2-46 N-0774-01 LET MAN.pdf

PDF 4 MB Posted

Attached to
Cedar Creek Trail - Phase 3
Solicitation number
46 N-0774-01
Issued by
Johnson County, Kansas

About this file

This is a comprehensive set of contract documents for the Cedar Creek Trail - Phase 3 project, issued by the City of Olathe, Kansas Infrastructure Department Engineering Division. The project involves constructing 0.9 miles of a 10-foot wide recreational trail with generally asphalt construction and installing a 125 linear foot, 14-foot wide pedestrian bridge. Sealed bids will be received online through the Olathe, Kansas electronic bidding platform (https://olatheks.bonfirehub.com) until 2:00 p.m. local time on October 24, 2025. The contract time is set at 200 days for substantial completion and 230 days for final completion, with liquidated damages of $500 per day for delays. An owner's contingency allowance of $100,000 is included in the bid, and bidders must provide a 5% bid bond.

The project is federally funded and requires compliance with multiple federal and state regulations, including Davis-Bacon wage rates, equal employment opportunity provisions, and disadvantaged business enterprise (DBE) participation requirements. A 10% DBE contract goal has been established, and bidders must either meet this goal or demonstrate good faith efforts to do so. The project will be subject to prevailing wage rates, and contractors must follow specific guidelines for workforce composition, subcontracting, and reporting. The City of Olathe will provide a tax exemption certificate to help contractors minimize project costs, and all materials and labor must adhere to specified federal, state, and local standards.

View the file

Other files

File Type Posted
1-46 N-0774-01 LET.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contract Documents for:

Cedar Creek Trail – Phase 3

Project Number 46 N-0774-01

Prepared by:

City of Olathe, Kansas

Infrastructure Department

Engineering Division

8/29/25

CITY OF OLATHE, KANSAS

ENGINEERING DIVISION

NOTICE TO BIDDERS

Sealed bids will be received online at https://olatheks.bonfirehub.com, until 2:00 p.m. local time, on October 24, 2025, for the construction of Cedar Creek Trail – Phase 3, Project No. 46 N-0774-01.

At said time and place, and promptly thereafter, all bids that have been duly received will be publicly opened online at https://olatheks.bonfirehub.com.

The work consists of the following:

0.9 Miles of 10-foot Recreational Trail (Generally Asphalt Construction) Installation of a 125 LF, 14-foot wide, Pedestrian Bridge

Bid documents including drawings and specifications are on file at the office of Public Works of Olathe, Kansas, and are open for public inspections. Bid documents and drawings may be downloaded free of charge from https://olatheks.bonfirehub.com. Only bids submitted electronically at https://olatheks.bonfirehub.com will be accepted.

An Owner’s Allowance (set price) is included within the Schedule of Values for this Project and shall be bid at $100,000.00. Failure to do so may result in disqualification.

A satisfactory bid bond executed by the bidder or an acceptable surety, in an amount equal to five percent (5%) of the total bid for work shall be submitted with each proposal. A scanned copy of the BID BOND must be included with the online bid submitted at https://olatheks.bonfirehub.com. The original copy of the BID BOND form must be submitted to the ENGINEER within 48 hours of bid opening. Failure to submit original copy of the bid bond will result in rejection of bid and OWNER’s selection of the next low qualified bidder.

The successful bidder will be required to furnish and pay satisfactory performance and payment bond or bonds.

Attention is called to the fact that not less than the minimum salaries and wages as set forth in the contract documents must be paid on this project, and that the contractor must ensure that employees and applicants for employment are not discriminated against because of their race, color, religion, sex, or national origin.

Contractors must comply with Title 29 relating to the employment of apprentices in accordance with requirements published by the United States Department of Labor as contained in the contract documents.

Bidders are informed that the prime contractor and subcontractors are required to comply with Section 109 of the Housing and Community Development Act of 1974, Title VI of the Civil Rights Act of 1964, Executive Order 11246, and Section 3 of the Housing and Urban Development Act of 1968. Contractors responsibilities under these laws are outlined at Title 24, CFR Part 1 and Part 570 relating to non-discrimination in federally-assisted programs of the Department of Housing and Urban Development; Title 24, Part 130 relating to equal employment opportunity under HUD-assisted construction contract; and Title 24, Part 135 relating to employment opportunities for businesses and lower income persons in connection with assisted projects.

https://olatheks.bonfirehub.com/

City of Olathe NB-2 46 N-0774-01

The prime general contractor, and subcontractors where appropriate, under the terms of the contract, shall be required to comply with the following requirements prior to issuance of a construction work order:

(A) Maintain an affirmative action file detailing efforts to meet affirmative action hiring responsibilities and utilize minority firms as subcontractors and supplier;

(B) Submit a copy of their affirmative action plan to the city for review and HUD concurrence;

(C) Provide a preliminary statement of work force needs by category for the project and goals for minorities; and

(D) Attend a scheduled pre-construction conference for orientation on HUD equal opportunity and labor standards requirements.

The City of Olathe, Kansas, reserves the right to reject any or all bids or to waive any informality in the bidding.

Bids may be held by the City of Olathe, Kansas, for a period not to exceed sixty (60) days from the date of the opening of bids for the purpose of reviewing the bids and investigating the qualifications of bidders, prior to awarding the contract.

