The file is a detailed cost breakdown spreadsheet for a prefabricated container installation project at the U.S. Consulate General in Barcelona, Spain. The total cost breakdown is structured across six main categories: General Requirements, Site Preparation and Civil Works, Prefabricated Container Fabrication, On-site Installation, Final Cleanup & Handover, and Contingency & Overhead. The spreadsheet provides a comprehensive itemization of estimated costs for each phase, including tasks such as site survey, permitting, container fabrication, electrical work, HVAC installation, and project closeout. While the spreadsheet shows placeholder values of EUR 0, it outlines a structured approach to budgeting the entire project.

The related solicitation (19SP1025Q0002) seeks a contractor to supply and install a modular, stand-alone structure at the U.S. Consulate Barcelona's parking lot. Key dates include a mandatory site visit on July 2nd, 2025, with attendee registration required by June 27th, 2025. Proposals must be submitted via email by July 14th, 2025, at 17:30 CEST. The contract will be awarded to the lowest-priced technically acceptable offeror, with a firm fixed-price structure. Contractors must be registered in the System for Award Management (SAM), possess necessary Spanish business permits, and submit proposals not exceeding 45MB.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet2

1. General Requirements
ItemDescriptionUNITEstimated Cost (EUR)
PASite Visit & SurveyPre-award measurements, geotechnical study, utilities identification1
PAPermitting & CoordinationLocal authority permits, embassy coordination1
PASafety & Work Plan SubmittalsAHA, CPM, samples, product data, shop drawings, schedule1
PAEngineering & DesignStructural, MEP, and stamped drawings1
PAOther1
SUBTOTAL 1€ 0
2. Site Preparation and Civil Works
ItemDescriptionEstimated Cost (EUR)
PAArea Isolation & FencingTemporary barrier, signage1
PADemolitionPavement, curbs, mortar, old screen, trenches1
PAExcavationFor slab foundation and utilities (2m depth)1
PAConcrete FoundationOn-site RFC slab for container1
PAAccess Path15 cm concrete path to container1
PAWood FencingWood fence and new doors1
PAOther1
SUBTOTAL 2€ 0
3. Prefabricated Container Fabrication
ItemDescriptionEstimated Cost (EUR)
PAContainer UnitTwo-room, ISO-standard, prefabricated, fully finished (per SOW)1
PAFactory PrewiringElectrical, lighting, duress button, preinstalled1
PAHVAC UnitsSplit units, R32 refrigerant, 2 rooms1
PAVentilation SystemTransfer fan, backdraft damper, louver1
PAInterior FinishesWalls, vinyl flooring, doors, paint, cove base1
PALighting & PowerWaterproof/dustproof LED fixtures, switches, outlets, panels1
PADuress System InterfaceRough-in wiring, coordination (device provided by Post)1
PALifting Eyes, Anchoring PlatesFactory installed1
PAOther1
SUBTOTAL 3€ 0
4. On-site Installation
ItemDescriptionEstimated Cost (EUR)
PATransportationContainer delivery via crane truck1
PAAnchoringBolt and plate anchoring to slab1
PAElectrical TrenchingDitching, conduit installation (6 pipes)1
PAElectrical ConnectionsFeeder wires, breaker panel, connections1
PADuress WiringPulling wire, fitting panels1
PAFinal TestingPower, HVAC, lighting, duress pre-check1
PAOther1
SUBTOTAL 4€ 0
5. Final Cleanup & Handover
PAItemDescriptionEstimated Cost (EUR)
PARepair/Touch-upPaint, flooring repair as needed1
PADebris DisposalDaily removal and site cleanup1
PAAs-Built DocumentationDrawings, specs, digital submittal1
PACloseout ReviewEmbassy walk-through, punch list1
PAOther
SUBTOTAL 5€ 0
6. Contingency & Overhead
ItemDescriptionEstimated Cost (EUR)
PAContractor Overhead & Profit1
PAContingency (Design Changes, Delays, etc.)1
PAOther1€ 0
SUBTOTAL 6€ 0
SUB-TOTAL 1€ 0
SUB-TOTAL 2€ 0
SUB-TOTAL 3€ 0
SUB-TOTAL 4€ 0
SUB-TOTAL 5€ 0
SUB-TOTAL 6€ 0
SUBTOTAL 1 THROUGH 6€ 0
PAVAT21%1€ 0
TOTAL€ 0
Contractor may include other items in accordance with their technical proposal. If a thorough explanation is required, please include it in the Technical Proposal