This document is a detailed Deliverables Table for the Biomedical Research Application Evaluation and Support Services (BRAES) contract. The table outlines 47 specific deliverables with precise timelines, ranging from daily to annual reporting requirements. Key deliverables include compliance tracking sheets, application review reports, reviewer recruitment documentation, summary statements, data file transfers, budget reports, and administrative documentation. Deliverables are primarily related to managing electronic research application processes, including pre-application and full application reviews, panel member identification, peer review coordination, score reporting, and technical support documentation. Each deliverable specifies the Performance Work Statement (PWS) reference, distribution method, and specific timeline for submission, with most requiring submission within 1-20 business days of specified events. The deliverables are designed to support comprehensive tracking, review, and management of biomedical research applications across multiple funding cycles.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1b. BRAES_MultiAward.pdf | ||
| 1a. CDMRP Data flows.pdf | ||
| 1. PWS.docx | DOCX document | |
| 3. LCATs and Descriptions Final Draft.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DELIVERABLES
Minimum deliverables for this contract, as solicited, are outlined in the Deliverables Table below.
All listed deliverables shall flow down into all Task Orders, unless stated otherwise. Additionally, if a deliverable is irrelevant for a specific Task Order, it can be ignored. Other deliverables may be included at the task order level.
| Item |
| PWS |
Reference
| Title |
| Distribution |
| Initial |
Deliverable 1
4.0
Deliverables/Receivables Tracking Sheet (D/RTS)
PM
NLT 10 business days after the last FOA of the cycle release. (Template with agreed upon elements, to be provided by the government)
Deliverable 2
4.4.1.1 eBRAP set-up and compliance Specification Sheets/Checklist (DRAFT and FINAL versions)
| Per DRTS |
| Within 10 Business Days after FOA release |
(Template with agreed upon elements, to be provided by the government)
Deliverable 3
4.1.3.3 Listing of pre- applications with compliance issues and administrative modifications in eBRAP
Per DRTS
1) Within 24 hrs for automated compliance; 2) NLT 2 business days for < 250 pre-applications;
3) NLT 4 business days for >250 pre-applications.
Deliverable 4
4.1.3.4 Listing of full applications with compliance issues and administrative modifications in eBRAP
1) Within 48 hrs for automated compliance; 2) NLT 3 business days for < 100 applications; 3) NLT 5 business days for 101-250 applications; 4) NLT 7 business days for >250 applications
Deliverable 5
4.4.4.21 Programmatic panel member identification report (pre-applications)
NLT 1 business days after compliance review is complete
Deliverable 6
4.4.4.21 Programmatic panel member identification report (full applications)
5 business day after application compliance completion
Deliverable 7
4.1.3.5 Multiple Submission Report (eBRAP)
Same day as application compliance completion
Deliverable 8
4.1.3.7 Annual Template Letter for non-compliant notification
Within 20 Business Days following release of the first fiscal year FOA
Deliverable 9
4.5.4 Summary of Program Deliverables Report
Quarterly
Deliverable 10
4.4.3.2 Review specification sheets (RSS) by mechanism
NLT 10 business days prior to preapplication receipt
Deliverable 11
4.4.4.13 Recruited Reviewers Report I
10 business days after application receipt
Deliverable 12
4.4.4.43 Recruited Reviewers Report II
15 business days prior to peer review meeting
Deliverable 13
4.4.4.14 OCI Report
15 business days prior to peer review meeting
Deliverable 14
4.4.4.18 Consumer Nomination materials
Annually
Deliverable 15
4.4.4.18
Consumer Outreach Plan
NLT 20 Business Days following Vision Setting or Strategic Planning Meeting
Deliverable 16
4.4.4.10
Reviewer demographics report
NLT 15 business days after peer review meeting, if requested; optional deliverable at the task order level
Deliverable 17
4.4.4.11 Peer Reviewer Debriefing Report
NLT 15 business days prior to programmatic review meeting, or as specified in task order
Deliverable 18
4.4.5.2 Expedited (triage) review report
2 business days prior to peer review meeting
Deliverable 19
4.4.5.3
Final score report
1 business day after peer review meeting
Deliverable 20
4.4.5.4
Pre/post score comparison report
NLT 1 business day after peer review meeting, if requested; optional deliverable at the task order level
Deliverable 21
4.4.5.5 Score Distribution Reports
NLT 2 business days after delivery of Final Score Report
Deliverable 22
4.4.5.6 All reviewers for all cycles report for web posting
NLT 30 business days after last peer review meeting for all cycles
Deliverable 23
4.4.7.2 Draft Summary Statements
As they become available
Deliverable 24
4.4.7.3
Accelerated (non-fully edited, non-PI version) Summary Statements (if applicable)
NLT 15 Business Days prior to the appropriate programmatic review meeting.
