This is a technical specifications document from the City of Scottsdale for IIP Project 017, involving the construction of 36-inch and 16-inch Zone 4 potable water transmission pipelines. The project encompasses installing new waterlines from the western boundary of the City's Central Arizona Project Water Treatment Plant to connection points on Hayden Road, including realignment of existing infrastructure, installation of fire hydrants, valves, sampling stations, and related appurtenances. The work involves predominantly ductile iron pipe with some high-density polyethylene sections, concrete thrust blocks, tie-ins to existing infrastructure, hydrostatic pressure testing, flushing and disinfection, and preparation of as-built drawings. Construction will occur on City-owned property and Honor Health property, with the contractor responsible for all permits, notifications to agencies including ADOT and utilities, and coordination of shutdown windows that may require night and weekend work.
The specifications detail comprehensive technical requirements including materials standards (AWWA, ASTM, ANSI), construction methods, testing procedures, quality control measures, and contractor responsibilities for surveying, environmental compliance including stormwater pollution prevention, safety protocols, and warranty provisions. The contractor must provide all labor, materials, equipment, and services for complete installation including excavation, pipe bedding, backfilling, concrete work, painting, and system commissioning. Technical specifications cover multiple construction divisions from site preparation and earthwork to mechanical systems, with detailed requirements for ductile iron pipe, HDPE pipe, valves, fittings, concrete work, and protective coatings. The project includes provisions for traffic control, utility coordination, native plant surveys, and comprehensive testing and documentation requirements to ensure the completed water transmission system meets all applicable standards and specifications.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF SCOTTSDALE
IIP PROJECT 017 36 & 16-INCH
ZONE 4 PIPELINES
FOR CONSTRUCTION
TECHNICAL SPECIFICATIONS
VOLUME 3 OF 3
Wilson Project No. 23-056
OCTOBER 2024
ATTACHMENT A
City of Scottsdale
October 2024 IIP 017 36” & 16” Zone 4 Pipelines
23-056 TOC-2 For Construction
DIVISION 2 - SITEWORK
02100 SITE PREPARATION
02200 EARTHWORK
02531 MANHOLES
DIVISION 3 - CONCRETE
03100 CONCRETE FORMWORK
03200 CONCRETE REINFORCEMENT
03300 CAST-IN-PLACE CONCRETE
03600 GROUT
DIVISION 9 - FINISHES
09900 PAINTING
DIVISION 15 - MECHANICAL
15050 PIPING SYSTEMS
15051 BURIED PIPING INSTALLATION
15061 DUCTILE IRON PIPE
15064 COPPER PIPE
15070 HIGH DENSITY POLYETHLYENE PRESSURE PIPE
15101 GATE VALVES, OPERATORS AND APPURTENANCES
15103 BUTTERFLY VALVES, OPERATORS AND APPURTENANCES
15212 PIPING SPECIALTIES AND ACCESSORIES
NATIVE PLANT SURVEY
END OF TABLE OF CONTENTS
23-056 01010-1 For Construction
SECTION 01010
SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. The Work to be accomplished under these Contract Documents consists of furnishing all labor, materials, and equipment for the construction of the City of
Scottsdale’s 36-inch along with realignment and installation of an existing 16-inch
Zone 4 potable water transmission main segment along the Union Hills Drive alignment as part of the IIP 017 project, complete and ready for use in accordance with the Contract Documents.
B. The OWNER shall refer to the City of Scottsdale.
C. The CONTRACTOR shall be responsible for site and personnel safety during all phases and all aspects of construction.
D. The Work includes, but is not limited to, the following principal processes and structures:
1. Installation of a new 36-inch diameter waterline along the Union Hills Drive alignment. This 36-inch pipeline segment will extend from western boundary of the City’s Central Arizona Project Water Treatment Plant (CAP WTP) to its connection point to existing City infrastructure in Hayden Road.
2. Realignment and installation of 16-inch diameter waterline along the Union
Hills Drive alignment. This 16-inch pipeline segment will extend from western boundary of the City’s Central Arizona Project Water Treatment Plant (CAP
WTP) to its connection point to existing City infrastructure in Hayden Road.
3. The pipeline is predominantly ductile iron pipe (DIP).
4. Short section of the pipeline is high-density polyethylene pipe (HDPE) under the Detention Basin 53R.
5. To deal with the Detention Basin 53R crossing, isolation valves and sampling stations will be installed on either end.
6. There are fire hydrants, combination air release-vacuum valves, sampling ports, and butterfly valves along the 36-inch pipeline.
7. There are gate valves, air release-vacuum valves, and sampling ports along the realigned 16-inch pipeline.
8. There are pipe access ports to be used for camera inspections and/or maintenance inside the pipe.
9. There are stub outs for future connections to supply Zone 4 water within the project area.
10. Tie-ins to the existing City infrastructure shall be coordinated with the Owner and Engineer. Contractor may be required to perform nights and/or weekends to accommodate shut down windows.
23-056 01010-2 For Construction
11. Contractor shall be responsible for all notifications to governmental and public agencies as well as utilities including but not limited to ADOT, APS, SRP, ASLD, and others.
12. Contractor shall be responsible for application(s) and securing of all permits.
13. Hydrostatically pressure test all segments of piping associated with this project.
14. Flush and disinfect piping associated with this project and coordinate bacteriological testing.
15. Prepare As-Built Contract Documents to accurately reflect the final state of construction.
16. Prepare and maintain Construction Schedules.
17. Provide one year warranty on all materials and labor.
18. All other miscellaneous items of Work specified in the Contract Documents.
1.2 ACCESS TO AND FROM THE SITE
A. The City of Scottsdale IIP 017 36-inch potable water transmission main alignment will connect to existing potable water infrastructure and will pass through both undeveloped land and a detention basin. The pipeline alignment is within two properties, including one owned by the City (Assessor’s Parcel Number, APN 212-
31-125C) and one owned by Honor Health (APN 212-31-966C). The pipeline alignment will also interact with several existing easements within the Honor
Health property.
B. The City of Scottsdale IIP 017 16-inch potable water pipeline will be realigned and will pass through both undeveloped land and a detention basin. The pipeline alignment is within two properties, including one owned by the City (Assessor’s
Parcel Number, APN 212-31-125C) and one owned by Honor Health (APN 212-
31-966C). The pipeline alignment will also interact with several existing easements within the Honor Health property.
C. The approximate pipeline address is near the City of Scottsdale Water Campus located at 8787 E Hualapai Drive, Scottsdale, AZ 85255.
1.3 GEOTECHNICAL INVESTIGATION
A. A copy of the geotechnical investigation is available from the OWNER upon request.
1.4 COORDINATION WITH EXISTING UTILITIES
A. Various utilities including, but not limited to, potable water pipes, sanitary sewer, electrical duct banks, communications cables, drainage and irrigation channels and associated structures are in existence on the construction site in roadways, right-of-ways, and adjoining properties.
B. Where required by the Contract Documents, the CONTRACTOR shall make connection to proposed or existing utilities.
23-056 01010-3 For Construction
C. The CONTRACTOR shall connect to existing utilities without disrupting or interrupting the operation of the services of the existing utilities.
D. The existing utilities shall be assumed to be in service at the time the
CONTRACTOR makes connection.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
++ END OF SECTION ++
October 2024 IIP 017 36” Zone 4 Pipeline 23-056 01013-1 For Construction
SECTION 01013
ENGINEERING SERVICES
PART 1 - GENERAL
1.1 SUMMARY
A. The Work to be accomplished under these Contract Documents has been designed for the OWNER by a Registered Professional Engineer, retained by the OWNER for this purpose. It is understood that normal engineering for the purpose of interpretation of the Contract Documents is provided by the OWNER. Should any services of the ENGINEER be required to assist in the corrections of errors or omissions in construction by the CONTRACTOR, or services of the ENGINEER be required because of changes in structure or equipment where the CONTRACTOR has requested approval of substitute methods or materials, those services will be provided by the ENGINEER at the standard hourly rates previously negotiated with the OWNER and shall be paid for by the CONTRACTOR. Other services shall be described further in this Section.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
3.1 ENGINEERING SERVICES
A. The ENGINEER shall be reimbursed by the CONTRACTOR for the ENGINEER'S additional services to the Project through no fault of the OWNER or ENGINEER including, but not limited to, the following conditions:
1. Additional Shop Drawing review(s) by the ENGINEER as described in
Section 01300, Submittals.
2. Additional site visits, investigations, inspections, design work and/or reports by the ENGINEER which are required due to damages to existing facilities or completed Work caused by the CONTRACTOR in his performance, the CONTRACTOR'S negligence, or the CONTRACTOR'S Work which is rejected as defective or as failing to conform to the Contract Documents.
3. All retesting required due to the failure of the CONTRACTOR'S Work to meet the requirements of the Contract Documents shall be at the CONTRACTOR'S expense. All standby and travel time by the OWNER'S testing lab or ENGINEER due to CONTRACTOR'S inability to be prepared for testing at the agreed upon time or inability of CONTRACTOR to meet performance requirements shall be at the CONTRACTOR'S expense. An hourly rate of three times the direct labor cost, but not less than $150/hour, will be charged
23-056 01013-2 For Construction to the CONTRACTOR for every hour of engineering or testing lab personnel time, plus the cost of any retesting on a per test basis.
4. The ENGINEER shall bill the OWNER for additional engineering services performed as described in these Documents. The OWNER shall withhold payment for this from the CONTRACTOR'S final payment. A change order shall be executed deleting the amount due from the Contract sum and final payment.
23-056 01025-1 For Construction
SECTION 01025
MEASUREMENT AND PAYMENT
PART 1 - GENERAL
1.1 SUMMARY
A. Payment for Work performed by the CONTRACTOR under these Contract
Documents shall be made at the approved Contract agreement prices for each of the items listed in the Bid Schedule. Such payment shall compensate the
CONTRACTOR for all materials, labor, and equipment incorporated into the Work in accordance with the Drawings and other Contract Documents. In addition, all applicable Federal, State, County, and local taxes shall be included in such payment.
B. The items listed in the Bid Schedule constitutes all of the Bid Items for the completion of the Work. No direct or separate payment will be made for providing miscellaneous or temporary works, testing, safety, Shop and Record Drawings, and the removal of waste. Compensation for all such services and materials shall be included in the prices stipulated for the lump sum and unit pay items.
C. The Bid Schedule will include items 1 through 33 listed on the Bid Schedule.
1.2 MEASUREMENT
A. Measurements of the completed Work will be made in place, with no allowance for waste.
B. Measurements of distances will be made in a horizontal plane, unless otherwise stated.
C. Measurements of areas will be made in a horizontal plane, unless otherwise stated.
Widths of pavement removal areas and trenching will be measured based on
Maricopa County Association of Governments (MAG) limits, regardless of the construction techniques used.
23-056 01025-2 For Construction
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
3.1 BID FORM DESCRIPTION
A. Payment shall be made for the actual quantities constructed or installed; said quantities being measured as specified hereinafter. Payment will be made for installed work only. Payment will not be made for stored, uninstalled materials.
Work items not specifically identified in the Bid Schedule, but shown and specified, shall be considered incidental items. No additional payment will be made for incidental items as costs should be included in the Bid Schedule.
