Construction Agreement and Bonds Summary
This is a Construction Agreement document executed between the City of McKinney, Texas, and a contractor for the Intersection Capacity Improvements project (FY 23) in Collin County. The agreement establishes the terms, conditions, and requirements for completing construction work in accordance with the North Central Texas Council of Governments (NCTCOG) Fifth Edition (2023) Public Works Construction Standards. The contractor must begin work within ten calendar days of receiving a written Notice to Proceed and complete all work within a specified timeframe outlined in the notice. The contract incorporates multiple documents in order of precedence: the Construction Agreement itself, authorized change orders, addenda, Special Conditions, Technical Specifications and Construction Drawings, standard construction details, NCTCOG Specifications, written notice to proceed, the contractor's bid proposal, performance/payment/maintenance bonds, and any other bid materials distributed by the City.
The agreement establishes a payment structure whereby the contractor submits progress payment requests based on completed work value, with the City withholding retainage according to contract amount tiers: 15 percent for contracts up to $25,000, 10 percent for $25,000 to $400,000, and 5 percent for contracts exceeding $400,000. The contractor must provide Commercial General Liability insurance with minimum limits of $2,000,000 per occurrence and $4,000,000 general aggregate, Workers' Compensation insurance with Texas statutory limits, Business Automobile Liability insurance with $1,000,000 minimum combined single limit, and Builder's Risk Insurance at 100 percent of project completed value. Performance, payment, and maintenance bonds must each equal 100 percent of the total bid price, with the maintenance bond covering a two-year warranty period from project acceptance. The contractor is required to comply with Texas Government Code requirements including Certificate of Interested Parties (Form 1295) filing, Israel boycott verification, energy company boycott verification, and firearm entity non-discrimination verification. Final payment is withheld until the contractor provides original lien releases from all subcontractors, redline as-built construction plans, surety consent to final payment, and other required closeout documentation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1-05 Bid Bond.pdf | ||
| 6-03 Plans.pdf | ||
| 5-02 Bid Proposal.pdf | ||
| 3-01 Construction Specifcations.pdf | ||
| 4-04 Required Forms Fillable.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONSTRUCTION AGREEMENT
THE STATE OF TEXAS )
) KNOW ALL MEN BY THESE PRESENTS:
COUNTY OF COLLIN )
PROJECT NAME
Project No.: __ XXXX Bid No.: XX-XX-XX
This Construction Agreement (the "Agreement") is made by and between ________________________________, a ____________, (the "Contractor") and the City of McKinney, Texas, a municipal corporation (the "Owner"). For and in consideration of the payment, agreements and conditions hereinafter mentioned, and under the conditions expressed in the bonds herein, Contractor hereby agrees to complete the construction of improvements described as follows:
PROJECT NAME, Project Number __ XXXX in the City of McKinney, Texas, and all extra work in connection therewith, under the terms as stated in the North Central Texas Council of Governments (NCTCOG) Fifth Edition (2023) of the Public Works Construction Standards - North Central Texas as it may be amended from time to time (hereinafter called "NCTCOG Specifications"), and under the terms of the Special Conditions of this Contract; and at his, her or their own proper cost and expense to furnish all superintendence, labor, insurance, equipment, tools and other accessories and services necessary to complete the said construction in accordance with all the Contract Documents, incorporated herein as if written word for word, and in accordance with the Plans, which include all maps, plats, blueprints, and other drawings and printed or written explanatory manner therefore, and the Specifications as prepared by City of McKinney or its consultant hereinafter called Engineer, who has been identified by the endorsement of the Contractor's written proposal, these General Provisions of the NCTCOG Specifications, the Special Conditions of this Contract, the payment, performance, and maintenance bonds hereto attached; all of which are made a part hereof and collectively evidence and constitute the entire Contract.
A. Contract Documents and Order of Precedence
The Contract Documents shall consist of the following documents:
1. this Construction Agreement;
2. properly authorized change orders;
3. any listed and numbered addenda;
4. the Special Conditions;
5. Technical Specifications & Construction Drawings;
6. the OWNER's Standard Construction Details;
7. the Fifth Edition (2023) of the Public Works Construction Standards - North Central Texas as amended and published by the North Central Texas Council of Governments, as amended by the Owner (collectively, the "NCTCOG Specifications ");
8. the OWNER’s written notice to proceed to the CONTRACTOR;
9. the Contractor’s Bid Proposal;
10. the Performance, Payment, and Maintenance Bonds; and,
11. any other bid materials distributed by the Owner that relate to the Project.
These Contract Documents are incorporated by reference into this Construction Agreement as if set out here in their entirety. The Contract Documents are intended to be complementary; what is called for by one document shall be as binding as if called for by all Contract Documents. It is specifically provided, however, that in the event of any inconsistency in the Contract Documents, the inconsistency shall be resolved by giving precedence to the Contract Documents in the order in which they are listed herein above. If, however, there exists a conflict or inconsistency between the Technical Specifications and the Construction Drawings it shall be the Contractor’s obligation to seek clarification as to which requirements or provisions control before undertaking any work on that component of the project. Should the Contractor fail or refuse to seek a clarification of such conflicting or inconsistent requirements or provisions prior to any work on that component of the project, the Contractor shall be solely responsible for the costs and expenses - including additional time - necessary to cure, repair and/or correct that component of the project.
B. Total of Payments Due Contractor
For performance of the Work in accordance with the Contract Documents, the Owner shall pay the Contractor in current funds an amount not to exceed __________________________ Dollars and _____ cents ($ _____________). This amount is subject to adjustment by change order in accordance with the Contract Documents.
