2-3014-1026 City of Joliet Western Avenue Greenway Bid Scope 1.pdf
PDF 284 KB Posted
- Attached to
- Western Avenue Greenway Improvements
- Solicitation number
- 3027-0227
- Issued by
- Will County, Illinois
About this file
This is a Bid Scope document issued by the City of Joliet, Illinois for Western Avenue Greenway Improvements, Contract Number 3027-1126. The project encompasses landscape removals and public-space improvements along the north side of the 300 block of Western Avenue, including the corner of Western Avenue and Hickory Street, spanning approximately 600 feet long by 60 feet wide. Work includes three main projects: removal of 10 deciduous shade trees (6 to 24 inch caliper) and 3 evergreen trees with stump grinding and lawn restoration; corner landscaping improvements including removal of three flagpoles, power washing of retaining walls, groundcover and lawn removal, shrub and groundcover planting, and installation of engineered fiber mulch; and central seating and holiday tree area work including landscape removals, installation of 4 commercial steel benches, concrete seating pad, topsoil and sodded lawn over 3,510 square feet, 20 screening shrubs, and landscape mulch. The bid due date is November 18, 2026 at 10:00 a.m. Contractors must visit and examine the site before bidding, coordinate with City staff for tree tagging before removals begin, and contact JULIE for utility markings before excavation. The bidder shall propose calendar days to substantial completion, with final completion required within 15 calendar days after substantial completion. Maximum excavation depth is 42 inches below existing grade unless written authorization is issued by the City.
Bidders must price the work as a complete project with component pricing as requested in the bid schedule. Quantities are subject to field verification, and the contractor shall notify the City of any discrepancies before disturbing the site. The project is funded through City and federal funding sources, as identified in the bid package. Federal and City contract requirements apply and may include Davis-Bacon and Related Acts wage rates, certified payroll requirements, Section 3 requirements under 24 CFR Part 75, Build America Buy America requirements, 2 CFR Part 200 contract provisions, Illinois Prevailing Wage Act compliance when applicable, and City insurance, indemnification, licensing, bonding, and vendor-registration requirements. The contractor must provide product submittals including planting plans with botanical names, shop drawings, warranties, and manufacturer installation instructions. The contractor is responsible for all labor, supervision, materials, equipment, traffic and pedestrian controls, permits, utility coordination, and site restoration. Contractor workmanship and non-plant materials are warranted for one year after final acceptance, and dead or unacceptable plant material must be replaced through one full growing season after acceptance.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1-3014-1026 LEGAL NOTICE Greenway.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
City of Joliet Western Avenue Greenway Improvements Bid Scope
CITY OF JOLIET
Western Avenue Greenway Improvements Bid Scope
Western Avenue and Hickory Street Joliet Illinois
Contract Number 3027-1126
Bid Due Date and Time 11/18/2026 10am
Project Funding City and federal funding requirements, as identified in the bid package
1 Project Purpose and Bid Intent
The City of Joliet seeks a qualified contractor to furnish all labor, supervision, materials, equipment, delivery, traffic and pedestrian controls, permits, utility coordination, protection, installation, testing, cleanup, and restoration required to complete landscape removals and public-space improvements along the north side of the 300 block of Western Avenue, including the corner of Western Avenue and Hickory Street and the central seating and holiday tree area. The work shall be complete, operational, and accepted by the City.
Bidders shall price the work as a complete project and provide the component pricing requested in the bid schedule.
Quantities are based on the project description and are subject to field verification. The contractor shall notify the City of discrepancies before disturbing the site.
2 Site and General Limits
• General location: north side of the 300 block of Western Avenue, between Pine Street and Broadway Street, Joliet, Illinois, including the Western Avenue and Hickory Street corner.
• Approximate project envelope: 600 feet long by 60 feet wide. Contractor shall verify actual limits in the field and confine operations to City-authorized areas.
• Maximum excavation depth: 42 inches below existing grade unless the City issues written authorization based on completed environmental and regulatory review.
• Maintain safe access to adjoining properties, sidewalks, streets, utilities, and existing improvements throughout construction.
3 Base Scope of Work
3.1 Project 1 Landscape Removals
Item Description Unit Qty
1 Remove deciduous shade trees, 6 to 24 inch caliper; grind each stump to 18 inches below grade;
remove debris; backfill with topsoil; and restore with lawn seed.
Each 10
2 Remove evergreen trees, approximately 20 feet high; grind each stump to 18 inches below grade;
remove debris; backfill with topsoil; and restore with lawn seed.
Each 3
Before removals begin, the contractor shall walk the site with City staff. The City and contractor shall jointly tag and confirm every tree approved for removal. No untagged tree may be removed.
3.2 Project 2 Corner Landscaping at Western Avenue and Hickory Street
Item Description Unit Qty
1 Remove three existing flagpoles and their foundations. Remove materials from the site and restore disturbed areas. Excavation shall not exceed the authorized depth.
Each 3
2 Power wash the segmental retaining-wall sections east and west of Hickory Street. Use methods that clean the units without damaging surfaces, joints, adjacent planting, or signage.
