The North Texas Municipal Water District (NTMWD) has issued a Request for Best Value Bid No. 25-219-B for material supply and installation of Carbon Fiber Reinforced Polymer (CFRP) liners for internal repair of large water and wastewater pipes. The virtual pre-bid meeting is scheduled for Monday, September 22, 2025, at 10:00 AM Central, with bid submittals due prior to Thursday, October 2, 2025, at 3:00 PM Central. Bids must be submitted electronically to ntmwd.bonfirehub.com. The initial contract term is 20 months, with automatic renewals for four additional one-year periods unless terminated by either party with 90 days' notice. The project involves rehabilitating concrete and metallic water and wastewater pipes using CFRP technologies throughout North Texas.

The bid will be awarded based on a best value determination using a weighted evaluation criteria: 30 points for methodology and approach, 35 points for prior experience, and 35 points for price. Bidders must provide detailed qualifications, including at least 30 completed CFRP installation projects, certifications for key personnel, and documentation of technical capabilities. The contract allows for multiple awards, with a primary and potential secondary vendor. Pricing will be per linear foot of pipe lined, with additional line items for extra CFRP layers, work on slopes, increased distances between access points, and other specific project requirements. The bidder must provide various certifications, including compliance with Texas laws regarding energy companies, firearm industries, and interested parties disclosure.

View the file

Other files

File Type Posted
1-25-219-B Bid Table.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR BEST VALUE BID NO. 25-219-B

MATERIAL SUPPLY AND INSTALLATION OF CFRP

LINERS FOR INTERNAL REPAIR OF LARGE WATER

AND WASTEWATER PIPES

VIRTUAL PRE-BID MEETING:

Monday, September 22, 2025, at 10:00 AM Central

BID SUBMITTALS ARE DUE PRIOR TO:

Thursday, October 2, 2025, at 3:00 PM Central

BID MUST BE SUBMITTED ELECTRONICALLY TO (Registration is free):

ntmwd.bonfirehub.com

NORTH TEXAS MUNICIPAL WATER DISTRICT CONTACT:

Trey Benton, CTCD, CPPB, NIGP-CPP tbenton@ntmwd.com mailto:tbenton@ntmwd.com

NORTH TEXAS MUNICIPAL WATER DISTRICT

INSTRUCTIONS TO BIDDERS

1. REQUIRED INFORMATION

A. The North Texas Municipal Water District’s (NTMWD or District) solicitation packets contain various documents that require completion by the bidder. Said information must be completed and submitted prior to the closing date and time for the submission of bids. Failure to provide required information may result in the rejection of your bid.

2. SUBMISSION OF BIDS

A. A response to a Request for Bid (RFB) may be submitted to NTMWD by any of the following means:

i. Electronically submitted via ntmwd.bonfirehub.com;

ii. No hard copy, oral, telegraphic, telephonic, or facsimile submittals will be considered or accepted.

3. OFFICIAL TIME & LATE SUBMITTALS

A. Submit bids in Bonfire prior to the due date and time. Bonfire will not allow submittals to be uploaded after the due date and time. The submission of a Bid is incontrovertible representation by the Bidder that he has complied with every requirement stated in this Request for Best Value Bid.

4. NOTIFICATION

A. NTMWD uses www.bonfire.com and The Wylie News to disseminate notification of bid opportunities. NTMWD shall not be responsible for receipt of notification and information from any source other than those listed above.

It shall be the Bidder’s responsibility to verify the validity of all information received by sources other than those listed.

5. ELECTRONIC SUBMITTALS

A. NTMWD exclusively uses Bonfire for the electronic notification and dissemination of all bids. The receipt of documents through any other company may result in the receipt of incomplete specifications and/or addenda.

NTMWD accepts no responsibility for the receipt and/or notification of solicitations through any other company.

B. To streamline the solicitation process, all Bidders are highly encouraged to utilize the Bonfire system. There is no cost to the Bidder to download or respond to NTMWD solicitations on Bonfire. Even though electronic response submission are recommended, Bidders may continue to submit a hard copy, paper bid directly to NTMWD if desired.

6. MODIFICATION AND WITHDRAWAL

A. Bids may be withdrawn at any time prior to the official opening of the bids. Alterations made by a bidder before opening time may be made through the withdrawal of any submission in Bonfire and must be resubmitted prior to the submission deadline. After the official opening, bids become the property of NTMWD and may not be amended, altered, or withdrawn without the authorization of the Procurement Manager.

7. BID OPENINGS

A. All submittals will be opened and presented according to the legal requirements for the type of solicitation at the designated time and place specified in the solicitation. However, the reading of a bid at the opening should not be construed as a comment on the responsiveness of such bid or as any indication that NTMWD accepts such bid as responsive. NTMWD will make a determination as to the responsiveness of bids submitted based upon compliance with all applicable laws, NTMWD purchasing guidelines, and project documents, including but not limited to the specifications and required submittal documents. NTMWD will notify the successful bidder upon award of the contract and, according to State law, all bids received will be available for inspection at that time.