BY Brenda Swearingian City Clerk

TC-1 City of Olathe

TABLE OF CONTENTS

NOTICE TO BIDDERS ............................................................................................................. NB-1 TABLE OF CONTENTS ........................................................................................................... TC-1 INSTRUCTIONS TO BIDDERS............................................................................................... ITB-2 01 Defined Terms ....................................................................................................... ITB-2 02 Copies of Bidding Documents....................... ....................................................... ITB-2 03 Qualifications of Bidders......................... .............................................................. ITB-2 04 Examination of Contract Documents and Site............................................ .......... ITB-2 05 Interpretations................................... ..................................................................... ITB-3 06 Bid Security...................................... ..................................................................... ITB-3 07 Contract Time..................................... ................................................................... ITB-4 08 Liquidated Damages................................ .............................................................. ITB-4 09 Substitute Material and Equipment................... .................................................... ITB-4 10 Subcontractors, Etc............................... ................................................................. ITB-4 11 Bid Form................................................................................................................ ITB-5 12 Submission of Bids................................ ................................................................ ITB-5 13 Modification and Withdrawal of Bids............... .................................................... ITB-5 14 Opening of Bids..................................................................................................... ITB-5 15 Bids to Remain Open............................... ............................................................. ITB-5 16 Award of Contract................................. ................................................................ ITB-6 17 Performance and Other Bonds............................................................................... ITB-6 18 Signing of Agreement.............................. ............................................................. ITB-6 19 Special Legal Requirements........................ .......................................................... ITB-7 20 Non-Resident Contractors.......................... ........................................................... ITB-7 21 Equal Employment Opportunity...................... ..................................................... ITB-7 22 Wages and Salaries........................ ........................................................................ ITB-7 23 Compliance with Affirmative Action Requirements.......................... ................... ITB-7 24 Compliance with Section 3 Requirements...................... ...................................... ITB-8 25 Compliance with Department of Labor Regulations...................... ....................... ITB-8 26 Title 29 Documents...................... ......................................................................... ITB-8 27 Tax Exemption..................................... ................................................................. ITB-8 ANTI-DISCRIMINATION FORM ........................................................................................... ADF-1 STATEMENT OF BIDDERS QUALIFICATIONS........................ .......................................... BQ-1 BID BOND................................................... .............................................................................. BB-1 BID FORM................................................... .............................................................................. BF-1 STANDARD FORM OF AGREEMENT....................... ........................................................... EJCDC-1 PERFORMANCE AND MAINTENANCE BOND........................... ....................................... EJCDC-8 STATUTORY BOND............................................. ................................................................... EJCDC-10 APPOINTMENT OF PROCESS AGENT............................... .................................................. EJCDC-12 NON-COLLUSIVE AFFIDAVIT OF PRIME BIDDER.................... ...................................... EJCDC-13 STANDARD GENERAL CONDITIONS................................ ................................................. 100-1 SUPPLEMENTARY CONDITIONS................................... ..................................................... SC-1 KDOT CONTRACT SPECIFICATIONS ACKNOWLEDGEMETN FORM.......................... RSC-i KDOT CONTRACT SPECIFICATIONS...................................................................................RSC-1 GENERAL DECISION—WAGE RATES....................................... ......................................... JOCO-KS-1 PROJECT REQUIREMENTS....................................... ............................................................ PR-1 TEMPORARY FACILITIES....................................... .............................................................. TF-1 SUBMITTALS................................................. .......................................................................... SB-1 TECHNICAL SPECIFICATIONS............................................................................................. TS-1 SPECIAL CONDITIONS......................................... ................................................................. SPC-1 MEASUREMENT AND PAYMENT.................................... .................................................... M&P-1

City of Olathe ITB-2 46 N-0774-01

INSTRUCTIONS TO BIDDERS

1. DEFINED TERMS

These Instructions to Bidders which are defined in the Standard General Conditions of the

Construction Contract, EJCDC C-700, 2013 Edition have the meanings assigned to them in the General Conditions. The term “Successful Bidder” means the lowest qualified, responsible BIDDER to whom OWNER (on the basis of OWNER’S evaluation as hereinafter provided) makes an award.

2. COPIES OF BIDDING DOCUMENTS

A. Complete sets of the Bidding Documents in the number and for the deposit sum, if any, stated in the Advertisement or Invitation may be obtained from ENGINEER via https://oaltheks.bonfirehub.com.

B. Complete sets of Bidding Documents shall be used in preparing bids; neither OWNER nor

ENGINEER assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.

C. OWNER and ENGINEER in making copies of Bidding Documents available on the above terms do so only for the purpose of obtaining bids on the work and do not confer a license or grant for any other use.

3. QUALIFICATIONS OF BIDDERS

A. Contractor to provide a Certificate of Good Standing from the Kansas Secretary of State prior to the project award.

B. To demonstrate qualifications to perform the work, each BIDDER must be prepared to submit, within five (5) days of OWNER's request, a notarized "Statement of Bidder's Qualifications." A form for this purpose is included in this document. All information requested on the form must be provided. Each bid must contain evidence of BIDDER's qualification to do business in the state where the project is located or covenant to obtain such qualification prior to award of the contract.

4. EXAMINATION OF CONTRACT DOCUMENTS AND SITE

A. Before submitting a bid, each BIDDER must (a) examine the Contract Documents thoroughly, (b) visit the site to familiarize himself with local conditions that may in any manner affect cost, progress or performance of the work, (c) familiarize himself with federal, state and local laws, ordinances, rules and regulations that may in any manner affect cost, progress or performance of the work; and (d) study and carefully correlate BIDDER'S observations with the Contract Documents.