Deliverable 25
Assigned Summary Statements
NLT 15 Business Days prior to the appropriate programmatic review meeting
Deliverable 26
Unassigned Summary Statements
NLT 5 Business Days prior to programmatic review meeting
Deliverable 27
Re-Review Summary Statements
PM
NLT 5 Business Days after the re- review peer review meeting
Deliverable 28
Principal Investigator version of Summary Statements (if applicable)
NLT 2 weeks after the programmatic review meeting
Deliverable 29
4.4.6.1 Administrative notes Transfer to EGS
NLT 1 business day after All Summary Statements delivery
Deliverable 30
4.1.4.1 Original pre-application data and files (eBRAP)
1 business day after pre- application receipt
Deliverable 31
Original Full Application Data and Files (eBRAP)
5 business days after application receipt
Deliverable 32
4.6.1 Full Application Budget Report
6 business days after application receipt
Deliverable 33
Compliant version of pre- application data
1 business day after compliance report approval and decision
Deliverable 34
Compliant version of pre- application files
1 business day after compliance report approval and decision
Deliverable 35
Compliant version of full application files (Peer Reviewed Application Files I)
1 business day after compliance is complete
Deliverable 36
Compliant version of full application data
Up to 20 business days after application receipt
Deliverable 37
4.6.1 Application Score Data
2 business days after peer review meeting
Deliverable 38
Compliant version of full application files (Peer Reviewed Application Files II) (eBRAP)
2 business days after peer review meeting
Deliverable 39
4.6.2 Reviewer online/webinar orientation briefing
NLT 10 business days prior to webinar
Deliverable 40
4.6.5.1 List of conferences and meetings for reviewer recruitment purposes
NLT business 60-90 calendar days prior to conference/meeting
Deliverable 41
4.6.5.2 Summary of recruitment results from conferences/meeting
NLT 20 business days following the conference/meeting
Deliverable 42
4.9.1.1;
4.9.4.2 Requirements documents (traceability matrix, SOPs, epic reports mockups, project/sprint plans, backlog)
Within 5 days of request to support enhancements and new development efforts
Deliverable 44
4.1.5.6 Helpdesk tickets and responses
COR/PM
Monthly metrics report and continuous access to helpdesk system
| Deliverable 45 |
| Section H |
| Monthly Reporting – Base level (only) |
| COR/CS |
| 28th calendar day of each month. |
| Deliverable 46 |
| Section D |
| Draft Invoice-Provide base Contracting Officer’s Representative (COR) with a draft invoice for review prior to submission via WAWF. Backup documentation adequate enough to determine validity of all salary and non-salary costs shall be included. Upon receiving COR recommendation, the invoice may be submitted to WAWF. If contractor does not receive COR recommendation after 5 calendar days, the invoice may be submitted to WAWF. |
| Base COR |
| 5 calendar days prior to submitting each task order invoice to WAWF. |
| Deliverable 47 |
| 5.3 |
| CDMRP Confidentiality Agreement |
| Base COR |
| Upon contract award, onboarding new hires, and annually in January |