8. BID SUBMISSIONS

A. Due care and diligence have been used in preparation of the information contained in this request for bids, and the information is believed to be substantially correct. However, it is Bidder’s responsibility to determine the full extent of its exposure and to verify all information presented in the request for bids. NTMWD and its representatives are not responsible for any errors or omissions in these specifications. Additionally, NTMWD and its representatives are not responsible for Bidder’s failure to determine the full extent of the exposure and risk associated with this request for bids.

http://www.bonfire.com/

A. This bid is issued in compliance with the NTMWD Purchasing Policy and with authorization from NTMWD’s Board of Directors.

a) Bids will be considered irregular if they show any omissions, alteration of form, additions or conditions not called for, or other irregularities of any kind. However, NTMWD reserves the right to waive any irregularities and to make one or more awards in the best interest of NTMWD.

b) NTMWD reserves the right to accept or reject in part or in whole any bids submitted and to waive any technicalities in the best interest of NTMWD. Bids may be rejected, among other reasons, for any of the following specific reasons:

i. Bids containing any irregularities, and

ii. Unbalanced value of any items.

c) Bidders may be disqualified and their submissions not considered, among other reasons, for any of the following specific reasons:

i. If NTMWD believes collusion exists among the bidders;

ii. Reasonable grounds for believing that any bidder has an interest in more than one bid for the work contemplated;

iii. The bidder having an interest in any litigation against NTMWD;

iv. The bidder being in arrears on any existing contract or having defaulted on a previous contract;

v. Lack of competency as revealed by a financial statement, experience, equipment, questionnaires, etc.;

and

vi. Uncompleted work which, in the sole judgment of NTMWD, will prevent or hinder the prompt completion of additional work, if awarded.

d) It is the bidders’ sole responsibility to print and review all pages of the bid document, attachments, questions and their responses, addenda and special notices.

e) When in the best interest of NTMWD, NTMWD reserves the right to request additional information or clarification from bidders to determine bidders’ ability to meet the requirements specified by this bid.

f) On the Bid Pricing Form, in the case of a conflict between the unit price indicated and the extended amount shown, the unit price indicated multiplied by the stated quantity shall govern.

g) NTMWD reserves the right to reject any of all submissions without cause prior to award, to waive formalities, or to proceed otherwise when in the best interest of NTMWD.

9. EXAMINATION OF CONTRACT DOCUMENTS AND SITE

A. Bidders must examine the Solicitation, make observations and investigations, correlate knowledge and observations with the requirements of the Solicitation and consider these in preparation of a bid for the project.

B. Bidders must read the Solicitation and related technical data and reports thoroughly. Use a complete set of Solicitation Documents in preparing Bids. Assume responsibility for errors or misinterpretations resulting from the use of partial or incomplete documents.

C. Bidders must become familiar with federal, state and local laws, ordinances, rules, and regulations affecting cost, progress, or performance of the work.

D. By the submission of a Bid for this project, Bidders acknowledge sole responsibility for job site safety.

E. The submission of a Bid is an incontrovertible representation by the Bidder that Bidder has complied with every requirement of this Section.

10. UNIT OF MEASURE

A. Responses to the RFB must be submitted in the units of measure specified in the bid pricing form.

11. INTERPRETATIONS

A. Bidders must submit all questions about the meaning or intent of the Solicitation to NTMWD to Bonfire by the question due date and time. Replies are issued by Addenda to all parties recorded as having received the bidding documents. Only questions answered by formal written Addenda are binding. Oral and other interpretations or clarifications will be without legal effect.

12. ADDENDA

A. Any interpretations, corrections, or changes to this bid will be made by written addenda. Sole issuing authority of addenda shall be vested in NTMWD’s Procurement Department. Addenda will be issued via ntmwd.bonfirehub.com. It is the responsibility of the bidder to ensure receipt of all addenda and acknowledge by signing and including with the bid submittal.

13. CONFIDENTIALITY

A. Any material that is to be considered confidential must be clearly marked as such and shall be treated as confidential to the extent allowable under Chapter 552, Government Code.

B. The Texas Public Information Act gives the public the right to request access to government information, subject to certain narrow exceptions. NTMWD is an entity subject to this Act. Therefore, please be advised that your company's declaration that certain information submitted in response to a bid request is "confidential" will not be treated as such if NTMWD receives a request for a copy of the bid proposal. NTMWD will of course make an effort to inform your company of such a request and to provide you with an opportunity to object to the release of any proprietary information, but NTMWD cannot and will not make an agreement to withhold information from the public contrary to NTMWD’s responsibilities under the Act.

C. To the extent your response is incorporated into the contract, that contract will become an official record available for public inspection.

D. Bids shall be opened so as to avoid disclosure of content to competing bidders and kept secret during the process of awarding a contract. All bids that have been submitted shall be open for public inspection after the contract is awarded, except for trade secrets and confidential information contained in the submission and identified as such.

14. BID TABULATIONS

A. As-Read Bid tabulations will be electronically posted to ntmwd.bonfire.com within forty-eight (48) hours after the bid opening.

15. PREPARATION COSTS

A. NTMWD will not be liable for any costs associated with the preparation, transmittal, or presentation of any bids or materials submitted in response to this bid.

16. TAXES

A. NTMWD is exempt from Federal Excise and State Sales Taxes. Tax must not be included in the pricing.

17. PRICING

A. Prices must be firm for a minimum of ninety (90) days from the date of the bid closing. In the case of an annual contract, the prices must remain firm for the period as specified in the solicitation.

18. BIDDER QUALIFICATIONS

A. A prospective Bidder must meet the following minimum requirements:

i. Must have adequate financial resources, or the ability to obtain such resources as required;

ii. Must be able to comply with the required or proposed delivery/completion schedule;

iii. Must have a satisfactory record of performance;

iv. Must have a satisfactory record of integrity and ethics;

v. Must be otherwise qualified and eligible to receive an award;

vi. NTMWD may request representation and other information sufficient to determine the Bidder’s ability to meet these minimum standards listed above.

19. AWARD OF CONTRACT

A. NTMWD reserves the right to award this contract by one of the following methods. The method selected will be in the best interest of NTMWD, as determined by the Procurement Manager.

i. To the lowest responsible Bidder(s), bidding all items and meeting all specifications;

ii. To one or more Bidders, if deemed in the best interest of NTMWD;

iii. To the lowest responsible Bidder(s) meeting specifications per line item;

iv. If specified, to the low Bidder(s) meeting specifications, per category. To qualify for an award of a category, a Bidder must bid all items within that category. If all items of a category are not bid by all Bidders, award shall be made in the best interest of NTMWD;

file://sgh.com/offices/BOS/Projects/2021/211207.15-SPEC/Specification%20Review/ntmwd.bonfirehub.com file://sgh.com/offices/BOS/Projects/2021/211207.15-SPEC/Specification%20Review/ntmwd.bonfire.com

v. To the Bidder(s) who provide the goods or services specified in the solicitation at the best value to

NTMWD.

vi. NTMWD reserves the right to compare all bids against any State and/or Interlocal contracts in determination of the award of this bid.

