2-26-003 Proposal Book.pdf

PDF 1 MB Posted

Attached to
CTH-H - George St. to E. Geneva Square
Solicitation number
26-003
Issued by
Winnebago County, Wisconsin

About this file

CTH-H George Street to E. Geneva Square Highway Work Proposal

This is a Highway Work Proposal issued by Walworth County, Wisconsin Department of Public Works for the reconditioning of County Trunk Highway H (CTH-H) from George Street to E. Geneva Square in Lake Geneva, Wisconsin. The project scope consists of asphaltic milling, HMA pavement placement, manhole and inlet adjustments, removal and replacement of curb and gutter, concrete sidewalk and ramps, erosion control, staged traffic control, pavement markings, restoration, and all incidental items necessary to complete the work. The project centerline length is approximately 0.75 miles. Sealed electronic bids were due on March 5, 2026, at 10:00 a.m. local time through the Bonfire procurement platform. Bid documents were issued on February 12, 2026, with final questions due by February 24, 2026, at 3:30 p.m. The project award was scheduled for March 16, 2026. Substantial completion of all work necessary to safely open all lanes to through traffic is required by August 21, 2026, with final completion by September 18, 2026. Liquidated damages of $1,570.00 per calendar day apply for failure to meet these completion dates. A virtual public bid opening was conducted on March 5, 2026, at 10:15 a.m. via Microsoft Teams.

The bid requires a 5 percent proposal guaranty payable to Walworth County. Walworth County is a tax-exempt municipality, and bidders must account for applicable sales and use taxes in their proposals. Neither Wisconsin prevailing wage rates nor Federal Davis-Bacon prevailing wage rates apply to this project. All bidders must be prequalified with the Wisconsin Department of Transportation for the class and amount of their bid and may not appear on the Department's List of Disapproved, Suspended, and Debarred Contractors. Comprehensive insurance requirements include Workers Compensation, Commercial General Liability with minimum limits of $1,000,000 per occurrence and $2,000,000 aggregate (increased to $2,000,000 per occurrence for excavation work), Automobile Liability, and Contractor's Pollution Liability with minimum $1,000,000 per occurrence and aggregate. Walworth County must be named as additional insured on applicable policies. The project is funded entirely by Walworth County. The Schedule of Items lists 84 line items with quantities ranging from single units to thousands of units, including base aggregates, HMA pavement, concrete work, traffic control, erosion control, and specialized items such as Rectangular Rapid Flashing Beacon systems, sanitary manhole adjustments, and water valve box adjustments.

View the file

Other files

File Type Posted
3-26-003 Plan Set.pdf PDF
1-26-003 List of Subcontractors.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HIGHWAY WORK PROPOSAL

Walworth County, Wisconsin

COUNTY PROJECT NO. PROJECT DESCRIPTION HIGHWAY

Walworth 26-003 CTH-H; CTH-H George St. to E. Geneva Square

Proposal Guaranty Required:

5% of Bid Amount, Payable to Walworth County

Bid Submittal:

Date: March 5, 2026

Time (Local Time): 10:00 am

Contract Completion Time:

Substantial Completion: August 21, 2026

Final Completion: September 18, 2026

This Page Intentionally Left Blank

PROJECT ID 26-003

CTH-H

GEORGE ST. TO E. GENEVA SQUARE

TABLE OF CONTENTS

Title No. of Pages

Proposal Cover 1

Table of Contents 1

Advertisement for Bids 2

Bid Requirements and Conditions 2

Bid Opening Teleconference 1

Insurance Requirements 2

Bid Preparation 1

List of Subcontractors 1

Special Provisions 19

Schedule of Items (Informational Only) 2

ADVERTISEMENT FOR BIDS

PROJECT ID 26-003

GEORGE ST. TO E. GENEVA SQUARE

NOTICE: Sealed (electronic) bids for the Reconditioning of CTH-H from George St. to E. Geneva Square will be received by the Walworth County Purchasing Division, Department of Public Works, W4097

County Road-NN, Elkhorn, Wisconsin 53121, until 10:00 A.M. local time on Thursday, March 5, 2026, at which time all bids will be publicly opened virtually.

SCOPE: In general, the work under this project consists of asphaltic milling, HMA pavement, manhole and inlet adjustments, removal and replacement of curb and gutter, sidewalk and ramps, erosion control, staged traffic control, pavement markings, restoration and all incidental items necessary to complete the work as shown on the plans and included in the proposal and contract. The centerline length of the project is approximately 0.75-miles.

This project is funded by Walworth County.

ELECTRONIC BIDDING: Walworth County utilizes an internet-based procurement software called

‘Bonfire’ as the interface to exchange all official information between the County and Bidders.

Obtaining Bid Documents, Project Inquiries, and Bid Submittal will be accomplished through the Bonfire software platform.

Bidders may register for a Bonfire account at no charge through Walworth County’s Bonfire Portal at:

https://walworthcountywi.bonfirehub.com/

It is the bidder’s responsibility to check the project website for future announcements, addendums, etc.

prior to the bid deadline. Bids that do not acknowledge addendums may be rejected.

All questions must be received by the deadline(s) indicated. No information provided verbally, or by any other personnel, will be considered binding.

PROJECT COMPLETION: All work under this Contract shall be substantially completed by August 21, 2026, with final completion no later than September 18, 2026. Liquidated damages for failure to complete the work in accordance with the date(s) set forth above shall be One Thousand Five Hundred Seventy dollars ($1,570.00) for each calendar day in excess thereof.

