2-2. REQUIRED ATTACHMENT A - PRICE SCHEDULE.xlsx
XLSX spreadsheet 13 KB Posted
- Attached to
- Substation Battery Replacement
- Solicitation number
- IFB-015-26-RM
- Issued by
- Leon County, Florida
About this file
This is a Price Schedule Attachment A for a substation battery replacement procurement issued by the City of Tallahassee, Florida. The City seeks to replace several existing 125VDC nicad substation battery strings used in switchgear applications, with approximately two battery banks per year anticipated for replacement over the next three to five years. The bid is structured based on two battery banks, with each bank requiring 94 cells. The solicitation includes three line items: Saft SBM138-2 NiCad cells with hardware and connection cables (47 units), a Saft SL2290 2-step non-seismic battery rack (1 unit), and factory commissioning of the 125VDC battery string prior to shipment (1 unit). All items must be delivered to the Utility Supply Center at 2641 Municipal Way, Tallahassee, Florida 32304, with delivery available Monday through Friday from 9:00 a.m. to 3:30 p.m. The bid must include recycling services for the existing battery banks.
All prices are firm-fixed and must include labor, supervision, materials, supplies, equipment, tools, transportation, handling, and applicable taxes unless itemized separately. Delivery terms are F.O.B. Utility Supply Center, with all freight and handling fees included in the quoted prices. The City of Tallahassee is exempt from Florida excise taxes on materials and appliances; however, respondents are not exempt from Florida Sales Tax on materials and services. In the event of a discrepancy between unit cost and total price calculations, unit cost will prevail. Bidders must be able to bid on all items specified in the schedule. The contractor certifies that they have reviewed the entire solicitation and associated attachments and are duly authorized to execute the bid and bind the contractor to the terms and conditions of the contract.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1-1. IFB-015-25-RM - SEC 1,2,3 SUBSTATION BATTERY REPLACEMENTS.docx | DOCX document | |
| 6-6. REQUIRED Certification of a Drug Free Workplace (1).pdf | ||
| 9-9. REQUIRED Local Vendor Affidavit.docx | DOCX document | |
| 5-5.REQUIRED HUMAN TRAFFICKING AFFIDAVIT.pdf | ||
| 3-3. Standard Contract Template 2025.docx | DOCX document | |
| 10-10. REQUIRED Representations Certifications.docx | DOCX document | |
| 8-8. REQUIRED Vendor Conflict of Interest.docx | DOCX document | |
| 7-7. REQUIRED Non Collusion Affidavit of Respondent.docx | DOCX document | |
| 4-4. REQUIRED Responsible Vendor Review Form.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
ATTACHMENT A
BID PRICE SCHEDULE
(Bonfire Line Item 1)
| Name of Company: |
| Contact Person: |
| Email Address: |
| Authorized Signature: |
THE CONTRACTOR AGREES --
To furnish the below listed items of supplies and/or services, awarded in whole or in part by the City, at the price set for each item offered by the Contractor, in accordance with the terms and conditions of its bid submission. Therefore, bidders must be able to bid on all items specified in this Section.
PRICE RELATED FACTORS--
1.The price set for each item is a "firm-fixed" price, and inclusive of all labor, supervision, materials, supplies, equipment, tools, transportation, handling, assessments, fees, and taxes, unless any of these factors are listed below as a separate line item.
2. Delivery shall be "F.O.B Utility Supply Center, 2641 Municipal Way, Tallahassee, FL". The price set for each item shall include all freight/handling fees, and 3.The Contractor is not exempt from the Florida Sales Tax on materials or services.
| NOTES: | |
| 1. | PRICE TAX EXEMPT - The Respondent(s) will not be exempt from the Florida Sales Tax on materials and services. The City is exempt from the Florida excise taxes on materials, appliances, etc. |
| 2. | IN THE EVENT OF AN ERROR IN TOTAL PRICE, UNIT COST WILL PREVAIL. |
| ITEM No. | DESCRIPTION | QUANITY | UNIT | UNIT PRICE | TOTAL |
| 001 | Saft SBM138-2 NiCad cells with hardware, connection cables, and no-ox grease (125VDC battery bank using 94 cells) | 47 | EA | $ - 0 | |
| 002 | Saft SL2290 2-step non-seismic battery rack | 1 | EA | $ - 0 | |
| 003 | Factory commissioning charge of 125VDC battery string prior to shipment | 1 | EA | $ - 0 | |
| Total Cost | $ - 0 | ||||
| CERTIFICATION OF CONTRACTOR |
In response to the solicitation, I, the undersigned representative of the named contractor, hereby certify and represent as follows --
| 1. | That I have read and examined the solicitation in full and all attachments thereto, and that I have satisfied myself with respect to any questions I have regarding the solicitation; and |
| 2. | That I am duly authorized by the named contractor to execute the bid and associated contract intending to bind the contractor to the City as stated in those documents; and |
| 3. | That, if awarded the subject contract, the contractor will satisfactorily perform all work under that contract in strict accordance with its terms and conditions. |
File details come from the government source that posted it. Updated .