This is a Performance-Based Work Statement (PWS) for an AVB (Anti-Vehicle Barrier) Assessment at the 147th Security Forces Squadron, Ellington Field JRB, Texas, dated 8 July 2026.

The contractor must provide all management, tools, supplies, equipment, and labor necessary to troubleshoot and assess six (6) existing wedge barriers to determine if replacement of electrical and hydraulic components alone will resolve functionality issues or if the entire barrier system requires replacement. Basic services include: (1) hooking up temporary hydraulic hoses and electrical lines to the government-furnished wedge barriers; (2) performing physical tests to ensure barriers fully deploy, maintain deployed position for 60 seconds, and fully retract upon command; (3) conducting visual assessment to identify corrosion or rust damage and evaluating whether such damage would degrade system capability; (4) returning barriers to inert/inoperative condition post-testing; and (5) providing a written report detailing test criteria, results, and recommendations for permanent repair. The contractor must complete a Contractor Verification Test (CVT) with government personnel present to observe and concur on the assessment findings. Normal hours of operation are Tuesday through Friday, 0700-1700, excluding federal holidays, though extended hours may be approved at no additional cost. The contractor must comply with security requirements including completion of 147 ATKW Form 17 visitor/contractor pass applications, establish a comprehensive Quality Control Program, maintain records, follow environmental compliance protocols, implement safety procedures, and report any accidents or incidents within one hour.

View the file

Other files

File Type Posted
3. SCA WD.pdf PDF
1. Combo W50S77-26-Q-0012.pdf PDF
Appendix B - K12 Operation and Maintenance Manual.pdf PDF
Appendix A - K12 Wedge Flyer.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE-BASED WORK STATEMENT (PWS)

FOR

AVB Assessment

147th SECURITY FORCES SQUADRON

ELLINGTON FIELD JRB, TEXAS

8 July 2026

DISTRIBUTION STATEMENT C: Distribution authorized to U.S. Government agencies and their Contractors for Administrative and Operational Use. Other requests for this document shall be referred to 147th Attack Wing Contracting Office.

DESTRUCTION NOTICE: Destroy by any method that will prevent disclosure of contents or reconstruction of the document.

PERFORMANCE-BASED WORK STATEMENT

TABLE OF CONTENTS

SECTION PAGE

1 DESCRIPTION OF SERVICES 3

2 SERVICES SUMMARY 3

3 GOVERNMENT FURNISHED PROPERTY AND SERVICES 4

4 GENERAL INFORMATION 4

5 APPENDICES 7

1. DESCRIPTION OF SERVICES. The contractor shall provide all management, tools, supplies, equipment, and labor necessary to troubleshoot and determine the functionality of the existing six (6) wedge barriers in relation to hinge points, gearing, corrosion and/or rust damage to existing wedge surfaces, etc. This assessment is to determine if replacement of electrical and hydraulic components alone will fix the barriers, or if the whole barrier system needs to be replaced.

1.1. Basic Services:

1.1.1. Hook up temporary hydraulic hoses and electrical lines to the GFE wedge barriers.

1.1.2. Perform a physical test of the six (6) GFE existing wedge barriers.

1.1.3. The test will ensure that the wedge barriers will fully deploy, maintain deployed position (60 seconds), and fully retract upon command.

1.1.4. By visual assessment, determine (if any) corrosion or rust damage is present and if damage is observed will it degrade the wedge system capability to function as designed by manufacturer.

1.1.5. Upon completion of the test, contractor will return GFE wedge barriers to the inert/inoperative condition before the test began.

1.1.6. Provide government with a written report of test criteria, results, and recommendations for the permanent repair of the six (6) AVBs.

1.2. Contractor Verification Test (CVT): Contractor testing shall include individual equipment inspection/test; as listed above in basic service paragraphs. Once testing completed, the barriers will be placed back into a safe inert status awaiting approval on final repair decisions by the 147 ATKW leadership.

1.3. Government Acceptance Testing (GAT): The Government will be present to observe CVT to evaluate and concur with Contractor on the assessment of the six (6) GFE wedge barrier condition and operational performance.