BID SECURITY: Bids must be accompanied by a Bid Bond the amount of five (5) percent of the bid price, payable to Walworth County, Wisconsin, as a guarantee that if the Bid is accepted, the Bidder will execute and file the proper contract documents within fifteen (15) days after notification of award of the contract. In case the successful bidder shall fail to execute such contract documents, the bid bond shall be forfeited to Walworth County as liquidated damages.

BIDDING SCHEDULE:

Bid Documents Issued: February 12, 2026

Pre-Bid Meeting: N/A

Final Questions Due: February 24, 2026 ( 3:30 p.m.)

Bids Due: March 5, 2026 (10:00 a.m.)

Project Award: March 16, 2026

WAGE RATES: Neither State of Wisconsin prevailing wage rates nor Federal (Davis-Bacon) prevailing wage rates are applicable to this project.

QUALIFICATIONS: Bidders shall be experienced in this type of work and shall be prequalified with the

Wisconsin Department of Transportation for work in the class and amount of their bid.

BID WITHDRAWAL: No bid shall be withdrawn for a period of thirty (30) days after the scheduled opening of bids. Bids may be withdrawn only in total and only by a written request to Walworth County

Purchasing, Department of Public Works, prior to the time and date of the scheduled bid deadline.

BID ACCEPTANCE – REJECTION: Walworth County reserves the right to accept or reject any or all bids, in whole or in part, received in response to this advertisement, to waive any irregularities in bidding, or to accept any bid they deem most advantageous to the County.

Published by the authority of: Walworth County

BID REQUIREMENTS AND CONDITIONS

The bidder, submitting this bid, agrees and declares as a condition thereof, to be bound by the following conditions and requirements.

All prospective bidders shall be on the Wisconsin Department of Transportation list of approved

Contractors. Any Contractor that appears on the Wisconsin Department of Transportation’s List of

Disapproved, Suspended, and Debarred Contractors will be disallowed.

The bidder declares that he has carefully examined the site of, and the bid, plans, specifications and contract forms for the work contemplated and it is assumed that the bidder has investigated and is satisfied as to the conditions to be encountered, as to the character, quality, and quantities of work to be performed and materials to be furnished, and as to the requirements of the specifications, special provisions, and contract. It is mutually agreed that submission of a bid shall be considered conclusive evidence that the bidder has made such examination.

The bidder submits herewith a proposal guarantee in proper form and amount payable to the party as designated in the advertisement inviting bids, to be retained by and become the property of the owner of the work in the event the undersigned shall fail to execute the contract and return the same to the County within fifteen (15) days after having been notified in writing to do so; otherwise to be returned.

The form of agreement or contract resulting from the acceptance of the bid shall be on forms either supplied by Walworth County or approved by Walworth County.

The bidder declares that he understands that the estimate of quantities in the schedule of items is approximate only and that the actual quantities may be greater or less in accordance with the specifications.

The bidder agrees to perform the said work, for and in consideration of the payment in the amount becoming due on account of work being performed, according to the unit prices in the schedule of items, and to accept such amounts in full payment of said work.

Retainage on project estimates will be applied in accordance with the Section 66.0901(9)(b), Statutes of

Wisconsin.

Walworth County is a tax-exempt municipality under WI Stats. 77.54(9a). The bidder shall investigate the statutory requirements for payment of sales and use taxes and, if required, shall include taxes in the bid.

Bidder shall comply with the provisions set forth in the Wisconsin Administrative Code and Statutes in order to obtain a state sales tax exemption on the purchase of certain items and shall forward this information to his suppliers in order that the sale of such material and equipment be properly recorded as a tax-exempt sale.

The bidder declares that all of the said work will be performed at his own cost and expense, that he will furnish all necessary materials, labor, tools, machinery, apparatus, and other means of construction in a manner provided on the plans, specifications, special provisions and contract of which this bid will become a part. The bidder further agrees that the plans, specifications and special provisions are made a part hereof, as fully and completely as if attached hereto.

The bidder, if awarded the contract, shall pay all claims as required by Section 779.14of the Wisconsin

Statutes and shall be subject to and discharge all liabilities for injuries pursuant to Chapter 102 of the

Wisconsin Statutes, and all acts amendatory thereto. He shall further be responsible for any damage to property or injury to persons occurring through his own negligence or that of his employees or agents, incident to performance of work under this contract.

Upon completion of the work and receipt of all required documentation and material reports, Walworth

County (or designee) may submit to the contractor a tentative-final estimate of the quantities of work performed by the contractor. Within 30 calendar days of receiving the tentative-final estimate, the contractor shall submit a written statement of agreement with the final quantities. In the event of a discrepancy, the contractor shall submit item-by-item documentation of the quantities to be reviewed. If the contractor does not submit a written statement within those 30-days, Walworth County will process the estimate as a final payment with no further negotiation.

Prior to release of final payment and retainage, the contractor shall submit lien waivers for the prime contractor and subcontractors on forms supplied by, or approved by Walworth County.

The bidder, if awarded the contract, shall permit authorized representatives of the Federal, State, and

County government to inspect and audit all data and records of the contractor as they relate to this contract. Said right shall extend to any subsidiary, subcontractor, or parent corporation which relate to the construction on this project.

It is expressly agreed and understood that the bidder is in all respects an independent contractor, and the bidder is in no respect an agent, servant, or employee of Walworth County.

Walworth County reserves the right to cancel any agreement that may result from this request for bids, with no penalty, if the Walworth County Board of Supervisors fails to appropriate funds for this contract.

BID OPENING TELECONFERENCE

1. PUBLIC BID OPENING

No in-person bid openings for Public Works projects will be conducted in Walworth County.

Vendors may participate in the public bid opening for this project as described in this Section.