B. Reference may be made in the Supplementary Conditions for the identification of those reports of investigations and tests of subsurface and latent physical conditions at the site or otherwise affecting cost, progress, or performance of the work which have been relied upon by the ENGINEER used in preparing the drawings and specifications. OWNER will make copies of such reports available to any BIDDER requesting them. These reports are not guaranteed as to accuracy or completeness, nor are they part of the Contract

City of Olathe ITB-3 46 N-0774-01

Documents. Before submitting his bid each BIDDER will, at his own expense, make such additional investigations and tests as the BIDDER may deem necessary to determine his bid for performance of the work in accordance with the time, price and other terms and conditions of the Contract Documents.

C. On request, OWNER will provide each BIDDER access to the site to conduct such investigations and tests as each BIDDER deems necessary for submission of his bid.

D. The lands upon which the work is to be performed, rights-of-way for access thereto and other lands designated for use by CONTRACTOR in performing the work are identified in the Supplementary Conditions, General Requirements, or drawings.

E. The submission of a bid will constitute an incontrovertible representation by the BIDDER that he has complied with every requirement of this Article 4 and that the Contract Documents are sufficient in scope and detail to indicate and convey understanding of all terms and conditions for performance of the work.

5. INTERPRETATIONS

All questions about the meaning or intent of the Contract Documents shall be entered online via https://olatheks.bonfirehub.com. Replies will be issued by addenda via https://olatheks.bonfirehub.com to all parties recorded as having received the bidding documents. Questions received less than three (3) days prior to the date for opening of bids will not be answered. Only questions answered via https://olatheks.bonfirehub.com through an addenda will be binding. Oral and other interpretations or clarifications will be without legal effect.

6. BID SECURITY

A. Bid Security shall be made payable to OWNER in an amount of five percent (5%) of the

BIDDER'S maximum bid price and in the form of a Bid Bond (on form attached, if a form is prescribed) issued by a Surety meeting the requirements of paragraph 6.01 of the General Conditions.

B. The Bid Security of the successful BIDDER will be retained until such BIDDER has executed the agreement and furnished the required Contract Security, whereupon it will be returned; if the successful BIDDER fails to execute and deliver the agreement and furnish the required Contract Security within ten (10) days of the Notice of Award, OWNER may annul the Notice of Award and the Bid Security of that BIDDER will be forfeited. The Bid Security of any BIDDER whom OWNER believes to have a reasonable chance of receiving the award may be retained by OWNER until the earlier of the seventh day after the "effective date of the agreement" (which term is defined in the General Conditions) by OWNER to CONTRACTOR and the required Contract Security is furnished on the sixty-first (61) day after the bid opening. Bid Security of other BIDDERS will be returned within sixty (60) days of the bid opening.

C. A scanned copy of the BID BOND must be included with the online bid submitted at https://olatheks.bonfirehub.com. The original copy of the BID BOND form must be submitted to the ENGINEER within 48 hours of bid opening. Failure to submit original copy of the bid bond will result in rejection of bid and OWNER’s selection of the next low qualified bidder.

City of Olathe ITB-4 46 N-0774-01

7. CONTRACT TIME

The number of days within which, or the date by which, the work is to be completed (the contract time) is set forth in the Bid Form and will be included in the Agreement.

8. LIQUIDATED DAMAGES

Provisions for liquidated damages, if any, are set forth in the Agreement.

9. SUBSTITUTE MATERIAL AND EQUIPMENT

The contract, if awarded, will be on the basis of material and equipment described in the drawings or specified in the specifications without consideration of possible substitute or "or-equal" items. Whenever it is indicated in the drawings or specified in the specifications that a substitute or "or-equal" item of material or equipment may be furnished or used by CONTRACTOR if acceptable to ENGINEER, application for such acceptance will not be considered by ENGINEER until after the "effective date of the agreement." The procedure for submittal of any such application by CONTRACTOR and consideration by ENGINEER is set forth in paragraphs 7.04 and 7.05 of the General Conditions and paragraphs SC 7.04.A and SC 7.04.D of the Supplementary Conditions.

10. SUBCONTRACTORS, ETC.

A. If the Supplementary Conditions require the identity-identities of certain

SUBCONTRACTORS and other persons and organizations to be submitted to OWNER in advance of the Notice of Award, the apparent Successful BIDDER, and any other BIDDER so requested, will within thirty (30) days after the day of the bid opening submit to OWNER a list of all SUBCONTRACTORS and other persons and organizations (including those who are to furnish the principal items of material and equipment) proposed for those portions of the work as to which such identification is so required.

Such list shall be accompanied by an experience statement with pertinent information as to similar projects and other evidence of qualification for each such SUBCONTRACTOR, person and organization if requested by OWNER. If OWNER or ENGINEER, after due investigation-investigations, has reasonable objection to any proposed SUBCONTRACTOR, other person or organization, either may before giving the Notice of Award request the apparent Successful BIDDER to submit an acceptable substitute without an increase in bid price. If the apparent Successful BIDDER declines to make any such substitution, the contract shall not be awarded to such BIDDER, but his declining to make any such substitution will not constitute grounds for sacrificing his Bid Security. Any SUBCONTRACTOR, other person or organization so listed and to whom OWNER or ENGINEER does not make written objection prior to the giving of the Notice of Award will be deemed acceptable to OWNER and ENGINEER.