Each 2
Item Description Unit Qty
3 Remove existing groundcover southeast of the retaining wall and Joliet sign; dispose off site; prepare area for new planting.
SF 350
4 Remove lawn northwest of the retaining wall and Joliet sign; dispose off site; prepare subgrade for log steppers and engineered fiber mulch.
SF 675
5 Furnish and install shrubs and groundcover planting over the identified area. Contractor shall submit a planting plan, plant list, sizes, spacing, soil amendments, and maintenance recommendations for City approval before procurement.
SF 350
6 Excavate and install 12-inch-deep engineered fiber mulch around log steppers, including excavation, subgrade preparation, containment/edge transition, placement, and finish grading.
3.3 Project 3 Central Seating and Holiday Tree Area
Item Description Unit Qty
1 Complete landscape and groundcover removals required for the work. Tree removals are included in Project 1;
other removals necessary for this area shall be included in the applicable bid item and coordinated with the
City.
LS 1
2 .Purchase and install Model #CBPB-6SB-BK Commercial Steel Outdoor Bench with Straight Black River Finish
Belson.com or nationaloutdoorfurniture,com have example of model Each 4
3 Furnish and install 4” concrete seating area for benches to be installed on, facing towards tree area SF 750
4 Furnish and install 4 inches of topsoil and sodded lawn. Fine grade for positive drainage and flush, safe transitions.
SF 3,510
5 Furnish and install screening shrubs, minimum 4 feet high at installation, spaced 4 feet on center, subject to
City approval of species and layout.
Each 20
6 Furnish and install 3-inch-deep landscape mulch in approved planting areas. Confirm limits in field with City before installation.
4 Products Submittals and Substitutions
• Basis-of-design products identify the intended appearance, dimensions, durability, installation method, and compatibility. Proposed equals are permitted only if the bid documents allow them and the City approves them in writing before the applicable procurement or substitution deadline.
• Submit product data, color and finish samples, shop drawings, anchorage details, concrete pad and footing details, lifting and installation plans for heavy precast units, warranties, and manufacturer installation instructions.
• Submit the proposed planting plan with common and botanical names, quantities, container or caliper sizes, mature dimensions, spacing, and substitutions. Do not order plant material until approved.
• Coordinate final locations with the City. The central seating layout shall align with the center of the existing evergreen tree and existing pathways as shown in the project concept plan.
5 Contractor Responsibilities
• Visit and examine the site before bidding. Verify dimensions, quantities, access, staging, overhead constraints, surface conditions, and conflicts that can reasonably be observed.
• Before excavation, contact JULIE and coordinate utility markings. Protect marked and visible utilities. Use hand excavation where required and immediately report conflicts.
• Provide a project schedule, sequencing plan, site logistics plan, and emergency contact before mobilization.
• Provide temporary fencing, barricades, signs, pedestrian detours, and traffic control necessary to keep the public outside work zones. Maintain ADA-compliant routes where required by the City.
• Protect existing trees, the evergreen holiday tree, paths, retaining walls, signs, utilities, landscaping, and adjacent property designated to remain. Repair contractor-caused damage at no additional cost.
• Manage dust, mud, noise, runoff, and debris. Do not stockpile excavated soil or demolition debris outside City-approved areas.
• Remove waste lawfully. No burning or on-site burial is permitted. Provide disposal tickets or documentation when requested.
• Maintain daily housekeeping and leave the site broom clean. Restore all disturbed lawn, pavement, planting, and grades not included in permanent work.
• Obtain and pay for permits and inspections assigned to the contractor in the bid documents. Coordinate City inspections and provide at least two business days notice for required hold points.
• Use qualified personnel and manufacturer-authorized methods. Comply with applicable OSHA requirements and all federal, state, and local laws.
6 Installation and Quality Requirements
• Layout: Stake all work and receive City approval of locations before removals, excavation, concrete placement, planting, or anchoring. City review does not relieve the contractor from responsibility for measurements or compliance.
• Earthwork: Keep excavation within approved limits. Compact aggregate base in lifts to a stable, uniform surface.
Remove unsuitable material only after notifying the City. Do not conceal unexpected soil, debris, utilities, or environmental conditions.
• Concrete and anchorage: Coordinate footings, pads, inserts, templates, reinforcement, curing, finish, and tolerances with approved shop drawings and manufacturer instructions. Do not place concrete on frozen, saturated, or unstable subgrade.
• Furnishings: Use suitable lifting equipment and protect finished surfaces. Set units plumb, level, securely anchored, and aligned. Replace chipped, cracked, stained, or otherwise damaged units.
• Planting and lawn: Provide healthy, nursery-grade material. Prepare soil, water thoroughly, mulch uniformly, and maintain until acceptance. Sod shall be tightly fitted, rolled, watered, and free of gaps and settlement.
• Final condition: Provide positive drainage, smooth grade transitions, stable walking surfaces, and no exposed sharp edges, protruding anchors, trip hazards, or ponding.
7 Inspections Closeout and Acceptance
• Required hold points include completed layout, excavations before concrete or backfill, prepared aggregate bases, anchorage templates, planting layout, and substantial completion walkthrough.