The bids opened and read are considered preliminary and subject to review and verification of applicable bid requirements. Contract(s) will be awarded to the lowest responsive, responsible bidder unless stated otherwise in the request for bids.

2. INSTRUCTIONS FOR PROJECT 26-003

The County will host this bid opening on Thursday, March 5, 2026, at 10:15 a.m. via Microsoft Teams.

Interested participants may attend electronically via the live stream video conference or may participate by using the audio-only option provided herein.

Microsoft Teams meeting

Join: https://teams.microsoft.com/meet/23930573954311?p=up6DduVPqPHjSTQ4PF

Meeting ID: 239 305 739 543 11

Passcode: iW6LJ3bB

Dial in by phone

+1 414-219-0219,,897194098# United States, Milwaukee

Phone conference ID: 897 194 098# https://teams.microsoft.com/meet/23930573954311?p=up6DduVPqPHjSTQ4PF tel:+14142190219,,897194098

INSURANCE REQUIREMENTS

1.01 Contractor shall furnish County with Certificate of Insurance indicating proof of the following insurance from companies licensed in the State of Wisconsin:

A. Workers Compensation and Employers' Liability - The Contractor shall procure and maintain during the life of this contract Workers’ Compensation insurance with a minimum limit as required by Wisconsin Statutes. The Contractor shall also carry Employers Liability limits of at least $100,000 Each Accident, $100,000 Disease – Each Employee, and $500,000 Disease – Policy Limit. Contractor shall require all subcontractors not protected under its insurance to take out and maintain such insurance throughout the project term.

B. Commercial General Liability - with a minimum limit of $1,000,000 per occurrence and

$2,000,000 aggregate combined single limit for bodily injury and property damage liability. The County reserves the right to require higher or lower limits where warranted.

1) If excavating, underground or collapse is involved, the limits of liability stated above shall be increased to $2,000,000 per occurrence.

2) If Asbestos and/or hazardous materials are involved, the limits of liability stated above shall be changed to $5,000,000 per occurrence.

3) This insurance shall include, but is not limited to, the following coverage:

a) Premises – Operations

b) Products and Completed Operations

c) Personal and Advertising Injury

d) Contractual Liability

e) Underground, Explosion, and Collapse

f) Contractor’s indemnity obligations under this contract

4) This insurance must not include the following:

a) Any exclusion for water intrusion or water damage

b) Any exclusion of coverage relating to earth subsidence or movement

c) Any exclusion for the insured’s vicarious liability, strict liability, or statutory liability (other than worker’s compensation)

d) Any limitation or exclusion based on the nature of Contractor’s work

e) Any limitation or exclusion for damages arising from the work performed by a subcontractor

f) Any limitation or exclusion for damages related to roofing, if the work involves roofing

g) Any provisions resulting in the erosion of insurance limits by defense costs other than those already incorporated in to ISO form CG 00 01

C. Automobile Liability – with a minimum limit of $1,000,000 per occurrence and $2,000,000 aggregate combined single limit for bodily injury and property damage liability. This insurance shall include coverage for all of the following:

1) Owned Automobiles

2) Hired Automobiles

3) Non-Owned Automobiles

D. Professional Liability – Not Required

E. Contractor’s Pollution – with minimum requirements of $1,000,000 per occurrence and

$1,000,000 aggregate. Coverage must cover third-party injury and property damage, including cleanup costs, as a result of pollution conditions arising from Contractor’s operations and completed operations. Coverage must be carried for a minimum of two years following completion of the project.

F. Umbrella or Excess Coverage – Umbrella or Excess Coverage may be used in combination with the required primary coverage in (A.) through (E.) to meet the minimum insurance limits that are specified in this section, provided such insurance result in the same or greater coverage as the coverages required. In no event shall any Umbrella or Excess insurance provide narrower coverage than the primary policy. The Excess policy shall not require exhaustion of the underlying limits only through the actual payment by the underlying insurers.

G. Property Insurance – Contractor is responsible for obtaining or maintaining any other insurance deemed necessary, such as property or inland marine, to cover any property or equipment that is owned or rented by the Contractor and used within the scope of this project.

1.02 If any insurance specified above is a claims-made policy, the retroactive date must pre-date the commencement of furnishing any service under this contract, including design. An Extended Reporting Period, or “tail” coverage, must be provided for at least 2 years following completion of the work.

1.03 Walworth County, shall be named as additional insureds under the Contractor’s Commercial General

Liability, Automobile Liability, Employer’s Liability, Umbrella or Excess, and Pollution Liability insurance policies. Walworth County shall be listed as, “Walworth County, its employees, elected officials, representatives, members of its boards and/or commissions and engineering consultants.”

1.04 Unless prohibited by law, Walworth County shall be provided a waiver of subrogation by endorsement to the Commercial General Liability, Automobile Liability, Workers’ Compensation, Employer’s Liability, Contractor’s Pollution, and Umbrella or Excess Insurance.

1.05 Contractor’s insurance shall provide a thirty (30) day notice to the County prior to cancellation or material policy change. The notice shall be given to Walworth County Purchasing, Department of Public Works, W4097 County Road NN, Elkhorn, Wisconsin 53121. NOTE: Standard Cancellation Clause on a Certificate of Insurance is not acceptable. Upon receipt of notice from insurer, Owner shall have the right to stop the Work until the lapse in coverage has been cured by the procurement of replacement coverage by the Contractor. The furnishing of notice shall not relieve the Contractor of any contractual obligation to provide required coverage.

1.06 The Contractor’s certificate shall list the Certificate Holder and address as follows: Walworth County, Attn: Walworth County Purchasing, Department of Public Works, W4097 County Road NN, Elkhorn, Wisconsin 53121.

1.07 Contractor shall require all of its contractors and subcontractors performing work related to this contract to carry sufficient minimum insurance to cover liabilities arising from or out of the performance of this contract. Contractor shall require subcontractor to furnish Certificates of Insurance to Walworth County upon request.

BID PREPARATION

Walworth County utilizes an internet-based procurement software called ‘Bonfire’ as the interface to exchange all official information between the County and Bidders, including the preparation and submission of bids.

Bidders may register for a Bonfire account at no charge through Walworth County’s Bonfire

Portal at: https://walworthcountywi.bonfirehub.com/

Bidder shall assume full responsibility for timely delivery of Electronic Bids.

Within the Bonfire software:

Complete the electronic / online unit price Bid Form.

Upload a Bid Security to the electronic submittal.

Upload a List of Subcontractors to the electronic submittal.

CERTIFICATION

Submitting a bid (electronically on the internet) to the Walworth County Department of Public

Works, shall certify that the bidder has examined and carefully prepared his bid from the plans and specifications (highway work proposal), and all addenda, and has checked the same in detail before submitting said proposal or bid.

LIST OF SUBCONTRACTORS

Section 66.0901(7) of the Wisconsin Statutes provides that a bidder, as a part of his bid, shall submit a list of the subcontractors he proposes to contract with and the class of work to be performed by each, provided that to qualify for such listing, each subcontractor must first submit his bid in writing to the general contractor at least 48 hours prior to the time of bid closing. It further provides that a bid of a bidder shall not be invalid if any subcontractor, and the class of work to be performed by such subcontractor, has been omitted from a bid.

No subcontract, whether listed or later proposed, may be entered into without the written consent of the

Walworth County.

* * TO BE COMPLETED ELECTRONICALLY IN BONFIRE * *

26-003 1 of 19

Special Provisions

Table of Contents

Article Description Page #

1. General

2. Scope of Work

3. General Information, Definitions, and Terms

4. Control of Work

5. Control of Materials

6. Legal Regulations and Responsibility to the Public

7. Public Convenience and Safety

8. Holiday and Special Event Work Restrictions

9. Prosecution and Progress

10. Measurement and Payment

11. Notice to Contractor – Modification or Elimination of Bid Items

12. Traffic

13. Work by Others

14. Utilities

16. Breaker Run

17. HMA Pavement

18. Reconstructing Inlets and Manholes

19. Supplemental Traffic Control, Item SPV.0055.01

20. Rectangular Rapid Flashing Beacon (RRFB) System, Item SPV.0060.01

21. Adjusting Sanitary Manholes, Item SPV.0060.02

22. Adjusting Water Valve Boxes, Item SPV.0060.03

23. Loop Detector Removal and Replacement, Item SPV.0060.04

24. Inlet Covers Type BH, Item SPV.0060.05

25. Curb & Gutter Removal and Replacement, Item SPV.0090.01

26. Grade and Shape Ditches, Item SPV.0090.02

27. Traffic Control (Phase 1), Item SPV.0105.01

28. Traffic Control (Phase 2), Item SPV.0105.02

29. Traffic Control (Phase 3), Item SPV.0105.03

30. Proof Rolling, Item SPV.0170.01

26-003 2 of 19

STSP’S Revised January 1, 2026

SPECIAL PROVISIONS

1. General.

Perform the work under this construction contract for Project 26-003 CTH H (George Street to E. Geneva Square), Walworth County, Wisconsin as the plans show and execute the work as specified in the State of Wisconsin, Department of Transportation, Standard Specifications for Highway and Structure Construction, 2025 Edition, as published by the department, and these special provisions.

These special provisions and other documents in the Project Manual take precedence over any conflicting provisions in Part 1 of the State of Wisconsin, Department of Transportation, Standard Specifications for Highway and Structure Construction, 2025 Edition.

2. Scope of Work.

The work under this contract shall consist of asphaltic milling, HMA pavement, concrete curb and gutter, spot curb & gutter repairs, concrete sidewalk, base aggregate, structure adjustments, traffic control, pavement markings, signs, restoration, and all incidental items necessary to complete the work as shown on the plans and included in the proposal and contract.

104-005 (20090901)

3. General Information, Definitions, and Terms.

Amend section 101.3 of the Standard Specifications as follows:

Department The Walworth County Department of Public Works.

Engineer The Walworth County Director of Public Works/Highway Commissioner or the County’s authorized representative limited by the particular duties assigned to the representative.

4. Control of Work.

Add the following to the beginning of paragraph (1) of Section 105.8:

The engineer or project engineer may designate an inspector or inspectors to act as the engineer’s field representative with limited authority during the progress of construction to observe daily operations.

Add the following to the list of authorized activities in paragraph (2) of Section 105.8:

4. Take field measurements and perform calculations of completed work as required by contract for progress payment as estimated by the engineer. Inspector may verify such measurements and calculations with the contractor.

5. Assist the contractor with obtaining interpretation and clarification of the contract documents from the engineer.

6. Consider and evaluate contractor suggestions for modifications to plans or specs and report such suggestions, along with inspector’s recommendation, if any, to the engineer for determination.

7. Observe, record, and report to the engineer appropriate details of tests performed by the contractor.

8. Prepare, keep, and maintain a daily report, diary, or log book for the days inspector is present on site to record contractor’s operations, weather, discussions, decisions, and general observation and provide copies to the engineer.

Add the following to the list of unauthorized activities in paragraph (3) of Section 105.8:

4. Authorize any deviation from or modification to the contract documents, extra work, or material substitutions.

26-003 3 of 19

5. Exceed the limitations of the engineer’s authority in 105.1, 105.7, and these special provisions.

6. Participate in any specialized tests or inspections the inspector is not otherwise qualified to perform.

7. Accept or approve shop drawings or material samples.

Add the following to Section 105.1 of the Standard Specifications:

The Department and engineer are not responsible for the contractor’s means, methods, techniques, sequences, or procedures; or for the contractor’s safety, health, and sanitation programs.

5. Control of Materials.

Add the following paragraph to Section 106.3.3.2 of the Standard Specifications:

Provide the engineer material documentation no later than three working days prior to delivery to the project. Failure to provide the engineer with required materials documentation may lead to reduced or no payment at the discretion of the department. Provide the results of any field or laboratory testing completed during construction within three working days of performance. Notify the engineer as soon as possible the results of any failed tests.

6. Legal Regulations and Responsibility to the Public.

Add the following paragraphs to Section 107.11.1 of the Standard Specifications:

The contractor shall protect all mailboxes not in direct conflict with the construction operations. The contractor shall remove all mailboxes that interfere with construction operations and erect them at temporary locations. As soon as construction operations permit, the contractor shall set the mailboxes at their permanent locations in accordance with US Postal Service requirements as directed by the engineer. The contractor shall replace, at no additional cost to the department, any mailbox or post which has been damaged by contractor’s operations.

Any elaborate mailbox structures are not expected to be replaced in kind. The contractor shall carefully remove and salvage parts of such structures and given to the owner. The contractor shall furnish and erect standard mailbox posts when replacing such mailboxes. Owners may replace their structure at the owner’s expense.

Handling of mailboxes within the project limits shall be incidental to the contract.

Revise the first sentence of Section 107.12 of the Standard Specifications to read as follows:

The contractor and their insurer shall defend, indemnify, and save harmless the engineer and governmental entities that are involved in the project, or in which all or a part of the project site is located, including officers, agents, and employees of any of the foregoing from suits, actions, or claims brought because of injuries or damages sustained by any person or property arising from one or more of the following:

7. Public Convenience and Safety.

Revise standard spec 107.8(6) as follows:

Check for and comply with local ordinances governing the hours of operation of construction equipment.

Do not operate motorized construction equipment from 9:00 PM until the following 7:00 AM on weekdays and 9:00 PM until the following 8:00 AM on weekends, unless prior written approval is obtained from the engineer.

stp-107-001 (20060512)

8. Holiday and Special Event Work Restrictions.

Do not perform work on, nor haul materials of any kind along or across any portion of the highway carrying CTH H traffic, and entirely clear the traveled way and shoulders of such portions of the highway of equipment, barricades, signs, lights, and any other material that might impede the free flow of traffic during the following holiday and special event periods:

- From noon Friday, May 22, to 6:00 AM Tuesday, May 26 (Memorial Day);

26-003 4 of 19

- From noon Friday, July 3, to 6:00 AM Monday, July 6 (Independence Day);

- From noon Friday, September 4, to 6:00 AM Tuesday, September 8 (Labor Day).

stp-107-005 (20210113)

9. Prosecution and Progress.

Begin work within 10 calendar days after the engineer issues a written notice to do so.

Provide the start date to the engineer in writing within a month after executing the contract but at least 14 calendar days before the preconstruction conference. Upon approval, the engineer will issue the notice to proceed within ten calendar days before the approved start date.

To revise the start date, submit a written request to the engineer at least two weeks before the intended start date. The engineer will approve or deny that request based on the conditions cited in the request and its effect on the department’s scheduled resources.

The contractor is expected to meet project schedules, including start and both interim and final completion dates. Failure to complete the work on time will subject the contractor to calendar day liquidated damages as provided in subsection 108.11 of the Standard Specifications.

Construction Start

The contractor shall not begin work or erect conflicting traffic control between Williams Street and E.

Sheridan Springs Road until the Lake Geneva Utility Commission has completed their utility improvement work. See Work by Others and Utilities special provisions for additional information.

Interim Completion – Road open to traffic

Substantially complete all work, including final HMA pavement layer and permanent pavement markings, necessary to safely open all lanes to through traffic by August 21, 2026. If the contractor fails to complete this work by this interim completion date, the department will assess the contractor liquidated damages in accordance with standard spec 108.11 for each calendar day the work remains incomplete after that date.

Final Completion

All remaining contract work, including completing punch-list items, except any County or City-completed work, shall be complete and ready for department acceptance by September 18, 2026. If contract time expires prior to completing all work specified in the contract, additional liquidated damages will be affixed according to standard spec 108.11.

The contractor shall have a superintendent or designated representative on the job site during all controlling work operations, including periods limited to subcontractor work operations, to serve as a primary contact person and to coordinate all work operations. Notify the engineer immediately upon discovery of differing conditions or plan discrepancies for review and direction.

The contractor shall schedule and conduct bi-weekly progress meetings (or at a frequency agreed to) at a location agreed to at the pre-construction conference. Subcontractors that are actively completing work or are scheduled to complete work in the two weeks following the progress meeting shall attend the bi-weekly progress meeting.

10. Measurement and Payment.

Amend section 109.1.1 of the Standard Specifications to add the following subsections:

109.1.1.1 Bid Items Designated as Pay Plan Quantity

109.1.1.1.1 General

If the schedule of items designates a bid item with a **P** in the item description, the department will not measure that bid item. The department will use the plan quantity, the approximate quantity the schedule of items shows, for payment unless one or both of the following occurs:

• Scope changes resulting in a quantity for the designated bid item that varies by more than 5 percent from plan quantity.