B. In contracts where the contract price is on the basis of cost-of-the-work plus a fee, the apparent Successful BIDDER, prior to the Notice of Award, shall identify in writing to OWNER those portions of the work that such BIDDER proposes to subcontract and after the Notice of Award may only subcontract other portions of the work with OWNER'S written consent.

C No CONTRACTOR shall be required to employ any SUBCONTRACTOR, other person, or organization against whom he has reasonable objection.

City of Olathe ITB-5 46 N-0774-01

D As provided in Article 7 of the General Conditions, the CONTRACTOR may utilize the services of SUBCONTRACTORS on those parts of the Work which, under normal contracting practices, are performed by SUBCONTRACTORS; provided, however that the CONTRACTOR shall not award subcontracts which total more than 50% of the total Contract Price based upon the unit prices within the Bid submitted to the OWNER by the

CONTRACTOR.

11. BID FORM

The bid form attached hereto is for reference only; bidders must download and complete the required bid form and enter line item unit amounts online at https://olatheks.bonfirehub.com.

12. SUBMISSION OF BIDS

Bids shall be submitted at the time and place indicated in the Invitation to Bid, only bids submitted electronically at https://olatheks.bonfirehub.com will be considered. A scanned copy of the BID BOND must be included with the online bid. Bidders shall acknowledge receipt of any bid addenda issued by signing the bid addendum form and uploading with the Bid.

13. MODIFICATION AND WITHDRAWAL OF BIDS

A. Bids may be modified or withdrawn online at any time up to the time and date of bid opening listed on the Notice to Bidders.

B. If, within twenty-four (24) hours after bids are opened, any BIDDER files a duly signed written notice with OWNER and promptly thereafter demonstrates to the reasonable satisfaction of OWNER that there was a material and substantial mistake in the preparation of his bid, that BIDDER may withdraw his bid and the Bid Security will be returned.

Thereafter, that BIDDER will be disqualified from further bidding on the work.

14. OPENING OF BIDS

Bids will be opened (publicly).

A. Bids will be opened publicly online at https://olatheks.bonfirehub.com. The online process shall be utilized in place of a bid opening meeting, unless otherwise noted in the contract documents. An abstract of the base bids and major alternatives (if any) will be available online after the opening of the bids.

B. When bids are opened publicly at a bid opening meeting they will be read aloud, and an abstract of the amounts of the base bids and major alternates (if any) will be made available after the opening of bids.

C. When bids are opened privately, an abstract of the same information will be made available to BIDDERS within seven (7) days after the date of bid opening upon receipt of a written request to the OWNER by the CONTRACTOR.

15. BIDS TO REMAIN OPEN

City of Olathe ITB-6 46 N-0774-01

All bids shall remain open for sixty (60) days after the date of the bid opening, but OWNER may, in his sole discretion, release any bid and return the Bid Security prior to that date.

16. AWARD OF CONTRACT

A. OWNER reserves the right to reject any and all bids, to waive any and all informalities and to negotiate contract terms with the Successful BIDDER, and the right to disregard all nonconforming, non-responsive or conditional bids. Discrepancies between words and figures will be resolved in favor of words. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.

B. In evaluating bids, OWNER shall consider the qualifications of the BIDDERS, whether or not the bids comply with the prescribed requirements, and alternates and unit prices if requested in the bid forms. It is OWNER'S intent to accept alternates (if any are accepted) in the order in which they are listed in the bid form but OWNER may accept them in any order or combination.

C. OWNER may consider the qualifications and experience of SUBCONTRACTORS and other persons and organizations (including those who are to furnish the principal items of material or equipment) proposed for those portions of the work as to which the identity of SUBCONTRACTORS and other persons and organizations must be submitted as provided in the Supplementary Conditions. Operating costs, maintenance considerations, performance data and guarantees of materials and equipment may also be considered by

OWNER.

D. OWNER may conduct such investigations as he deems necessary to assist in the evaluation of any bid and to establish the responsibility, qualifications and financial ability of the BIDDERS, proposed SUBCONTRACTORS and other persons and organizations to do the work in accordance with the Contract Documents to OWNER'S satisfaction within the prescribed time.

E. OWNER reserves the right to reject the bid of any BIDDER who does not pass any such evaluation to OWNER'S satisfaction.

F. If the contract is to be awarded it will be awarded to the lowest responsive and responsible

BIDDER whose evaluation by OWNER indicates to OWNER that the award will be in the best interests of the project.

G. If the contract is to be awarded, OWNER will give the Successful BIDDER a Notice of

Award within sixty (60) days after the day of the bid opening.

17. PERFORMANCE AND OTHER BONDS

Paragraph 6.01 of the General Conditions and Section SC 6.01.A of the Supplementary

Conditions set forth OWNER'S requirements as to performance and other bonds. When the Successful BIDDER delivers the executed agreement to OWNER it shall be accompanied by the required Contract Security.

18. SIGNING OF AGREEMENT

When OWNER gives a Notice of Award to the Successful BIDDER, it will be accompanied by at least five (5) unsigned counterparts of the agreement and all other Contract Documents.

City of Olathe ITB-7 46 N-0774-01

Within ten (10) days thereafter CONTRACTOR shall sign and deliver at least five (5) counterparts of the agreement to OWNER with all other Contract Documents attached. Within fifteen (15) days thereafter OWNER will deliver all fully signed counterparts to CONTRACTOR. ENGINEER will identify those portions of the Contract Documents not fully signed by OWNER and CONTRACTOR and such identification shall be binding on all parties.

