This document is a comprehensive specification volume for the Ada County Jail Phase 1 Kitchen Remodel and Site Work project, involving Ada County Operations and the Ada County Jail facility located in Boise, Idaho. The project encompasses a full remodel of the kitchen facility and associated site work, with detailed technical specifications spanning multiple divisions including architectural, mechanical, electrical, and plumbing systems. The project will be executed using a construction contract that requires providing materials and labor for comprehensive renovations, with the work being designed by Lombard/Conrad Architects and involving significant upgrades to the existing facility's infrastructure.
The specification volume provides extensive technical details across 33 divisions, covering everything from procurement requirements to specific equipment installations, with a particular focus on mechanical, electrical, and plumbing systems. The project appears to be funded directly by Ada County, with a projected completion date of July 25, 2025. The specifications indicate a comprehensive approach to the renovation, including specialized requirements for detention facility modifications, energy efficiency standards, seismic considerations, and specific technical specifications for equipment like boilers, HVAC systems, fire protection, and kitchen-specific installations. The documents suggest a thorough, standards-compliant approach to the renovation, with careful attention to technical details, safety requirements, and operational functionality.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 5-Bid26009 Veolia Bid Sheet.pdf | ||
| 3-Bid26009 Plans.pdf | ||
| 4-Bid26009 Bidders Bid Form.pdf | ||
| 1-Bid26009 Specifications Volume 1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIFICATION | VOL.2
PROJECT: Ada County Jail Phase 1 Kitchen Remodel & Site Work 7210 Barrister Dr.
Boise, ID 83704
OWNER: Ada County Operations 200 W. Front Street Boise, ID 83702
ARCHITECT: Lombard/Conrad Architects 472 W Washington Street Boise, ID 83702 208.345.6677
CONTACT: Ken Gallegos
JOB NO.: 24301.01
DATE: July 25, 2025
07/25/25
Ada County Jail Phase 1 Kitchen Remodel & Site Work 24301.01
Table of Contents 000110 - 1
TABLE OF CONTENTS
VOLUME 1 | DIV.00 – DIV.13
DIVISION 00 — PROCUREMENT AND CONTRACTING REQUIREMENTS
001116 - REQUEST FOR BID
002113 - INSTRUCTIONS TO BIDDERS
004114 - BIDDERS FORM
004393 - CHECK-OFF LIST FOR BID SUBMITTAL
004413 - EXHIBIT B QUALITY CONTROL SPECIFICATION
005132 - GEOTECHNICAL DATA
DIVISION 01 — GENERAL REQUIREMENTS
011000 - SUMMARY
011101 - SPECIAL CONDITIONS
011350 - SECURITY SCREWS
012100 - ALLOWANCES
012500 - SUBSTITUTION PROCEDURES
012600 - CONTRACT MODIFICATION PROCEDURES
012900 - PAYMENT PROCEDURES
013100 - PROJECT MANAGEMENT AND COORDINATION
013300 - SUBMITTAL PROCEDURES
013513.16 - SPECIAL PROJECT PROCEDURES FOR DETENTION FACILITIES
014000 - QUALITY REQUIREMENTS
014200 - REFERENCES
015000 - TEMPORARY FACILITIES AND CONTROLS
015400 - SECURITY
015723 - TEMPORARY STORM WATER POLLUTION CONTROL
016000 - PRODUCT REQUIREMENTS
017300 - EXECUTION
017329 - CUTTING AND PATCHING
017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
017700 - CLOSEOUT PROCEDURES
017823 - OPERATION AND MAINTENANCE DATA
017839 - PROJECT RECORD DOCUMENTS
017900 - DEMONSTRATION AND TRAINING
019113 - GENERAL COMMISSIONING REQUIREMENTS
DIVISION 02 — EXISTING CONDITIONS
024119 - SELECTIVE DEMOLITION
DIVISION 03 — CONCRETE
031000 - CONCRETE FORMING AND ACCESSORIES
032000 - CONCRETE REINFORCING
033000 - CAST-IN-PLACE CONCRETE
DIVISION 04 — MASONRY
042200 - CONCRETE UNIT MASONRY
DIVISION 05 — METALS
051200 - STRUCTURAL STEEL FRAMING
052100 - STEEL JOIST FRAMING
053100 - STEEL DECKING
055000 - METAL FABRICATIONS
055213 - PIPE AND TUBE RAILINGS
Table of Contents 000110 - 2
DIVISION 06 — WOOD, PLASTICS, AND COMPOSITES
061000 - ROUGH CARPENTRY
061600 - SHEATHING
066400 - PLASTIC PANELING
DIVISION 07 — THERMAL AND MOISTURE PROTECTION
071416 - COLD FLUID-APPLIED WATERPROOFING
072100 - THERMAL INSULATION
072500 - WEATHER BARRIERS
075419 - POLYVINYL-CHLORIDE (PVC) ROOFING
076200 - SHEET METAL FLASHING AND TRIM
078413 - PENETRATION FIRESTOPPING
078443 - JOINT FIRESTOPPING
079200 - JOINT SEALANTS
DIVISION 08 — OPENINGS
081113 - HOLLOW METAL DOORS AND FRAMES
083113 - ACCESS DOORS AND FRAMES
087100 - DOOR HARDWARE
088853 - SECURITY GLAZING
DIVISION 09 — FINISHES
092216 - NON-STRUCTURAL METAL FRAMING
092900 - GYPSUM BOARD
095113 - ACOUSTICAL PANEL CEILINGS
096513 - RESILIENT BASE AND ACCESSORIES
096516 - RESILIENT SHEET FLOORING
096900 - ACCESS FLOORING
099113 - EXTERIOR PAINTING
099123 - INTERIOR PAINTING
099600 - HIGH-PERFORMANCE COATINGS
DIVISION 10 — SPECIALTIES
101426 - POST AND PANEL-PYLON SIGNAGE
102600 - WALL AND DOOR PROTECTION
102800 - TOILET, BATH, AND LAUNDRY ACCESSORIES
102813.63 - DETENTION TOILET ACCESSORIES
104413 - FIRE PROTECTION CABINETS
104416 - FIRE EXTINGUISHERS
DIVISION 11 — EQUIPMENT
114000 - FOOD SERVICE EQUIPMENT
119812 - DETENTION DOORS AND FRAMES
119814 - DETENTION DOOR HARDWARE
DIVISION 13 — SPECIAL CONSTRUCTION
133423.16 - FABRICATED CONTROL BOOTHS
Table of Contents 000110 - 3