REMAINDER OF PAGE INTENTIONALLY LEFT BLANK

SPECIAL CONDITIONS

1. GENERAL INFORMATION

The North Texas Municipal Water District (NTMWD) is soliciting sealed bids to establish a service contract agreement for the internal repair of large diameter concrete and metallic water and wastewater pipes using carbon fiber reinforced polymer (CFRP) technologies throughout North Texas in accordance with the specifications provided herein.

In this RFB and in the Scope of Services, the terms bidder, applicator and contractor are used interchangeably and refer to the same entity.

2. PRE-BID MEETING

A non-mandatory virtual pre-bid meeting will be on Monday, September 22, 2025, at 10:00 AM Central via Microsoft Teams. It is highly recommended that all bidders attend the pre-bid meeting. Bidders may ask questions about the specification and bid process during the meeting. Questions and answers will be made in the presence of all attendees. All answers provided in the pre-bid meeting shall be considered unofficial, and all official answers will be provided via written addendum and distributed through Bonfire.

URL:

https://teams.microsoft.com/l/meetup-join/19%3ameeting_MDE2NDJiZTktMzk3Zi00YzEzLWE5MjUtNzQ5YzIyZjAyYmZi%40thread.v2/0?context= %7b%22Tid%22%3a%226761e290-960c-4c95-b8b0-aacfa43af673%22%2c%22Oid%22%3a%227d3560e9-

8ca9-4a10-96bc-5b049a561277%22%7d

OR

TEL: 1-929-336-1597

Access Code: 947 673 075#

3. DURATION OF AGREEMENT

A. The initial term of this agreement shall commence on the date of the last signatory and shall be for a period of twenty (20) months. The agreement will automatically renew under the same pricing, terms, and conditions for four (4) additional one-year periods unless NTMWD provides Contractor with written notice of its intent to terminate the agreement at least ninety (90) days prior to the expiration of the current term. If said notice is given by NTMWD, the agreement shall terminate at the conclusion of the current one-year term.

B. Prices shall remain firm for the duration of the initial contract period. Thereafter, price changes are subject to the price adjustment provisions of this Contract.

C. NTMWD reserves the option to temporarily extend this service for an additional ninety (90) days from its expiration date for any reason.

4. BID QUESTIONS & CLARIFICATION

A. All questions regarding this request for bid shall be submitted in writing on ntmwd.bonfirehub.com no later than

4:00 PM Central on Thursday, September 25, 2025. All questions will be addressed in an addendum.

Questions received after the deadline may not be answered.

5. ESTIMATED ANNUAL CONTRACTS

A. The quantities specified are estimates of our projected annual requirements. The award of an estimated annual contract allows NTMWD to use the items and services as the requirements and needs of NTMWD arise on an annual basis and during any subsequent renewal period(s). Quantities may be increased beyond the estimated quantities listed in this bid, as necessary, provided funding is available. Quantities may be decreased below the estimated quantities listed in this bid, as necessary, if funding is not available or if items and services are no longer needed. NTMWD is not obligated to pay for or use a minimum or maximum amount of items or services and payment will be made pursuant to the unit prices bid in the contract. The Contractor shall have no claim against NTMWD for anticipated profits for the estimated quantities listed, diminished, or deleted.

6. BID SUBMITTAL REQUIREMENTS & OPENING

A. The bid opening will be held on the bid due date and time via Webex:

https://teams.microsoft.com/l/meetup-join/19%3ameeting_MDE2NDJiZTktMzk3Zi00YzEzLWE5MjUtNzQ5YzIyZjAyYmZi%40thread.v2/0?context=%7b%22Tid%22%3a%226761e290-960c-4c95-b8b0-aacfa43af673%22%2c%22Oid%22%3a%227d3560e9-8ca9-4a10-96bc-5b049a561277%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_MDE2NDJiZTktMzk3Zi00YzEzLWE5MjUtNzQ5YzIyZjAyYmZi%40thread.v2/0?context=%7b%22Tid%22%3a%226761e290-960c-4c95-b8b0-aacfa43af673%22%2c%22Oid%22%3a%227d3560e9-8ca9-4a10-96bc-5b049a561277%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_MDE2NDJiZTktMzk3Zi00YzEzLWE5MjUtNzQ5YzIyZjAyYmZi%40thread.v2/0?context=%7b%22Tid%22%3a%226761e290-960c-4c95-b8b0-aacfa43af673%22%2c%22Oid%22%3a%227d3560e9-8ca9-4a10-96bc-5b049a561277%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_MDE2NDJiZTktMzk3Zi00YzEzLWE5MjUtNzQ5YzIyZjAyYmZi%40thread.v2/0?context=%7b%22Tid%22%3a%226761e290-960c-4c95-b8b0-aacfa43af673%22%2c%22Oid%22%3a%227d3560e9-8ca9-4a10-96bc-5b049a561277%22%7d https://ntmwd.bonfirehub.com/contracts/36875/people

URL:

https://ntmwd.webex.com/meet/tbenton

OR

TEL: 1-844-621-3956

Access Code: 2661 330 6951

B. The following documents must be included with this bid. Failure to supply the required forms may deem you non-responsive:

• Bid Signature Form

• Bid Pricing Form

• Qualifications of Applicator

• Qualifications of Manufacturer

• Reference Projects

• All information listed under Bidder Submittals

7. METHOD OF AWARD

A. The District’s intent is to award to the responsible bidder(s) providing the best value to NTMWD. All bidders must provide documentation and information requested in this solicitation (see Questionnaire in Bidder Forms section) in order to determine the best value as outlined in the table below.