19. SPECIAL LEGAL REQUIREMENTS

The contract awardee, if not a resident of Kansas, shall appoint a Process Agent as provided by the form in these documents. Refer to the Supplementary Conditions for further instructions.

20. NON-RESIDENT CONTRACTORS

A. If the Successful BIDDER is a corporation organized outside the state of Kansas, it will be necessary to apply to the Secretary of State for authority to engage in business in this state as a foreign corporation (see K.S.A. 17-7301 et. seg.).

B. All non-resident CONTRACTORS and SUBCONTRACTORS, as defined in K.S.A. 79-

1008, desiring to engage in the business of construction in the State of Kansas and who have not registered this contract with the Director of Revenue for the state of Kansas, post a good and valid surety bond in the sum of $1,000.00 and conditioned that all taxes, including contributions due under the employment security law, which may accrue to the state of Kansas and all taxes, including contributions due under the employment security law, which may accrue to the State of Kansas, and all taxes which may accrue to the political subdivisions thereof on such Contract shall be paid (see K.S.A. 79-1009 et. seg.).

21. EQUAL EMPLOYMENT OPPORTUNITY

Attention of BIDDERS is particularly called to the requirements for assuring that employees and applicants for employment are not discriminated against in the performance of any work done under the contract because of race, religion, color, sex, physical handicap unrelated to such person's ability to engage in the particular work, or national origin or ancestry. (See GENERAL

SPECIFICATIONS).

22. WAGES AND SALARIES:

A. Attention of BIDDERS is particularly called to the requirements concerning the payment of the not less than the prevailing wage and salary rates specified in the contract documents and the conditions of employment with respect to certain categories and classifications of employees. See GENERAL SPECIFICATIONS, PART II.

B. The rates of pay set forth under GENERAL SPECIFICATIONS, PART II, are the minimal to be paid during the life of the contract. It is, therefore, the responsibility of the BIDDERS to inform themselves as to local labor conditions, such as the length of work day and work week overtime compensation, health and welfare contributions, labor supply and prospective changes or adjustments of rates.

23. COMPLIANCE WITH AFFIRMATIVE ACTION REQUIREMENTS:

City of Olathe ITB-8 46 N-0774-01

BIDDERS on this project will be required to comply with the bid conditions affirmative action requirements referred to as the Kansas City plan. Failure to comply with the above will result in the bid not being awarded.

24. COMPLIANCE WITH SECTION 3 REQUIREMENTS:

BIDDERS on this project will be required to comply with Section 3 of the Housing and Urban

Development Act of 1968. This section provides that to the greatest extent feasible, opportunities for training and employment shall be given to lower income residents of HUD-assisted project areas, and that contracts for work in connection with such projects be awarded to business concerns which are located in, or are owned in substantial par by persons residing in the area of the project. BIDDERS should familiarize themselves with Title 24, CFR Part 135, outlining their responsibilities under this law.

25. COMPLIANCE WITH DEPARTMENT OF LABOR REGULATIONS:

BIDDERS on this project shall comply with the provisions of the Department of Labor regulations--Title 29 (CFR 29, part 5 and part 5A. See GENERAL SPECIFICATIONS, PART II). Copies of Department of Labor regulations (Title 29) are available from the City of Olathe.

26. TITLE 29 DOCUMENTS:

Attention of BIDDERS is called to familiarize themselves with the requirement for the use of apprentice-apprentices. (See DIVISION 220--General Specifications)

27. TAX EXEMPTION

All applicable taxes, sales, consumer, use and other similar taxes, imposed by any taxing authority, on materials, equipment or supplies to be incorporated in the work, shall be tax exempt and not included in the Bid.

The low BIDDER shall be required to furnish taxing authorities any necessary information or reports pertaining thereto, as required.

Pursuant to KSA 79-3606, both services and materials for this project are exempt from the

Kansas Retailers' Sales Tax and the Kansas Compensating Tax. Within fifteen (15) days after the date of Contract, OWNER will provide a Kansas sales and compensating tax exemption certificate number to CONTRACTOR. CONTRACTOR and each SUBCONTRACTOR or repairman must furnish the exemption certificate number to each supplier on Kansas Sales Tax Division Form STD 74. The exemption certificate number shall be placed on all invoices for material to be incorporated in the work. All invoices shall be held by CONTRACTOR for five

(5) years, and shall be subject to audit by the Director of Taxation. Upon completion of the work, CONTRACTOR shall file with OWNER on a form provided by the Director of Taxation, a sworn statement that all purchases made under the exemption certificate were entitled to be exempt from the Kansas Retailers' Sales Tax and the Kansas Compensating Tax.

CONTRACTOR shall assume full responsibility for proper use of the exemption certificate number and shall pay all legally assessed penalties for improper use of the certificate number.

ADF - 1

***For completion by bid finalists ONLY***

When selected as the successful bidder for a contract with the City of Olathe, the Contracting Company, Firm or Agency will submit the following information in accordance with the requirements of the

Municipal Code. All questions must be answered, and the data given must be clear and comprehensive.

If necessary, questions may be answered on separate attached sheets. This questionnaire must be notarized. Misrepresentation of fact will disqualify the bidder. Please e-mail the completed

Questionnaire separately to your Olathe contract liaison if you are selected as a bid finalist. If you have already completed this questionnaire or received Compliance Certification after August 2017, you do not need to resubmit these forms unless there have been significant changes to your ownership and/or business practices. Instead, please submit the date and project number and project description related to your submission of these form. For questions, please contact the Office of Community Relations at

(913) 971-8827.