VOLUME 2 | DIV.21 – DIV.33
DIVISION 21 — FIRE SUPPRESSION
210500 - COMMON WORK RESULTS FIRE PROTECTION
211000 - WATER BASED FIRE PROTECTION
DIVISION 22 — PLUMBING
220500 - COMMON WORK RESULTS FOR PLUMBING
220509 - PLUMBING FIRE STOPPING
220513 - COMMON MOTOR REQUIREMENTS FOR PLUMBING EQUIPMENT
220523 - GENERAL DUTY VALVES FOR PLUMBING PIPING
220529 - HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT
220548 - VIBRATION AND SEISMIC CONTROLS FOR PLUMBING PIPING AND EQUIPMENT
220553 - IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT
220700 - PLUMBING INSULATION
221116 - DOMESTIC WATER PIPING
221119 - DOMESTIC WATER PIPING SPECIALTIES
221316 - SANITARY WASTE AND VENT PIPING
221319 - SANITARY WASTE PIPING SPECIALTIES
221413 - FACILITY STORM DRAINAGE PIPING
221423 - STORM DRAINAGE PIPING SPECIALTIES
224000 - PLUMBING FIXTURES
DIVISION 23 — HEATING VENTILATING AND AIR CONDITIONING
230500 - COMMON WORK RESULTS FOR HVAC
230513 - COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT
230519 - METERS AND GAUGES FOR MECHANICAL PIPING
230523 - GENERAL DUTY VALVES FOR HVAC PIPING
230529 - HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT
230548 - VIBRATION AND SEISMIC CONTROL FOR HVAC PIPING AND EQUIPMENT
230553 - IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT
230593 - TESTING ADJUSTING AND BALANCING FOR HVAC
230700 - HVAC INSULATION
230800 - COMMISSIONING OF HVAC
230923 - DIRECT DIGITAL CONTROLS FOR HVAC
231123 - FACILITY NATURAL GAS PIPING
232113 - HYDRONIC PIPING
232116 - HYDRONIC PIPING SPECIALTIES
232123 - HYDRONIC PUMPS
232513 - WATER TREATMENT FOR CLOSED LOOP HYDRONIC SYSTEMS
233113 - METAL DUCTS
233300 - AIR DUCT ACCESSORIES
233423 - HVAC POWER VENTILATORS
233713 - DIFFUSERS REGISTERS AND GRILLES
235216 - CONDENSING BOILERS
237424 - ROOFTOP MAKE UP AIR UNITS (MAU-1)
237443.13 - ROOFTOP HEATING AND COOLING UNITS RTU (7)
238000 - DECENTRALIZED HVAC EQUIPMENT
238316 - RADIANT HEATING HYDRONIC PIPING
Table of Contents 000110 - 4
DIVISION 26 — ELECTRICAL
260100 - BASIC ELECTRICAL REQUIREMENTS
260519 - LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
260523 - CONTROL-VOLTAGE ELECTRICAL POWER CABLES
260526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
260529 - HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
260533 - RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS
260543 - UNDERGROUND DUCTS AND RACEWAYS FOR ELECTRICAL SYSTEMS
260544 - SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND CABLING
260548 - VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS
260553 - IDENTIFICATION FOR ELECTRICAL SYSTEMS
260572 - OVERCURRENT PROTECTIVE DEVICE SHORT-CIRCUIT STUDY
260573 - OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY
260574 - OVERCURRENT PROTECTIVE DEVICE ARC-FLASH STUDY
260800 - ELECTRICAL COMMISSIONING REQUIREMENTS
260944 - NETWORK LIGHTING CONTROLS
262413 - SWITCHBOARDS
262416 - PANELBOARDS
262726 - WIRING DEVICES
262813 - FUSES
262816 - ENCLOSED SWITCHES AND CIRCUIT BREAKERS
262913 - MANUAL AND MAGNETIC MOTOR CONTROLLERS
263213 - ENGINE GENERATORS
263353 - STATIC UNINTERRUPTIBLE POWER SUPPLY
263600 - TRANSFER SWITCHES
265119 - LED INTERIOR LIGHTING
265219 - EMERGENCY AND EXIT LIGHTING
265613 - LIGHTING POLES AND STANDARDS
265619 - LED EXTERIOR LIGHTING
268000 - ELECTRICAL DEMOLITION AND REPAIR
DIVISION 27 — COMMUNICATIONS
270100 - BASIC COMMUNICATIONS REQUIREMENTS
271000 - COMMUNICATIONS
275133 - EMERGENCY RESPONDER RADIO COVERAGE SYSTEMS
DIVISION 28 — ELECTRONIC SAFETY AND SECURITY
280100 - BASIC ELECTRONIC SAFETY AND SECURITY REQUIREMENTS
280200 - DETENTION SECURITY ELECTRONICS SYSTEMS GENERAL PROVISIONS
280513 - CONDUCTORS AND CABLES FOR ELECTRONIC SAFETY AND SECURITY
283111 - DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM
285220 - DETENTION PROGRAMMABLE LOGIC CONTROLLERS
285230 - DETENTION TOUCHSCREEN CONTROL SYSTEM
285240 - DETENTION DIGITAL INTERCOM SYSTEM
DIVISION 31 — EARTHWORK
311000 - SITE CLEARING
312000 - EARTH MOVING
Table of Contents 000110 - 5
DIVISION 32 — EXTERIOR IMPROVEMENTS
321216 - ASPHALT PAVING
321313 - CONCRETE PAVING
321373 - CONCRETE PAVING JOINT SEALANTS
321723 - PAVEMENT MARKINGS
323113 - CHAIN LINK FENCES AND GATES
323114 - CHAIN LINK VERTICAL PIVOT GATES
323115 - CHAIN LINK AUTOMATED OVERHEAD BEAM SLIDING GATES
328400 - LANDSCAPE IRRIGATION
328500 - LANDSCAPE GRADING
329113 - SOIL PREPARATION
329200 - TURF AND GRASSES
329290 - TREE PROTECTION AND TRIMMING
329300 - PLANTS
DIVISION 33 — UTILITIES
331100 - SITE DOMESTIC WATER DISTRIBUTION
331300 - SITE SANITARY SEWERS
334100 - STORM DRAINAGE
COMMON WORK RESULTS FOR FIRE PROTECTION 210500 - 1
SECTION 210500 - COMMON WORK RESULTS FIRE PROTECTION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. All drawings associated with the entire project, including general provisions of the Contract, including The General Conditions of the Contract for Construction, General and Supplementary Conditions and Division-1 Conditions specification sections shall apply to the Division 21 specifications and drawings. The Contractor shall be responsible for reviewing and becoming familiar with the aforementioned and all other Contract Documents associated with the project.