B. Pursuant to the Texas Local Government Code, § 252.043, Award of Contract, “Best Value” will be determined utilizing the following criteria:

Criteria Description Weight (100 total)

Methodology and Approach

• Effectiveness of the plan to ensure successful and timely project implementation.

• Strength and clarity of the proposed QA/QC approach throughout construction.

• Identification of potential risks and quality of proposed risk mitigation strategies.

• Demonstrated ability to minimize delays caused by unforeseen conditions.

30 points

Prior Experience Completing Similar Projects

• Depth and relevance of experience related to the project scope.

• Strength of qualifications in meeting specification requirements.

• Demonstrated expertise and past performance on comparable projects.

• Alignment of team capabilities with project needs.

35 points

Price • Fill out provided Bid Sheet in Microsoft Excel in entirety. 35 points

SPECIFICATIONS - MATERIAL SUPPLY AND INSTALLATION OF CFRP LINERS FOR

INTERNAL REPAIR OF LARGE WATER AND WASTEWATER PIPES

1. QUALIFICATION OF BIDDERS

A. The successful bidder shall be an established CFRP Applicator with at least five years of experience in the installation of carbon fiber reinforced polymer liners to repair water and wastewater pipes internally as specified herein. The successful bidder must possess the capacity to provide the products and services necessary through the duration of the agreement. The bidder shall maintain an adequate experienced labor force and an inventory of all necessary materials and equipment to satisfy the account without extended delivery or service time. The Applicator’s workforce shall self-perform the CFRP installation; it is not acceptable for the CFRP applicator to subcontract surface preparation or CFRP installation.

2. BIDDER SUBMITTALS

A. Methodology and Approach

a. Describe how the requirements of this project will be implemented successfully and in a timely manner.

Explain your approach to QA/QC throughout construction. Identify possible risks associated with the work and demonstrate by example your ability to provide and implement risk mitigation plans and minimize delays due to unforeseen conditions that may arise. No more than ten (10) 8.5”x11” pages with size 11 Arial font.

B. The submittals defined in this section must be provided with the bid to document qualifications of the Applicator and Manufacturer. For a reference project to be considered applicable, it must involve the following:

a. Minimum pipeline diameter: 36-inches for internal and external projects

b. Minimum pipeline normal operating pressure: 50 psi

c. Minimum project length: 20 lineal feet

d. CFRP installation was a stand-alone repair without reliance on the host pipe for structural integrity.

e. Project location in North America.

C. At least 25 of the 30 projects must be repair of concrete (pre-stressed concrete cylinder pipe or bar-wrapped) pipe. At least two pipes must be repair of wastewater pipes.

For each reference project include:

a. Project information:

i. Project name,

ii. Owner name and Owner representative contact information,

iii. Name of CFRP application company,

iv. Name of CFRP manufacturer,

v. Name of design engineer,

b. Host pipe information

i. Pipe material and type,

ii. Diameter,

iii. Soil cover,

iv. Design pressure

c. Repair information

i. Length of repair

ii. Type of repair (internal or external)

D. Applicator:

a. Provide a list of at least thirty (30) completed independent CFRP installation projects for concrete or metallic pipe rehabilitation projects in the past three years.

b. Certification that the Project Manager, foreman, head supervisor, at least ten (10) CFRP installation technicians, and quality inspector available to perform the work for NTMWD have a minimum of three years of experience each in large diameter (greater than 36-inches) pipe repair projects using CFRP, with a minimum of 15 projects each, and are employed full time by the Applicator. A list of names, titles, and projects shall be provided for each.

c. Written verification from the Manufacturer that the Applicator’s personnel are trained and certified in the use of the proposed CFRP system.

d. Applicator shall provide a letter from their surety company confirming that they can furnish a five-year bonded warranty starting from final acceptance as described in Section 4.05 of this specification.

e. Safety: Applicator shall submit notarized documentation of the following in the name of the legal entity bidding:

i. Experience Modification Rates (EMR) for worker's compensation insurance for the past five (5) years with no year indicating an EMR above 1.5. A letter from company's surety must also be provided verifying this information and it must match the legal entity bidding the project.

ii. OSHA TRIR for years for the past five (5) years with no year indicating a TRIR above 2.0 for the same legal entity bidding the project.

E. Manufacturer:

a. Provide a list of at least thirty (30) completed independent CFRP projects for concrete or metallic pipe rehabilitation projects in the past three years for which the manufacturer’s product was used.

F. Provide additional submittals specified in Section 1.04.A to document material properties. Bidders shall note manufacturer and part number (if applicable) on documentation. Failure to provide requested items may be grounds for disqualification.

3. PAYMENT AND PERFORMANCE BONDS

A. The District shall require Payment and/or Performance Bonds for any project at its sole discretion. The District shall notify the awarded Vendor of such requirements at the time work is requested. The Vendor shall furnish all required bonds to the District prior to the commencement of any work. Each bond shall be issued in the full amount of the proposed scope of work.

4. WELDING SERVICES

A. Welding services included in this work shall be performed by welders who are full-time employees of one of the companies on NTMWD’s pre-approved list for pipe welding services. The current list of preapproved welders is as follows:

1. Thompson Pipe: 972-262-3600

2. Rangeline Pipeline Services: 682-250-2153

3. Fuller’s Service Company, Barry Fuller: 817-477-3841

4. Scott’s Welding, Scott Fowler: 972-978-7865

5. Fletcher’s Welding, Darrel Fletcher: 817-307-8750

6. Eddie’s Welding Service, Eddie Pierce: 817-909-6089

7. National Welding Corporation, Nash Williams: 801-255-5959

5. WORK REQUEST REQUIREMENTS

A. To comply with these specifications, the awarded Contractor must obtain a duly issued NTMWD Purchase Order (“PO”) prior to performing any services or delivering any materials, unless expressly authorized otherwise by NTMWD. The PO shall reflect the pricing set forth in the Contractor’s submitted price sheet.