Name of Contracting Company, Firm or Agency:

Name of your Equal Employment Officer or designated contact person:

Address: ________________________________________________________

City: ______________________State: _____________________Zip: ________

Contact Person’s Phone: __________________________________________

Email: _______________________________________________________________

Type of Company, Firm or Agency: __________________________________

Name of Company, Firm or Agency President: _________________________

I certify that that my company:

1. Does not discriminate, will not discriminate, and has never discriminated against any employee or applicant for employment because of Race, Religion, Color, Sex, Age, Disability, National

Origin or Ancestry.

Yes ☐ No☐

If No, explain

ADF - 2

2. Will adhere to Local, State, and Federal laws and mandates; and will adhere to Affirmative

Action/Equal Opportunity in all its employment procedures including advertising, recruiting, hiring, training, promotions and upgrading.

3. Will require that any subcontractor my company hires for any work for the City comply with these non-discrimination policies.

I understand that an act of discrimination is a breach contract with the City. I also understand that the

Community Relations Manager or designee is authorized to initiate investigations, receive discrimination complaints, and refer them to the Olathe Human Relations Commission on an ongoing basis. An Act of discrimination or a misleading or a dishonest response to this form may result in the contract being rescinded, terminated, or suspended in whole or in part.

Dated this ___________day of ____________, 202___.

Firm Name _________________________________________________________________

Signature of Person Completing Form: __________________________________________________________________

Print Name __________________________________________________________________

Title __________________________________________________________________

Email______________________________________ Phone _________________

To be completed by a Notary Public:

State of ___________________________

(County) of ________________________

Signed and sworn to (or affirmed) before me on _______________ by ___________________________.

(Signature of notarial officer)

(Seal)

Title (and Rank)

[My appointment expires: ________]

Revised September 96 BQ-1 City of Olathe

STATEMENT OF BIDDER'S QUALIFICATIONS

(To be submitted by the Bidder only upon specific request of the City of Olathe).

All questions must be answered and the data given must be clear and comprehensive. This statement must be notarized. If necessary, questions may be answered on separate attached sheets. The Bidder may submit any additional information he desires.

1. Name of Bidder:

2. Permanent main office address:

3. When organized:

4. If a corporation, where incorporated:

5. How many years have you been engaged in the contracting business under your present firm or trade name?

6. Contracts on hand: (Schedule these, showing amount of each contract and the appropriate anticipated dates of completion.)

7. General character of work performed by your company:

8. Have you ever failed to complete any work awarded to you?

If so, where and why?

9. Have you ever defaulted on a contract?

If so, where and why?

10. List the more important projects recently completed by your company, stating the approximate cost for each, and the month and year completed:

11. Experience in construction work similar in importance to this project:

12. List your major equipment available for this contract:

Revised September 96 BQ-2 City of Olathe

13. Background and experience of the principal members of your organization, including the officers.

14. Credit available: $_______________________.

15. Give bank references:

16. Will you, upon request, fill out a detailed financial statement and furnish any other information that may be required by the City of Olathe?

17. The undersigned hereby authorized and requests any person, firm, or corporation to furnish any information requested by the City of Olathe in verification of the recitals comprising this Statement of Bidder's Qualifications.

Dated at ______________________this ________ day of _________________________, 20____.

By _________________________________ Title ________________________________

State of ) )ss County of ) being duly sworn, deposes and says that he is ________________________________________________ of ___________________________________________________ and that the answers to the foregoing questions and all statements therein contained are true and correct.

Subscribed and sworn to me before this _____ day of _______________________, 20____.

Notary Public My commission expires ________________________, 20_________.

Revised 2013 BB – 1 City of Olathe

BID BOND

KNOW ALL MEN BY THESE PRESENTS, that we ______________________________________________, a

___________________________________________ duly organized under the laws of the State of ___________, as PRINCIPAL, and

_____________________________________, a corporation duly organized under the laws of the State of ___________, as SURETY, are held and firmly bound unto the City of Olathe, Kansas, herein after called the City of Olathe, in the penal sum of ______ Percent of the Amount of Bid

( __%), for the payment of which sum will and truly to be made, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION IS SUCH, that whereas the Principal has submitted the accompanying bid, dated__________________________,20________, for the following project:

NOW, THEREFORE, if the Principal shall not withdraw said Bids within the period specified therein after the opening of the same, or, if no period be specified, within thirty (30) days after the said opening, and shall within the period specified therefore, or if no period be specified, within ten (10) days after the prescribed forms are presented to SURETY for signature, enter into a written Contract with the City of

Olathe in accordance with the Bid as accepted, and give bond with good and sufficient surety or sureties, as may be required, for the faithful performance and proper fulfillment of such Contract; or in the event of the withdrawal of said Bid within the period specified, or the failure to enter into such Contract and give such bond within the time specified, if the Principal shall pay the City of Olathe the difference between the amount specified in said Bid and the amount for which the City of Olathe may procure the required work or supplies for both, if the latter be in excess of the former, then the above obligation shall be void and of no effect, otherwise to remain in full force and virtue.

IN WITNESS WHEREOF, the above-bounded parties have executed this instrument under their several seals this _____ day of_____________________, 20____, the name and corporate seal of each corporate party being hereto affixed.