C. Dates to Start and Complete Work
Contractor shall begin work within ten (10) calendar days after receiving a written Notice to Proceed or written Work Order from the Owner. All Work required under the Contract Documents shall be completed within XXX calendar days after the date of the Notice to Proceed for the base bid.
Under this Construction Agreement, all references to “day” are to be considered “calendar days” unless noted otherwise.
D. CONTRACTOR'S INDEMNITY TO THE OWNER AND OTHERS
CONTRACTOR DOES HEREBY AGREE TO WAIVE ALL CLAIMS, RELEASE,
INDEMNIFY, DEFEND AND HOLD HARMLESS THE CITY OF MCKINNEY (OWNER)
TOGETHER WITH ITS MAYOR AND CITY COUNCIL AND ALL OF ITS OFFICIALS,
OFFICERS, AGENTS AND EMPLOYEES, IN BOTH THEIR PUBLIC AND PRIVATE
CAPACITIES, FROM AND AGAINST ANY AND ALL CITATIONS, CLAIMS, COSTS,
DAMAGES, DEMANDS, EXPENSES, FINES, JUDGMENTS, LIABILITY, LOSSES,
PENALTIES, SUITS OR CAUSES OF ACTION OF EVERY KIND INCLUDING ALL EXPENSES
OF LITIGATION AND/OR SETTLEMENT, COURT COSTS AND ATTORNEY FEES WHICH
MAY ARISE BY REASON OF INJURY TO OR DEATH OF ANY PERSON OR FOR LOSS OF,
DAMAGE TO, OR LOSS OF USE OF ANY PROPERTY OCCASIONED BY ERROR,
OMISSION, OR NEGLIGENT ACT OF CONTRACTOR, ITS SUBCONTRACTORS, ANY
OFFICERS, AGENTS OR EMPLOYEES OF CONTRACTOR OR ANY SUBCONTRACTORS,
INVITEES, AND ANY OTHER THIRD PARTIES OR PERSONS FOR WHOM OR WHICH
CONTRACTOR IS LEGALLY RESPONSIBLE, IN ANY WAY ARISING OUT OF, RELATING
TO, RESULTING FROM, OR IN CONNECTION WITH THE PERFORMANCE OF THIS
CONTRACT, AND CONTRACTOR WILL AT HIS OR HER OWN COST AND EXPENSE
DEFEND AND PROTECT CITY OF MCKINNEY (OWNER) FROM ANY AND ALL SUCH
CLAIMS AND DEMANDS.
CONTRACTOR DOES HEREBY AGREE TO WAIVE ALL CLAIMS, RELEASE,
INDEMNIFY, DEFEND AND HOLD HARMLESS CITY OF MCKINNEY (OWNER) TOGETHER
WITH ITS MAYOR AND CITY COUNCIL AND ALL OF ITS OFFICIALS, OFFICERS, AGENTS,
AND EMPLOYEES, FROM AND AGAINST ANY AND ALL CITATIONS, CLAIMS, COSTS,
DAMAGES, DEMANDS, EXPENSES, FINES, JUDGMENTS, LIABILITY, LOSSES,
PENALTIES, SUITS OR CAUSES OF ACTION OF EVERY KIND INCLUDING ALL EXPENSES
OF LITIGATION AND/OR SETTLEMENT, COURT COSTS AND ATTORNEYS FEES FOR
INJURY OR DEATH OF ANY PERSON OR FOR LOSS OF, DAMAGES TO, OR LOSS OF USE
OF ANY PROPERTY, ARISING OUT OF OR IN CONNECTION WITH THE PERFORMANCE
OF THIS CONTRACT. SUCH INDEMNITY SHALL APPLY WHETHER THE CITATIONS,
CLAIMS, COSTS, DAMAGES, DEMANDS, EXPENSES, FINES, JUDGMENTS, LIABILITY,
LOSSES, PENALTIES, SUITS OR CAUSES OF ACTION ARISE IN WHOLE OR IN PART
FROM THE NEGLIGENCE OF THE CITY OF MCKINNEY (OWNER), ITS MAYOR AND CITY
COUNCIL, OFFICERS, OFFICIALS, AGENTS OR EMPLOYEES. IT IS THE EXPRESS
INTENTION OF THE PARTIES HERETO THAT THE INDEMNITY PROVIDED FOR IN THIS
PARAGRAPH IS INDEMNITY BY CONTRACTOR TO INDEMNIFY AND PROTECT CITY OF
MCKINNEY (OWNER) FROM THE CONSEQUENCES OF CITY OF MCKINNEY’S (OWNER'S)
OWN NEGLIGENCE, WHETHER THAT NEGLIGENCE IS A SOLE OR CONCURRING CAUSE
OF THE INJURY, DEATH OR DAMAGE.
IN ANY AND ALL CLAIMS AGAINST ANY PARTY INDEMNIFIED HEREUNDER BY
ANY EMPLOYEE OF THE CONTRACTOR, ANY SUB-CONTRACTOR, ANYONE DIRECTLY
OR INDIRECTLY EMPLOYED BY ANY OF THEM OR ANYONE FOR WHOSE ACTS ANY OF
THEM MAY BE LIABLE, THE INDEMNIFICATION OBLIGATION HEREIN PROVIDED SHALL
NOT BE LIMITED IN ANY WAY BY ANY LIMITATION ON THE AMOUNT OR TYPE OF
DAMAGES, COMPENSATION OR BENEFITS PAYABLE BY OR FOR THE CONTRACTOR OR
ANY SUB-CONTRACTOR UNDER WORKMEN'S COMPENSATION OR OTHER EMPLOYEE
BENEFIT ACTS.
