1. Statement of Work.pdf
PDF 127 KB Posted
- Attached to
- 127EAW22R0064 - Paskenta and Covelo Metal Roof
- Solicitation number
- 127EAW22R0064
- Issued by
-
Department of Agriculture Forest Service
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A00001 - RFI Responses.pdf | ||
| 5. WD Davis-Bacon Act WD #CA20220004.pdf | ||
| 2. Schedule.docx | DOCX document | |
| 3. Specifications.pdf | ||
| 6. RFI Form.docx | DOCX document | |
| 127EAW22R0064 - Paskenta and Covelo Metal Roof.pdf | ||
| 4. Project Maps & Pictures.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C.1 DESCRIPTION OF WORK
The intent of this contract includes but is not limited to: furnishing all labor, equipment and materials necessary to remove and replace metal roofing, metal ridge, and gable and eve flashing on one building located on the Mendocino National Forest and a BID OPTION for a second building located on the Mendocino National Forest. See project specifications for details.
C.2 PROJECT LOCATIONS
Paskenta: 13280 Paskenta Road, Paskenta CA 96074 Covelo: 78150 Covelo Road, Covelo CA 95926
C.3 CONTRACT TIME
Contractor shall complete the work as stated in Section F. The time stated for completion shall include final cleanup of the premises.
C.4 SPECIAL CONDITIONS AFFECTING WORK
(a) Surveys - The indications of physical conditions on the drawings and in the specifications are the result of site investigations by surveys and measurements performed by the Government.
(b) Weather - Weather conditions should not be a problem for this project during the contract time period. Note the contract time in Section F.
(c) Access - Contractor will have access to the work site during the contract time period by Forest Service and County roads.
(e) Use of Utilities – Not available.
(f) Tracked Equipment - Tracked Equipment will not be permitted on bituminous and concrete surfaces unless proper precautions are taken to protect them.
C.5 TECHNICAL SPECIFICATIONS
(a) A list of CSI Specifications that are included and applicable to this solicitation are as follows:
NO. PAGES
DIVISION 1 – GENERAL REQUIREMENTS
01 30 00 Shop Drawings and Submittals 2
01 80 00 Project Clean Up 1
01 90 00 Mobilization 1
DIVISION 7 – THERMAL AND MOISTURE PROTECTION
07 14 13 Preformed Metal Roof Panels 4
SECTION F--DELIVERIES OR PERFORMANCE
FAR 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF
WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives Notice to Proceed, (b) presecute the work diligently, and (c) complete the entire work ready for use not later that 30 days after receipt of the Notice to Proceed. The anticipated start work date is September 5th, 2022.
AGAR 452.236-75 MAXIMUM WORKWEEK – CONSTRUCTION SCHEDULE
(NOV 1996)
Within seven (7) calendar days after receipt of a written request from the Contracting Officer, the Contractor must submit the following information in writing for approval:
(a) A schedule as required by FAR clause 52.236-15, SCHEDULES FOR
CONSTRUCTION CONTRACTS, and
(b) The hours (including the daily starting and stopping times) and days of the week the Contractor proposed to carry out the work.
PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
SECTION J--LIST OF ATTACHMENTS
Attachments Number of Pages
Maps and Photographs 4
Special Project Specifications 8
SECTION L--INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS
OR RESPONDENTS
FAR 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site
Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
A pre-bid tour will not be held. The Contractor is encouraged to visit the site prior to submitting a bid.
File details come from the government source that posted it. Updated .