PRINCIPAL SURETY

_____________________________________________ (SEAL) _______________________________________________ (SEAL)

(Principal) (Surety)

Business Address: ___________________________________ By: __________________________________________________

___________________________________ Attorney-in-Fact, State of _______________________

By: _______________________________________________ Surety Phone No: ______________________________________

(Corp. Principal)

__________________________________________________ Witness: _____________________________________________ (Title)

Witness: ___________________________________________

UNITS APPROX. AMOUNT

QUANTITY DOLLARS CENTS DOLLARS

P.N. 46-N0774-01

1 Mobilization LS 1

2 Mobilization (DBE) LS 1

3 Contractor Construction Staking LS 1

4 Field Office and Laboratory (Type C) EA 1

5 Owners Contingency Allowance EA 1 100,000 00 $100,000.00

6 Clearing and Grubbing AC 3.9

7 Demolition and Removals LS 1

8 Salvaged Topsoil SY 15,352

9 Unclassified Excavation CY 4,904

10 Compaction of Earthwork (Type B) (MR-90) CY 3,441

11 Compaction of Earthwork (Type AA) (MR-3-3) CY 328

12 Water (Grading) (Set Price) MGAL 1

13 Foundation Stabilization (Set Price) CY 1

14 Riprap (Light Stone) (100 LB) SY 10

15 Fence (Special) LF 156

16 Fence (Chain Link) (6'-0") LF 310

17 Fence (Chain Link) (Removal and Resetting) LF 140

18 Posts (Corner) (Chain Link) EA 1

19 Fence (Chain Link) (Top Rail) LF 275

20 Posts (Chain Link) EA 6

21 Posts (End) (Chain Link) EA 2

22 Gate (Chain Link Fence) (20') (Remove and Reset) EA 1

23 Fence (Removal of Existing) LF 45

24 Sidewalk Construction (5")(AE) SY 121

25 Cap and Abandon Waterline EA 4

26 Cross Road Pipe (18") (RCP) LF 80

27 Cross Road Pipe (19"x30") (RCPHE) LF 25

28 End Section (18") (RC) EA 2

29 End Section (19"X30") (RC) EA 2

30 Class I Excavation CY 2

31 Piles (Steel)(HP12x53) LF 184

32 Cast Steel Pile Points EA 8

33 Concrete (Grade 4.0)(AE) CY 20

34 Reinforcing Steel (Grade 60)(Epoxy Coated) LBS 3,080

35 Prefabricated Bridge (Steel) LS 1

36 Slope Protection (Riprap Stone) CY 72

37 BM-2B Base Course (3") TON 745

38 BM-2 Surface Course (2") TON 577

39 Milling (2") SY 872

40 Aggregate Base (AB-3) (6") SY 5,973

41 Tensar TX-160 Geogrid SY 5,973

42 Water (Aggregate Base) (Set Price) MGAL 1

43 Permanent Signage & Pavement Markings LS 1

44 Temporary Fertilizer (15-30-15) LB 465

45 Temporary Seed (Canada Wildrye) LB 62

46 Temporary Seed (Grain Oats) LB 139.5

47 Temporary Seed (Sterile Wheatgrass) LB 139.5

48 Sediment Removal (Set Price) CY 1

49 Temporary Berm (Set Price) LF 1

50 Temporary Ditch Check (Rock) CY 59

51 Biodegradable Log (9") LF 140

Schedule of Values

The following table is a list of bid items, estimated quantities, and the unit prices submitted by the bidder for the Cedar Creek Trail - Phase 3, Project Number 46-N0774-01.

ITEM UNIT PRICE

BID FORM

P.N. 46-N-0774-01

P.N. 46-N0774-01 BF-1 City of Olathe

52 Biodegradable Log (20") LF 70

53 Silt Fence LF 2,792

54 SWPPP Design LS 1

55 SWPPP Inspection EA 16

56 Water Pollution Control Manager EA 30

57 Mulch Tacking Slurry LB 2,790

58 Mulching (Temporary) TON 6.2

59 Water (Erosion Control) (Set Price) MGAL 1

60 Fertilizer (15-30-15) LB 310

61 Seed (Fescue) (Turf Type Tall Fescue Blend) LB 558

62 Traffic Control LS 1

Contractor

By

Title

Date

Contact Person

ASPHALT MATERIAL INDEX:

The undersigned successfully completed the bid process online at olatheks.bonfire.com and affirms that the schedule of values table above matches the unit prices, line item amounts, and bid total amount submitted electronically.

Telephone Number

The price included for Asphaltic Concrete Surface will be based on the computed monthly Asphalt Material Index for the month of the bid opening, if current month is not available at the time of bid opening the previous month prior to the bid opening month's index value will be used, as listed at the following web site, http://www.ksdot.org/burconsmain/ppreq/asphaltpriceindex.asp. The bid unit price for Asphaltic Concrete Surface shall be adjusted in subsequent months based on specification number 07-01009-

R05, Price Adjustment for Asphalt Materials, in the 2007 Edition of Kansas Department of Transportation Special Provisions for the

Standard Specification.