• Provide manufacturer warranties, contractor warranty, approved shop drawings, product data, maintenance instructions, plant material schedule, disposal records requested by the City, and record information showing installed locations and footing depths.
• Correct punch-list items within the time directed by the City. Final payment is subject to completion, closeout, acceptance, and submission of required certified payroll and federal compliance records, if applicable.
• Contractor shall warrant workmanship and non-plant materials for one year after final acceptance unless a longer manufacturer warranty applies. Replace dead or unacceptable plant material through one full growing season after acceptance, subject to final contract terms.
8 Schedule and Coordination
Notice to Proceed: To be established by the City.
Substantial Completion: Bidder shall state proposed calendar days from Notice to Proceed.
Final Completion: Within 15 calendar days after substantial completion unless otherwise stated by the City.
The contractor shall coordinate shutdowns, deliveries, heavy lifts, street or sidewalk impacts, and work near community activities with the City. Work outside permitted hours requires prior written approval. Weather delays and concealed-condition impacts shall be documented promptly in writing.
9 Federal and City Contract Requirements
The successful bidder and every subcontractor shall comply with the City of Joliet procurement and contracting requirements and all applicable requirements tied to the project funding. The City will include the controlling clauses and forms in the final solicitation and contract. Requirements may include, as applicable:
• Davis-Bacon and Related Acts wage rates, certified payrolls, worker interviews, and labor-standards compliance;
• Section 3 requirements under 24 CFR Part 75 when the applicable HUD-assistance threshold is met;
• Build America Buy America requirements when the funding and infrastructure activity are covered, including required product documentation and approved waivers;
• 2 CFR Part 200 contract provisions, debarment and suspension verification, Equal Employment Opportunity requirements, and applicable civil rights requirements;
• Illinois Prevailing Wage Act requirements when applicable to the funding and contract;
• City insurance, indemnification, licensing, bonding, background, and vendor-registration requirements.
The bidder shall not assume that omission of a requirement from this technical scope waives a requirement contained in the solicitation, funding agreement, general conditions, special conditions, or applicable law.
10 Bid Pricing Schedule
Item Description Unit Qty Unit Price Extended
1-1 Deciduous tree removal and restoration Each 10 $________ $________
1-2 Evergreen tree removal and restoration Each 3 $________ $________
PROJECT 1 TOTAL $________
2-1 Power wash retaining-wall sections Each 2 $________ $________
2-2 Groundcover removal SF 350 $________ $________
2-3 Lawn removal SF 675 $________ $________
2-4 Shrubs and groundcover planting SF 200 $________ $________
2-5 12-inch engineered fiber mulch system SF 675 $________ $________
PROJECT 2 TOTAL $________
3-1 Incidental removals for central area LS 1 $________ $________
3-2 Topsoil and sod SF 3,510 $________ $________
3-3 Screening shrubs Each 20 $________ $________
3-4 Landscape mulch SF 675 $________ $________
PROJECT 3 TOTAL $________
TOTAL BASE BID $________
11 Bidder Acknowledgments
Company legal name: ________________________________________________________________________
Authorized representative: ________________________________________________________________________
Signature: ________________________________________________________________________
Date: ________________________________________________________________________
Proposed calendar days to substantial completion:
Addenda acknowledged: ________________________________________________________________________
12 City Completion Items Before Advertisement
The following administrative and design items should be completed or confirmed in the final solicitation package:
• Solicitation number, bid date, procurement method, award basis, engineer or City estimate, and whether projects may be awarded separately.
• Final plans or marked site exhibits showing work limits, furnishing layout, sign location, habitat-house locations, mulch limits, and restoration limits.
• Final sign artwork and performance specifications; confirmation whether any product is City-furnished.
• Approved planting performance requirements or plant palette and the scope of plant establishment/warranty.
• Concrete, reinforcement, aggregate, engineered fiber, paint, soil, sod, and mulch technical specifications.
• Funding source determination and the final federal and state labor/compliance clauses, current wage decision, Section 3 applicability, and Build America Buy America applicability.
• Contract time, liquidated damages if any, bid security, performance and payment bond requirements, insurance limits, permit assignments, and payment procedures.
• Environmental conditions and controls, including the 42-inch excavation limit and protocol for unexpected contaminated soil, archaeological material, utilities, or other concealed conditions.
| 1 Project Purpose and Bid Intent |
| 2 Site and General Limits |
| 3 Base Scope of Work |
| 3.1 Project 1 Landscape Removals |
| 3.2 Project 2 Corner Landscaping at Western Avenue and Hickory Street |
| 3.3 Project 3 Central Seating and Holiday Tree Area |
| 4 Products Submittals and Substitutions |
| 5 Contractor Responsibilities |
| 6 Installation and Quality Requirements |
| 7 Inspections Closeout and Acceptance |
| 8 Schedule and Coordination |
| 9 Federal and City Contract Requirements |
| 10 Bid Pricing Schedule |
| 11 Bidder Acknowledgments |
| 12 City Completion Items Before Advertisement |
File details come from the government source that posted it. Updated .