B. Where contradictions occur between this section and Division 1, the more stringent requirement shall apply.
C. Contractor shall be defined as any and all entities involved with the construction of the project.
1.2 SUMMARY
A. This Section specifies the basic requirements for Fire Protection installations and includes requirements common to more than one section of Division 21. It expands and supplements the requirements specified in Division 1.
B. Security shrouds: DIV 21 is responsible for providing and installing security shrouds on all exposed sprinkler piping and module exposed ductwork where shown on drawing. Contractor shall coordinate with DIV 23 contractor.
1.3 DEFINITIONS
A. Finished Spaces: Spaces other than mechanical and electrical equipment rooms, furred spaces, pipe chases, unheated spaces immediately below roof, spaces above ceilings, unexcavated spaces, crawlspaces, and tunnels.
B. Exposed, Interior Installations: Exposed to view indoors. Examples include finished occupied spaces and mechanical equipment rooms.
C. Exposed, Exterior Installations: Exposed to view outdoors or subject to outdoor ambient temperatures and weather conditions. Examples include rooftop locations.
D. Concealed, Interior Installations: Concealed from view and protected from physical contact by building occupants. Examples include above ceilings and in chases.
E. Concealed, Exterior Installations: Concealed from view and protected from weather conditions and physical contact by building occupants but subject to outdoor ambient temperatures.
Examples include installations within unheated shelters.
F. The following are industry abbreviations for rubber materials:
1. EPDM: Ethylene propylene diene monomer rubber.
COMMON WORK RESULTS FOR FIRE PROTECTION 210500 - 2
2. NBR: Acrylonitrile-butadiene rubber.
1.4 FIRE PROTECTION INSTALLATIONS
A. The Contract Documents are diagrammatic, showing certain physical relationships which must be established within the Fire Protection work and its interface with all other work. Such establishment is the exclusive responsibility of the Contractor. Drawings shall not be scaled for the purpose of establishing material quantities.
B. Drawings and specifications are complementary. Whatever is called for in either is binding as though called for in both. Report any discrepancies to the Engineer and obtain written instructions before proceeding. Where any contradictions occur between the specifications and the drawings the more stringent requirement shall apply. The contractor shall include pricing for the more stringent and expensive requirements.
C. Drawings shall not be scaled for rough-in measurements or used as shop drawings. Where drawings are required for these purposes or have to be made from field measurement, Contractor shall take the necessary measurements and prepare the drawings.
D. The exact location for some items in this specification may not be shown on the drawings. The location of such items may be established by the Engineer during the progress of the work.
E. The contract documents indicate required size and points of terminations of pipes, and suggest proper routes to conform to structure, avoid obstructions and preserve clearances. It is not intended that drawings indicate necessary offsets. The contractor shall make the installation in such a manner as to conform to the structure, avoid obstructions, preserve headroom and keep openings and passageways clear, without further instructions or costs to the Owner. All equipment shall be installed so access is maintained for serviceability.
F. Before any work is installed, determine that equipment will properly fit the space; that required piping grades can be maintained and that ductwork can be run as intended without interferences between systems, structural elements or work of other trades.
G. Verify all dimensions by field measurements.
H. Coordinate installation in chases, slots and openings with all other building components to allow for proper installations.
I. Sequence, coordinate, and integrate installations of materials and equipment for efficient flow of the work. Give particular attention to large equipment requiring positioning prior to closing-in the building.
J. Where mounting heights are not detailed or dimensioned, install services and overhead equipment to provide the maximum headroom possible.
K. Install equipment to facilitate maintenance and repair or replacement of equipment components.
As much as practical, connect equipment for ease of disconnecting, with minimum of interference with other installations.
L. Make allowance for expansion and contraction for all building components and piping systems that are subject to such.
COMMON WORK RESULTS FOR FIRE PROTECTION 210500 - 3
M. The ceiling space shall not be “layered”. It is the contractor’s responsibility to offset and system as required to allow installation within the identified ceiling cavity. The contractor shall include labor and material in the base bid to accommodate such offsets.
N. In general, all “static” piping systems shall be routed as high as possible, i.e. fire protection systems. Keep all equipment in accessible areas such as corridors and coordinate with systems and equipment from other sections.
O. The Contractor shall provide all labor and material necessary but not limited to the starting/stopping of all equipment, opening/closing of all valves, draining/refilling all systems and operating/verifying the operation of all systems controls as required to accomplish all work necessary to meet construction document requirements. Contractor shall submit records of such activities to engineer and include in the O & M manuals.
1.5 COORDINATION
A. Work out all installation conditions in advance of installation. The Contractor shall be responsible for preparing coordination drawings, showing all work, in all areas. The Contractor shall be responsible for providing all labor and material, including but not limited to all fittings, isolation valves, offsets, hangers, control devices, etc., necessary to overcome congested conditions at no increase in contact sum. The Contractors base bid shall include any and all time and manpower necessary to develop such coordination efforts and drawings. Increases to contract sum or schedule shall not be considered for such effort.
B. Provide proper documentation of equipment, product data and shop drawings to all entities involved in the project. Coordination shall include, but not be limited to the following:
1. Fire Protection and Fire Alarm Contractor shall provide shop drawings to all other Division 23 Contractors.
C. Utility Connections:
1. Coordinate connection of Fire Protection systems with existing utilities and services.
Comply with requirements of governing regulations, franchised service companies and controlling agencies. Provide required connection for each service.
2. The contract documents indicate the available information on existing utilities and services and on new services (if any) to be provided to the project by utility companies and agencies. Notify Engineer immediately if discrepancies are found.
3. Coordinate utility interruptions one week in advance with the Owner and the Utility Company. Plan work so that duration of the interruption is kept to a minimum.
1.6 COORDINATION WITH OTHER DIVISIONS
A. General:
1. Coordinate all work to conform to the progress of the work of other trades.
2. Complete the entire installation as soon as the condition of the building will permit. No extras will be allowed for corrections of ill-timed work, when such corrections are required for proper installation of other work.