• Errors and omissions that affect the plan quantity by more than 5 percent.

109.1.1.1.2 Scope Changes

26-003 5 of 19

For engineer-directed quantity increases, the engineer will measure the additional work and pay for the addition quantity under the designated pay item. For engineer-directed quantity decreases, the engineer will measure the work eliminated and make an equitable reduction to the plan quantity under the designated bid item.

109.1.1.1.3 Errors and Omissions

The engineer will adjust the plan quantity of the designated pay item to an agreed quantity for an error or omission with no change in contract unit price.

109.1.1.2 Bid Items Designated as **R**

If the schedule of items designates a bid item with **R** in the item description due to budget restraints this item may not be used or may be used in part or in its entirety and the County will not make adjustments to the contract unit price as included in the section 104.2.2.4, section 104.2.2.5, and section 109.5.

Add the following paragraph to Section 109.6.3.2.1 of the Standard Specifications:

Provide copies of weight bills and delivery tickets to the engineer as the work progresses. Payment quantities will be determined from the approved weight bills and delivery tickets. Verify total daily tonnage with the engineer on a daily basis. Only quantities agreed upon as the work progresses will be paid.

Weight bills and delivery tickets must be provided to the engineer within 7 days of placement to be considered for payment.

Revise the second paragraph of section 109.6.3.3 of the Standard Specifications to read as follows:

In addition to the above retainage, the department will retain 5% of the value of the work completed, and 5% of the value of materials and equipment delivered and suitably stored, until 50% completion. At 50% completion, no additional amounts will be retained unless the engineer certifies that the work is not proceeding satisfactorily, but amounts previously retained will not be paid to the contractor until final acceptance of the work by the department. When the contractor substantially completes the work under the contract or upon completion and acceptance of the work, and pending final payment, the engineer may choose to reduce the amount retained.

11. Notice to Contractor – Modification or Elimination of Bid Items.

The department will not allow for a Cost Reduction Incentive as described in subsection 104.10 of the standard specifications for any elimination and/or modification of any contract bid items. Further, the department will not apply standard spec 109.5 for the total elimination or partial elimination, whether by the department or the contractor, of contract bid items.

12. Traffic.

Provide advance notification to the Wisconsin Lane Closure System (LCS) for all lane closures. Provide 7 calendar days advance notice to LCS when a width restriction is required and 3 calendar days advance notice in all other instances, including changes in staging or lane closures.

Discuss LCS completion dates and provide changes in the schedule to the engineer at project meetings in order to manage closures nearing their completion date.

Provide emergency access to properties within the construction limits at all times. Maintain access for US Mail delivery, garbage collection, and school busses.

Maintain access to all businesses and private properties at all times except when completing work adjacent thereto. Restore access immediately after operations are complete. Stage construction of any commercial entrance that requires continuous access as incidental to the contract. Coordinate with local businesses.

Submit to the engineer for approval, a detailed traffic control plan if different than the traffic control plan provided in the plans. Submit this plan to the engineer 14 working days prior to anticipated use.

Additional intermediate construction staging or staging gaps, not shown on the plans, may be necessary to maintain continuous access to all properties. If the contractor coordinates the closure of any access to

26-003 6 of 19 a business or private property with the owner(s), provide written documentation or coordination with the owner(s) to the engineer 48 hours prior to any closure.

Do not perform construction operations until all traffic control devices for such work are in proper location.

All open lanes shall be a minimum 10 feet wide, from face of drum to face of drum or face of curb.

Provide 1-foot buffers from drums/curbs and other vertical elements as space allows.

The project will generally be constructed in three stages.

Stage 1:

Traffic

• Close inside lanes from Williams Street to E. Geneva Square. Shift traffic to outside lanes/shoulder lane.

• Close cross-access at minor intersections and driveways. Maintain cross access at E. Sheridan Springs Road.

Construction

• Mill existing asphaltic pavement on inside lanes within work zone.

• Proof roll exposed aggregate base and complete necessary EBS and base patch remaining asphaltic pavement as determined by the engineer.

• Adjust drainage and utility structures within the work zone

• Install lower layer HMA binder course within work zone.

• Apply temporary paint double yellow centerline for Stage 2.

Stage 2:

Traffic

• Shift traffic to inside lanes and close outside lanes/shoulder lane from Williams Street to E.Geneva Square.

• Provide full access to intersections and driveways across the closed lanes, temporarily closing access during the workday only to complete adjacent work.

• Close all sidewalks into the work zone. Provide a temporary pedestrian detour if necessary.

• Utilize flagging operations to install traffic signal detector loops.

Construction

• Complete sawcuts, removals, excavation, aggregate, and concrete work within the work zone.

• Complete storm sewer work. Place topsoil and begin lawn restoration.

• Mill existing asphaltic pavement in outside lanes within work zone.

• Proof roll exposed aggregate base and complete necessary EBS and base patch remaining asphaltic pavement as determined by the engineer.

• Adjust drainage and utility structures within the work zone.

• Pave lower layer HMA binder course within work zone.

• Install replacement detector loops for the E. Sheridan Springs Rd traffic signal, temporarily closing open inside lane daytime only under flagging operation. Do not close both directions at the same time.

Stage 3:

Traffic

• Perform work from the Beginning of the project to E. Sheridan Springs Road under flagging operations.

• Shift traffic to the east side of the road at George Street and Gardner Street to construct bump-out at George Street; utilize flagging operations to close an open lane during daytime hours to complete adjacent work (Substages 3B and 3C).

26-003 7 of 19

• Place cones or drums along any open lanes next to any drop-offs exceeding 2-inches.