NTMWD shall not be liable for any services or materials provided without a valid PO, except in cases of emergency as determined by NTMWD’s program administrator.

The PO shall constitute notice to the Contractor to secure and submit all required bonds prior to commencing work. A written Notice to Proceed will also be issued by NTMWD authorizing the Contractor to perform services or deliver materials. Any work performed or materials provided by the Contractor without a valid PO and Notice to Proceed shall be deemed unauthorized and performed at the Contractor’s sole risk, with no obligation of payment by NTMWD.

NTMWD may, at its discretion, establish a progress payment schedule at the time of the work request. All payments are contingent upon NTMWD verification that work has been satisfactorily completed and that all estimates and invoices are accurate and consistent. Payment shall be released only upon completion of such verification.

If additional work is discovered during the course of performance, the Contractor shall not proceed with such work without prior written authorization from NTMWD. Unauthorized work or charges shall not be compensated.

6. INVOICE REQUIREMENTS

A. All original invoices are to be sent to: NTMWD Accounts Payable, accountspayable@ntmwd.com and a copy sent to the assigned department requesting the purchase. Invoices submitted for payment must have the following information:

1. Vendor’s name and company address

2. Name and address of the department where product(s) were delivered

3. Date of delivery

4. Delivery order number that authorized the purchase

5. Manufacturer’s part number (if applicable) and a detailed description of each item delivered.

6. Pay Item name and number per Bid Form, unit cost and extended cost of each item

7. Total cost of the order

8. Purchase Order

9. Contract Number

B. Invoices submitted without this information will be returned to the supplier, and payment will not be made until required information is provided on the invoice. Payment shall be made after services have been rendered, inspected, and accepted.

7. CONTRACTOR RESPONSE TIME

A. NTMWD intends to schedule most of the work requested under this contract at least 60 days in advance so that adequate planning and coordination can occur. Work will predominantly occur in the seasons identified in Section 1.01.G.4 of the specification. The awarded contractor shall be prepared to mobilize within fourteen (14) days after receipt of a purchase order. In EMERGENCIES, NTMWD may issue verbal Purchase Orders and need expedited deployment within 72 hours of notification. Verbal orders will require acknowledgment within twenty-four (24) hours.

8. CURE NOTICE

A. In the event a party to this Agreement, including Contractor or Subcontractor, fails to perform its obligations under this Contract, including but not limited to timely completion, quality of work, or payment obligations, the non-breaching party may issue a written cure notice. Such notice shall specify the nature of the breach or deficiency, provide a reasonable period, not less than seven (7) days unless otherwise agreed, for the breaching party to remedy the issue, and state the potential consequences of non-compliance, including termination of the Contract. All cure notices shall comply with the terms of this Agreement. This process is intended to facilitate resolution and ensure continued performance while preserving the rights of all parties.

The issuance of a Cure Notice may hinder the vendor from receiving a future award with NTMWD.

9. WARRANTY

A. All the products provided shall be new and warranted to be free from defects in workmanship, design, and materials. The warranty period shall be five (5) years, and the warranty period is to be bonded. The warranty will begin upon NTMWD’s written acceptance of the product, installation, or service. A Maintenance Bond for stated warranty shall be submitted prior to a Notice to Proceed being issued by NTMWD.

mailto:accountspayable@ntmwd.com

SCOPE OF SERVICES

PART 1

1.01 GENERAL REQUIREMENTS

A. In this Scope of Services, the terms bidder, applicator and contractor are used interchangeably and refer to the same entity.

B. The applicator shall furnish labor, all materials, tools, equipment, transportation, storage, supervision, and inspection required for the supply and installation of internally and externally bonded Carbon Fiber-Reinforced Polymer (CFRP), including protective coatings, to rehabilitate ductile iron, cast iron, steel, reinforced concrete pipe, bar wrapped pipe (BWP), or prestressed concrete cylinder pipe (PCCP) used to convey raw water, treated water, and wastewater at locations shown on the Project Drawings or designated by NTMWD.

C. Substrate preparation and repair as well as supply of environmental equipment and clean-up after the completion of work. No separate pay item.

D. The work related to the installation of CFRP shall be coordinated with other trades working in the area.

E. The CFRP system shall be installed by an applicator certified by the product manufacturer by means of written verification.

F. Timeliness

1. The Applicator shall be required to respond to immediate project needs and mobilize for site walks within 48 hours and possess the ability to initiate emergency repair projects within 72 hours of receipt of notice-to-proceed.

2. The work will require NTMWD to remove one or more pipes, and possibly pumps or other equipment, from normal operating service. The allowable time that the infrastructure can remain out of service, referred to as the shutdown tolerance, will be finite, will vary from pipe to pipe, and will vary based on the time of year according to seasonal demands in the NTMWD system. It is critically important that the Applicator plan, coordinate and conduct the work in a timely manner so that delays are minimized.

a. The Contractor shall prepare and submit a detailed implementation plan and work scheduled in accordance with Section 1.04.B.

i. Work times for activities inside pipe shall typically be 12-hours per day, seven days a week..

NTMWD may require longer shifts for emergency repairs.

ii. These work times do not apply to specified activities requiring continuous monitoring (bypass/ dewatering pumping operations, etc.), which shall be conducted 24 hours per day as needed.

b. For the work to proceed, the time required to perform the work must be less than the shutdown duration. NTMWD will estimate the allowable shutdown tolerance for each project and coordinate each installation with the contractor to verify sufficient time will be available to perform the work.

c. The contractor must sufficiently plan and prepare to perform the work expeditiously once the shutdown begins so that the work is completed without significant delays. The Contractor shall provide sufficient equipment and manpower to complete the work within the time allotted for each project.

d. Planned, non-emergency repairs will typically be performed during the following windows for each pipe type

i. Potable Water pipelines: November – April

ii. Critical potable water pipelines: January – February

iii. Raw water pipelines: TBD

iv. Wastewater Pipelines: TBD

1.02 REFERENCES

Installation of the composite system must comply with pertinent provisions of the following codes and standards.

