- FAC-Switchgear equipment cooling system detailed plan design and installation of equipment
- Solicitation number
- 19MK8025Q0009
- Issued by
-
Department of State
About this file
This is a Request for Quotations (RFQ) issued by the United States Embassy in Skopje, North Macedonia, seeking a contractor to design and install a new cooling system for the embassy's utility building switchgear room. The solicitation (RFQ 19MK8025Q0009) requires a two-phase project: Phase 1 involves detailed design services, and Phase 2 covers the construction and installation of the cooling system. The project specifications call for a VRV (Variable Refrigerant Volume) cooling system with a capacity of 15-20 kW, designed to maintain the switchgear room temperature at 23°C (±2°C) with 35-50% relative humidity.
Key requirements include a modular outdoor unit with at least 65% redundancy, multiple indoor units for uniform temperature distribution, independent temperature zone controls, and condensate drainage outside the room. The contractor must be registered in the System for Award Management (SAM), comply with specific electrical and safety standards, and provide comprehensive documentation including design drawings, warranties, and operation manuals. Quotations must be submitted electronically by 11:00 a.m. on April 7, 2025, to skopjegsoprocurement@state.gov. The government intends to award the contract to the responsible company submitting the lowest-priced acceptable offer, with the potential to hold discussions if necessary.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FY25__SWITCHGEAR ROOM COOLING SOW_Skopje.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Embassy Skopje
Date: 03/20/2025
To: Prospective Quoters
Subject: Request for Quotations number 19MK8025Q0009.
Enclosed is a Request for Quotations (RFQ) for purchase of FAC-Switchgear equipment cooling system detailed plan design and installation of equipment for American Embassy Skopje. If you would like to submit a quotation, follow the instructions in Section 3 of the solicitation, complete the required portions of the attached document, and submit it to the email address shown on the Standard Form 1449 that follows this letter.
The U.S. Government intends to award a contract/purchase order to the responsible company submitting an acceptable offer at the lowest price. We intend to award a contract/purchase order based on initial proposals, without holding discussions, although we may hold discussions with companies in the competitive range if there is a need to do so.
Your quotation must be submitted electronically by 11:00 a.m., on Monday April 7, 2025. No quotations will be accepted after this time. Quotations must be in English and incomplete quotations will not be accepted.
Direct any questions regarding this solicitation to Ivan Tashovski, Procurement Agent by an email to skopjegsoprocurement@state.gov, tashovskii@state.gov or by telephone +389 (0)2 310 2186, during regular business hours.
It is important to make sure the submission is made in specific size and format; in MS-Word 2007/2010 or MS-
Excel 2007/2010 or Adobe Acrobat (pdf) file format. The file size must not exceed 30MB. If the file size should exceed the 30MB, the submission must be made in separate files and attached to separate emails with less than
30MB each.
In order for a quotation to be considered, you must also complete and submit the following:
1. SF-1442
2. Section A, Pricing
3. Section L Representations and Certifications
4. Additional information as required in Section J
5. Proof of SAM Registration
Offerors shall be registered in the SAM (System for Award Management) database at https://www.sam.gov prior to submittal of their offer/proposal as prescribed under FAR 4.1102. Failure to be registered at time of proposal submission may deem the offeror’s proposal to be considered non-responsible and no further consideration will be given. Therefore, offerors are highly encouraged to register immediately if they are interested in submitting a response to this requirement.
Sincerely, Michael J. Fundahn
Contracting Officer mailto:tashovskii@state.gov https://www.sam.gov/
TABLE OF CONTENTS
SF-1442 COVER SHEET
A. PRICING
B. STATEMENT OF WORK
C. PACKAGING AND MARKING
D. INSPECTION AND ACCEPTANCE
E. DELIVERIES AND PERFORMANCE
F. CONTRACT ADMINISTRATION DATA
G. SPECIAL TERMS AND CONDITIONS
H. CLAUSES
I. LIST OF ATTACHMENTS
Attachment 1: Breakdown of Price by Divisions of Specifications
Attachment 2: Drawings
Attachment 3: Specifications
J. INSTRUCTIONS ON HOW TO SUBMIT A QUOTATION
K. EVALUATION CRITERIA
L. REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS
OMB APPROVAL NO. 2700-0042
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
19MK8025Q0009
2. TYPE OF SOLICITATION
SEALED BID (IFB)
[ ] NEGOTIATED (RFP)
3. DATE ISSUED
03/21/2025
PAGE OF PAGES
IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
5. REQUISITION/PURCHASE REQUEST NO.
PR15226314
6. PROJECT NO.
7. ISSUED BY CODE MK800 8. ADDRESS OFFER TO
AMERICAN EMBASSY SKOPJE
UL. SAMOILOVA # 21, 1000,
SKOPJE
NORTH MACEDONIA
ATTN: GSO/PROCUREMENT
skopjegsoprocurement@state.gov tashovskii@state.gov
AMERICAN EMBASSY SKOPJE
UL. SAMOILOVA # 21, 1000,
ATTN: GSO/PROCUREMENT
SKOPJE
NORTH MACEDONIA
9. FOR INFORMATION
CALL:
A. NAME
Ivan Tashovski
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
+389 (2) 310-2186
SOLICITATION
NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):
-Scope Of Work Section B
-Please fill clause 52.204-26 Covered Telecommunications Equipment or Services- Representation (DEC 2019) located in the clauses section below.
Send the filled clause 52.204-26 together with your quote.
-Please fill in in section L.8 CERTIFICASTION REGARDING COMPLIANCE WITH APPLICABLE
FEDERAL ANTI-DISRIMINATION LAW
11. The Contractor shall begin performance within __5__ calendar days and complete it within _90___ calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable. (See _______________.)