INDEMNIFIED ITEMS SHALL INCLUDE ATTORNEYS' FEES AND COSTS, COURT
COSTS, AND SETTLEMENT COSTS. INDEMNIFIED ITEMS SHALL ALSO INCLUDE ANY
EXPENSES, INCLUDING ATTORNEYS' FEES AND EXPENSES, INCURRED BY AN
INDEMNIFIED INDIVIDUAL OR ENTITY IN ATTEMPTING TO ENFORCE THIS INDEMNITY.
In its sole discretion, the Owner shall have the right to approve counsel to be retained by Contractor in fulfilling its obligation to defend and indemnify the Owner. Contractor shall retain approved counsel for the Owner within seven (7) business days after receiving written notice from the Owner that it is invoking its right to indemnification under this Construction Agreement. If Contractor does not retain counsel for the Owner within the required time, then the Owner shall have the right to retain counsel and the Contractor shall pay these attorneys' fees and expenses.
The Owner retains the right to provide and pay for any or all costs of defending indemnified items, but it shall not be required to do so. To the extent that Owner elects to provide and pay for any such costs, Contractor shall indemnify and reimburse Owner for such costs.
(Please note that this “broad-form” indemnification clause is not prohibited by Chapter 151 of the Texas Insurance Code as it falls within one of the exclusions contained in Section 151.105 of the Texas Insurance Code.)
E. Insurance Requirements
1. Before commencing work, the contractor shall, at its own expense, procure, pay for and maintain the following insurance written by companies approved by the state of Texas and acceptable to the City of McKinney. The contractor shall furnish to the City of McKinney Procurement Services Manager certificates of insurance executed by the insurer or its authorized agent stating coverages, limits, expiration dates and compliance with all applicable required provisions. Certificates shall reference the project/contract number and be addressed as follows:
City of McKinney c/o Procurement Services P O Box 517 McKinney, TX 75070
a) Commercial General Liability insurance, including, but not limited to Premises/Operations, Personal & Advertising Injury, Products/Completed Operations, Independent Contractors and Contractual Liability, with minimum limits of $2,000,000 per-occurrence and $4,000,000 general aggregate. Coverage must be written on an occurrence form. The General Aggregate shall apply on a per project basis.
b) Workers’ Compensation insurance with Texas statutory limits; and Employer’s Liability coverage with minimum limits for bodily injury: a) by accident, $1,000,000 each accident, b) by disease, $1,000,000 per employee with a per policy aggregate of $1,000,000.
c) Business Automobile Liability insurance covering owned, hired and non-owned vehicles, with a minimum combined single limit of $1,000,000.
d) Builder’s Risk Insurance providing All-Risk coverage including Flood (if located in a flood zone) in an amount equal to one hundred percent (100%) of the completed value of the project in question. The policy shall be written on a Completed Value Form, including materials delivered and labor performed for the project. The policy shall list the City of McKinney, its officials, employees and officers as loss payee as their interests may appear.
2. With reference to the foregoing required insurance, the contractor agrees to the following:
a) A waiver of subrogation in favor of City of McKinney, its officials, employees, and officers shall be contained in the Workers’ Compensation insurance policy.
b) The City of McKinney, its officials, employees and officers shall be covered as additional insureds on the Commercial General Liability and Business Automobile Liability policies.
c) Policies of insurance shall not be cancelled non-renewed, terminated, or materially changed unless and until thirty (30) days’ notice has been given to City of McKinney.
3. The total limits required may be satisfied by any combination of primary, excess or umbrella liability insurance provided all policies comply with all requirements. The contractor may maintain reasonable deductibles, subject to approval by the City of McKinney
4. All insurance shall be purchased from insurance companies that meet a financial rating of A-VI or better as assigned by A.M. Best Company or equivalent.
5. The contractor shall require any sub-contractors and other persons doing business with or for the contractor related to the work to maintain at least the insurance as required, or their liability shall be covered by the contractor.
6. The Contractor agrees to comply with all applicable provisions of Texas Administrative Code regarding building or construction contracts with governmental entities and the contractual requirements.
a) Certain language must be included in this Construction Agreement and in the Contractor’s contracts with subcontractors and others relating to the work;
b) the Contractor is required to submit to the City certificates of coverage for its employees and for all others providing services relating to the work until all project work is completed; and
c) the Contractor is required to post certain notices at job sites.
F. Workers' Compensation Insurance Coverage
1. Definitions:
Certificate of coverage ("certificate")- A copy of a certificate of insurance, a certificate of authority to self-insure issued by the commission, or a coverage agreement (TWCC-81, TWCC-82, TWCC-83, or TWCC-84), showing statutory workers' compensation insurance coverage for the person's or entity's employees providing services on a project, for the duration of the project.
Duration of the project - includes the time from the beginning of the work on the project until the Contractor's/person's work on the project has been completed and accepted by the governmental entity.
Persons providing services on the project ("subcontractor" in §406.096) - includes all persons or entities performing all or part of the services the Contractor has undertaken to perform on the project, regardless of whether that person contracted directly with the Contractor and regardless of whether that person has employees.
This includes, without limitation, independent contractors, subcontractors, leasing companies, motor carriers, owner-operators, employees of any such entity, or employees of any entity which furnishes persons to provide services on the project.
"Services" include, without limitation, providing, hauling, or delivering equipment or materials, or providing labor, transportation, or other service related to a project.
"Services" does not include activities unrelated to the project, such as food/beverage vendors, office supply deliveries, and delivery of portable toilets.