B. The following are descriptions of the items listed on the bid form.
1. Bid Item No. 1 – “General Requirements / Mobilization/Demobilization” shall be paid for at the Contract lump sum price and shall include compensation for mobilizing and demobilizing the CONTRACTOR'S construction equipment and personnel, and shall include compensation for all of the temporary facilities required to complete the Project including the CONTRACTOR'S storage yard, field offices, construction photographs, permits, insurance bonds, coordination, CONTRACTOR’S quality control testing (such as soil density), utility services, sound barricades, clean-up, Record Drawings, progress schedules, and all other incidental and appurtenant Work not specifically specified in the other paragraphs of this Section.
2. Bid Item No. 2 – “Survey/Staking” shall be paid for at the Contract lump sum price and shall include compensation for the cost for all surveying/staking and all necessary incidental Work as shown on Contract Documents.
3. Bid Item No. 3 – “Verification of Field Measurements and Utility Locations” shall be paid for at the Contract lump sum price and shall include full compensation for the cost of verifying the depth, location and size of buried utilities and other Work shown on the Plans, identified by blue staking or evident from surface features, and all incidental and appurtenant Work to complete the item as specified and indicated on the Drawings and as specified, with the exception of Work included in Bid Item No. 2 – “Survey/Staking.”
4. Bid Item No. 4 – “Construction Surveying As-builts” shall be paid for at the
Contract lump sum price and shall include full compensation for the cost of maintaining a full size set of project drawings that shall be kept on-site and updated on a weekly basis with a red pencil or red ink to reflect any field adjustments, changes, omissions, additions, etc. as they occur on the project.
The City Inspector will check site as-builts on a weekly basis to insure all modified project elements have been properly recorded on the field plan set.
23-056 01025-3 For Construction
The City will be the sole judge in determining whether the as-builts are acceptable.
5. Bid Item No. 5 – “Traffic Control and Temporary Plating” shall be paid for at the Contract lump sum price. This shall include all costs incidental by proving barricades, signage for traffic control including obliteration of existing pavement and temporary pavement markings pilot cars, flagmen, sign panels, sign stands, warning lights, and related temporary pavements during construction hours and temporary plating during non-construction hours. All traffic control shall be in conformance with City of Scottsdale Barricade Plan in the Design Standards and Policies Manual, within City’s approval. No direct measurement of variable message sign shall be made and the cost considered included in the lump sum measurement. Variable message board signs are required in each direction of traffic to notify traveling public of construction work and along major arterial roads approaching the construction area. No direct measurement of individual traffic control elements or device will be made. All traffic control devices shall be considered as included in the lump sum measurement. No direct measurement of temporary pavement will be made. All saw cutting, grading, aggregate base course material, asphalt concrete pavement, labor, and equipment, shall be considered as included in the lump sum measurement. Traffic Control devices shall be in accordance with City of Scottsdale Barricade Plan in the Design Standards and Policies
Manual. CONTRACTOR shall be responsible for installing the temporary plating as required by the Contract Documents.
6. Bid Item No. 6 – “Off-Duty Police Officer” shall be paid at the Contract unit price as hourly. The off-duty police officer compensation during construction along Bell road and park entrance intersection to assist with traffic control.
This compensation will include overhead, profit, taxes, officer hourly rate, officer’s workmen’s compensation, and office vehicle costs. Payment under this item will be based on the actual cost of the hours officer shall be present at the construction site as directed by the OWNER.
7. Bid Item No. 7 – “Landscaping and Native Plant” shall be paid for at the
Contract lump sum price and shall include compensation for the cost of native tree salvage and removal, landscape fine grading, soil preparation, tree supports and headers, planting, restoration to previous condition of irrigation, curb and gutter, asphalt, and all other incidental and appurtenant Work to complete the item as specified and indicated on the Drawings.
8. Bid Item No. 8 – “Site Grading and Access Road, and On-Site Decomposed
Granite” shall be paid for at the Contract lump sum price and shall include full compensation for the cost of site Work, clearing and grubbing, grading, and placement of the access road, restoration to previous condition of irrigation
23-056 01025-4 For Construction systems, asphalt, curb and gutter, and all incidental and appurtenant Work to complete the item as specified and indicated on the Drawings.
9. Bid Item No. 9 – “Stormwater Pollution Prevention Plan” (SWPPP) shall be paid for at the Contract lump sum price. This item shall include all cost incidental to provide SWPPP, permitting, installation, on-going maintenance of SWPPP in field, inspection, protection, and removal to prevent any storm water pollution from the project site to the adjacent areas as specified within section 01412 – Stormwater Pollution Prevention Plan and Permit.
10. Bid Item No. 10 – “Curb and Gutter” shall be paid for at Contract price per linear foot and shall include compensation for all work incidental towards the removal and replacement of curbs and gutter as shown in the Contract
Documents.
11. Bid Item no. 11 - “Concrete Sidewalks” shall be paid for at Contract price per square foot and shall include compensation for all work incidental towards the removal (saw cut) and replacement of concrete sidewalks as shown in the
Contract Documents.
12. Bid Item no. 12 - “Concrete Lined Channel” shall be paid for at Contract price per square foot and shall include compensation for all work incidental towards the removal (saw cut) and replacement of concrete lined channel back to the nearest joints as shown in the Contract Documents.
13. Bid Item no. 13 - “Concrete Anchor Blocks” shall be paid for at the Contract price per each concrete anchor block. This shall include all compensation for all the work incidental towards installation of reinforced concrete including but not limited to steel reinforcements, formwork, excavations, backfilling, and testing. Payment shall be made based on the actual quantity installed in the field.