3. Coordinate with ductwork to be concealed within security soffit.
COMMON WORK RESULTS FOR FIRE PROTECTION 210500 - 4
B. Coordinate ceiling cavity space carefully with all trades. In the event of conflict, install mechanical and electrical systems within the cavity space allocation in the following order of priority:
1. Equipment and required clearances
2. Plumbing waste, cooling coil drain piping and roof drain mains and leaders.
3. Ductwork mains
4. Plumbing vent piping
5. Low pressure ductwork and air devices.
6. Electrical and communication conduits, raceways and cabletray.
7. Domestic hot and cold water
8. Fire sprinkler mains, branch piping and drops (locate as tight to structure as possible).
9. DDC control wiring and other low voltage systems.
10. Fire alarm systems.
C. Chases, Inserts and Openings:
1. Provide measurements, drawings and layouts so that openings, inserts and chases in new construction can be built in as construction progresses.
2. Check sizes and locations of openings provided. Including the access panels for equipment in hard lid ceilings and wall cavities.
3. Any cutting and patching made necessary by failure to provide measurements, drawings and layouts at the proper time shall be done at no additional cost in contract sum.
D. Support Dimensions: Provide dimensions and drawings so that concrete basis and other equipment supports to be provided under other sections of the specifications can be built at the proper time.
E. Coordinate the installation of required supporting devices and sleeves to be set in poured in place concrete and other structural components, as they are constructed.
F. Coordinate the cutting and patching of building components to accommodate the installation of equipment and materials. Refer to Division 1 and Division 21.
G. Modifications required as result of failure to resolve interferences, provide correct coordination drawings or call attentions to changes required in other work as result of modifications shall be paid for by responsible Contractor/Subcontractor.
H. Coordination with Electrical Work: Refer to Division 1 and 26.
1.7 DESIGN WORK REQUIRED BY CONTRACTOR
A. The work of this Division requires the Contractor to include the detailing and design of several systems and/or subsystems. All such design work associated with the development of the coordination drawings shall be the complete responsibility of the Contractor.
B. The Contractor shall take the full responsibility to develop and complete routing strategies which will allow fully coordinated system to be installed in a fully functional manner. The Engineers contract drawings shall be for system design intent and general configurations.
C. Systems or subsystems which require design responsibility by the contractor include but are not limited to:
1. Any system not fully detailed
COMMON WORK RESULTS FOR FIRE PROTECTION 210500 - 5
2. Fire protection systems
3. Equipment supports, hangers, anchors and seismic systems not fully detailed nor specified in these documents, or catalogued by the manufacturer.
4. Seismic restraint systems
D. Design Limitations:
1. The Contractor shall not modify the Engineers design intent in any way.
2. The Contractor shall not change any pipe size or equipment size without prior written approval from the Engineer.
1.8 PROJECT CONDITIONS
A. The Contractor shall be required to attend a mandatory pre-bid walk-thru and shall make themselves familiar with the existing conditions. No additional costs to the Owner shall be accepted for additional work for existing conditions.
B. Field verify all conditions prior to submitting bids.
C. Report any damaged equipment or systems to the Owner prior to any work.
D. Protect all work against theft, injury or damage from all causes until it has been tested and accepted.
E. Be responsible for all damage to the property of the Owner or to the work of other contractors during the construction and guarantee period. Repair or replace any part of the work which may show defect during one year from the final acceptance of all work, provided such defect is, in the opinion of the Architect, due to imperfect material or workmanship and not due to the Owner's carelessness or improper use.
F. The Contractor shall coordinate and co-operate with Owner at all times for all new to existing connections, system shutdowns and start-ups, flushing and filling both new and existing systems.
G. Provide temporary services, where required, to maintain existing areas operable.
H. Coordinate all services shut-down with the Owner; provide temporary services. Coordinate any required disruptions with Owner, one week in advance.
I. Minimize disruptions to operation of systems in occupied areas.
1.9 SAFETY
A. Refer to Division 1.
1.10 REQUIREMENTS OF REGULATORY AGENCIES
A. Refer to Division 1.
B. Execute and inspect all work in accordance with all Underwriters, local and state codes, rules and regulations applicable to the trade affected as a minimum, but if the plans and/or specifications call for requirements that exceed these rules and regulations, the greater
COMMON WORK RESULTS FOR FIRE PROTECTION 210500 - 6
requirement shall be followed. Comply with standards in effect at the date of these Contract Documents, except where a standard or specific date or edition is indicated.
C. After entering into contract, Contractor will be held to complete all work necessary to meet these requirements without additional expense to the Owner.
1.11 REQUIREMENTS OF LOCAL UTILITY COMPANIES
A. Comply with rules and regulations of local utility companies. Include in bid the cost of all valves, valve boxes, meter boxes, meters and such accessory equipment which will be required but not provided by Local Utility Company for the project.
1.12 PERMITS AND FEES
A. Refer to Division 1.
B. Contractor shall arrange for and pay for all inspections, fees, licenses and certificates required in connection with the work.
1.13 PROJECT SEISMIC REQUIREMENTS
A. All systems shall be installed to meet NFPA and IBC Seismic requirements.
1. Where any conflicts arise the more stringent requirements shall be applicable.
2. The design of the seismic requirements shall be the full responsibility of the Contractor.
B. Seismic Design Category (SDC) --- D
C. Soil Site Classification --- D / Risk Category III
D. Seismic Importance Factor of all Fire Protection systems:1.5
E. Refer to structural package for additional requirements.
1.14 SPECIFIC CATEGORY SUBMITTAL REQUIREMENTS
A. In addition to the requirements of Division 1, comply with the following
B. Product Data:
1. Where pre-printed data covers more than one distinct product, size, type, material, trim, accessory group or other variation, mark submitted copy with black pen to indicate which of the variations is to be provided.
2. Delete or mark-out portions of pre-printed data which are not applicable.
3. Where operating ranges are shown, mark data to show portion of range required for project application.
4. For each product, include the following:
a. Sizes.
b. Weights.
c. Speeds.
COMMON WORK RESULTS FOR FIRE PROTECTION 210500 - 7
d. Capacities.
e. Piping and electrical connection sizes and locations.
f. Statements of compliance with the required standards and regulations.
g. Performance data.
h. Manufacturer's specifications.