2. The Contractor shall provide coverage, based on proper reporting of classification codes and payroll amounts and filing of any coverage agreements, which meets the statutory requirements of Texas Labor Code, Section 401.011(44) for all employees of the Contractor providing services on the project, for the duration of the project.
3. The Contractor must provide a certificate of coverage to the governmental entity prior to being awarded the contract.
4. If the coverage period shown on the Contractor's current certificate of coverage ends during the duration of the project, the Contractor must, prior to the end of the coverage period, file a new certificate of coverage with the governmental entity showing that coverage has been extended.
5. The Contractor shall obtain from each person providing services on a project, and provide to the governmental entity:
(a) a certificate of coverage, prior to that person beginning work on the project, so the governmental entity will have on file certificates of coverage showing coverage for all persons providing services on the project; and
(b) no later than seven days after receipt by the Contractor, a new certificate of coverage showing extension of coverage, if the coverage period shown on the current certificate of coverage ends during the duration of the project.
6. The Contractor shall retain all required certificates of coverage for the duration of the project and for one year thereafter.
7. The Contractor shall notify the governmental entity in writing by certified mail or personal delivery, within 10 days after the Contractor knew or should have known, of any change that materially affects the provision of coverage of any person providing services on the project.
8. The Contractor shall post on each project site a notice, in the text, form and manner prescribed by the Texas Workers' Compensation Commission, informing all persons providing services on the project that they are required to be covered, and stating how a person may verify coverage and report lack of coverage.
9. The Contractor shall contractually require each person with whom it contracts to provide services on a project, to:
(a) provide coverage, based on proper reporting of classification codes and payroll amounts and filing of any coverage agreements, which meets the statutory requirements of Texas Labor Code, Section 401.011(44) for all of its employees providing services on the project, for the duration of the project;
(b) provide to the Contractor, prior to that person beginning work on the project, a certificate of coverage showing that coverage is being provided for all employees of the person providing services on the project, for the duration of the project;
(c) provide the Contractor, prior to the end of the coverage period, a new certificate of coverage showing extension of coverage, if the coverage period shown on the current certificate of coverage ends during the duration of the project;
(d) obtain from each other person with whom it contracts, and provide to the Contractor:
(1) a certificate of coverage, prior to the other person beginning work on the project; and
(2) a new certificate of coverage showing extension of coverage, prior to the end of the coverage period, if the coverage period shown on the current certificate of coverage ends during the duration of the project;
(e) retain all required certificates of coverage on file for the duration of the project and for one year thereafter;
(f) notify the governmental entity in writing by certified mail or personal delivery, within 10 days after the person knew or should have known, of any change that materially affects the provision of coverage of any person providing services on the project; and
(g) contractually require each person with whom it contracts, to perform as required by paragraphs (1) - (7), with the certificates of coverage to be provided to the person for whom they are providing services.
10. By signing this contract or providing or causing to be provided a certificate of coverage, the Contractor is representing to the governmental entity that all employees of the Contractor who will provide services on the project will be covered by workers' compensation coverage for the duration of the project, that the coverage will be based on proper reporting of classification codes and payroll amounts, and that all coverage agreements will be filed with the appropriate insurance carrier or, in the case of a self-insured, with the commission's Division of Self-Insurance Regulation. Providing false or misleading information may subject the Contractor to administrative penalties, criminal penalties, civil penalties, or other civil actions.
11. The Contractor's failure to comply with any of these provisions is a breach of contract by the Contractor which entitles the governmental entity to declare the contract void if the Contractor does not remedy the breach within ten days after receipt of notice of breach from the governmental entity.
G. Performance, Payment and Maintenance Bonds
The Contractor shall procure and pay for performance and payment bonds applicable to the work in the amount of the total bid price. The Contractor shall also procure and pay for a maintenance bond applicable to the work in the amount of one hundred percent (100%) of the total bid price. The period of the Maintenance Bond shall be two years from the date of acceptance of all work done under the contract, to cover the guarantee as set forth in the Special Conditions.
The performance, payment and maintenance bonds shall be issued in the form attached to this Construction Agreement as Exhibits B, C and D. Other performance, payment and maintenance bond forms shall not be accepted. Among other things, these bonds shall apply to any work performed during the two-year warranty period after acceptance as described in this Construction Agreement.
The performance, payment and maintenance bonds shall be issued by a corporate surety, acceptable to and approved by the City, authorized to do business in the State of Texas, pursuant to Chapter 2253 of the Texas Government Code. Further, the Contractor shall supply capital and surplus information concerning the surety and reinsurance information concerning the performance, payment and maintenance bonds upon City request. In addition to the foregoing requirements, if the amount of the bond exceeds One Hundred Thousand Dollars ($100,000) the bond must be issued by a surety that is qualified as a surety on obligations permitted or required under federal law as indicated by publication of the surety’s name in the current U.S. Treasury Department Circular 570. In the alternative, an otherwise acceptable surety company (not qualified on federal obligations) that is authorized and admitted to write surety bonds in Texas must obtain reinsurance on any amounts in excess of One Hundred Thousand Dollars ($100,000) from a reinsurer that is authorized and admitted as a reinsurer in Texas who also qualifies as a surety or reinsurer on federal obligations as indicated by publication of the surety’s or reinsurer’s name in the current U.S. Treasury Department Circular 570.
H. Progress Payments and Retainage
As it completes portions of the Work, the Contractor may request progress payments from the Owner. Progress payments shall be made by the Owner based on the Owner's estimate of the value of the Work properly completed by the Contractor since the time the last progress payment was made. The "estimate of the value of the work properly completed" shall include the net invoice value of acceptable, non-perishable materials actually delivered to and currently at the job site only if the Contractor provides to the Owner satisfactory evidence that material suppliers have been paid for these materials.