• Re-open sidewalks after completion of all upper layer surface paving.

Construction

• Complete remaining sawcuts, removals, excavation, aggregate, and concrete work. Place topsoil and begin lawn restoration.

• Mill the existing asphaltic pavement from the begin resurfacing limits to the Stage 1 and 2 limits.

• Adjust drainage and utility structures within the work zone.

• Place lower layer HMA binder course for remaining resurfacing area.

• Construct butt joints and place upper layer HMA surface course. Complete asphaltic driveway surface.

• Place permanent pavement markings

• Reopen road to traffic by substantial completion date.

Post Staging:

Traffic

• Perform work under flagging operations.

Construction

• Complete permanent sign installations, including RRFBs.

• Complete remaining lawn restoration.

• Complete punch list work.

• Complete finish roadway work and remove all remaining traffic control.

Coordinate traffic restrictions and full intersection closures (daytime only) with the Walworth County dispatch so emergency vehicle routes are known and access is maintained at all times.

Pedestrian Access

Maintain pedestrian access to all businesses and residences to the maximum extent feasible within the project limits by means of existing sidewalk or temporary pedestrian accommodation items. Preserve the existing sidewalk as long as practicable to maintain pedestrian access. Close sidewalks entering the work zone at locations where an alternative pedestrian route is available. Provide temporary pedestrian access as directed by the engineer if required by the City of Lake Geneva meeting current Americans with Disabilities Act (ADA) Accessibility Guidelines (ADAAG) and Public Right-of-Way Accessibility Guidelines (PROWAG) to the maximum extent feasible.

Butt joints exposed to traffic at the ends of the project, intersecting side roads, and driveways shall be constructed with a temporary wedge of asphalt millings or base aggregate. Temporary wedges will be required at these locations upon completion of the milling and surface removal operations and construction of butt joints until placement of the lower HMA layer. Temporary Wedges are incidental to construction.

13. Work by Others.

Lake Geneva Utility Commission

The Lake Geneva Utility Commission will be performing Sanitary Sewer and Watermain construction between Williams Street and East Sheridan Springs Road in the Winter/Spring of 2026. It is anticipated that this work will be completed by early May 2026, during this period, no mainline milling or paving operations shall take place. Coordinate work operations with Josh Gajewski at (262) 248-2311 (EXT:403) or jgajewski@lgutilities.org.

14. Utilities.

This contract does not come under the provision of Administrative Rule Trans 220.

mailto:jgajewski@lgutilities.org

26-003 8 of 19

It is the contractor’s responsibility to coordinate all work with each utility. This includes giving proper notification when utility work is to be performed in conjunction with project construction activities. Call Diggers Hotline at least three business days before the start of any excavation work.

There are underground and overhead utility facilities located within the project limits. Use caution to ensure the integrity of underground facilities and maintain code clearance from overhead facilities at all times.

Any utility facility locations (stations, offsets, elevations, depths) listed in this article are approximate.

Alliant Energy - Electric has existing underground and overhead cables within the project limits. A utility pole located at Sation 100+76, 24’ RT will be relocated ahead of construction. No additional conflicts are anticipated. Maintain appropriate operating clearance from these lines.

AT&T - Communications has existing underground and overhead telecommunications cables within the project limits. A Telecom Manhole located at Station 117+52 1’ RT to be adjusted to final roadway elevation by the utility. No additional conflicts are anticipated.

Charter Communications has existing underground and telecommunications cables north along Williams street that end at the George St. Intersection.

No Conflicts are anticipate.

WE Energies - Gas has 2-inch underground gas lines located along both sides of Williams Street from the beginning of the project to East Sheridan Springs Road. From Williams Street east along County Trunk Highway H to the intersection with Sheridan Springs Road, there is a steel gas main ranging in size from 8 inches to 10 inches located on the north side of the roadway, which crosses to the south side east of Sage Street. In addition, a 2-inch plastic gas line is located on the south side of County Trunk Highway H and crosses to the north side east of Center Street. From Sheridan Springs Road to the end of the project limits, a 2-inch plastic gas line is located along the south side of County Trunk Highway H, with various service laterals extending to properties located on the north side of the roadway.

There may be potential conflicts between underground gas facilities and the proposed storm sewer work at approximately station 123+50 left, or with proposed ditching operations. However, no conflicts were identified by the utility at the time of bid.

15. Municipality Acceptance of Storm Sewer, Sanitary Sewer, and Water Main Construction.

The department, City of Lake Geneva, and Lake Geneva Utility Commission personnel will inspect materials placement of storm sewer, sanitary sewer, and water main items under this contract. However, final acceptance of the storm sewer items will be by the City of Lake Geneva, and final acceptance of the sanitary sewer and water main items will be by the Lake Geneva Utility Commission.

Stp-105-001 (20250701)

16. Breaker Run.

Replace standard spec 311.2 (1) with the following:

Furnish either 3-inch clear crushed stone or concrete from a department-approved source substantially free of overburden materials, topsoil, organic materials, steel, recycled asphalt, and other deleterious materials or Base Aggregate Dense 3-inch consisting of 100% crushed limestone meeting standard spec

305.2.2. Submit samples or allow engineer to inspect source material to obtain engineer’s approval prior to delivery to the site.

17. HMA Pavement.

Construct HMA Pavement conforming to standard spec 460, except as modified herein.

Tack Coat shall conform to standard spec 455, except Sections 455.2.2 and 455.2.3 will not apply.

HMA ride incentive in standard spec 740 shall not apply to this contract, but smoothness conforming to standard spec 450.3.2.9.1 will remain in effect.