2. SERVICES SUMMARY.

Performance Objective SOW Para Performance Threshold Hookup temp hydraulic & electric to wedge barriers

1.1.1. Must pass field testing conducted by

contractor

Operate (open & close) wedge barriers

1.1.2. Must pass field testing conducted by

contractor

Validate full functionality of wedge barriers

1.1.3. Must pass field testing conducted by

contractor

Visually assess for corrosion or rust structural damage on wedge barriers

1.1.4. Must pass field testing conducted by

contractor

Return wedge barriers to inert status

1.1.5. Must pass field testing conducted by

contractor

Provide gov’t. written report of test criteria findings

1.1.6. Must pass field testing conducted by

contractor

3. GOVERNMENT FURNISHED PROPERTY AND SERVICES. None

4. GENERAL INFORMATION.

4.1. Security Requirements. The contract administrator shall complete a 147 ATKW Form 17 “visitor/contractor pass application” for each employee of the contractor requiring access to Ellington Field JRB. The requests shall be submitted to 147 SFS Visitor Control Center (VCC) (Bldg #1035, 147 SFS). Hours of operation are from 0700 to 1600, Monday through Friday.

4.1.1. Access and General Protection/Security Policy and Procedures. This standard language is for contractor employees with an area of performance within Government controlled installation, facility, or area. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

4.1.2. For Contractors that do not require CAC, but require access to a DoD Facility and/or Installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (DAFI 10-245, DAFI 31-101 and DAFMAN 31-101V3), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

4.2. Quality Control Program. In compliance with the clause entitled “Inspection of Services”, 52.246-4, the contractor shall establish a complete Quality Control Program to ensure the requirements of this contract are provided as specified. The contracting officer will notify the contractor of acceptance or required modifications to the plan before the contract start date.

The contractor shall make appropriate modifications (at no additional costs to the government) and obtain acceptance of the plan by the contracting officer before the start of the first operational performance period.

4.3. Quality Assurance. The government will periodically evaluate the contractor’s performance by appointing a representative(s) to monitor performance to ensure services are received. The government representative will evaluate the contractor’s performance through intermittent on-site inspections of the contractor's quality control program and receipt of complaints from base personnel. The government may inspect each task as completed or increase the number of quality control inspections if deemed appropriate because of repeated failures discovered during quality control inspections or because of repeated customer complaints. Likewise, the government may decrease the number of quality control inspections if merited by performance. The government will also investigate complaints received from various customers located on the installation. The contractor shall be responsible for initially validating customer complaints. However, the government representative shall make final determination of the validity of customer complaint(s) in cases of disagreement with customer(s).

4.3.1. Quality Assurance Personnel (QAP): The Quality Assurance Personnel QAP(s) is the authorized government representative(s) who will perform assessments of the contractor’s performance.

4.3.2. The QAP(s) or alternate(s) will inform the contract manager in person when discrepancies occur and will request corrective action. The QAP(s) or alternate(s) will make a notation of the discrepancy on their surveillance checklist with the date and time the discrepancy was noted and will request the contract manager (or authorized representative) to initial the entry on the checklist.

4.4. Any matter concerning a change to the scope, prices, terms or conditions of this contract shall be referred to the Contracting Officer and not to the QAP(s).

4.5. The services to be performed by the contractor during the period of this contract shall at all times and places be subject to review by the Contracting Officer or authorized representative(s).

4.6. PHYSICAL SECURITY. The contractor shall be responsible for safeguarding all government property provided for contractor use. At the close of each work period, government facilities, property, and materials shall be secured.

4.7. Contractor ID Control. The contractor shall establish and implement methods of ensuring that all contractor ID cards issued to the contractor by the 147 SFS are not lost or misplaced.

Report lost/stolen ID cards to SFS immediately. The contractor shall prohibit the unauthorized use of contractor ID cards issued by Security Forces to any person other than the contractors.

4.8. HOURS OF OPERATION.

4.8.1. Normal Hours of Operation. The contractor shall perform the services required under this contract during the following hours: Tuesday – Friday, 0700-1700, with the exception of federal holidays. The contractor may work, with prior approval of the

Contracting Officer, extended hours to ensure timely completion of work at no additional cost to the government.