14. Bid Item No. 14 – “36-inch Water System Piping & Fittings” shall be paid for at the Contract price per linear foot of ductile iron pipe. This shall include all compensation for connection with open trenching, discovery and protection of subsurface obstructions, pipe bedding, trench backfill, mill and overlay, pavement saw cut; pavement replacement to include pipe trench and pavement
T-top per MAG standard specifications; trench stabilization, over excavation, disposal of surface and waste material at approved locations, furnishing and installing all below ground 36-inch water pipe and fittings, and all incidental and appurtenant work to complete the item as specified and indicated on the
15. Bid Item No. 15 – “36-inch Water System Piping & Fittings” shall be paid for at the Contract price per linear foot of high-density polyethylene pipe. This
23-056 01025-5 For Construction shall include all compensation for connection with open trenching, discovery and protection of subsurface obstructions, pipe bedding, trench backfill, mill and overlay, pavement saw cut; pavement replacement to include pipe trench and pavement T-top per MAG standard specifications; trench stabilization, over excavation, disposal of surface and waste material at approved locations, furnishing and installing all below ground 36-inch water pipe and fittings, and all incidental and appurtenant work to complete the item as specified and indicated on the Contract Documents.
16. Bid Item No. 16 – “30-inch Water System Piping & Fittings” shall be paid for compensation for connection with open trenching, discovery and protection of subsurface obstructions, pipe bedding, trench backfill, mill and overlay, pavement saw cut; pavement replacement to include pipe trench and pavement
T-top per MAG standard specifications; trench stabilization, over excavation, disposal of surface and waste material at approved locations, furnishing and installing all below ground 30-inch water pipe and fittings, and all incidental
17. Bid Item No. 17 – “24-inch Water System Piping & Fittings” shall be paid for compensation for connection with open trenching, discovery and protection of subsurface obstructions, pipe bedding, trench backfill, mill and overlay, pavement sawcut; pavement replacement to include pipe trench and pavement
T-top per MAG standard specifications; trench stabilization, over excavation, disposal of surface and waste material at approved locations, furnishing and installing all below ground 24-inch water pipe and fittings, and all incidental
18. Bid Item No. 18 – “16-inch Water System Piping & Fittings” shall be paid for compensation for connection with open trenching, discovery and protection of subsurface obstructions, pipe bedding, trench backfill, mill and overlay, pavement saw cut; pavement replacement to include pipe trench and pavement
T-top per MAG standard specifications; trench stabilization, over excavation, disposal of surface and waste material at approved locations, furnishing and installing all below ground 16-inch water pipe and fittings, and all incidental
19. Bid Item No. 19 – “16-inch Water System Piping & Fittings” shall be paid for at the Contract price per linear foot of high-density polyethylene pipe. This shall include all compensation for connection with open trenching, discovery
23-056 01025-6 For Construction and protection of subsurface obstructions, pipe bedding, trench backfill, mill and overlay, pavement saw cut; pavement replacement to include pipe trench and pavement T-top per MAG standard specifications; trench stabilization, over excavation, disposal of surface and waste material at approved locations, furnishing and installing all below ground 16-inch water pipe and fittings, and all incidental and appurtenant work to complete the item as specified and indicated on the Contract Documents.
20. Bid Item No. 20 – “6-inch Water System Piping & Fittings” shall be paid for compensation for connection with open trenching, discovery and protection of subsurface obstructions, pipe bedding, trench backfill, mill and overlay, pavement saw cut; pavement replacement to include pipe trench and pavement
T-top per MAG standard specifications; trench stabilization, over excavation, disposal of surface and waste material at approved locations, furnishing and installing all below ground 6-inch water pipe and fittings, and all incidental
21. Bid Item No. 21 – “2-inch and Smaller Copper Pipe Water System Piping &
Fittings” shall be paid for at the Contract price per linear foot. This shall include all compensation for connection with open trenching, discovery and protection of subsurface obstructions, pipe bedding, trench backfill, surface replacement to match existing, trench stabilization, over excavation, disposal of surface and waste material at approved locations, furnishing and installing all below ground 2-inch and smaller water pipe and fittings, and all incidental
22. Bid Item No. 22 – “36-inch Butterfly Valves along with Butterfly Valve
Operator Manhole and Bypass Assembly" shall be paid for at the Contract price as each unit. This shall include compensation for all the work incidental towards installation of 36-inch diameter butterfly valves along with operator manhole and bypass assembly as specified on the Contract Documents.
Payment shall be made based on the actual quantity of valves installed in the
23. Bid Item No. 23 – “30-inch Butterfly Valves along with Butterfly Valve price as each unit. This shall include compensation for all the work incidental towards installation of 30-inch diameter butterfly valves along with operator manhole and bypass assembly as specified on the Contract Documents.
23-056 01025-7 For Construction
24. Bid Item No. 24 – “24-inch Butterfly Valves along with Butterfly Valve price as each unit. This shall include compensation for all the work incidental towards installation of 24-inch diameter butterfly valves along with operator manhole and bypass assembly as specified on the Contract Documents.
25. Bid Item No. 25 – “16-inch Gate Valves along with Valve Box" shall be paid for at the Contract price as each unit. This shall include compensation for all the work incidental towards installation of 16-inch Gate valves along with valve box as specified on the Contract Documents. Payment shall be made based on the actual quantity of valves installed in the field.
26. Bid Item No. 26 – “8-inch Gate Valves along with Valve Box" shall be paid the work incidental towards installation of 8-inch diameter gate valves as specified on the Contract Documents. Payment shall be made based on the actual quantity of valves installed in the field.
27. Bid Item No. 27 – “6-inch Gate Valves along with Valve Box" shall be paid the work incidental towards installation of 6-inch diameter gate valves as specified on the Contract Documents. Payment shall be made based on the actual quantity of valves installed in the field.