C. Shop Drawings:
1. Shop Drawings are defined as system layout drawings prepared specifically for this project, or fabrication and assembly type drawings of system components to show more detail than typical pre-printed materials.
2. Prepare Shop Drawings, except diagrams, to accurate scale, min 1/8”-1'-0", unless otherwise noted.
a. Show clearance dimensions at critical locations.
b. Show dimensions of spaces required for operation and maintenance.
c. Show interfaces with other work, including structural support.
D. Test Reports:
1. Submit test reports which have been signed and dated by the accredited firm or testing agency performing the test.
2. Prepare test reports in the manner specified in the standard or regulation governing the test procedure (if any) as indicated.
3. Submit test reports as required for O & M manuals.
E. Product Listing:
1. Prepare listing of major Fire Protection equipment and materials for the project, within (2) two weeks of signing the Contract Documents and transmit to the Architect. A sample schedule is included at the end of this section to complete this requirement.
a. Provide all information requested.
b. Submit this listing as a part of the submittal requirement specified in Division 1, "PRODUCTS AND SUBSTITUTION."
2. Unless otherwise specified, all materials and equipment shall be of domestic (USA) manufacture and shall be of the best quality used for the purpose in commercial practice.
3. When two or more items of same material or equipment are required (pumps, valves, etc.) they shall be of the same manufacturer. Product manufacturer uniformity does not apply to raw materials, bulk materials, pipe, tube, fittings (except flanged and grooved types), sheet metal, wire, steel bar stock, welding rods, solder, fasteners, motors for dissimilar equipment units and similar items used in work, except as otherwise indicated.
a. Provide products which are compatible within systems and other connected items.
F. If more than two submittals (either for product data, shop drawings, record drawings, or test and balance reports) are made by the Contractor, the Owner reserves the right to charge the Contractor for subsequent reviews by their consultants. Such extra fees shall be deducted from payments by the Owner to the Contractor.
1.15 DELIVERY, STORAGE, AND HANDLING
A. Refer to Division 1.
COMMON WORK RESULTS FOR FIRE PROTECTION 210500 - 8
B. Deliver products to project properly identified with names, model numbers, types, grades, compliance labels and similar information needed for distinct identifications; adequately packaged and protected to prevent damage or contamination during shipment, storage, and handling.
C. Check delivered equipment against contract documents and submittals.
D. Store equipment and materials at the site, unless off-site storage is authorized in writing.
Protect stored equipment and materials from damage, dirt, dust, freezing, heat and moisture.
E. Coordinate deliveries of materials and equipment to minimize construction site congestion.
Limit each shipment of materials and equipment to the items and quantities needed for the smooth and efficient flow of installations.
F. Provide factory-applied plastic end-caps on each length of pipe and tube. Maintain end-caps through shipping, storage and handling to prevent pipe-end damage and prevent entrance of dirt, debris and moisture.
1.16 CUTTING AND PATCHING
A. Refer to Division 1.
B. Do not endanger or damage installed work through procedures and processes of cutting and patching.
C. Arrange for repairs required to restore other work, because of damage caused as a result of Fire Protection installations.
D. No additional compensation will be authorized for cutting and patching work that is necessitated by ill-timed, defective or non-conforming installations.
E. Perform cutting, fitting and patching required to:
1. Uncover work to provide for installation of ill-timed work;
2. Remove and replace defective work;
3. Remove and replace work not conforming to requirements of the Contract Documents;
4. Remove samples of installed work as specified for testing;
5. Upon written instructions from the Architect or Engineer, uncover and restore work to provide for Architect or Engineer observation of concealed work.
1.17 ROUGH-IN
A. Verify final locations for rough-ins with field measurements and with the requirements of the actual equipment to be connected.
B. Refer to equipment shop drawings and manufacturer's requirements for actual provided equipment for rough-in requirements.
C. Work through all coordination before rough-in begins.
COMMON WORK RESULTS FOR FIRE PROTECTION 210500 - 9
1.18 ACCESSIBILITY
A. Install equipment and materials to provide required access for servicing and maintenance.
Coordinate the final location of concealed equipment and devices requiring access with final location of required access panels and doors. Allow ample space for removal of all parts that require replacement or servicing.
B. Furnish hinged steel access doors with concealed latch, whether shown on drawings or not, in all walls and ceilings for access to all concealed valves and other operating devices requiring adjustment or servicing. Refer to Division 8 for access door specification.
C. The minimum size of any access door shall not be less than the size of the equipment to be removed or 12 inches x 12 inches if used for service only.
D. Furnish doors to trades performing work in which they are to be built, in ample time for building-in as the work progresses. Whenever possible, group valves, cocks, etc., to permit use of minimum number of access doors within a given room or space.
E. Factory manufactured doors shall be of a type compatible with the finish in which they are to be installed. In lieu of these doors, approved shop fabricated access doors with DuroDyne hinges may be used.
F. Access doors in fire-rated walls and ceilings shall have equivalent U.L. label and fire rating.
1.19 NAMEPLATE DATA
A. Provide permanent operational data nameplate on each item of equipment, indicating manufacturer, product name, model number, serial number, capacity, operating and power characteristics, labels of tested compliances, and similar essential data. Locate nameplates in an accessible location. Coordinate with Owner for specific requirements.
1.20 LUBRICATION OF EQUIPMENT
A. Refer to Division 1. The following paragraphs supplement the requirements of Division 1.
B. Contractor shall properly lubricate all mechanical pieces of equipment which he provided before turning the building over to the Owner. He shall attach a linen tag or heavy duty shipping tag on the piece of equipment showing the date of lubrication and the type and brand of lubricant used.
C. Furnish the Engineer with a typewritten list included in the O and M manuals of each item lubricated and type of lubricant used, no later than two (2) weeks before completion of the project, or at time of acceptance by the Owner of a portion of the building and the systems involved.
1.21 CLEANING
A. Refer to Division 1.
1.22 RECORD DOCUMENTS
A. Refer to Division 1.
COMMON WORK RESULTS FOR FIRE PROTECTION 210500 - 10
1.23 WARRANTIES
A. Refer to the Division 1 for procedures and submittal requirements for warranties. Refer to individual equipment specifications for warranty requirements. In any case the entire mechanical system shall be warranted no less than one year from the time of acceptance by the Owner.
B. Compile and assemble the warranties specified in Division 21, into the operating and maintenance manuals.
C. Provide complete warranty information for each item to include product or equipment to include date or beginning of warranty or bond; duration of warranty or bond; and names, addresses, and telephone numbers and procedures for filing a claim and obtaining warranty services.