No progress payment shall be due to the Contractor until the Contractor furnishes to the Owner:
1. copies of documents reasonably necessary to aid the Owner in preparing an estimate of the value of Work properly completed;
2. full or partial releases of liens, including releases from subcontractors providing materials or delivery services relating to the Work, in a form acceptable to the Owner releasing all liens or claims relating to goods and services provided up to the date of the most recent previous progress payment;
3. an updated and current schedule clearly detailing the project’s critical path elements in accordance with SC.11 CONSTRUCTION SCHEDULE; and
4. any other documents required under the Contract Documents.
Progress payments shall not be made more frequently than once every thirty (30) calendar days unless the Owner determines that more frequent payments are appropriate. Further, progress payments are to be based on estimates and these estimates are subject to correction through the adjustment of subsequent progress payments and the final payment to Contractor. If the Owner determines after final payment that it has overpaid the Contractor, then Contractor agrees to pay to the Owner the overpayment amount specified by the Owner within thirty (30) calendar days after it receives written demand from the Owner.
The fact that the Owner makes a progress payment shall not be deemed to be an admission by the Owner concerning the quantity, quality or sufficiency of the Contractor's work.
Progress payments shall not be deemed to be acceptance of the Work, nor shall a progress payment release the Contractor from any of its responsibilities under the Contract Documents.
After determining the amount of a progress payment to be made to the Contractor, the Owner shall withhold a percentage of the progress payment as retainage. The amount of retainage withheld from each progress payment shall be set depending upon the value of the Contract Work on the effective date of the Contract:
Contract Amount Retainage Percentage
Up to $25,000 15%
$25,000 to $400,000 10%
Over $400,000 5%
Retainage shall be withheld and may be paid to:
a. ensure proper completion of the Work. The Owner may use retained funds to pay replacement or substitute contractors to complete unfinished or defective work;
b. ensure timely completion of the Work. The Owner may use retained funds to pay liquidated damages; and
c. provide an additional source of funds to pay claims for which the Owner is entitled to indemnification from Contractor under the Contract Documents.
Retained funds shall be held by the Owner in accounts that shall not bear interest.
Retainage not otherwise withheld in accordance with the Contract Documents shall be returned to the Contractor as part of the final payment.
I. Withholding Payments to Contractor
The Owner may withhold payment of some or all of any progress or final payment that would otherwise be due if the Owner determines, in its discretion, that the Work has not been performed in accordance with the Contract Documents. The Owner may use these funds to pay replacement or substitute contractors to complete unfinished or defective Work.
The Owner may withhold payment of some or all of any progress or final payment that would otherwise be due if the Owner determines, in its discretion, that it is necessary and proper to provide an additional source of funds to pay claims for which the Owner is entitled to indemnification from Contractor under the Contract Documents.
Amounts withheld under this section shall be in addition to any retainage.
J. Acceptance of the Work
When the Work is completed, the Contractor shall request that the Owner perform a final inspection. The Owner shall inspect the Work. If the Owner determines that the Work has been completed in accordance with the Contract Documents, it shall issue a written notice of acceptance of the Work. If the Owner determines that the Work has not been completed in accordance with the Contract Documents, then it shall provide the Contractor with a verbal or written list of items to be completed before another final inspection shall be scheduled.
It is specifically provided that Work shall be deemed accepted on the date specified in the Owner's written notice of acceptance of the Work. The Work shall not be deemed to be accepted based on "substantial completion" of the Work, use or occupancy of the Work, or for any reason other than the Owner's written Notice of Acceptance. Further, the issuance of a certificate of occupancy for all or any part of the Work shall not constitute a Notice of Acceptance for that Work.
In its discretion, the Owner may issue a Notice of Acceptance covering only a portion of the Work. In this event, the notice shall state specifically what portion of the Work is accepted.
K. Acceptance of Erosion Control Measures
When the erosion control measures have been completed, the Contractor shall request that the Owner perform a final inspection. The Owner shall inspect the Work. If the Owner determines that the Work has been completed in accordance with the Contract Documents and per TPDES General Construction Permit, it shall issue a written Notice of Acceptance of the Work.
If the Owner determines that the Work has not been completed in accordance with the Contract Documents or TPDES General Construction Permit, then it shall provide the Contractor with a verbal or written list of items to be completed before another final inspection shall be scheduled.
L. Final Payment
After all Work required under the Contract Documents has been completed, inspected, and accepted, the City shall calculate the final payment amount promptly after necessary measurements and computations are made. The final payment amount shall be calculated to:
1. include the estimate of the value of Work properly completed since the date of the most recent previous progress payment;
2. correct prior progress payments; and
3. include retainage or other amounts previously withheld that are to be returned to Contractor, if any.
Final payment to the Contractor shall not be due until the Contractor provides original full releases of liens from the Contractor and its subcontractors, or other evidence satisfactory to the Owner to show that all sums due for labor, services, and materials furnished for or used in connection with the Work have been paid or shall be paid with the final payment. To ensure this result, Contractor consents to the issuance of the final payment in the form of joint checks made payable to Contractor and others. The Owner may but is not obligated to issue final payment using joint checks.