TOTAL:

P.N. 46-N0774-01 BF-2 City of Olathe

AGREEMENT

BETWEEN OWNER AND CONTRACTOR

FOR CONSTRUCTION CONTRACT (STIPULATED PRICE)

THIS AGREEMENT is dated as of the _____ day of _____________________, 20___ (“Effective Date”), by and between the City of Olathe, Kansas (“Owner”) and ___________________________________________________ (“Contractor”). Owner and Contractor, in consideration of the mutual covenants hereinafter set forth, agree as follows:

ARTICLE 1 – WORK

1.01 Contractor shall complete all Work as specified or indicated in the Contract Documents. The Work is generally described as follows:

0.9 Miles of 10-foot Recreational Trail (Generally Asphalt Construction)

Installation of a 125 LF, 14-foot wide, Pedestrian Bridge

ARTICLE 2 – THE PROJECT

2.01 The Project, of which the Work under the Contract Documents is a part, is generally described as follows: Cedar Creek Trail – Phase 3, Project Number 46-N-0774-01

ARTICLE 3 – ENGINEER

3.01 The Project has been designed by Alfred Benesch & Co.

3.02 The Owner has retained Alfred Benesch & Co. (“Engineer”) to act as Owner’s representative, assume all duties and responsibilities, and have the rights and authority assigned to Engineer in the Contract Documents in connection with the completion of the Work in accordance with the Contract Documents.

ARTICLE 4 – CONTRACT TIMES

4.01 Time of the Essence

A. All time limits for Milestones, if any, Substantial Completion, and completion and readiness for final payment as stated in the Contract Documents are of the essence of the Contract.

4.02 Contract Times: Days

A. The Work will be substantially completed within 200 days after the date when the Contract Times commence to run as provided in Paragraph 4.01 of the General Conditions, and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions within 230 days after the date when the Contract Times commence to run.

4.03 Liquidated Damages

A. Contractor and Owner recognize that time is of the essence as stated in Paragraph 4.01 above and that Owner will suffer financial and other losses if the Work is not completed and Milestones not achieved within the times specified in Paragraph 4.02 above, plus any extensions thereof allowed in accordance with the Contract. The parties also recognize the

EJCDC® C-520, Agreement Between Owner and Contractor for Construction Contract (Stipulated Price).

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page xiv delays, expense, and difficulties involved in proving in a legal or arbitration preceding the actual loss suffered by Owner if the Work is not completed on time. Accordingly, instead of requiring any such proof, Owner and Contractor agree that as liquidated damages for delay (but not as a penalty):

1. Substantial Completion: Contractor shall pay Owner $500 for each day that expires after the time (as duly adjusted pursuant to the Contract) specified in Paragraph 4.02.A above for Substantial Completion until the Work is substantially complete.

2. Completion of Remaining Work: After Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Time (as duly adjusted pursuant to the Contract) for completion and readiness for final payment, Contractor shall pay Owner $500 for each day that expires after such time until the Work is completed and ready for final payment.

3. Liquidated damages for failing to timely attain Substantial Completion and Final Completion are not additive and will not be imposed concurrently.

4. Milestones: Contractor shall pay Owner $500 for each day that expires after the time (as duly adjusted pursuant to the Contract) specified above for achievement of Milestone 1, until Milestone 1 is achieved.

4.04 Incentive Award

A. The amount of the incentive award for early completion of the Work compared to the Contract Times will be $____________________ per calendar day, up to a maximum of ___ calendar days, counted from the actual date of completion of all Work required by any partial day will be rounded to the nearest full day compared to the anticipated date of completion in the Contract Times. The maximum incentive award to be paid under the Contract under any circumstances will not exceed $_____________________.

ARTICLE 5 – CONTRACT PRICE

5.01 Owner shall pay Contractor for completion of the Work in accordance with the Contract Documents in current funds the amount that follows, subject to adjustment under the Contract:

[Here insert a lump sum, unit prices or both, if necessary attach exhibits and list them in Article 8.]

[CONTRACTOR's Bid may be attached as an exhibit to avoid lengthy retyping of unit price schedules, formulae for escalation of prices, information as to alternatives, etc.]

ARTICLE 6 – PAYMENT PROCEDURES

6.01 Submittal and Processing of Payments

A. Contractor shall submit Applications for Payment in accordance with Article 15 of the General Conditions. Applications for Payment will be processed by Engineer as provided in the General Conditions.

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page xv

6.02 Progress Payments; Retainage

A. Owner shall make progress payments on account of the Contract Price on the basis of Contractor’s Applications for Payment on or about the first day of each month during performance of the Work as provided in Paragraph 6.02.A.1 below, provided that such Applications for Payment have been submitted in a timely manner and otherwise meet the requirements of the Contract. All such payments will be measured by the Schedule of Values established as provided in the General Conditions (and in the case of Unit Price Work based on the number of units completed) or, in the event there is no Schedule of Values, as provided elsewhere in the Contract.

1. Prior to Substantial Completion, progress payments will be made in an amount equal to the percentage indicated below but, in each case, less the aggregate of payments previously made and less such amounts as Owner may withhold, including but not limited to liquidated damages, in accordance with the Contract.

a. 95% percent of Work completed (with the balance being retainage) and

b. 95% percent of cost of materials and equipment not incorporated in the Work (with the balance being retainage).

B. Upon Substantial Completion, Owner shall pay an amount sufficient to increase total payments to Contractor to 97% of the Work completed, less such amounts set off by Owner pursuant to Paragraph 15.01.E of the General Conditions, and less 200% of Engineer’s estimate of the value of Work to be completed or corrected as shown on the punch list of items to be completed or corrected prior to final payment.

6.03 Final Payment

A. Upon final completion and acceptance of the Work in accordance with Paragraph 15.06 of the General Conditions, Owner shall pay the remainder of the Contract Price as recommended by Engineer as provided in said Paragraph 15.06.