Section 460.2.8.3 will not apply to this contract; however, the department reserves the right to complete random sampling and testing conforming to Standard Spec 460.2.8.3 if the department deems necessary.

The department will rely on the contractor’s QMP testing as monitored by the State and any corrections

26-003 9 of 19 made to ensure HMA pavement mix placed on the project meets specifications. QMP testing requirements are incidental to HMA pavement. The contractor shall provide the engineer with all test results.

The department may not perform its own density testing per standard spec 460.3.3; however, the department reserves the right to order contractor-provided nuclear density testing of all asphalt pavements as they desire and determine necessary as incidental to the HMA pavement. The department will expect the density to meet the minimums required in table 460-3 and air voids within tolerances. Density incentives will only be paid conforming to standard spec 460.5.2.3 if a contractor-provided independent tester performs density testing. If any individual density test result falls more than 3.0 percent below the minimum required target density, the engineer may order work stopped to conduct a review of construction operations with the contractor.

18. Reconstructing Inlets and Manholes.

Reconstructing Manholes and Inlets per Standard Spec 611 shall include, but is not limited to, the following as required to complete the reconstruction and restore the structure to a fully functional condition:

• Removal and replacement of manhole or inlet tops, or cone sections, and adjusting rings.

• Partial or full removal and reconstruction of structure walls as required to accommodate new elevations, alignments, or connections.

• Rotating eccentric flat tops or cone sections to relocate opening location.

• Connecting new storm sewer pipes or laterals, including forming or cutting new openings.

• Sealing of abandoned pipe openings after removal or disconnection of existing pipes using approved materials.

• Grouting, patching, and sealing of joints, pipe penetrations, and structure walls.

19. Supplemental Traffic Control, Item SPV.0055.01.

A Description

This special provision describes providing a contingent cash allocation for additional traffic control on an as-needed basis, as determined by the engineer.

B Materials

Furnish temporary traffic control signs, barricades, drums, lights, supports, sign colors, sign legends, portable changeable message signs (PCMS), etc. in accordance spec 643.2.

C Construction

When the engineer or department requests in writing additional traffic control work not already included in the contract as part of the plans, plan details, standard detail drawings, notes, standard specifications, or special provisions; process in accordance with spec 104.2.2.1.

These additional traffic control measures may include, but are not limited to, custom signs, business signs, way-finding signs, additional signs or barricades placed on private property, or any other custom traffic control outside typical highway construction traffic control or otherwise shown on the plans.

Any additional, relocated, or differing standard signs, barricades, drums, lights, or supports to improve or enhance traffic control or detour signage already included in the contract, as determined by the engineer, will not be considered supplemental traffic control under this pay item and will be incidental to other contract items.

D Measurement

The Department will measure Supplemental Traffic Control by the authorized dollar value of work performed in accordance with Spec 109.4.4.

E Payment

The department will pay for measured quantities at the contract unit price under the following bid item:

ITEM NUMBER DESCRIPTION UNIT

SPV.0055.01 Supplemental Traffic Control DOL

26-003 10 of 19

Payment is full compensation from the allotment for an authorized dollar value of supplemental traffic control recommended by the engineer. Contract quantity will be correspondingly adjusted. All or none of the contract quantity may be used on this project. No adjustments to the contract will be made if less than the full allotment is used for this purpose.

20. Rectangular Rapid Flashing Beacon (RRFB) System, Item SPV.0060.01.

A Description

This work shall consist of furnishing and installing a solar powered rectangular rapid flashing beacon (RRFB) system consisting of multiple assemblies as described herein and as shown in the plans. Each assembly shall be solar powered, and pedestrian activated. The assemblies shall be wirelessly controlled, and multiple units shall be synchronized. This specification is according to requirements contained in FHWA interim approval 1A-21 dated March 20, 2018 for flashing requirements and beacon operation.

B Materials

Furnish a RRFB system with multiple assemblies. Each assembly may consist of, but not limited to, light indications, and electrical components (wiring, solid-state circuit boards, etc.). An assembly may include the following items:

B.1 Light Indications

Each indication shall be a minimum size of 7" wide x 3" high with 8 high power LEDs.

Two indications shall be installed on an assembly facing in the direction of approaching vehicular traffic.

The two indications shall be aligned horizontally, with the longer dimension of the indication horizontal, and a minimum space between the two indications of approximately 7" measured from inside edge of one indication to inside edge of second indication.

A 6 LED or approved equal indication shall be installed on an assembly facing in the direction of approaching pedestrian traffic to serve as a confirmation for the pedestrian that the system has been activated.

The outside edges of the two indications, including any housing, shall not protrude beyond the outside edges of the integral signage of the assembly.

The light intensity of the indications shall be certified to meet the minimum specifications of the Society of Automotive Engineers (SAE) standard J595 Class 1 (Directional Flashing Optical Warning Devices for 7864-00-74 8 of 13 Authorized Emergency, Maintenance, and Service Vehicles) dated January 2005 and be available upon request.

Each indication shall be located between the bottom of the crossing warning sign and the top of the supplemental downward diagonal arrow plaque.

All exposed hardware shall be anti-vandal.

All individual components of the system shall be replaceable to allow for easy field repair and maintenance.

To minimize excessive glare during nighttime conditions, an automatic signal dimming device should be used to reduce the brilliance of the RRFB indications during nighttime conditions. All lights and related work are incidental to RRFB item.

B.2 Sign

All signs shall be supplied and installed under as part of the RRFB system. All signs and installation are incidental to RRFB item. However, the assemblies must be constructed to allow the appropriate space for the installation of the signs in the field.

B.3 Control Circuit

The control circuit shall have the capability of…