END OF SECTION 230500
WATER BASED FIRE PROTECTION 211000 - 1
SECTION 211000 - WATER BASED FIRE PROTECTION
PART 1 - GENERAL
1.1 DESCRIPTION OF WORK
A. This Section specifies automatic sprinkler systems for buildings and structures. Materials and equipment specified in this Section include:
1. Pipe, fittings, valves and specialties.
2. Sprinklers and accessories.
B. Products furnished but not installed include sprinkler head cabinet with spare sprinkler heads.
Furnish to the Owner's maintenance personnel.
C. The work of this section includes design by the Contractor. The Contractor shall provide NICET Level III design for all fire protection work.
D. This Contractor shall provide security soffits to cover all exposed sprinkler piping and ductwork where indicated.
1.2 DEFINITIONS
A. Pipe sizes used in this Specification are Nominal Pipe Size (NPS).
B. Other definitions for fire protection systems are listed in NFPA Standards 13, 14, 20 and 24.
C. Working plans as used in this Section means those documents (including drawings and calculations) prepared pursuant to the requirements contained in NFPA 13 and 14 for obtaining approval of the authority having jurisdiction.
1.3 SYSTEM DESCRIPTION
A. Provide a complete fire sprinkler system for the remodel and new areas for entire building (including, but not limited to, electrical rooms, mechanical rooms, chases per local interpretation, cells, control room window wash etc., as shown on drawings and per NFPA and specified herein.
B. Fire protection system is a remodel and extension of an existing "wet-pipe" system employing automatic sprinklers attached to a piping system containing water and connected to a water supply so that water discharges immediately from sprinklers opened by fire.
1.4 PROJECT SEISMIC REQUIREMENTS
A. All fire protection systems shall be installed to meet NFPA and IBC Seismic Zone requirements.
1. Where any conflicts arise the more stringent requirements shall be applicable.
WATER BASED FIRE PROTECTION 211000 - 2
1.5 SUBMITTALS
A. Product data for each type sprinkler head, valve, piping and piping specialty, fire protection specialty, fire department connection and any equipment installed in accordance with the Contract Documents. Index per specification chapter and item number.
B. Shop drawings prepared in accordance with NFPA 13 identified as "working plans," including detailed riser schematics indicating pipe sizes and lengths; and hydraulic calculations applicable, which have been approved by the authority having jurisdiction.
C. Contractor shall stamp shop drawings indicating compliance with applicable codes and contract drawings. Contractor shall stamp drawing "Approved for Construction."
D. Maintenance data for each type sprinkler head, valve, piping specialty, fire protection specialty, fire department connection and hose valve specified, for inclusion in operating and maintenance manual specified in Division 1 and Division-23 Section "Basic Mechanical Requirements."
E. Welder's qualification certificate.
F. Test reports and certificates including "Contractor's Material and Test Certificate for Aboveground Piping" and "Contractor's Materials and Test Certificate for Underground Piping" as described in NFPA 13.
G. Hydraulic calculations and drawings submitted to the Engineer shall be prepared under the direct supervision of and bear the signed stamp of a NICET Level III technician familiar with this type of installation and with previous similar experience (practicing in the Fire Protection field) showing that the fire sprinkler system has been designed and hydraulically calculated in compliance with NFPA and governing codes.
H. Fire sprinkler piping design drawings shall coordinate with all ductwork, air devices, lighting and electrical panels.
I. Shop drawings and hydraulic calculations shall be stamped and signed by the local fire prevention authority prior to submitting shop drawings to the Architect/Engineer.
1.6 HYDRAULIC DESIGN
A. The Fire Sprinkler System shall be hydraulically calculated by the Contractor and comply with
NFPA -13
B. Velocities in pipes shall be shown on hydraulic calculations. Velocities in overhead piping shall not exceed 32 feet per second. Velocities in underground piping shall not exceed 16 feet per second.
C. Allow 10 feet of loss for electric water flow switches and note on hydraulic calculations.
D. The Fire Protection Contractor shall provide as many sets of hydraulic calculations as necessary, performed and submitted to prove that the most remote and demanding areas are calculated.
E. Design information shall be permanently affixed to the main riser as described in NFPA Pamphlet 13.
F. Water flow data for bidding purposes shall be obtained from local utility.
WATER BASED FIRE PROTECTION 211000 - 3
G. The Fire Protection Contractor shall be responsible for water flow data from the appropriate water department. A copy of the water flow test data from the water department shall accompany the hydraulic calculations before hydraulically calculating equipment fire sprinkler system.
1.7 QUALITY ASSURANCE
A. Installer Qualifications: Installation and alterations of fire protection piping, equipment, specialties, and accessories, and repair and servicing of equipment shall be performed only by qualified installer. The term qualified means experienced in such work (experienced shall mean having a minimum of 5 previous projects similar in size and scope to this project), familiar with all precautions required, and has complied with all the requirements of the authority having jurisdiction. The contractor shall be licensed for the design and installation for the specific type of system in the jurisdiction where the work is to be performed and the State of Idaho. Upon request, submit evidence of such qualifications to the Engineer.
B. Qualifications for Welding Processes and Operators: Comply with the requirements of AWS D10.9, Specifications of Qualifications of Welding Procedures and Welders for Piping and Tubing, Level AR-3."
C. Regulatory Requirements: Comply with the requirements of the following codes:
1. NFPA 13 - Standard for the installation of Sprinkler System, including applicable seismic requirements.
2. NFPA 14 - Standard for the Installation of Standpipe and Hose Systems.
3. NFPA 24 - Installation of Private Fire Service Mains and their applications.
4. NFPA 1961 - Standard for Fire Hose.
5. NFPA 1963 - Screw Threads and Gaskets for Fire Hose Connections.
6. UL and FM Compliance: All fire protection system materials and components shall be
Underwriter's Laboratories and Factory Mutual listed as well as labeled for the application anticipated.
7. National Electrical Code (NEC).
8. International Building Codes, including applicable seismic requirements.
9. Requirements of the local Building Department and Fire Department.
D. Reference and standards listed are minimum requirements. Where more stringent requirements are specified or noted on the drawings, this shall be applicable.