Final payment to the Contractor shall not be due until the Contractor has supplied to the Owner original copies of all documents that the Owner determines are reasonably necessary to ensure both that the final payment amount is properly calculated, and that the Owner has satisfied its obligation to administer the Construction Agreement in accordance with applicable law. The following documents shall, at a minimum, be required to be submitted prior to final payment being due: redline as-built construction plans; consent of surety to final payment; public infrastructure inventory; affidavit of value for public infrastructure; and final change order(s). “Redline as-built construction plans” shall include, but are not limited to markups for change orders, field revisions, and quantity overruns as applicable. The list of documents contained in this provision is not an exhaustive and exclusive list for every project performed pursuant to these Contract Documents and Contractor shall provide such other and further documents as may be requested and required by the Owner to close out a particular project.
Subject to the requirements of the Contract Documents, the Owner shall pay the Final Payment within thirty (30) calendar days after the date specified in the Notice of Acceptance. This provision shall apply only after all Work called for by the Contract Documents has been accepted.
M. Contractor’s Warranty
For a two-year period after the date specified in a written notice of acceptance of Work, Contractor shall provide and pay for all labor and materials that the Owner determines are necessary to correct all defects in the Work arising because of defective materials or workmanship supplied or provided by Contractor or any subcontractor. This shall also include areas of vegetation that did meet TPDES General Construction Permit during final close out but have since become noncompliant.
Forty-five (45) to sixty (60) calendar days before the end of the two-year warranty period, the Owner may make a warranty inspection of the Work. The Owner shall notify the Contractor of the date and time of this inspection so that a Contractor representative may be present. After the warranty inspection, and before the end of the two-year warranty period, the Owner shall mail to the Contractor a written notice that specifies the defects in the Work that are to be corrected.
The Contractor shall begin the remedial work within ten (10) calendar days after receiving the written notice from the City. If the Contractor does not begin the remedial work timely or prosecute it diligently, then the Owner may pay for necessary labor and materials to effect repairs and these expenses shall be paid by the Contractor, the performance bond surety, or both.
If the Owner determines that a hazard exists because of defective materials and workmanship, then the Owner may take steps to alleviate the hazard, including making repairs.
These steps may be taken without prior notice either to the Contractor or its surety. Expenses incurred by the Owner to alleviate the hazard shall be paid by the Contractor, the performance bond surety, or both.
Any Work performed by or for the Contractor to fulfill its warranty obligations shall be performed in accordance with the Contract Documents. By way of example only, this is to ensure that Work performed during the warranty period is performed with required insurance and the performance and payment bonds still in effect.
Work performed during the two-year warranty period shall itself be subject to a one-year warranty. This warranty shall be the same as described in this section.
The Owner may make as many warranty inspections as it deems appropriate.
N. Compliance with Laws
The Contractor shall be responsible for ensuring that it and any subcontractors performing any portion of the Work required under the Contract Documents comply with all applicable federal, state, county, and municipal laws, regulations, and rules that relate in any way to the performance and completion of the Work. This provision applies whether or not a legal requirement is described or referred to in the Contract Documents.
Ancillary / Integral Professional Services: In selecting an architect, engineer, land surveyor, or other professional to provide professional services, if any, that are required by the Contract Documents, Contractor shall not do so on the basis of competitive bids but shall make such selection on the basis of demonstrated competence and qualifications to perform the services in the manner provided by Section 2254.004 of the Texas Government Code and shall so certify to the City the Contractor's agreement to comply with this provision with Contractor's Bid Proposal.
Certificate of Interested Parties (Form 1295): In 2015, the Texas Legislature adopted House Bill 1295, which added section 2252.908 of the Government Code. The law states that a governmental entity or state agency may not enter into certain contracts with a business entity unless the business entity submits a disclosure of interested parties to the governmental entity or state agency at the time the business entity submits the signed contract to the governmental entity or state agency. The disclosure requirement applies to a contract entered into on or after January 1, 2016.
Form 1295 Filing Process: The commission has made available on its website a new filing application that must be used to file Form 1295. The Contractor must use the application to enter the required information on Form 1295 and print a copy of the completed form, which will include a certification of filing that will contain a unique certification number. An authorized agent of the Contractor must sign the printed copy of the form. The completed Form 1295 with the certification of filing must be filed with the Owner.
The Owner must notify the commission, using the commission’s filing application, of the receipt of the filed Form 1295 with the certification of filing not later than the 30th day after the http://www.legis.state.tx.us/tlodocs/84R/billtext/html/HB01295F.htm date the contract binds all parties to the contract. The commission will post the completed Form 1295 to its website within seven business days after receiving notice from the Owner.
Form 1295 Availability: Certificate of Interested Parties Form is available from the Texas Ethics Commission website at the following address:
https://www.ethics.state.tx.us/whatsnew/elf_info_form1295.htm
For questions regarding and assistance in filling out this form, please contact the Texas Ethics Commission at 512-463-5800.
Pursuant to the requirements of Texas Government Code Chapter 2271, Contractor hereby affirms and verifies by its signature on this Contract below that Contractor:
(a) does not boycott Israel; and
(b) will not boycott Israel during the term of this Contract.
Chapter 2271 does not apply to (1) a company that is a sole proprietorship; (2) a company that has fewer than ten (10) full-time employees; or (3) a contract that has a value of less than One Hundred Thousand Dollars ($100,000.00). Unless the company is not subject to Chapter 2271 for the reasons stated herein, the signatory executing this contract on behalf of the company verifies by its signature on this Contract that the company does not boycott Israel and will not boycott Israel during the term of this contract.
In accordance with Senate Bill 13, 87th Leg., R.S., to be codified in Chapter 2274, Texas Government Code, a Texas governmental entity may not enter into a contract with a company for the provision of goods or services unless the contract contains a written verification from the company that it:
(a) does not boycott energy companies; and
(b) will not boycott energy companies during the term of the contract.