28. Bid Item No. 28 – “Fire Hydrant Assembly” shall be paid for at the Contract price as each unit. This shall include all compensation for all the work incidental towards installation of fire hydrant assemblies. Payment shall be made based on the actual quantity of fire hydrants installed in the field.
29. Bid Item No. 29 – “Concrete Manhole” shall be paid for at the Contract price as each unit. This shall include all compensation for all the work incidental towards installation of precast concrete manholes. Payment shall be made based on the actual quantity of manholes installed in the field.
30. Bid Item No. 30 – “Combination Air/Vacuum Release Valve” shall be paid for at the Contract price as each unit. This shall include all compensation for all the work incidental towards installation and testing of valves. Payment shall be made based on the actual quantity installed in the field.
31. Bid Item No. 31 – “Water Quality Sampling Station” shall be paid for at the
Contract price as each unit. This shall include all compensation for all the work incidental towards installation of stations. Payment shall be made based on the actual quantity installed in the field.
23-056 01025-8 For Construction
32. Bid Item No. 32 – “Extra Protection of Waterlines - Concrete” shall be paid for at the Contract price per cubic yard. This shall include all compensation for all the work incidental towards installation of concrete including but not limited to steel reinforcements, formwork, excavations, backfilling and testing.
Payment shall be made based on the actual quantity installed in the field.
33. Bid Item No. 33 – “Steel Casing” shall be paid for at the Contract price per linear foot. This shall include all compensation for all the work incidental towards installation of steel casing including but not limited to excavations, backfilling, welding, testing, and steel material. Payment shall be made based on the actual quantity installed in the field.
34. Bid Item No. 34 – “Traffic Lane Marking Replacement” shall be paid for at the Contract lump sum price. This shall include all compensation for all work incidental to replacement of temporary and permanent traffic lane markings as shown on the Contract Documents and as directed by the Owner. Payment shall be made based on the actual quantity of markings replaced in the field.
35. Bid Item No. 35 – “Slope Stabilization” shall be paid for at the Contract price per square foot. This shall include all compensation for all the work towards installation of slope stabilization including but not limited to excavations, backfilling, testing, fabrics, and rip rap material. Payment shall be made based on the actual quantity installed in the field.
36. Bid Item No. 36 – “16-inch CCP Tie-in and Line Stop” shall be paid for at the incidental towards installation and testing of each connection to the existing
16-inch waterline, including work associated with the additional restraining of the CCP as well as installing a line stop. Payment shall be made based on the actual quantity of tie-ins installed in the field.
37. Bid Item No. 37 – “Tapping Sleeve and Valve” shall be paid for at the Contract price as each unit. This shall include all compensation for all the work incidental towards installation and testing of each Tapping Sleeve and Valve.
Payment shall be made based on the actual quantity of tie-ins installed in the
38. Bid Item No. 38 – “AC Pavement” shall be paid for at the Contract price per square yard. This shall include all compensation for all the work incidental towards saw cut and replacement of the asphalt concrete pavement. Payment shall be made based on the actual quantity installed in the field.
23-056 01025-9 For Construction
39. Bid Item No. 39 – “Rip Rap” shall be paid for at the Contract price per square foot. This shall include all compensation for all the work incidental towards replacing Rip Rap. Payment shall be made based on the actual quantity installed in the field.
40. Bid Item No. 40 – “Drivable Surface” shall be paid for at the Contract price per square foot. This shall include all compensation for all the work incidental towards replacing Driving Surface. Payment shall be made based on the actual quantity installed in the field.
41. Bid Item No. 41 – “Testing, Flushing and Disinfection” shall be paid for at the incidental towards testing, flushing and disinfecting of each phased tie-in.
Payment shall be made based on the actual quantity of Phased testing, flushing and disinfections performed in the field.
42. Bid Item No. 42 – “Owner’s Allowance” The OWNER initiated allowance for additional Work as directed by the ENGINEER/OWNER. This allowance is not be used by the CONTRACTOR to complete any work already identified in the Contract Documents. Payment under this item will be based on the actual cost of the Work performed and/or the items provided.
23-056 01040-1 For Construction
SECTION 01040
COORDINATION WITH OWNER’S OPERATIONS
PART 1 - GENERAL
1.1 DESCRIPTION
A. The intent of this Section is to provide CONTRACTOR a sequence to perform the
Work in such a manner that continuous, uninterrupted Plant Treatment Processes and all essential Plant services and facilities are maintained operational throughout the construction period.
B. The Sequences of Work and Schedule of Completion are specified under Section
01010, Summary of Work. The sequences have been assembled to maintain plant operations during construction.
C. Except for the shutdown durations specified in this Section, CONTRACTOR’S means and methods shall be implemented such that the existing plant or facility, shall remain in continuous satisfactory operation during the entire construction period. Work shall be so scheduled and conducted by CONTRACTOR such that it shall not impede any treatment process, compromise plant security, create potential hazards to operating equipment and plant personnel, reduce the quality of the plant effluent or cause odor or other nuisances. In performing the Work shown and specified, plan and schedule the Work to meet both the constraints outlined in this Section and plant operating requirements.
D. Work not specifically covered in Section 01010, Summary of Work; or in the following paragraphs may, in general, be done at anytime during normal work hours during the Contract period, subject to the operating requirements outlined in this Section. All references to days in this Section are consecutive calendar days.
E. The option of providing additional temporary facilities that can eliminate a constraint provided it is done without additional cost to the OWNER, presents no safety hazards, and provided that all requirements of these Specifications are fulfilled.
