This is a bid sheet for required tests and proposed fees related to sprinkler, FDC (fire department connection), and pump testing and maintenance services at Milwaukee Mitchell International Airport in Wisconsin. The contract encompasses weekly, annual, three-year, and five-year inspection and maintenance schedules for fire suppression systems at the airport's main facility located at 5300 S. Howell Ave., Milwaukee, WI 53207. A mandatory pre-bid meeting is scheduled for Monday, June 8th, 2026 at 9:00 AM Central Time at the Milwaukee County Milwaukee Mitchell International Airport Fire Department (5800 S. Howell Ave., Milwaukee, WI 53207), unless bidders have completed the required work within the last 18 months. The bid sheet document outlines the specific tests required and allows bidders to propose their fees for performing these services according to the established testing schedule.
The revised bid sheet (dated March 17, 2026) serves as the pricing proposal mechanism for this contract opportunity, requiring bidders to submit their proposed fees for each category of testing and maintenance work. The document establishes the framework for fee submission and comparison among competing bidders, enabling the airport authority to evaluate cost proposals alongside compliance with the mandatory testing requirements and schedules. This procurement allows the airport to solicit competitive pricing while ensuring all required fire safety inspections and maintenance activities are performed in accordance with applicable codes and regulations.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Fire Alarm Locations
| GMIA- Grounds | ||
| Building | Alarm System | All buildings are Simplex unless specified |
| Air Freight Cargo Upper Level | ||
| Air Freight Cargo Lower Level | ||
| Firehouse Deck Level | ||
| Firehouse Main Level | ||
| Cold Storage | Attached to Firehouse Simplex | |
| IAB Lower Level | ||
| IAB Main Level | ||
| Powerhouse Deck Level | ||
| Powerhouse Main Level | ||
| Regulator Building Ground Floor | ||
| Regulator Building Basement | ||
| Combined Maintenance Ground Level | ||
| Combined Maintenance Mezz Levels | ||
| Parking Lower Level | ||
| Parking Admin Office | ||
| Parking Structure Levels 1-6 | ||
| Terminal Basement Level | ||
| Main Terminal Ground Level | ||
| Main Terminal Gate Level | ||
| Terminal Mezz Level | ||
| Terminal Level 5 | ||
| Terminal Smoke Hatches | ||
| Cessna Pump House | ||
| Mezz and Baggage Matrix | ||
| College Ave Tunnel | Simplex/ Protect-o-wire | "Protectowire Fire system 2000" Ahern Fire Protection |
| Total of 33 NODES |
Fees
| Sprinkler, FDC, and Pump Tests/Fees | |||||||||||||||
| Bid Sheet Required Tests and Proposed Fees: Must be completed and uploaded to "Requested Information" for continued consideration. | Fill in White Squares only | ||||||||||||||
| Building Name | Location | Description | Type | Systems | Comments | Required Test | Annual Price | 3 year Price | 5 Year Price | Weekly | Weekly (Nov-Mar) | Fall Drain/Winterization | |||
| Per Year | Per 3 Year Test | Per 5 Yr Test | Per Week | Per Week (Nov-Mar) | Per Year | ||||||||||
| Firehouse Main Level | GMIA | Sprinkler System | Wet System | 1 | Annual/ 5 Year | x | x | ||||||||
| Cold Storage | GMIA | Sprinkler System | Dry System | 1 | Annual/ 5 Year | x | x | ||||||||
| Powerhouse- Mezzanine | GMIA | Sprinkler System | Dry System | 1 | Annual/ 5 Year | x | x | ||||||||
| Powerhouse- Ground Level, SW corner | GMIA | Sprinkler System | Wet System | 1 | Annual/ 5 Year | x | x | ||||||||
| College Ave Tunnel- East | GMIA | Sprinkler System | Dry System | 1 | Annual/ 5 Year | x | x | ||||||||
| College Ave Tunnel- West | GMIA | Sprinkler System | Dry System | 1 | Annual/ 5 Year | x | x | ||||||||
| College Ave West- Drain | GMIA | Sprinkler System | Dry System | 1 | Weekly Draining of dry system condenstaion/Heater Check | Weekly (Nov-Mar) | x | ||||||||
| Air Cargo Way | GMIA | Sprinkler System | Wet System | 1 | Annual/ 5 Year | x | x | ||||||||
| Combined Maintenance- Airport Maintenance | GMIA | Sprinkler System | Wet System | 1 | Annual/ 5 Year | x | x | ||||||||
| Combined Maintenance- Highway (Center Building) | GMIA | Sprinkler System | Wet System | 1 | Annual/ 5 Year | x | x | ||||||||
| Combined Maintenance- Fleet | GMIA | Sprinkler System | Wet System | 1 | Annual/ 5 Year | x | x | ||||||||
| Concourse C- Hammerhead RM C150 | GMIA | Sprinkler System | Wet System | 2 | Annual/ 5 Year | x | x | ||||||||
| Concourse C- Stem RM 130/ East and West | GMIA | Sprinkler System | Wet System | 2 | Annual/ 5 Year | x | x | ||||||||
| Concourse C- M201 | GMIA | Water Curtain | Wet System | 1 | Annual/ 5 Year | x | x | ||||||||
| Concourse D- Stem, Gate D35, RM D106 | GMIA | Sprinkler System | Wet System | 7 | Annual/ 5 Year | x | x | ||||||||
| Concourse D- Hamerhead South, RM D115A | GMIA | Sprinkler System | Wet System | 4 | Annual/ 5 Year | x | x | ||||||||
| Concourse D- Hamerhead North, RM D175 | GMIA | Sprinkler System | Wet System | 1 | Annual/ 5 Year | x | x | ||||||||
| Concourse D- RM 200C, behind TSA podium | GMIA | Water Curtain | Wet System | 1 | Annual/ 5 Year | x | x | ||||||||
| Concourse E/ New Itnter. Building- RM 294A | GMIA | Water Curtain | Wet System | 1 | Annual/ 5 Year | x | x | ||||||||
| Parking Admin Office/CPS | GMIA | Sprinkler System | Wet System | 1 | Annual/ 5 Year | x | x | ||||||||
| Main Terminal- Stair 1,2, 5, 7, and 9 | GMIA | Sprinkler System/FDC Connected | Wet System | 1 | Stair 2,5,and7 are Standpipes connected to the same loop | Annual/ 5 Year | x | x | |||||||
| Main Terminal- Basement, RM 1 | GMIA | Sprinkler System | Dry System | To Include area under floor in confrence room hallway | Annual/ 5 Year | x | x | ||||||||
| Baggage Matrix- Outside screening Room | GMIA | Sprinkler System | Dry System | 1 | 3 | Annual/ 5 Year | x | x | |||||||
| Baggage Matrix- RM T114 | GMIA | Sprinkler System | Dry System | 1 | Annual/ 5 Year | x | x |
| Parking Structure Levels 1-6 | GMIA | Standpipe | Dry System | 7 | 14 FCD's Per Floor | Annual/ 3 Year/Winterization | x | x | x |
| Baggae Road way Center | GMIA | Standpipe | Dry System | 1 | Hook ups on either end- 3 FDC along the run | Annual/ 3 Year | x | x | |
| Admininstartion Building/MCSO | GMIA | Standpipe | Dry System | 2 | 2- FDC Locations | Annual/ 3 Year | x | x | |
| Main Terminal-Basement- HMS Host | GMIA | Standpipe | Dry System | 1 | Stair 20, RM 6/3- Main connection is South Ticketting | Annual/ 3 Year | x | x | |
| Main Terminal-Basement- Center Island- Storage | GMIA | Standpipe | Dry System | 1 | Center of ticketting side | Annual/ 3 Year | x | x |
| Cessna Pump House | GMIA | Fire Pump | Annual, Weekly | x | x |
| BLD 120 Pump House | MKE Buisness Park | Fire Pump | Annual, Weekly | x | x |
| BLD 220 | MKE Buisness Park | Sprinkler System | Wet System | 1 | 2- Risers, 1st floor, and 2nd floor | Annual/5 Year | x | x | |||||||
| Freight Runners- BLD 217 | MKE Buisness Park | Sprinkler System | Wet System | 1 | 2- Water Cannon | Annual/5 Year | x | x | |||||||
| Total | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||||||
| Total (Five Years) | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||||
| Total 5 Year Price | |||||||||||||||
| Extra Fees | Price | ||||||||||||||
| Straight Time Hourly Charge | |||||||||||||||
| After Hour Hourly Charge | |||||||||||||||
| ***4 Hour Emergency Response Time*** | |||||||||||||||
| ***No Truck Charge*** |