These written specifications take precedence over incorporated references. The latest revision of the code or standard in effect at the time of execution of the contract shall be used.

American Concrete Institute (ACI) ACI 222R: Protection of Metals in Concrete Against Corrosion.

ACI 224.1R: Causes, Evaluation, and Repair of Cracks in Concrete Structures.

ACI 440.2R: Guide for the Design and Construction of Externally Bonded FRP System for Strengthening

Concrete Structures.

ACI 503R: Use of Epoxy Compounds with Concrete.

ACI 546R: Concrete Repair Guide.

American Society for Testing and Materials (ASTM) ASTM C811: Standard Practice for Surface Preparation of Concrete for Application of Chemical-

Resistant Resin Monolithic Surfacing’s.

ASTM C882: Standard Test Method for Bond Strength of Epoxy-Resin Systems used with Concrete by

Slant Shear.

ASTM D570: Standard Test Method for Water Absorption of Plastics.

ASTM D638: Standard Test Method for Tensile Properties of Plastics.

ASTM D695: Standard Test Method for Compressive Properties of Rigid Plastics.

ASTM D696: Standard Test Method for Coefficient of Linear Thermal Expansion of Plastics Between -

30°C and 30°C with a Vitreous Silica Dilatometer.

ASTM D790: Standard Test Methods for Flexural Properties of Unreinforced and Reinforced Plastics and Electrical Insulating Materials.

ASTM D792: Standard Test Methods for Density and Specific Gravity (Relative Density) of Plastics by

Displacement.

ASTM D1141: Standard Practice for the Preparation of Substitute Ocean Water.

ASTM D2240: Standard Test Method for Rubber Property-Durometer Hardness.

ASTM D2247: Standard Practice for Testing Water Resistance of Coatings in 100% Relative Humidity.

ASTM D2344: Standard Test Method for Short-Beam Strength of Polymer Matrix Composite Materials and Their Laminates.

ASTM D2369: Standard Test Method for Volatile Content of Coatings.

ASTM D2563: Standard Practice for Classifying Visual Defects in Glass-Reinforced Plastic Laminate

Parts.

ASTM D3039: Standard Test Method for Tensile Properties of Polymer Matrix Composite Materials.

ASTM D3045: Standard Practice for Heat Aging of Plastics Without Load.

ASTM D3410: Standard Test Method for Compressive Properties of Polymer Matrix Composite Materials with Unsupported Gage Section by Shear Loading.

ASTM D4065: Standard Practice for Plastics: Dynamic Mechanical Properties: Determination and Report of Procedures.

ASTM D4258: Standard Practice for Surface Cleaning Concrete for Coating.

ASTM D4473: Standard Test Method for Plastics: Dynamic Mechanical Properties: Cure Behavior.

ASTM D4541: Standard Test Method for Pull-Off Strength of Coatings using Portable Adhesion Testers.

ASTM D6641: Standard Test Method for Compressive Properties of Polymer Matrix Composite Materials

Using a Combined Loading Compression (CLC) Test Fixture.

ASTM D6379: Standard Test Method for Shear Properties of Composite Materials by the V-Notched

Beam Method.

ASTM D7290: Standard Practice for Evaluating Material Property Characteristic Values for Polymeric

Composites for Civil Engineering Structural Applications.

ASTM D7616: Standard Test Method for Determining Apparent Overlap Splice Shear Strength Properties of Wet-Layup Fiber-Reinforced Polymer Matrix Composites Used for Strengthening Civil Structures.

ASTM E2092: Standard Test Method for Distortion Temperature in Three-Point Bending by Thermomechanical Analysis.

American Water Works Association (AWWA) AWWA C301: Standard for Prestressed-Concrete Pressure Pipe, Steel-Cylinder Type.

AWWA C303: Standard for Concrete Pressure Pipe, Bar-Wrapped, Steel-Cylinder Type.

AWWA C305: Standard for Repair and Renewal of Pre-Stressed Concrete Cylinder Pipe.

AWWA M11: Steel Water Pipe: A Guide for Design and Installation.

International Code Council (ICC) AC125: Acceptance Criteria for Concrete and Reinforced and Unreinforced Masonry Strengthening

Using Fiber-Reinforced Polymer (FRP) Composite Systems.

AC178: Acceptance Criteria for Concrete and Reinforced and Unreinforced Masonry Strengthening

Using Externally Bonded Fiber-Reinforced Polymer (FRP) Composite Systems.

International Concrete Repair Institute (ICRI) ICRI 03730: Guide for Surface Preparation for the Repair of Deteriorated Concrete Resulting from

Reinforcing Steel Corrosion.

ICRI 03732: Selecting and Specifying Concrete Surface Preparation for Coatings, Sealers, and Polymer

Overlays.

ICRI 03733: Guide for Selecting and Specifying Materials for Repair of Concrete Surfaces.

NSF International (NSF) NSF 61: Drinking Water System Components – Health Effects.

NSF 372: Drinking Water System Components – Lead Content

1.03 DATA PROVIDED BY NTMWD

A. Lay schedules and plan and profile drawings showing the locations of access points.

B. Issued for Construction Drawings and Calculations prepared by NTMWD’s engineer. CFRP designs for CFRP liners will be developed in accordance with the load and resistance factor design (LFRD) approach of AWWA C305. Drawings will include:

1. Requirements and instructions for surface preparation, CFRP installation, and curing

2. Typical details, including cross-section views, design loads, materials and lay-up, required overlaps, and terminations.