4.8.2. Recognized Holidays. The contractor is not required to provide service on the following days: New Year’s Day, Martin Luther King Day, Presidents Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans Days, Thanksgiving Day, Juneteenth Day, and Christmas Day. If the holiday falls between Saturday-Monday, it is observed on Friday.

4.9. CONSERVATION OF UTILITIES. The contractor shall instruct employees in utilities conservation practices. The contractor shall be responsible for operating under conditions which prevent the waste of utilities which include the following:

4.9.1. Lights shall be used only in areas where and when work is actually being performed.

4.9.2. Mechanical equipment controls for heating, ventilation, and air conditioning systems shall not be adjusted by the contractor or by contractor employees unless authorized.

4.9.3. Water faucets or valves shall be turned off after the required use has been accomplished.

4.9.4. Government telephones shall be used only for official government business.

4.10. RECORDS. The contractor shall be responsible for creating, maintaining, and disposing of only those government required records that are specifically cited in this PWS or required by the provisions of a mandatory directive listed in Appendix C, Applicable Publications and Forms. If requested by the Government, the contractor shall provide the original record, or a reproducible copy of any such record within five working days of receipt of the request.

4.11. ENVIRONMENTAL CONTROLS:

4.11.1. Compliance with Laws and Regulations. The contractor shall be knowledgeable of and comply with all applicable Interstate, Federal, State, and Local laws, regulations, and requirements regarding environmental protection. In the event environmental laws/regulations change during the term of this contract, the contractor is required to comply as such laws come into effect. If there is an increase or decrease in cost as a result of the change, the contractor shall inform the Contracting Officer pursuant to notice requirements and negotiate a modification to the contract.

4.11.2. Notification of Environmental Spills. If the contractor spills or releases any substance contained in 40 CFR 302 into the environment, the contractor or its agent shall immediately report the incident to Ellington Field JRB Fire Dept. at 281-929-2337. The liability for the spill or release of such substances rests solely with the contractor and its agent.

4.11.3. Material Storage and Use. The contractor shall follow manufacturer’s guidelines and professional recommendations for control of humidity, temperature, cleanliness, and materials handling. This includes hazardous materials.

4.12. GOVERNMENT OBSERVATIONS. Government personnel, other than contracting officers (COs) and quality assurance personnel (QAPs), may from time-to-time, with CO coordination, observe contractor operations. However, these personnel may not interfere with contractor performance or make any changes to the contract.

4.13. SAFETY REQUIREMENTS. In performing work under this contract, the contractor shall:

4.13.1. Conform to the safety requirements contained in the contract for all activities related to the accomplishment of the work.

4.13.2. Take such additional immediate precautions as the contracting officer may reasonably require for safety and mishap prevention purposes.

4.13.3. Develop and provide at the start of the orientation period or the start of the first operational performance period (if there is no orientation period) a safety plan for the protection of government facilities and property and to provide a safe work environment for contractor personnel.

4.13.4. Provide protection to government property to prevent damage during the period of time the property is under the control or in possession of the contractor.

4.13.5. Include a clause in all subcontracts to require subcontractors to comply with the safety provisions of this contract as applicable.

4.13.6. Record and report promptly (within one hour) to the contracting officer or designated government representative (GR), all available facts relating to each instance of damage to government property or injury to either contractor or government personnel.

4.13.7. In the event of an accident/mishap, take reasonable and prudent action to establish control of the accident/mishap scene, prevent further damage to persons or property, and preserve evidence until released by the accident/mishap investigative authority through the contracting officer.

4.13.8. If the government elects to conduct an investigation of the accident/mishap, the contractor shall cooperate fully and assist government personnel in the conduct of investigation until the investigation is completed.

4.13.9. Include a clause in each applicable subcontract requiring the subcontractor's cooperation and assistance in accident reporting and investigation.

5. APPENDICES

A. Ameristar Sentinel K12 Wedge Flyer B. Ameristar Sentinel K12 Wedge Operation & Maintenance Manual

1 DESCRIPTION OF SERVICES 3
2 SERVICES SUMMARY 3
3 GOVERNMENT FURNISHED PROPERTY AND SERVICES 4
4 GENERAL INFORMATION 4

File details come from the government source that posted it. Updated .