F. CONTRACTOR shall be responsible for coordinating all shutdowns with the
OWNER and ENGINEER. Whenever possible, combine discrete shutdown procedures identified in this Section or by CONTRACTOR into a single shutdown when the duration of the shutdowns or the Work requirements allow such combining to occur on a unit process or work area. The intent of combining procedures is to minimize the impacts upon plant operations and processes by limiting the number of shutdowns required.
23-056 01040-2 For Construction
G. CONTRACTOR shall not shut-off or disconnect any operating system, unless approved by the ENGINEER, in writing. All shutdowns shall be executed by the
OWNER, unless otherwise noted. CONTRACTOR shall seal OWNER operated gates and valves to prevent unnecessary leakage as required. After
CONTRACTOR’S Work has been completed, remove the seal to the satisfaction of the ENGINEER.
H. This Section of the Specifications contains several references to equipment, piping, material and appurtenances to be removed or reinstalled. Refer to the
Drawings and other applicable Sections, for definition of the equipment, piping, material and appurtenances to be removed, turned over to the OWNER and stored on site, or to become the property of CONTRACTOR and removed from the site.
I. CONTRACTOR shall be responsible for supplying all temporary pipelines, valves, pumps, meters, spare parts, electrical, controls, any other appurtenances, and labor required for the installation and operation of temporary bypass lines, pumping systems, or conveyance systems required to maintain operations of the system during construction activities.
1.2 GENERAL CONSTRAINTS
A. Article 1.3 below specifies the sequence and shutdown durations, where applicable, for system units which are to be taken out of service. The operational status of new or existing units other than the designated units shall not be interrupted by CONTRACTOR during the specified time periods. New units may only be used after the specified testing is completed and the units are accepted for use by the ENGINEER, in writing.
B. The following constraints shall be applied to all equipment and appurtenant utility systems on the site.
1. Load limits on Access Roads: Existing and new underground facilities, such as electrical duct banks, pipelines, etc., are present in, under and crossing
2. roads. CONTRACTOR shall not exceed normal weight limits for vehicles and shall provide means of protecting the underground facilities.
3. Access to Site: An unobstructed traffic route through all gates shall be maintained at all times.
4. Safety Barriers: Place safety barriers around unsafe areas located around operational areas accessible to plant Personnel.
5. Personnel Access: Treatment plant Personnel shall have access to all areas which remain in operation throughout the construction period.
6. Potable Water System: The existing potable water system shall be kept in operation at all times, unless otherwise specified in Article 1.3, below.
7. Plumbing Facilities: Sanitary facilities in the existing structures shall be operational at all times for plant Operating Personnel, unless otherwise specified in Article 1.5, below. All other building plumbing systems, such as roof and floor drains, pumping, etc., shall be maintained for all structures.
23-056 01040-3 For Construction
8. Storm drainage: Storm drainage on the site shall be operational at all times, unless otherwise specified in Article 1.3, below.
9. Building Heating and Ventilating: In CONTRACTOR’S Work areas and areas affected by CONTRACTOR’S operations, building heating and ventilating shall be both provided and maintained in structures, including pipe galleries. The temperatures to be maintained in any area occupied by plant Personnel, such as offices, lunchrooms, locker rooms, toilet rooms, facilities containing computer control equipment, etc., shall be at least 65°F and not greater than 80°F. The temperatures to be maintained in all other interior plant areas, whether new, existing or temporary, shall be maintained at a minimum of 55°F and not greater than 90°F.
10. Power, Light and Communication Systems: Electric power, lighting service and communication systems shall be maintained in uninterrupted operation in all areas, unless otherwise specified in Article 1.3, below.
11. Sump Pumps and Sumps: All existing sumps shall be maintained in an operable condition with either existing pumps or temporary pumps provided by CONTRACTOR. Interim piping, power and controls shall be provided by
CONTRACTOR, as required by the construction sequence and as directed by the ENGINEER.
12. Seal and Service Water Piping: A supply of service and seal water and the necessary connections to existing equipment shall be maintained during construction, unless otherwise specified in Article 1.3, below. Interim piping shall be provided by CONTRACTOR, as required.
13. It is CONTRACTOR’S responsibility to maintain a clean and dry Work area by pumping and properly disposing of all washdown and cleaning water and stormwater that accumulates in the Work areas.
14. Draining Process Pipes and Conduits:
a. Unless otherwise specified, the contents of pipes and conduits undergoing modifications shall be removed by the OWNER.
b. Any spillage shall be brought to the ENGINEER’S attention immediately in writing. Wash down any spillage to floor drains, sumps and sump pump discharge piping and then flush out the system to prevent clogging and septic odors. If spillage is not suitable for drainage system, e.g. chemical spills, etc, as determined by the ENGINEER, remove spillage by other method such as Vactor truck, as approved by the ENGINEER.
15. Temporary Partitions and Enclosures: Provide temporary partitions and enclosures necessary to maintain dust-free, heated and ventilated spaces in all areas which are adjacent to his Work and which must be kept operational.
16. Dead End Valves or Pipe: Provide blind flanges on all valves or pipes which dead-end a line on a temporary or permanent basis. Blind flanges shall be braced and blocked, as required or as directed by the ENGINEER in the field.
17. Schedule all start-ups for Monday through Thursday. No start-ups will be allowed on Friday, Saturday, and Sunday.
23-056 01040-4 For Construction
1.3 SHUTDOWNS
A. General:
1. A shutdown shall be defined as a portion of the normal operation of a plant unit or conduit that has to be suspended or taken out of service in order to perform the specified Work. For each shutdown, compile an inventory of labor and materials required to perform tasks, provide an estimate of the time required (including time for the OWNER to take down and start-up the plant unit or conduit), and a written description of steps required to complete all tasks. The inventory, the estimate, and written procedures shall be submitted to the ENGINEER for review fourteen calendar days prior to the proposed start date of the shutdown. Request, in writing from the ENGINEER, approval for each shutdown a minimum of seven calendar days prior to the proposed shutdown date. No shutdown shall be initiated until the inventory of materials and labor is verified by the ENGINEER on site at least one week prior to the proposed start date.