3. Additional details specific to each pipeline section, such as cracks (if applicable)

C. Locations of NTMWD-owned, secure properties in the vicinity of the work that may be used for material and equipment storage. These may be relatively long distances away from the specific project site.

D. Peak wastewater flowrates for which bypass pumping must be designed, installed and operated for the duration of work inside wastewater pipes.

1.04 SUBMITTALS

A. Bid Submittals

1. The CFRP composite system shall consist of all associated fiber reinforcement and polymer adhesives/resins. All components of the CFRP composite system including primer, thickened epoxy, fiber reinforcement, impregnating resin, and topcoat resin shall be compatible and provided by the same supplier. Only two-part 100% solids epoxy shall be used for the CFRP system. Polyester or vinyl ester resin systems will not be approved as an alternate to an epoxy structural CFRP system matrix component.

Provide confirmation from the material manufacturer that the materials proposed comply with these requirements as well as the remainder of the requirements within this specification. Include:

a. Manufacturer’s product data sheet indicating physical, mechanical, and chemical characteristics of all materials used in the CFRP system.

b. Manufacturer’s Material Safety Data Sheets (SDS) for all materials to be used.

c. Properties of the composite materials as determined by independent laboratory testing in accordance with ASTM D3039 (tensile modulus, stress and strain).

d. Properties of the composite materials as determined by independent laboratory in accordance with

ASTM D695 (compression modulus, stress and strain).

e. Manufacturer’s certification that the installation process as well as all the materials used, including primers, fabrics, and saturating resins meet EPA and local ordinances for health and safety, including VOC compliance, NSF 61 approval and NSF 61 Annex G if lead is in any component.

2. A valid/current ICC Evaluation Service Report (ESR) compliant with 2021 IBC for the proposed CFRP composite system. Products that do not have an ESR number shall provide all the durability tests defined in ICC AC125 to validate the proposed system durability. The products in the ESR must be named and match the product data sheets submitted with bid. See submittal requirements with bid.

3. The Manufacturer shall provide documents indicating that all materials comply with the requirements of NSF 61 and NSF 61 Annex G. A printout from the NSF website, dated within one week of the due date, shall be submitted.

4. Testing report providing documentation of the degree of cure of the proposed CFRP at different temperatures and multiple time intervals to establish when sufficient cure has been achieved.

5. Provide documentation of mechanical properties of the FRP laminate listed in Table 1, durability of the FRP laminate (Table 2 and specified in AWWA Standard C305, Section 3.3.1), and the physical properties of the resin listed in Table 3. Reported properties shall be based on the listed standards and the number of tests required in these tables.

Table 1 – Mechanical Property Tests Required for CFRP Laminate1

Mechanical Property Minimum

Requirement ASTM Test

Method Minimum

Number of Tests

Tensile Strength 80,000 psi D3039 50 from

5 different lots Tensile Modulus 8x106 psi 10 Compressive Strength 40,000 psi D6641 10 Compressive Modulus 8x106 psi 10 Flexural Strength 15,000 psi D790 10 Flexural Modulus 0.35x106 psi 10 In-plane Shear Strength 12,000 psi D5379 10 In-plane Shear Modulus 0.40x106 psi 10 Interlaminar Shear Strength 4,000 psi D2344 10 Overlap Shear Strength 1,200 psi

D7616

Shear bond Strength between CFRP and Steel in absence of peel-off failure mode 1,100 psi 10

Shear bond Strength between CFRP and Steel when CFRP is used as joint harness and when peel-off failure mode is likely

550 psi 10

1Per AWWA Standard C305, Section 3 Table 2

Table 2 – Minimum Environmental Durability Tests Required for CFRP Laminate

Environmental Durability Test

ASTM Test Method Test Condition

Test Duration

(hrs)

Required % Retention of Tensile Properties per ASTM D3039

Water Resistance

D2247 E104

100%

RH100°F±2°F

1,000 3,000 10,000

Saltwater Resistance D1141 Immersion at

73°F±2°F

1,000 3,000 10,000

Temperature Resistance D3045 140°F±5°F 1,000

3,000

Table 3 – Physical Property Tests Required

Physical Property Requirement ASTM Test Method Minimum

Number of Tests Shore D Hardness of laminate

Greater than 50 for cured product D2240 10

Glass transition temperature (Tg) of resin

Greater than maximum of 175°F and exposure temperature + 40°F

D4065 20

Volatile organic compounds (VOC)

In compliance with state and local regulations D2369 2

Water absorption of fully cured resin

< 2% at room temperature D570 5

CFRP thickness per layer 0.04 in. ≤ t ≥ of 0.08 in. Nominal, per

Manufacturer data sheet 10

1Per AWWA Standard C305, Section 3 Table 3.

6. The test reports shall clearly indicate the commercial names of the products used, batch ID, sample dimensions, number of samples tested, number of fabric layers used, load and strain measurement techniques, failure modes, and obtained strength, modulus, and ultimate elongation for each sample tested.

Any deviation from the specified ASTM standards shall be clearly reported.

7. The environmental durability data provided by the FRP LINER Manufacturer shall be based on tests conducted on samples made with the same fabric and impregnating resin, and similar fiber content as the laminate to be used during the repair work.

8. Testing report demonstrating water tightness of the proposed CFRP system per AWWA Standard C305

Section 3.2.6. This shall demonstrate that at least three samples of the proposed layup for the CFRP system do not leak when subject to twice the maximum working-plus-transient pressure of the repair area.

9. Certification by the manufacturer that products supplied complies with local regulations controlling use of volatile organic contents.

10. Installation procedures and instructions, maintenance instructions and general recommendations regarding each material to be used.