1.8 SEQUENCING AND SCHEDULING
A. Schedule rough-in installations with installations of other building components.
B. Minimum time frame for notice of inspections, tests and meetings is five (5) days through Construction Manager.
1.9 EXTRA STOCK
A. Heads: For each style and temperature range (and length for dry heads) required, furnish additional sprinkler heads per NFPA-13.
1. Obtain receipt from Owner that extra stock has been received.
WATER BASED FIRE PROTECTION 211000 - 4
PART 2 - PRODUCTS
2.1 MATERIALS AND PRODUCTS
A. General: Provide piping materials and factory-fabricated piping products of sizes, types, pressure ratings, temperature ratings, and capacities as indicated. Where not indicated, provide proper selection as determined by Installer to comply with installation requirements.
Provide sizes and types matching piping and equipment connections; provide fittings of materials which match pipe materials used in fire protection systems.
B. All equipment used on this project shall be new and UL listed unless noted or specified otherwise.
2.2 MANUFACTURERS
A. Manufacturer: Subject to compliance with requirements, provide fire protection system products from one of the following:
1. Gate Valves:
a. Nibco
b. Kennedy Valve, Div. of ITT Grinnell Valve Co., Inc.
c. Mueller
d. Stockham
e. Grinnell
f. Milwaukee
2. Swing Check Valves:
a. Central
b. Mueller
c. Kennedy Valve, Div. of ITT Grinnell Valve Co., Inc.
d. Star Sprinkler Corp.
e. Viking
f. Victaulic
g. Globe
h. Potter Roemer
3. Butterfly and Ball Valves:
a. Grinnell
b. Mueller
c. Victaulic
d. Milwaukee
e. Kennedy
4. Grooved Mechanical Couplings:
a. Gruvlok
b. Victaulic Company of America
c. Central Sprink, Inc.
d. Anvil
e. Tyco
WATER BASED FIRE PROTECTION 211000 - 5
f. Shurjoint
5. Sprinkler Heads/Security Heads:
a. Automatic Sprinkler Corp. of America.
b. Central Sprinkler Corp.
c. ITT Grinnell
d. Reliable Automatic Sprinkler Co., Inc.
e. Star Sprinkler Corp.
f. Viking Corp.
g. Globe
h. Tyco
6. Fire Protection Specialties:
a. Croker-Standard Div.,; Fire-End & Croker Corp.
b. Elkhart Brass Mfg. Co., Inc.
c. Grinnell Fire Protection Systems Co., Inc.
d. Grunau Sprinkler Mfgr. Co., Inc.
e. Potter Roemer, Inc.
f. Globe
g. Viking
h. Tyco
7. Inspector's Test and Drain Module
a. Victaulic
b. A.G.F.
c. Grinnell/Gem
d. Triple “R”
e. Viking
2.3 BASIC IDENTIFICATION
A. General: Provide identification complying with NFPA-13 and Division-23 "Mechanical Identification", in accordance with the following listing:
1. Fire Protection Piping: Pipe markers.
2. Fire Protection Valves: Valve tags.
3. Fire Protection Signs: Provide the following signs:
a. At each sprinkler valve, sign indicating what portion of system valve controls.
b. At each outside alarm device, sign indicating what authority to call if device is activated.
c. At each drain or test, sign indicating its purpose.
B. Attach to the riser a metal sign indicating the name, address and telephone number of the fire protection contractor. Also indicate the date of installation.
2.4 BASIC PIPING SPECIALTIES
A. General: Provide piping specialties complying with NFPA-13 and Division-23 Basic Mechanical Materials and Methods section "Piping Specialties", in accordance with the following listing:
WATER BASED FIRE PROTECTION 211000 - 6
1. Pipe escutcheons.
2. Dielectric unions.
3. Drip pans.
4. Pipe sleeves.
5. Sleeve seals.
6. Fire Barrier Penetration Seals.
2.5 BASIC SUPPORTS AND ANCHORS
A. General: Provide supports and anchors complying with Division-23 "Supports and Anchors" in accordance with the following listing:
1. Adjustable steel clevis hangers, adjustable steel band hangers, or adjustable band hangers, for horizontal-piping hangers and supports.
2. Two-bolt riser clamps for vertical piping supports.
3. Steel turnbuckles and malleable iron sockets for hanger- rod attachments.
4. Concrete inserts, top-beam C-clamps, side beam or channel clamps or center beam clamps for building attachments.
5. Concrete inserts and other type hangers penetrating into or through structural members shall be submitted (by the Fire Protection Contractor) to and have the approval of the structural engineer contracted for this project.
6. Powder driven studs shall not be allowed.
7. Hangers (which are acceptable for project) and hanger spacing shall be in accordance with NFPA-13.
2.6 PIPE AND TUBING MATERIALS (INSIDE BUILDING)
A. General: Refer to Part 3 Article "Pipe Applications" for identification of systems where the below specified pipe and fitting materials are used.
B. Steel Pipe: ASTM A 53, A795 or A135, Schedule 40 or Schedule 10, U.S. manufacture, black steel pipe, plain ends.
C. American Tube Company "Dyna-Thread-40" and "Dyna-Flow" and Allied Tube and Conduit Corporation "Super Flo" are acceptable to Schedule 40 pipe. Installation shall be per manufacturer's recommendations.
D. Schedule 5 pipe shall not be allowed.
E. The Corrosion Resistance Ratio of the pipe shall be 1.00 or greater. Documentation shall be presented with product submittal.
F. Schedule 10 pipe shall only be allowed for pipe sizes 2-1/2inches and larger.
2.7 FITTINGS (INSIDE BUILDING)
A. Cast-Iron Threaded fittings: ANSI B16.4, Class 125 standard pattern, for threaded joints.
Threads shall conform to ANSI B1.20.1.
B. Malleable-Iron Threaded Fittings: ANSI B16.3, Class 300, standard pattern, for threaded joints.
Threads shall conform to ANSI B1.20.1. Install steel pipe with threaded joints and fittings for 2inches and smaller and where shown on drawings.
WATER BASED FIRE PROTECTION 211000 - 7
C. Steel Fittings: ASTM A234, seamless or welded, for welded joints.
D. Grooved Mechanical Fittings: ASTM A 536, Grade 65-45-12 ductile iron; ASTM A 47 Grade 32510 malleable iron; or ASTM A53, Type F or Types E or S.
E. Grooved Mechanical Couplings: Consist of ductile or malleable iron housing, a synthetic rubber gasket of a central cavity pressure-responsive design; with nuts, bolts, locking pin, locking toggle, or lugs to secure roll- grooved pipe and fittings.
