The file is a detailed Total Cost Breakdown (Attachment 4) for a prefabricated container project at the U.S. Consulate General in Barcelona, Spain. The cost breakdown is structured into six main categories: General Requirements, Site Preparation and Civil Works, Prefabricated Container Fabrication, On-site Installation, Final Cleanup & Handover, and Contingency & Overhead. The spreadsheet outlines specific line items for each category, including pre-award site visits, permitting, engineering design, container fabrication with two rooms, electrical work, HVAC, installation, and project closeout. A seventh section covers duress button line installation.

The associated federal contract opportunity (Solicitation 19SP1025Q0002) is a re-solicitation issued by the Department of State on July 25, 2025, with a submission deadline of August 25, 2025. The re-solicitation was prompted by initial quotations that were incomplete and lacked technical proposals. The contract is for supply and installation of a prefabricated container at the U.S. Consulate General in Barcelona, open to all eligible vendors under the Commercial and Institutional Building Construction NAICS category. Interested contractors must submit complete quotation packages containing both Volume I and Volume II components, with inquiries directed to GSO_Barcelona@state.gov.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet2

1. General Requirements
ItemDescriptionUNITEstimated Cost (EUR)
PASite Visit & SurveyPre-award measurements, geotechnical study, utilities identification1
PAPermitting & CoordinationLocal authority permits, embassy coordination1
PASafety & Work Plan SubmittalsAHA, CPM, samples, product data, shop drawings, schedule1
PAEngineering & DesignStructural, MEP, and stamped drawings1
PAOther1
SUBTOTAL 1€ 0
2. Site Preparation and Civil Works
ItemDescriptionEstimated Cost (EUR)
PAArea Isolation & FencingTemporary barrier, signage1
PADemolitionPavement, curbs, mortar, old screen, trenches1
PAExcavationFor slab foundation and utilities (2m depth)1
PAConcrete FoundationOn-site RFC slab for container1
PAAccess Path15 cm concrete path to container1
PAWood FencingWood fence and new doors1
PAOther1
SUBTOTAL 2€ 0
3. Prefabricated Container Fabrication
ItemDescriptionEstimated Cost (EUR)
PAContainer UnitTwo-room, ISO-standard, prefabricated, fully finished (per SOW)1
PAFactory PrewiringElectrical, lighting, duress button, preinstalled1
PAHVAC UnitsSplit units, R32 refrigerant, 2 rooms1
PAVentilation SystemTransfer fan, backdraft damper, louver1
PAInterior FinishesWalls, vinyl flooring, doors, paint, cove base1
PALighting & PowerWaterproof/dustproof LED fixtures, switches, outlets, panels1
PADuress System InterfaceRough-in wiring, coordination (device provided by Post)1
PALifting Eyes, Anchoring PlatesFactory installed1
PAOther1
SUBTOTAL 3€ 0
4. On-site Installation
ItemDescriptionEstimated Cost (EUR)
PATransportationContainer delivery via crane truck1
PAAnchoringBolt and plate anchoring to slab1
PAElectrical TrenchingDitching, conduit installation (6 pipes)1
PAElectrical ConnectionsFeeder wires, breaker panel, connections1
PADuress WiringPulling wire, fitting panels1
PAFinal TestingPower, HVAC, lighting, duress pre-check1
PAOther1
SUBTOTAL 4€ 0
5. Final Cleanup & Handover
PAItemDescriptionEstimated Cost (EUR)
PARepair/Touch-upPaint, flooring repair as needed1
PADebris DisposalDaily removal and site cleanup1
PAAs-Built DocumentationDrawings, specs, digital submittal1
PACloseout ReviewEmbassy walk-through, punch list1
PAOther
SUBTOTAL 5€ 0
6. Contingency & Overhead
ItemDescriptionEstimated Cost (EUR)
PAContractor Overhead & Profit1
PAContingency (Design Changes, Delays, etc.)1
PAOther1€ 0
SUBTOTAL 6€ 0
SUB-TOTAL 1€ 0
SUB-TOTAL 2€ 0
SUB-TOTAL 3€ 0
SUB-TOTAL 4€ 0
SUB-TOTAL 5€ 0
SUB-TOTAL 6€ 0
SUBTOTAL 1 THROUGH 6€ 0
PAVAT21%1€ 0
TOTAL€ 0
Contractor may include other items in accordance with their technical proposal. If a thorough explanation is required, please include it in the Technical Proposal
7. Dures Button line installation
ItemDescriptionEstimated Cost (EUR)
PALabor for an approximate 17m length trench and 26 m conduit1
PAMaterials for an approximate 17m length trench and 26 m conduit1
PAVAT21%1€ 0
TOTAL€ 0