2. The Work required herein and any other Work required by the ENGINEER which may interrupt the normal plant operations shall be accomplished at such times that will be convenient to the OWNER.
3. Have on hand and located in close proximity to the Work area, all tools, equipment, spare parts and materials, both temporary and permanent, necessary to complete each Work category without interruption. Adequate numbers of personnel shall be scheduled for each shutdown, so that the Work shall be accomplished within the specified time frame. Prefabrication of all piping and other assemblies shall be completed, to the greatest degree possible, prior to any shutdowns. The ENGINEER shall be satisfied that
CONTRACTOR has complied with these requirements, to the fullest extent possible, before shutdowns will be authorized.
4. If CONTRACTOR’S procedures cause an unscheduled shutdown of the facilities, perform Work as necessary to immediately re-establish satisfactory operation. Notify the ENGINEER, in writing, immediately of any unscheduled shutdown. Permit OWNER’S personnel to work with
CONTRACTOR’S personnel, as required, to maintain the plant in continuous satisfactory operation. Unscheduled shutdowns or interruptions of continued safe and satisfactory operation of the facilities that result in fines levied by the U.S. Environmental Protection Agency, Arizona Department of
Environmental Quality, Maricopa County Health Department, Bureau of Air
Pollution Control, or the Maricopa County Department of Environmental
Management shall be the responsibility of CONTRACTOR if it is demonstrated that CONTRACTOR was negligent in the Work or did not exercise proper precautions in the conduct of the Work.
5. All Work requiring the plant to be out-of-service shall be performed during the scheduled shutdowns shown. It should be noted plant staff shall continue to perform administrative, operation and maintenance functions during shutdowns.
23-056 01040-5 For Construction
6. Electrical Ductbank Installation: Shutdown and relocation of conflicting utilities alignments with electrical ductbank will only be allowed for certain types of process pipelines. Any shutdown and relocations shall follow a strict time schedule in order to minimize impact to plant operations.
B. Shutdowns of Electrical Systems: CONTRACTOR shall lock out and tag circuit breakers and switches operated by the OWNER and shall check cables and wires to be sure that they are de-energized to ground potential before Work begins.
Upon completion of the Work, remove the locks and tags and notify the
ENGINEER that the facilities are available for use.
1.4 OVERTIME
A. All overtime Work by CONTRACTOR necessary to conform to the requirements of this Section shall be performed by CONTRACTOR, at no additional cost to the
OWNER and shall be performed in accordance with the General Conditions.
Make no claims for extra compensation as a result thereof.
1.5 MAINTENANCE OF PLANT OPERATIONS SCHEDULE
A. In order to maintain a continuous plant operation during construction, a
Maintenance of Plant Operations (MOPOs) Schedule is included at the end of this
Section.
B. Within each MOPO item’s procedural steps, time and scheduling constraints and milestone dates may be outlined and are intended to assist CONTRACTOR in developing a sequence of Work and timing in order to maintain continuous operation of the plant.
C. Develop a detailed description of the complete sequence of construction for all the
MOPO events contained herein. The sequences shall be submitted to the
ENGINEER for review and approval thirty days following the Notice to Proceed.
D. The procedures contained herein were developed based upon available information. This list does not address all required tie-ins, but only those anticipated to be of significant impact to plant operations.
E. CONTRACTOR is required to make all tie-ins, connections, and replacements necessary to perform the Work.
F. CONTRACTOR is advised that Work in multiple areas of the plant, gravity sewer and force main system shall be performed simultaneously in order to complete the entire scope of the Work within the allotted Contract time.
23-056 01040-6 For Construction
PART 2 - PRODUCTS (NOT USED)
+ + END OF SECTION + +
23-056 01040-7 For Construction
1.0 Potable Water Tie-Ins
PHASE
NO.
EXTENTS OF
PHASE
CONNECTION NO.
DWG. NO.
STATION ITEM DESCRIPTION PROCEDURE
CONSTRAINTS AND
REMARKS
DURATION OF SHUTDOWN
30” Valve STA 103+20.81
No. 1 C-2
Profile A:
100+00.00
Install new tee on existing 16”
W.
Isolate using City Valves 7+98 and
12+27.
Preform Connection prior to Connection No. 2 No Shutdown Expected
36” Valve STA 100+93.15
No. 2 C-2
Profile B:
100+29.81
Connect new waterline to the existing 24” W
Remove existing flushing pipe assembly and perform tie-in. Isolate with existing valve east on 24” W
- No Shutdown Expected
Connection No. 3 No. 3 C-1 100+00.00
Connect new waterline to the existing 16” W Isolate using City Valve 13+07
Perform Connection prior to Connection No. 4 No Shutdown Expected
30” Valve STA 103+20.81
No. 4 C-1 100+79.63
Install new cross and connect to existing 16” W.
Isolate using City Valves 62+28, 62+24, and 62+60 and existing valve on 12” W south of cross
Verify any services on Hayden Road, north of isolation.
No Shutdown Expected
36” Valve STA 100+93.15
No. 5 C-9 127+29.31
Connect new 36” W to the existing 16” W
Install tapping sleeve and valve on existing 16” W.
- No Shutdown Expected 36” Blind Flange
STA 132+22.83
8” Tapping Sleeve
STA 113+61.21
No. 6 C-5 113+61.21
Connect new 8” to new 36” W and supply to Crossroads Lift Station
Install tapping sleeve and valve on new 36” W.
