2-004-Scope Of Work.docx

DOCX document 18 KB Posted

Attached to
TDCJ-Beeville Warehouse-2-Inch Crushed Limestone Work
Solicitation number
IW266697
Issued by
Bastrop County, Texas

About this file

Summary

This Scope of Work document outlines the project requirements for the Texas Department of Criminal Justice (TDCJ) Beeville Warehouse road preparation and limestone base installation project in Beeville, Texas. The project encompasses site clearing and grading, roadway preparation, delivery and installation of 2-inch crushed limestone (57 stone) base material, and final site preparation. The contractor must provide all labor, materials, equipment, transportation, and operational expenses to complete the work, including mechanical clearing using skid steers and motor graders, fine grading and moisture conditioning of the subgrade, spreading and compacting limestone material to proper density specifications, and removal and disposal of excess soil, vegetation, and debris at approved facilities. Required equipment includes motor graders, skid steers, water trucks, rollers, dump trucks, belly dump trailers, and tractor trailers. The final deliverable is a fully graded and compacted roadway base of 2-inch crushed limestone ready for the next phase of construction.

All operating costs are the contractor's responsibility and must be included in the total bid price, encompassing fuel, lubricants, routine maintenance, equipment repairs, tools and consumables, labor, water supply, and miscellaneous expenses necessary for safe and effective project completion. Transportation costs for material delivery, equipment movement, and debris hauling are also included in the contractor's estimate. The contractor must comply with all local, state, and federal regulations related to equipment operation, roadway construction, and material transport, and must maintain safety procedures throughout project execution. No specific response dates, contract terms, award dates, or pricing constraints are identified in the scope of work document.

View the file

Other files

File Type Posted
4-001-IW266697.pdf PDF
1-002-Terms and Conditions (1).pdf PDF
3-003-Drawing.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scope of Work Project: Road Preparation and Installation of 2-Inch Crushed Limestone (57 Stone) Base Location: [Insert Location] Contractor: [Insert Contractor Name] Client: [Insert Client/Agency Name]

1. Project Overview The contractor shall furnish all labor, materials, equipment, transportation, and operational expenses necessary to complete the road preparation, base installation, and material delivery using 2-inch crushed limestone (57 stone). Work includes site clearing, grading, hauling, placement, compaction, and final preparation of the designated roadway.

2. Work Tasks and Responsibilities A. Site Preparation

· Removal and disposal of excess grass, topsoil, dirt, vegetation, roots, rocks, and miscellaneous debris.

· Mechanical clearing using skid steers, motor graders, dump trucks, and other necessary equipment.

· Transportation of removed material to an approved disposal facility.

· Rough grading of roadway area to establish proper elevation and drainage prior to base installation.

B. Roadway Prepping

· Fine grading of the subgrade using a motor grader, ensuring proper crown, slope, and alignment for road stability.

· Moisture conditioning of the subgrade using a water truck to meet compaction requirements.

· Compacting the prepared surface with a roller to achieve required density.

C. Material Delivery

· Supply, transport, and deliver 2-inch crushed limestone 57 stone to the project site.

· Use of belly dump trucks, company work trucks, tractor trailers, and associated trailers for material hauling.

· Delivery scheduling to ensure continuous workflow and avoid construction delays.

D. Material Placement and Installation

· Spreading limestone base material evenly using a motor grader and/or skid steer.

· Watering the limestone material during placement to meet moisture requirements for compaction.

· Compacting limestone with a roller to achieve proper density and structural integrity.

· Final grading and shaping of the limestone base to meet project specifications.

3. Equipment Provided The contractor shall supply all necessary equipment, including but not limited to:

· Motor grader

· Skid steer

· Water truck

· Roller

· Dump truck(s)

· Belly dump trailer

· Tractor trailer

· Work truck and trailer

· Tools and accessories required for grading, compacting, and material handling

4. Operating Costs Included The contractor shall include all operating expenses required to complete the project. These costs include:

· Fuel for all equipment and vehicles

· Engine oil and hydraulic fluids

· Routine maintenance and preventative servicing

· Equipment repairs (minor and incidental)

· Tools, attachments, and consumables

· Tires and wear parts

· Operator labor costs

· Water supply for dust control and compaction

· Any other miscellaneous costs necessary to complete the work safely and effectively

5. Disposal Services

· Hauling and disposal of excess soil, vegetation, grass, debris, and unsuitable materials generated during site preparation.

· Disposal fees at approved facilities included in contractor’s total cost.

6. Transportation Costs All transportation costs associated with:

· Delivery of limestone materials

· Movement of equipment to and from the job site

· Hauling debris and spoil material shall be included in the contractor’s total estimated price.

7. Safety and Compliance

· Contractor shall follow all local, state, and federal regulations related to equipment operation, roadway construction, and material transport.

· Safety procedures must be adhered to at all times.

8. Final Deliverables

· A fully graded and compacted roadway base consisting of 2-inch crushed limestone 57 stone, ready for the next phase of construction.

· Clean worksite with all debris removed.

· Completion report if required by client.