This is a Standard Form 30 Amendment of Solicitation/Modification of Contract for a landscaping and grounds maintenance contract issued by the U.S. Embassy Bangkok, GSO/Procurement. Amendment 0001 modifies multiple sections of the original solicitation (No. 19TH2025Q0036) with specific changes to service requirements:

Key modifications include updated requirements for turf repair, leaf removal, and debris removal. The contractor must repair damaged turf areas, remove leaves and debris daily from various property areas, and replace any turf killed through negligent practices at no additional cost. For the NOB Front Office, the contractor must water and maintain approximately 100 square feet of plants, including exterior balcony and interior potted plants, at least 3 times per week between 6:20-7:00 a.m. The amendment specifies the contractor's responsibilities and exceptions for turf damage, and requires scheduling escorts in advance for plant maintenance services.

View the file

Other files for this federal contract opportunity

Other files attached to Gardening Services, newest first.
File Type Posted
Question and Answer_19TH2025Q0036_Gardening Services.pdf PDF
RFQ no. 19TH2025Q0036.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

Amendment No. 0001 Solicitation No. 19TH2025Q0036

1. SECTION 1, CONTINUATION TO SF-1449, SCHEDULE OF SUPPLIES/SERVICES,

BLOCK 20 is changed by deleting paragraph no. 1.4.5 and replaced as follows:

1.4.5. TURF REPAIR AND RE-ESTABLISHMENT

The Contractor shall, whenever necessary and as part of their responsibility under this contract, repair or restore areas of turf that are damaged by due to improper maintenance, unsuitable soil conditions, pest and or disease infestation, or the operation of vehicles or machinery vehicular traffic, oil and gas, and normal foot traffic by the Contractor or its personnel.

In such cases, the Contractor shall undertake all necessary horticultural practices such as aeration, de-thatching, correction of drainage and or soil erosion issues, or and installation of new seed or sod on areas where grasses are thinning, brown or dead to restore the turf to a healthy and uniform condition consistent with surrounding areas. The damaged area shall be filled in and leveled and then seeded or sodded, and maintained until the turf is fully re-established to conform to adjacent areas, but this does not include the installation of an underground sprinkler system or irrigation system.

The Contractor is not responsible for remedying damages or turf repairing and restoration under the following conditions:

(a) When the damage is caused by the Government or non-contractor personnel

(b) When the damage is the result of unforeseen circumstances (Acts of God or force majeure) and adequate preparatory measures had been taken by the Contractor

(c) When the damage is caused by vehicles which were not operated by the Contractor or its personnel

In all such cases, the Contractor shall promptly notify the COR in writing, provide details of the incident immediately.

2. SECTION 1, CONTINUATION TO SF-1449, SCHEDULE OF SUPPLIES/SERVICES,

BLOCK 20 is changed by deleting paragraph 1.6 and replaced as follows:

1.6. LEAF REMOVAL

The Contractor shall, on a monthly basis, remove leaves, flowers, and pine needles from the properties listed in 1.13 and on a daily basis (Monday – Saturday).

3. SECTION 1, CONTIUATION TO SF-1449, SCHEDULE OF SUPPLIES/SERVICES,

BLOCK 20 is changed by deleting paragraph 1.8 and replaced as follows:

1.8 REMOVAL OF DEBRIS

The Contractor shall remove foreign material, cuttings, grass, leaves, bark, limbs, dead vegetation, paper, and trash from the maintained areas including but not limited to gardens, lawns, ponds, canals, drainage systems (except specified roof gutter in paragraph 1.8.1), parking

Amendment No. 0001 Solicitation No. 19TH2025Q0036 lots, sidewalks, driveways and road, and all paths, walkways, stairways and curbs within or adjacent to the area on a daily basis. The Contractor shall remove all debris and equipment from the worksite before the end of each workday. Debris removal shall prevent unsightly accumulation. The Contractor shall promptly remove collected debris to an authorized disposal site. The Contractor is responsible for all expenses incurred in the collection and disposal of debris.

4. SECTION 1, CONTINUATION TO SF-1449, SCHEDULE OF SUPPLIES/SERVICES,

BLOCK 20 is changed by adding paragraph 1.4.7 as follows:

1.4.7. At no additional cost to the Government, the Contractor shall replace any turf that is killed or rendered unusable for its intended purpose through negligent or irresponsible practices that are attributable to the Contractor.

5. SECTION 1, CONTINUATION TO SF-1449, SCHEDULE OF SUPPLIES/SERVICES,

BLOCK 20 is changed by deleting paragraph no. 1.9.5 and replaced as follows:

1.9.5. The Contractor shall be responsible for watering and maintaining plants and vegetation located at the NOB Front Office. There are approximately 100 square feet of plants located at the exterior balcony area, and also potted plants located inside. The Contractor shall provide this service at least 3 times per week, or more frequently as needed based on the condition of the plants. The service shall be performed between 6:20 a.m. and 7:00 a.m., unless otherwise instructed by the COR. The schedule may be subject to change, and the COR will notify the Contractor in advance if any adjustments are required. approximately one hour each visit. The Contractor must schedule for an escort at least three days in advance, via email to the COR.

topmostSubform[0]:
Page1[0]:
AmendmentNo[0]: 0001
Code[0]:
Code[1]:
AccountingData[0]:
A13[0]:
C13[0]:
D13[0]:
NameandTitleSigner[0]:
NameandTitleOfficer[0]: Ramon Menendez-Carreira
Description[0]: The purpose of this amendment is to:

1. Revise paragraph no. 1.4.5, 1.6, 1.8 and 1.9.5 under Section 1, Continuation to SF-1449, Schedule of Supplies/Services, Block 20, per attachment

2. Add paragraph no. 1.4.7 to Section 1, Continuation to SF-1449, Schedule of Supplies/Services, Block 20, per attachment

FacilityCode[0]:
Code[2]:
IssuedBy[0]: U.S. Embassy Bangkok, GSO/Procurement

120 - 122 Wireless Road, Lumpini,Pathumwan, Bangkok 10330, Thailand

NameandAddress[0]:
AdministeredBy[0]:
ContractIDCode[0]:
ReqNumber[0]:
AmendmentNo[1]: 19TH2025Q0036
ModificationNo[0]:
ProjectNo[0]:
Page[0]: 1
Pages[0]: 3
EffectiveDate[0]: 08/07/2025
Dated9B[0]: 06/27/2025
Dated10B[0]:
CheckBox9[0]: 1
CheckBox10[0]: Off
CheckBox11[0]: 1
CheckBox13A[0]: Off
CheckBox13B[0]: Off
CheckBox13C[0]: Off
CheckBox13D[0]: Off
IsNot[0]: Off
Is[0]: Off
Extended[0]: Off
NotExtended[0]: 1
2025-08-07T15:09:56+0700
Ramon J Menendez Carreira
DateSigned[0]:
DateSigned[1]: 08/07/2025