Perform prior to abandonment of 8” W.
Crossroads Lift Station outage shall be no longer than 4 hours
Connection No. 6
16” Tee STA 100+00
No. 7 C-16 101+56.01
Connect new waterline to the existing 16” W
Isolate using City Valve 13+12.
Remove existing 8” W and install new 16” W.
Perform Connection Simultaneously with
Connection No. 8
No Shutdown Expected
Connection No. 8 No. 8 C-15 124+30.28
Connect new waterline to the existing 16” W
Isolate using Line Stop.
Perform Connection
Simultaneously with
Connection No. 7
No Shutdown Expected
No. 9 C-11 105+38.94
Connect new waterline to the existing 16” W
Isolate using City Valves STA 7+98 and 13+12.
Tie-in to be installed by others.
*Note: Perform Connections and Commission Sections Sequentially
COMMISIONING PHASING PLAN FIG 1-1
Commissioning Phase 1
Commissioning Phase 2
Commissioning Phase 3
Connection #2
Connection #1 Note: Color used to indicate limits of each distinct phase
Commissioning Phase 1
Commissioning Phase 2
Commissioning Phase 3
COMMISIONING PHASING PLANT FIG 1-2
Connection #3
Connection #4
Connection #2
Commissioning Phase 1
Commissioning Phase 2
Commissioning Phase 3
COMMISIONING PHASING PLAN FIG 1-3
Connection #5
Commissioning Phase 3
COMMISIONING PHASING PLAN FIG 1-4
Connection #6Commissioning Phase 4
Commissioning Phase 3
COMMISIONING PHASING PLAN FIG 1-5
Commissioning Phase 4
Commissioning Phase 5 Connection #7
Phase 4 Abandonment:
Crossroads Lift Station Service Connection, keep existing hydrant until connection No. 6 is completed
Then Abandon 8" W
COMMISIONING PHASING PLAN FIG 1-6
Commissioning Phase 5
Connection #7
Commissioning Phase 3
Connection #8
23-056 01050-1 For Construction
SECTION 01050
FIELD ENGINEERING/SURVEYING
PART 1 - GENERAL
1.1 SUMMARY
A. The CONTRACTOR shall hire a surveyor licensed in the State of Arizona to topographically survey the Project site to confirm the baseline conditions. It is also the CONTRACTOR'S responsibility to notify the ENGINEER of any discrepancy found between the topographic survey provided and the baseline conditions provided in the Contract Documents within 14 days of the Notice to Proceed. The
CONTRACTOR further takes the responsibility to correct any discrepancies not reported to the ENGINEER within the specified time frame as part of the finished grading required as part of this Project at no cost to the OWNER.
B. The licensed surveyor shall also fulfill construction staking requirements and responsibilities as specified in the General Conditions. A list of approximate coordinates for site and piping layouts are included on site plan of the drawings.
Dimensions for site, grading, and piping layout are included on the contract drawings.
C. The CONTRACTOR shall provide competent, qualified personnel and materials required to perform all construction layout staking of the Work, will protect and preserve the established reference points, and will make no change or relocations without the prior written approval of the OWNER.
D. The CONTRACTOR will report to the OWNER whenever any reference point is lost or destroyed or requires relocation because of necessary changes in grades or locations. The CONTRACTOR will replace and accurately relocate all reference points so lost, destroyed, or moved.
PART 2 - PRODUCTS (NOT USED)
23-056 01090-1 For Construction
SECTION 01090
REFERENCE STANDARDS/ABBREVIATIONS
PART 1 - GENERAL
1.1 SUMMARY
A. This Section lists many of the construction industry organizations, professional and technical associations, societies and institutes, and government agencies issuing, promoting, or enforcing standards to which references may be made in the Contract
Documents, along with the abbreviations commonly used for those references.
Also included are certain general requirements for the use of industry standards specified and for application of the standards in quality control.
1.2 USE OF REFERENCE STANDARDS
A. Work specified by reference to the published standard or specification of a government agency, technical association, trade association, professional society or institute, testing agency, or other organization shall conform to or surpass the minimum standards of quality for materials and workmanship established by the designated standard or specification.
B. Where so specified, products or workmanship shall also conform to the additional prescriptive or performance requirements included within the Contract Documents to establish a higher or more stringent standard of quality than that required by the referenced standard.
C. Where the specific date or issue of the standard is not included with the reference to the standard, the edition, including all amendments published and available on the first published date of the Invitation to Bid, shall apply.
D. Where two or more standards are specified to establish quality, the product and workmanship shall conform to or surpass the requirements of both.
E. In case of conflict between referenced standards, the more stringent shall apply.
F. Where both a standard and a brand name are specified for a product in the Contract
Document, the proprietary product named shall conform to or surpass the requirements of the specified reference standard. The listing of a trade name in a
Contract Document shall not be construed a warranting that such product conforms to the respective reference standard.
G. Copies of Standards:
1. Copies of applicable referenced standards have not been bound in this Contract
Document.
23-056 01090-2 For Construction
2. Where copies of standards are needed by the CONTRACTOR for superintendence and quality control of the Work, obtain a copy or copies directly from the publication source and maintain in an orderly manner at the job site, available to the CONTRACTOR'S personnel, subcontractors, OWNER, and ENGINEER.
3. Submittals: Submit for approval the requests to use products conforming to printed standards or publications with a different publication date from that effective under the Contract. Clearly indicate the changes in product or workmanship quality involved in the proposed change, if any, and reasons for the request.
1.3 ABBREVIATIONS
A. Abbreviations for Trade Organizations and Government Agencies: The following is a list of construction industry organizations and government agencies to which references may be made in the Contract…