separation and transfer.
B. Adherence to Security Policies and Procedures
1. The Contractor shall adhere to all Site, APHIS and USDA security policies and procedures including Code of Federal Regulations Requirements, Standard Operating Procedures, Security Directives, Security Procedures, General Orders, Post Orders and any applicable Government Policies and Procedures.
a. Failure to adhere to or violation of any above listed requirements, procedures, directives, orders and/or policies may result in criminal prosecution or contractor representative or contractor employee (violator) removal.
1.03 Intent of Contract Drawings
A. Government provided drawings, henceforth referred to as “Contract Drawings”, do not attempt to show complete details of building construction that may affect installation. Government provided diagrams of proposed systems are for reference only and do not necessarily show physical arrangement of all equipment and/or maximum number of devices. Minimum system requirements are shown.
B. Devices are shown diagrammatically only. System layout does not necessarily show maximum number of system components and should not be used for obtaining quantities for linear runs of conduits and wires.
C. Locations of existing and Government concept devices are approximate and may be distorted for clarity in representation.
D. Anything mentioned in this Scope of Work and not shown on the drawings or shown on the drawings and not mentioned in the Scope of Work, shall be of like effect as if shown or mentioned in both.
1.04 Regulatory Requirements
A. The equipment materials, installation, workmanship, and operation shall conform to the most stringent applicable requirements of the most recent editions of the associated publications, in the below section and in the attached specifications unless otherwise noted:
1. National Fire Protection Association (NFPA)
a. NFPA 101 – Safety to Life from Fire in Buildings and Structures.
b. NFPA 1 – Uniform Fire Code
c. NFPA 5000 – Building Construction and Safety Code
2. Underwriters Laboratories, Inc. (UL)
a. Appropriate UL Standards
3. State and Local Building Codes as adopted by the Authority Having Jurisdiction
(AHJ).
4. The Uniform Federal Accessibility Standards (UFAS)
5. Occupational Safety and Health Administration (OSHA)
6. Equipment Manufacturer Printed Instructions
B. All work shall be completed in accordance with the Iowa Statewide Urban Design and Specifications (SUDAS) most recent edition. The SUDAS Standard Specifications are modified by the following additions. These are supplemental specifications, and they shall prevail over those published in the SUDAS Standard Specifications Manual.
1. Underground Facilities:
a. Shown or Indicated: The information and data shown or indicated in the Contract Documents with respect to existing Underground Facilities at or contiguous to the Site is based on information and data furnished to Owner by the Owners of such underground facilities, including Owner, or by others.
Unless it is otherwise expressly provided in the Supplementary Conditions:
i. Owner shall not be responsible for the accuracy or completeness of any such information or data provided by others; and
ii. The cost of all of the following will be included in the Contract Price, and Contractor shall have full responsibility for:
1. Reviewing and checking all such information and data.
2. Locating all Underground Facilities shown or indicated in the
Contract Documents.
3. Coordination of the Work with the Owners of such
Underground Facilities, including Owner, during construction.
4. The safety and protection of all such underground facilities and repairing any damage thereto resulting from the Work.
a) Not Shown or Indicated: If an Underground Facility is uncovered or revealed at or contiguous to the Site which was not shown or indicated, or not shown or indicated with reasonable accuracy in the Contract Documents, Contractor shall, promptly after becoming aware thereof and before further disturbing conditions affected thereby or performing any Work in connection therewith (except in an emergency), identify the owner of such Underground Facility and give written notice to that owner and to the COR. COR will promptly review the Underground Facility and determine the extent, if any, to which a change is required in the Contract Documents to reflect and document the consequences of the existence or location of the Underground Facility. During such time, Contractor shall be responsible for the safety and protection of such Underground Facility. If Contractor concludes that a change in the Contract Documents is required, a
Work Change Directive or a Change Order will be issued to the Contracting Officer to reflect and document such consequences. An equitable adjustment shall be made in the Contract Price or Contract Times, or both, to the extent that they are attributable to the existence or location of any Underground Facility that was not shown or indicated or not shown or indicated with reasonable accuracy in the Contract Documents and that Contractor did not know of and could not reasonably have been expected to be aware of or to have anticipated. If Owner and Contractor are unable to agree on entitlement to or on the amount or extent, if any, of any such adjustment in Contract Price or Contract Times, Owner or Contractor may make a Claim.
1.05 Coordination
A. The contractor shall coordinate all work with the Contracting Officer's
Representative.
C. The contractor shall submit an installation schedule for review and approval by the Contracting Officer's Representative within ten (10) days of task order award.
D. The contractor shall be solely responsible for coordinating work with all subcontractors and ensuring that all items of joint use in conjunction with installations are completed.
1.06 Special Provisions
A. The Contractor shall confine all operations to within the work limits of the project and exercise special care to maintain natural surroundings undamaged. All surfaces that have been altered for the installation of the concrete or any other materials shall be refinished to match original condition by skilled personnel of the trades involved at no additional expense to the Government.
B. Finished surfaces of existing facilities that are affected, marred, scratched, or damaged by the contractor shall be refinished to match original condition.
1. Patching material shall be of the same type, style, and thickness, and shall be finished to match existing adjacent surface construction in color and texture.
2. Patching material, paint color, paint material and paint application methods shall be approved in advance by the Contracting Officer’s Representative.
C. No building structural members shall be cut or altered without prior approval of the Contracting Officer's Representative.
D. Any damage resulting from contractor's operation shall be brought to the attention of the Contracting Officer's Representative immediately.
E. The contractor shall take all necessary and reasonable measures to keep the work site clean of trash and debris. Work areas shall be cleaned immediately as work in that area is completed, and before moving to a new work site. Place all trash and debris in OSHA approved containers, remove, and dispose of trash off site daily.
F. The contractor shall move all materials and equipment, including ladders and scaffolding from the site at the completion of each day's operation unless otherwise approved by the Contracting Officer's Representative.
G. The contractor shall provide proper safety equipment to workmen and ensure a safe environment for employees and the general public at all times. The contractor shall work to ensure free, unobstructed, and safe access to and about the work area.
1.07 Temporary Facilities
A. Utilities: The existing USDA utilities at the site may be used by the Contractor for completion of the contract work at no cost to the Contractor. The Contractor shall be responsible for making and removing any utility connections.
B. Telephones: The Contractor shall equip all his foremen and work leaders with cell phones as necessary to coordinate the work effort. The Government will not provide any phone service to the project.
C. Construction Material Storage Trailer: The Contractor may locate a construction material storage trailer to the site. Location shall be coordinated with the COR prior to delivery of any materials and/or construction beginning on site.
D. Toilet Facilities: The Contractor shall provide and maintain portable toilet facilities for the project workmen.
1.08 Confined Space Program
A. The Contractor and/or subcontractor employees who will be entering Confined Spaces shall be adequately trained and equipped for access and extraction. The Contractor shall provide all ventilation equipment, air quality monitoring, harnesses, and other safety equipment as appropriate for OSHA compliance. The Contractor’s Confined Space program shall substantially conform to the NCAH plan.
B. The Contractor shall submit a written copy of their plan(s) for acceptance by the
COR prior to entry into any confined spaces.
C. The Contractor shall provide copies of entry logs and monitoring to the Owner’s
Representative at any time requested during the project effort.
1.09 Lock-out/Tag-out Program
A. The Contractor and/or subcontractor employees who will be working on the job will apply a lockout/tagout (LOTO) process to control dangerous energy sources. The Contractor/subcontractor shall have a LOTO program established and use Contractor LOTO locks, tags, and procedures.
B. The Contractor/subcontractor shall review their LOTO program with NCAH FEU personnel to coordinate LOTO programs before implementing LOTO.
1.10 Hot Work Plan
A. The Contractor/subcontractor shall have a written plan in place to manage the safety and fire hazards associated with hot work. The Plan shall include fire watch and all other requirements in accordance with OSHA. The Contractor/subcontractor shall maintain written records of hot work until final acceptance of the project and shall provide copies to the Owner’s Representatives at any time requested.
1.11 Submittal & Shop Drawings Procedures
A. Submittal Register: At the beginning of the project, the Contractor will provide a Submittal Register identifying all the items called out in the Specifications for submittal to the COR for approval. The Contractor will update and maintain the Submittal Register to show the current status of all required submittals.
B. Submittal Requirements
1. Format: There is no formal submittal transmittal or format for this project other than the documents shall be submitted as PDF files, scanned or created in documents that can be easily read when printed on 11x17 sheets. Exceptions for larger sheet sizes will be considered by the COR. Failure of the Contractor to provide legible submittals will be adequate grounds for rejection.
2. Identification: Submittals shall be labeled and marked for this project. The identification shall include: Contractor/subcontractor’s name, date of submittal, description of item, specification section, and details on product data that are marked clearly for this project.
C. Submittal Procedures: All submittals will be posted in PDF by the Contractor to the
Contracting Officer’s Representative (COR) for review and approval. This same submittal process will be used for RFIs, Change Bulletins, etc.
D. Approved Submittals: The approval/acceptance of submittals is not to be construed as a complete check. Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist.
E. Submittal items for this project :
1. Backfill materials
2. Piping repair materials,
3. Paving and landscaping materials used
1.12 Close-out Submittals
A. Warranty Documentation
1. Warranty List: Provide a warranty summary sheet in spreadsheet format with all the warranties listed by section, description, supplier, warranty contact, start date, end date. Provide electronic copy to the COR and place printed copy in the front of the Warranty Binder.
2. Warranty Copies in Binder: Provide one signed & dated copy of all warranties for products and equipment installed on the project. The Warranty binder shall be divided by Specification Section and shall be provided to the COR. An electronic (scanned) copy of the Warranty Binder in a PDF file shall be submitted with the final close-out documentation.
B. Operation & Maintenance Manuals: Contractor shall provide a printed copy of all
Operation & Maintenance documentation provided with equipment and systems installed in the project and place the manuals in an organized binder. The O&M
Manuals shall be organized by specification section and shall have an index at the front of the binder. The Contractor shall also provide a PDF version of the Manuals to be submitted with the close-out documentation.
C. Record Drawings
1. Redline Specifications: During the construction period the Contractor shall keep an updated & marked-up or “redline” copy of the project specifications on the jobsite. The redline set shall include notes on changes, RFI responses, and other field notes. At the end of the project the Contractor shall electronically scan the redline specifications and provide an electronic copy in PDF to the Owner along with the close-out documentation.
2. Redline Drawings: During the construction period the Contractor shall keep an updated “redline” or “conformed” copy of the project drawings on the jobsite. The redline set shall include notes on changes, RFI responses, and other field notes.
At the end of the project the Contractor shall electronically scan the redline drawings at full-size and in color and provide an electronic copy in PDF to the Owner along with the close-out documentation.
END OF SECTION