Chapter 2274 does not apply to (1) a company that has fewer than ten (10) full-time employees; and (2) a contract that has a value of less than One Hundred Thousand Dollars ($100,000.00). Unless the company is not subject to Chapter 2274 for the reasons stated herein, the signatory executing this contract on behalf of the company verifies by its signature on this Contract that the company does not boycott energy companies and will not boycott energy companies during the term of this contract.
In accordance with Senate Bill 19, 87th Leg., R.S., to be codified in Chapter 2274, Texas Government Code, a Texas governmental entity may not enter into a contract with a company for https://www.ethics.state.tx.us/whatsnew/elf_info_form1295.htm the provision of goods or services unless the contract contains a written verification from the company that it:
(a) does not have a practice, policy, guidance, or directive that discriminates against a firearm entity or firearm trade association; and
(b) will not discriminate during the term of the contract against a firearm entity or firearm trade association.
Chapter 2274 does not apply to (1) a company that has fewer than ten (10) full-time employees; and (2) a contract that has a value of less than One Hundred Thousand Dollars ($100,000.00). Unless the company is not subject to Chapter 2274 for the reasons stated herein, the signatory executing this contract on behalf of the company verifies by its signature on this Contract that the company does not discriminate against any firearm entity or firearm trade association and will not discriminate against any firearm entity or firearm trade association during the term of this contract. Notwithstanding the foregoing, such provision does not apply to a governmental entity that:
(a) contracts with a sole-source provider; or
(b) does not receive any bids from a company that is able to provide the required written verification.
O. Other Items
The Contractor shall sign the Construction Agreement, and deliver signed performance, payment and maintenance bonds and proper insurance policy endorsements (and/or other evidence of coverage) within ten (10) calendar days after the Owner makes available to the Contractor copies of the Contract Documents for signature. Two (2) copies of the Contract Documents shall be signed by an authorized representative of the Contractor and returned to the City.
The Construction Agreement "effective date" shall be the date on which the City Council acts to approve the award of the Contract for the Work to Contractor. It is expressly provided, however, that the City Council delegates the authority to the City Manager or their designee to rescind the Contract award to Contractor at any time before the Owner delivers to the Contractor a copy of this Construction Agreement that bears the signature of the City Manager and City Secretary or their authorized designees. The purpose of this provision is to ensure:
1. that Contractor timely delivers to the Owner all bonds and insurance documents;
and
2. that the Owner retains the discretion not to proceed if the City Manager or their designee determines that information indicates that the Contractor was not the lowest responsible bidder or that the Contractor cannot perform all of its obligations under the Contract Documents.
THE CONTRACTOR AGREES THAT IT SHALL HAVE NO CLAIM OR CAUSE OF
ACTION OF ANY KIND AGAINST OWNER, INCLUDING A CLAIM FOR BREACH OF
CONTRACT, NOR SHALL THE OWNER BE REQUIRED TO PERFORM UNDER THE
CONTRACT DOCUMENTS, UNTIL THE DATE THE OWNER DELIVERS TO THE
CONTRACTOR A COPY OF THE CONSTRUCTION AGREEMENT BEARING THE
SIGNATURES JUST SPECIFIED.
The Contract Documents shall be construed and interpreted by applying Texas law.
Exclusive venue for any litigation concerning the Contract Documents shall be Collin County, Texas.
Although the Construction Agreement has been drafted by the Owner, should any portion of the Construction Agreement be disputed, the Owner and Contractor agree that it shall not be construed more favorably for either party.
The Contract Documents are binding upon the Owner and Contractor and shall insure to their benefit and as well as that of their respective successors and assigns.
If City Council approval is not required for the Construction Agreement under applicable law, then the Construction Agreement "effective date" shall be the date on which the City Manager and City Secretary or their designees have signed the Construction Agreement. If the City Manager and City Secretary sign on different dates, then the later date shall be the effective date.
CONTRACTOR: CITY OF MCKINNEY, TEXAS
By: By: PAUL G. GRIMES
Title: Title: City Manager
Date: Date:
Address:
Phone:
Fax:
Address: 222 North Tennessee McKinney, Texas 75069
Phone: (972) 547 - 7500 Fax: (972) 547 - 2607
ATTEST:
EMPRESS DRANE, City Secretary TENITRUS BETHEL, Deputy City Secretary
CONSTRUCTION PERFORMANCE BOND
STATE OF TEXAS )
COUNTY OF COLLIN )
KNOW ALL MEN BY THESE PRESENTS: That ________________________________ whose address is
___________________________________________________________________, hereinafter called Principal, and __________________________________________________________, a corporation organized and existing under the laws of the State of __________________, and fully licensed to transact business in the State of Texas, as Surety, are held and firmly bound unto the
CITY OF McKINNEY, a home-rule municipal corporation organized and existing under the laws of the State of Texas, hereinafter called “Beneficiary”, in the penal sum of
________________________________________ Dollars ($____________) plus fifteen percent
(15%) of the stated penal sum as an additional sum of money representing additional court expenses, attorneys’ fees, and liquidated damages arising out of or connected with the below identified Contract in lawful money of the United States, to be paid in Collin County, Texas, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators and successors, jointly and severally, firmly by these presents. The penal sum of this Bond shall automatically be increased by the amount of any Change Order or Supplemental
Agreement, which increases the Contract price, but in no event shall a Change Order or
Supplemental Agreement, which reduces the Contract price, decrease the penal sum of this
Bond.