F. Grooved Mechanical Fittings and Couplings for the entire fire protection system shall be of the same manufacturer as submitted in shop drawing equipment review.
G. Cast-Iron Threaded Flanges: ANSI B16.1, Class 250; raised ground face, bolt spot faced.
H. Cast Bronze Flanges: ANSI B16.24, Class 300; raised ground face, bolt holes spot faced.
I. Plain end, hooker type, or push-on fittings or couplings shall not be allowed.
J. Bushings and reducing couplings shall not be allowed.
K. UL listed and Factory Mutual approved segmentally welded fittings are acceptable. Friction loss and flow data shall accompany hydraulic calculations.
2.8 JOINING MATERIALS
A. Welding Materials: Comply with Section II, Part C, ASME Boiler and Pressure Vessel Code for welding materials appropriate for the wall thickness and chemical analysis of the pipe being welded.
B. Gasket Materials: Thickness, materials and type suitable for fluid or gas to be handled, and design temperatures and pressures.
2.9 GENERAL DUTY VALVES
A. Gate Valves - 2 Inch and Smaller: Body and bonnet of cast bronze, 175 pound cold water working pressure - non-shock, threaded ends, solid wedge, outside screw and yoke, rising stem, screw-in bonnet, and malleable iron handwheel. Valves shall be capable of being repacked under pressure, with valve wide open.
B. Gate Valves - 2-1/2 Inch and Larger: Iron body; bronze mounted, 175 pound cold water working pressure - non-shock. Valves shall have solid taper wedge; outside screw and yoke, rising stem; flanged bonnet, with body and bonnet conforming to ASTM A 126 Class B;
replaceable bronze wedge facing rings; flanged ends; and a packing assembly consisting f a cast iron gland flange, brass gland, packing, bonnet, and bronze bonnet bushing. Valves shall be capable of being repacked under pressure, with valve wide open.
C. Butterfly Valves: 2-1/2inches to 12inches, grooved, ductile iron body and disc ASTM-536, disc EPDM coated, listed and approved minimum 175 psi service, actuator, self-contained supervisory switch, weatherproof approved for indoor or outdoor use.
D. Ball Valves: 1-1/2inches and smaller shall be threaded, forged brass construction, with Teflon seats and blow out proof stem. Ball shall be full port with chrome plated ball.
WATER BASED FIRE PROTECTION 211000 - 8
E. Ball Valves: 2inches to 3inches shall be listed to 300 p.s.i. with optional internal tamper switch.
Body shall be ductile iron with corrosion resistant coating. Ball shall be 316 stainless steel, standard port design.
F. Swing Check Valves: MSS SP-71; Class 175, cast iron body and bolted cap conforming to ASTM A 126, Class B; horizontal swing, with a bronze disc or cast iron disc with bronze disc ring, and flanged ends. Valve shall be capable of being refitted while the valve remains in the line.
2.10 BASIC METERS AND GAUGES
A. General: Provide meters and gauges complying with NFPA-13 and Division- 23 "Meters and Gauges", in accordance with the following listing
1. Pressure gauges, 0-250 psi range.
2.11 ALARM DEVICE AND FIRE PROTECTION SPECIALTIES:
A. General: Provide fire protection specialties, UL-listed, in accordance with the listing. Provide sizes and types which mate and match piping and equipment connections.
B. Water Flow Indicators: Vane type water flow detector, rated to 250 psig; designed for horizontal or vertical installation; have 2-SPDT circuit switches to provide isolated alarm and auxiliary contacts, 7 ampere 125 volts AC and 0.25 ampere 24 volts DC; complete with factory-set field-adjustable retard element to prevent false signals, tamper-proof cover which sends a signal when cover is removed, and with activation time retarding capability set at 30 seconds. The setting shall be verified through the inspectors test prior to final inspection.
C. Supervisory Switches: Provide products recommended by manufacturer for use in service indicated. SPST, normally closed contacts, designed to signal valve in other than full open position.
D. Pressure Switch: Indicating low pressure trouble in sprinkler system.
2.12 AUTOMATIC SPRINKLERS
A. Sprinkler Heads: Fusible link or frangible bulb type, and style as indicated or required by the application. Unless otherwise indicated, provide heads with nominal ½ inch discharge orifice, for "ordinary" temperature range with a minimum temperature of 155 degrees F. Provide "intermediate" temperature heads in Electrical rooms, where required as noted in NFPA 13, and as required by the Authority having jurisdiction.
B. Sprinkler Head Finishes: Provide heads with the following finishes:
1. Upright, Pendent and Sidewall Styles: Factory brass, rough bronze finish for heads in unfinished spaces.
2. Semi-Recessed Style: Bright chrome, with bright chrome escutcheon plate.
C. Sprinkler Head Cabinet and Wrench: Finished steel cabinet, suitable for wall mounting, with hinged cover and space for spare sprinkler heads plus sprinkler head wrench. Provide amounts of each style per NFPA-13. Locate head cabinet on shop drawing submittal.
WATER BASED FIRE PROTECTION 211000 - 9
D. Plastic fire sprinkler escutcheons are not acceptable.
E. Security sprinklers: Provide detention Type S sprinkler head in all inmate accessible areas.
2.13 INSPECTOR'S TEST AND DRAIN ASSEMBLY
A. Provide an alarm test module of a manufacturer listed in paragraph 2.2.
B. Test and drain piping shall be routed to exterior. Location shall meet Owner's approval and shall be secure.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine walls for suitable conditions where cabinets are to be installed.
B. Do not proceed until unsatisfactory conditions have been corrected.
3.2 PIPE APPLICATIONS
A. Install Schedule 40 steel pipe with threaded joints and fittings for 2 inches and smaller.
B. Install Schedule 40 steel pipe with roll-grooved ends and grooved mechanical coupling or with threaded joints and fittings.
C. American Tube Company "Dyna-Thread-40" and "Dyna-Flow" and Allied Tube and Conduit Corporation "Super Flo" are acceptable to Schedule 40 pipe. Installation shall be per manufacturer's recommendations.
3.3 PIPING INSTALLATIONS
A. Provide a minimum cover for all underground pipe installations per NFPA and local requirements. Install in accordance with AWWA C600.
B. Locations and Arrangements: Drawings (plans, schematics, and diagrams)…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .