2. Scope of Work.pdf

PDF 235 KB Posted

Attached to
Replace Toilets at Bates Canyon Campground (GAOA)
Solicitation number
1148294
Issued by

About this file

This document is a Statement of Work (SOW) for the USDA Forest Service project to replace toilets at Bates Canyon Campground in the Santa Lucia Ranger District of Los Padres National Forest. The project involves installing a new single vault precast concrete toilet building to replace two existing older vault toilet buildings, with associated site improvements including grading, excavation, concrete sidewalks, building aprons, and site preparation. The contract requires the contractor to develop a grading plan, perform all necessary excavation and site work, install the new toilet building, construct accessible sidewalks, compact base materials, demolish existing structures, and obtain all necessary permits. The work is to be completed between August 29, 2025, and March 12, 2026, with a contract value between $100,000 and $250,000, subject to Davis-Bacon wage requirements and bonding for projects over $35,000.

View the file

Other files

File Type Posted
10. SAM.gov Q&A.xlsx XLSX spreadsheet
4. Evaluation Factors.pdf PDF
3. Schedule of Items.pdf PDF
9. Davis-Bacon Act WD # CA20240014 (Santa Barbara County).txt TXT text file
10. SAM.gov Q&A.xlsx XLSX spreadsheet
5. Forest Service Supplemental Specifications.pdf PDF
6. Site Plan.pdf PDF
7. Fire Plan.pdf PDF
8. CXT Vault Restroom v.2 (Example Only).pdf PDF
1. SF 1442 - 127EAW25R0023 (NRE Included).pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

GAOA Replace Toilets at Bates Canyon Campground

Contents Project General Information

1.0 Scope of Work

2.0 Background

Contractor Requirements

3.0 Technical Requirements / Tasks

4.0 Government Furnished

5.0 Deliverables / Schedule

6.0 Travel

7.0 Contractor’s Key Personnel

8.0 Security Requirements

9.0 Data Rights

10.0 Section 508 – Electronic and Information Technology Standards Attachment ............................................................................................................................................. Error! Bookmark not defined.

Project Bates Canyon Campground SST Vault Toilet

General Information

1.0 Scope of Work

This project consists of installing a vault toilet, and other site improvements at Bates Canyon Campground located on the Santa Lucia Ranger District of the Los Padres National Forest.

2.0 Background

Bates Canyon Campground is located in the eastern portion of the Santa Lucia Ranger District, at the base of the Sierra Madre mountains. The campground consists of six camp sites, and is currently two older vault toilet buildings. This contract requirement shall replace the two existing buildings with one new SST concrete toilet building, including the associated site work.

Contractor Requirements

3.0 Technical Requirements / Tasks

Contract includes, but is not limited to, the following items of work:

1. Grading Plan Development.

2. Excavation and embankment required for toilet building installation and accessible sidewalks.

3. Provide and install Single Vault Precast toilet building or equivalent as approved by the contracting officer.

4. Construction of concrete sidewalks, building aprons, and associated site preparation.

5. Provide and compact base at optimum moisture for the installation of vault toilet building. Backfill shall be compacted in 8 inch lifts (compacted) at optimum moisture.

6. Demolition and removal of two existing toilet buildings.

7. Obtain permits if required for the work listed above and any other permits necessary to complete the project.

All permits are the responsibility of the contractor, and will not be provided by the government.

4.0 Government Furnished

No Government Furnished Materials

5.0 Deliverables / Schedule

• All deliverables and documents shall be presented to the Contracting Officer.

• Contractor to adhere to product submittals detailed in the specifications.

• The Contractor's hours of operation shall be restricted to 8:00 am to 4:30 pm, Monday through Friday. Work shall be shut down on Saturdays, Sundays and all Federally listed Holidays.

Item No. Deliverable Objective Due 1 Proposed Project Plan Defining the responsibilities, timeline, risks and milestones of contract objective.

No later than five (5) business days after contract award

2 Grading Plan Grading plan to ensure that the project improvements meet ADA accessible route (finished floor elevation and sidewalk) and that the site has properly functioning drainage, post construction.

No later than twenty (20) business days after contract award.

3 Pre-Cast Concrete Toilet Product Data

Proposed Pre-Cast Concrete Toilet product for installation in accordance with the project specifications and applicable codes.

No later than ten (10) business days after contract award

3 Product/Material Data Proposed Materials for installation in accordance with the project specifications and applicable codes

No later than ninety (90) days after contract award

4 Weekly Status Report Report documenting tasks & issues weekly. Weekly, every Friday, by 3:00 PM PST until the contract expires

6.0 Travel

Project location - From Santa Lucia District Office (1616 Carlotti Drive, Santa Maria, CA), take Bull Canyon Road to CA – 166 (3.6 miles), turn right onto CA – 166 East (36.2 miles), turn right onto Cottonwood Canyon Road and Forest Service Route 11N01 to Bates Canyon Campground.

7.0 Contractor’s Key Personnel

TBD

8.0 Security Requirements

There is no onsite security for this project except gates which may or may not be locked. All materials, supplies, vehicles, and equipment associated with the project is the responsibility of the contractor until completion and final acceptance by the Contracting Officer.

9.0 Data Rights

N/A

10.0 Section 508 – Electronic and Information Technology Standards N/A

Project
General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements
9.0 Data Rights
10.0 Section 508 – Electronic and Information Technology Standards