2. Schedule.docx

DOCX document 15 KB Posted

Attached to
127EAW22R0064 - Paskenta and Covelo Metal Roof
Solicitation number
127EAW22R0064
Issued by

View the file

Other files

File Type Posted
A00001 - RFI Responses.pdf PDF
1. Statement of Work.pdf PDF
5. WD Davis-Bacon Act WD #CA20220004.pdf PDF
3. Specifications.pdf PDF
6. RFI Form.docx DOCX document
127EAW22R0064 - Paskenta and Covelo Metal Roof.pdf PDF
4. Project Maps & Pictures.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PART I—THE SCHEDULE

SECTION B-- SCHEDULE OF ITEMS

B.1 SCHEDULE OF ITEMS - (BASE CONSTRUCTION)

Item
Construction Items
Qty
UOI
Unit Price
Total Price
01 90 00
Mobilization
1
Lump Sum
07 41 13 (b)
Metal Roof Demo / Install, Covelo
1
Lump Sum
BASE TOTAL:
___________

B.1 SCHEDULE OF ITEMS - (OPTION 1)

Item
Construction Items
Qty
UOI
Unit Price
Total Price
07 41 13 (a)
Metal Roof Demo / Install, Paskenta
1
Lump Sum
OPTION 1 TOTAL:
___________
BASE + OPTION 1 TOTAL:
___________

B.2 SCHEDULE NOTES

* QUANITIES ARE ESTIMATED, CONTRACTOR SHALL FIELD VERIFY TO SATISFY ALL REQUIREMENTS OF THE DRAWINGS, STATEMENT OF WORK, AND SPECIFICATIONS.

NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price.

Company Name:
POC & Title:
Email:
Phone Number:
DUNS Number:
Tax ID: