This is a Substitution Request Form issued by Walworth County in Wisconsin for RFB #26-024, the Judicial Center Additional Office Buildout project (GovTribe ID: 260014.00). The form is designed to document and track requests for material or product substitutions during the bidding and construction phases. Contractors and bidders may submit substitutions for pre-bid approval prior to the bid date, citing reasons such as product unavailability or cost savings to the owner. The form requires submission to Carolyn Holt, Senior Buyer, and must include the affected specification sections, drawings, manufacturer details, and proposed product information. Submitters are required to answer questions regarding whether the substitution affects dimensions shown on drawings, impacts work in other specification sections, or necessitates design modifications or drawing revisions.

The form establishes that the contractor or bidder assumes responsibility for coordination of any approved substitution and accepts all additional costs resulting from its incorporation into the project. The architect or project manager reviews all submissions and indicates acceptance, rejection, or requests for incomplete information. All checkboxes on the submitted form appear unchecked, indicating that the specific details of the substitution request were not completed at the time of submission. The project involves converting a white-box storage area into three offices for the Walworth County District Attorney, including selective demolition, installation of borrowed lites, modifications to lighting, HVAC and fire sprinkler systems, power and data extension, metal stud framing with gypsum board and insulation, carpet, paint and ceiling tile finishes, and a separate chain link enclosure for basement storage shelving.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Walworth County

SECTION 00 43 10

SUBSTITUTION REQUEST FORM

A/E Project No.:

Date Received:

Specification Section Number and Paragraph:

Drawings and details affected:

Proposed Substitution:

Manufacturer:

Product (model, pattern, etc.):

WHY IS SUBSTITUTION BEING SUBMITTED? (Select one of the following):

Pre-Bid Substitution (Prior Approval) Bid Date:

Specified product is not available. Explain Cost savings to Owner. Attach comparative cost analysis and proposed deduct.

Other. Explain.

EFFECTS OF PROPOSED SUBSTITUTION Answer the following questions and attach explanations.

Does substitution affect dimensions indicated on Drawings?

(NO) (YES, explain)

Does substitution affect Work of other Sections?

(NO) (YES, explain)

Does substitution require modifications to design, changes to Drawings, or revisions to Specifications to be incorporated into the Project?

(NO) (YES, explain)

CONTRACTOR’S/BIDDER’S REPRESENTATION

Undersigned accepts responsibility for coordination of proposed substitution and accepts all additional costs resulting from the incorporation of proposed substitution into the Project.

SUBMITTED BY: For Architect’s Use:

Accepted

Not Accepted

No Action Required Submission: Incomplete Too Late

Reviewed by/Date:

Comments:

Subcontractor’s signature and date:

Contractor’s signature and date:

To: Carolyn Holt, Senior Buyer Project: RFB # 26-024 Walworth County Judicial Center - Additional Office Buildout

260014.00

Date Received:
Specification Section Number and Paragraph:
Drawings and details affected:
Proposed Substitution:
Manufacturer:
Product model pattern etc:
SUBMITTED BY 1:
SUBMITTED BY 2:
Reviewed byDate:
Comments:
Check Box3: Off
Check Box4: Off
Check Box2: Off
Check Box5: Off
Check Box6: Off
Check Box7: Off
Check Box8: Off
Check Box9: Off
Check Box10: Off
Check Box11: Off

File details come from the government source that posted it. Updated .