11. Listing of any failures of the CFRP system, remediation measures and owner contact information.

12. Any product information that changes after the original bid submittal must be submitted to NTMWD for written approval. Use of products or materials that deviate from the bid submittals or changes approved by NTMWD may result in cancelation of the contract by NTMWD.

B. Submittals Prior to Purchase Order and Mobilization:

1. An itemized cost proposal for the specific work with quantities, unit cost and extended cost of each item in accordance with the Bid Form, along with the total cost of the order.

2. Manufacturer’s written installation procedures, including:

a. Method for preparing surfaces to accept CFRP.

b. Method, equipment, and procedures to be used to apply CFRP.

c. Existing pipe conditions required to successfully apply CFRP.

3. Method statement for installation of internal joint liner

a. List of equipment to be used during installation.

b. Technical data for proposed internal joint liner, including SDS, application instructions, and product data.

4. Document indicating the Applicator will have at least one dedicated field QA/QC personnel throughout the project execution.

5. General Confined Space Entry procedure. Include name and qualifications of rescue services personnel to be utilized. Contractor’s confined space entry permits and procedures shall cover all personnel who may enter the pipe during the work, including NTMWD and NTMWD representatives (engineers, inspectors, etc.).

6. A detailed schedule describing the work to be accomplished prior to the pipe being removed from the service (i.e. the shutdown), the proposed work shift duration for work inside the pipe, and the work to be accomplished during each shift for the duration of the shutdown. Detail daily activities and manpower used at each site, including activities that require manpower outside of the regular work shift for pipe activities.

If NTMWD deems any schedule to be inadequate to secure the completion of work in the time submittal, correct and re-submit schedules to change the order of prosecution of work to ensure proper and timely execution.

7. Job Hazard Analysis specific to job.

a. Include proposed locations and means of storing and securing materials and equipment.

8. Wastewater Bypass Pumping Plan

a. Manufacturer’s product data, instructions, recommendations, shop drawings, and necessary certifications

b. Staging areas for pumps.

c. Sewer plugging method and types of plugs.

d. Number, size, material, location and method of installation of suction piping.

e. Number, size, material, location and method of installation of discharge piping.

f. The proposed Dimension Ratio (DR) of the suction and discharge piping

g. Bypass pump sizes, capacity, number of each size to be on site, including spare pump, and power requirements.

h. Calculations of static lift, friction losses, and flow velocity.

i. pump curves showing pump operating range

j. Standby power generator size and location.

k. Downstream discharge plan.

l. Calculations for selection of bypass pumping pump size.

m. Method of noise control for each pump and/or generator.

n. Method of protecting discharge manholes or structures from erosion and damage.

o. Schedule for installation and maintenance of bypass pumping lines.

p. Detailed cost proposal to install, monitor, operate, maintain and remove bypass pumping for the duration of the work

C. Submittals Prior to Construction

1. Implementation Plan describing the installation, including the following:

a. Names of key personnel (project manager, foreman, head supervisor, and top five carbon fiber installation technicians) scheduled to perform the work and documentation that key personnel have the following qualifications:

i. Completed manufacturer-provided certified applicator training.

ii. Have a minimum of three years of experience in large diameter pipe repair projects using CFRP on at least fifteen projects involving.

iii. Are employed full time by the Applicator.

b. Name of dedicated field QA/QC personnel and documentation they have the following qualifications:

i. Required training by the Manufacturer on the installation of bonded CFRP Systems and are employed full time by the Applicator.

ii. A minimum of three years of experience in large diameter pipe repair projects using CFRP, and has performed the role of QA/QC inspector on at least fifteen projects involving CFRP application in Pipeline confined spaces.

iii. Training on the use of test equipment and procedures.

c. Document(s) indicating the details of the proposed quality control program.

d. Testing program for CFRP system.

e. Surface evaluation procedure.

f. Material testing of CFRP.

g. Method for ensuring that the adhesion of CFRP epoxy will conform to specified and indicated requirements.

h. Methods for repairing defective linings.

i. Contingency plan to meet specified requirements in the event of an interruption to the CFRP placement.

j. A detailed site-specific Safety Plan per AWWA C305.

k. Detailed confined space permit

l. All required bonds

D. Record Keeping During Construction:

1. Maintain and submit daily logs of lining operations, including lengths of pipe segments lined and duration of application. Have available for NTMWD’s review no later than the beginning of the following working day.

2. Maintain mark-ups of original pipeline record drawings.

E. Submittal After Project Close-Out:

1. Submit a completed QA/QC report describing the inspection of the installation in which documents all inspection steps. All quality control forms completed throughout the construction, including information on the products and installation process used, documentation of post-installation corrective actions, if any, and test results, described in Section 4 of this specification. All reports and documents shall include completion dates and the name(s) and signature(s) of the dedicated QA/QC personnel who prepared them.

2. Marked-up Drawings indicating as-built condition of the installed CFRP System including any changes or deviations from the contract documents

3. Provide a warranty for the completed work as outlined in Section 4.05.A of this specification.

4. Mark-ups of pipeline record drawings and lay drawings. Details showing location and tie-ins.

PART 2

2.01 PRODUCTS CARBON FIBER LINING SYSTEM

A. The CFRP System shall consist of an epoxy primer, thickened epoxy, unidirectional carbon fabric, bidirectional glass fabric, impregnating epoxy resin, and topcoat. Resin types other than epoxy (e.g., polyester, vinyl ester) shall not be used as any of these components.

B. Use composite materials for the CFRP system from a single manufacturer and ensure compatibility.

C. The method of application of the FRP layers shall be the wet lay-up method only. Pre-cured laminates or the dry lay-up method shall not be permitted. Wet lay-up fabric shall be impregnated with resin using saturating machine that produces uniform wetting process.

D. The proposed CFRP System shall satisfy all testing requirements and acceptance criteria listed in Section 1.04.A. Material not complying with these requirements and criteria shall be rejected.