THE OBLIGATION TO PAY SAME is conditioned as follows: Whereas, the Principal entered into a certain Contract with the City of McKinney, the Beneficiary, dated on or about the
_________ day of ___________________, A.D. 20____, a copy of which is attached hereto and made a part hereof, to furnish all materials, equipment, labor, supervision, and other accessories necessary for the construction of:
PROJECT NAME, Project Number __ XXXX in the City of McKinney, Texas, as more particularly described and designated in the above-referenced contract such contract being incorporated herein and made a part hereof as fully and to the same extent as if written herein word for word.
NOW, THEREFORE, if the Principal shall well, truly and faithfully perform and fulfill all of the undertakings, covenants, terms, conditions and agreements of said Contract in accordance with the Plans, Specifications and Contract Documents during the original term thereof and any extension thereof which may be granted by the Beneficiary, with or without notice to the Surety, and during the life of any guaranty or warranty required under this Contract, and shall also well and truly perform and fulfill all the undertakings, covenants, terms, conditions and agreements of any and all duly authorized modifications of said Contract that may hereafter be made, notice of which modifications to the Surety being hereby waived; and, if the Principal shall repair and/or replace all defects due to faulty materials and workmanship that appear within a period of one (1) year from the date of final completion and final acceptance of the Work by Owner; and, if the
Principal shall fully indemnify and save harmless the Beneficiary from and against all costs and damages which Beneficiary may suffer by reason of failure to so perform herein and shall fully reimburse and repay Beneficiary all outlay and expense which the Beneficiary may incur in making good any default or deficiency, then this obligation shall be void; otherwise, it shall remain in full force and effect.
PROVIDED FURTHER, that if any legal action were filed on this Bond, exclusive Venue shall lie in Collin County, Texas.
AND PROVIDED FURTHER, that the said Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Contract or to the Work to be performed thereunder or the Plans, Specifications and Drawings, etc., accompanying the same shall in anywise affect its obligation on this Bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the
Contract, or to the Work or to the Specifications.
This Bond is given pursuant to the provisions of Chapter 2253 of the Texas Government
Code, and any other applicable statutes of the State of Texas.
The undersigned and designated agent is hereby designated by the Surety herein as the
Resident Agent in Collin County or Dallas County to whom any requisite notices may be delivered and on whom service of process may be had in matters arising out of such suretyship, as provided by Article 7.19-1 of the Insurance Code, Vernon’s Annotated Civil Statutes of the State of Texas.
IN WITNESS WHEREOF, this instrument is executed in two (2) copies, each one of which shall be deemed an original, this, the ________ day of ________________, 20____.
ATTEST: PRINCIPAL:
Company Name
By: _________________________________ By: ________________________________ Signature Signature
Typed/Printed Name Typed/Printed Name
Title Title
Address Address
City State Zip City State Zip
Phone Fax Phone Fax
[Signatures continued on following page.]
ATTEST: SURETY:
Typed/Printed Name Typed/Printed Name
Title Title
Address Address
City State Zip City State Zip
The Resident Agent of the Surety in Collin County or Dallas County, Texas, for delivery of notice and service of the process is:
NAME:
STREET ADDRESS:
CITY, STATE, ZIP:
NOTE: Date on Page 1 of Performance Bond must be SAME date as Contract. Date on Page 2 of Performance Bond must be AFTER date of Contract. If Resident Agent is not a corporation, give a person’s name.
CONSTRUCTION PAYMENT BOND
COUNTY OF COLLIN )
KNOW ALL MEN BY THESE PRESENTS: That ________________________________ whose address is ___________________________________________________________________, hereinafter called Principal, and
__________________________________________________________, a corporation organized and existing under the laws of the State of __________________, and fully licensed to transact business in the State of Texas, as Surety, are held and firmly bound unto the CITY OF McKINNEY, a home-rule municipal corporation organized and existing under the laws of the State of Texas, hereinafter called “Beneficiary”, in the penal sum of
________________________________________ Dollars ($____________) in lawful money of the United States, to be paid in Collin County, Texas, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators and successors, jointly and severally, firmly by these presents. The penal sum of this Bond shall automatically be increased by the amount of any Change Order or Supplemental Agreement, which increases the Contract price, but in no event shall a Change Order or Supplemental Agreement, which reduces the
Contract price, decrease the penal sum of this Bond.
THE OBLIGATION TO PAY SAME is conditioned as follows: Whereas, the Principal entered into a certain Contract with the City of McKinney, the Owner, dated on or about the __________ day of _________________, A.D. 20___, a copy of which is attached hereto and made a part hereof, to furnish all materials, equipment, labor, supervision, and other accessories necessary for the construction of:
NOW THEREFORE, if the Principal shall well, truly and faithfully perform its duties and make prompt payment to all persons, firms, subcontractors, corporations and claimants supplying labor and/or material in the prosecution of the Work provided for in the above-referenced Contract and any and all duly authorized modifications of said Contract that may hereafter be made, notice of which modification to the Surety is hereby expressly waived, then this obligation shall be void;
otherwise it shall remain in full force and effect.
PROVIDED FURTHER, that if any legal action were filed on this Bond, exclusive venue shall lie in Collin County, Texas.
AND PROVIDED FURTHER, that the said Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Contract, or to the Work performed thereunder, or the Plans, Specifications, Drawings, etc., accompanying the same, shall in anywise affect its obligation on this Bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the Contract, or to the
Work to be performed thereunder.
This Bond is given pursuant to the provisions of Chapter 2253 of the Texas Government
Code, and any other applicable statutes of the State of Texas.
The undersigned and designated agent is hereby designated by the Surety herein as the
Resident Agent in Collin County or…