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If “YES,” indicate within how many calendar days after award in Item 12B.)
YES NO
12B. CALENDAR DAYS
N/A
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __1__ copies to perform the work required are due at the place specified in Item 8 by 11.00 a.m. (hour) local time ____04/07/2025_____ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, is not required.
C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _60___ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Computer Generated Prescribed by GSA FAR (48 CFR) 53.236-1(e) mailto:skopjegsoprocurement@state.gov mailto:tashovskii@state.gov
1 19MK8025Q0009
OFFER (Must be fully completed by offeror)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14)
CODE FACILITY CODE
17. The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within _____ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER
(Type or print)
20B. SIGNATURE
20C. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( )
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requisitions identified on this form and any continuation sheets for the consideration slated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by reference in or attached to this contract.
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED
TO SIGN (Type or print)
31A. NAME OF CONTRACTING OFFICER (Type or print)
Michael J. Fundahn
30B. SIGNATURE
30C. DATE
31B. UNITED STATES OF AMERICA
BY
31C. AWARD DATE
Computer Generated STANDARD FORM 1442 BACK (REV. 4-85)
2 19MK8025Q0009
U.S. EMBASSY, SKOPJE
SECTION A – PRICING
A. PRICE
The Contractor shall complete all work, including furnishing all labor, material, equipment, and services required under this purchase order for the following firm fixed price and within the time specified. This price shall include all labor, materials, all insurances, overhead and profit.
A.1. VALUE ADDED TAX
VALUE ADDED TAX (VAT). The Contractor shall include VAT as a separate charge on the Invoice and as a separate line item in Section B.
The Contractor shall deliver the following items:
Item No.
Quan tity
Unit
Description
Price
1 1 LOT UTL building switchgear room cooling system upgrade project. Project Phase 1 -cooling system design.
MKD
2 1 LOT UTL building switchgear room cooling system upgrade project. Project Phase 2 -cooling system installation, testing and commissioning.
MKD
3 VAT TAX MKD
4 1 LOT DBA Insurance MKD
Total firm-fixed price
MKD
SECTION B - STATEMENT OF WORK
B.1. INTRODUCTION
1.1 The US Embassy Skopje requires engineering design and construction services to install new cooling system in in the embassy compound Utility building switchgear room. The following Statement of Work (SOW) shall describe the cooling equipment installation and any related scope items.
1.2 The contractor shall provide complete design and construction services, SWITCHGEAR ROOM COOLING SYSTEM
3 19MK8025Q0009
contractor coordination/supervision, including but not limited to the management, professional design services, and construction necessary to meet the requirements listed in this SOW within the established schedules.
1.3 The SOW shall consist of two phases as described in sections 3 & 4.
1.3.1 Phase 1 – Design Services
1.3.2 Phase 2 – Construction Services
PROJECT WORK SPECIFICS
1.4 Mechanical works
1.4.1 The goal of the project is to provide cooling capacity to the existing switchgear room located in the embassy compound UTL building.
Currently the room does not have any cooling system installed. The goal is to maintain the ambient temperature inside the room at 23 [OC]
± 2 OC all year round.
1.4.2 Relative air humidity in the room shall be kept within the usual range of 35 – 50 [%].
1.4.3 The project shall take into consideration the heat load generated by the electrical equipment installed/operating in the room. Information about the heat load shall be given to prospective bidders during site visits.
1.4.4 Preferred cooling system is VRV design. The cooling demand is estimated at 15- 20 kW. This is just an approximate value to be used only for information purposes by the prospective bidders. The actual cooling demand shall be determined during the design phase.
1.4.5 Preferred configuration shall consist of an outdoor unit circulating refrigerant to several indoor units. The number and locations of the indoor units shall be determined based on the requirement to provide uniform ambient temperature throughout the room (at elevation of 1.5 above the floor)
1.4.6 The number of room temperature zones/sensors shall correspond to the number of interior units. Each temperature zone shall have independent control.
1.4.7 Preferably, the outdoor unit shall be with modular design, consisting of at least 2 modules. This modular design shall provide for at least
65% redundancy in case of a failure of any of the individual modules.
1.4.8 The indoor units’ condensate shall be piped and discharged outside
4 19MK8025Q0009
the switchgear room. The condensate from individual indoor units may be piped into one common condensate pipe, if convenient.
Discharge of condensate by gravity is preferred.
1.4.9 Due to presence of high current electrical equipment, care must be taken to reduce the risk of condensate leaks. In case of a leak, special care must be taken to eliminate any possibility of leaked condensate affecting the electrical equipment
1.4.10 Floor mounted equipment and piping shall have seismic supports and bracing (spring isolators and bracings) provided for Skopje seismic zone.
1.4.11 Wherever required, all concrete wall pipe penetrations shall be core drilled. Upon installation completion, the interstitial space shall be caulked with fire resistant caulking per NFPA norms.
1.5 Electrical works
1.5.1 All electrical installations shall comply to NFPA 70 National Electrical Code.
1.5.2 The contractor shall provide all electric materials and accessories, including electrical power supply and control panels for the NEW cooling system.
1.5.3 The embassy shall provide the main power supply cable to the new cooling system electrical panel. The contractor shall provide information about the total electrical load of the new equipment.
1.5.4 Contractor may, wherever possible, use the existing electrical duct-banks and/or conduits, as approved by embassy facility management/project COR,
1.5.5 Wherever required, all concrete wall conduit penetrations shall be core drilled. Upon installation completion, all penetrations shall be caulked with fire resistant caulking per NFPA norms.
1.5.6 All new equipment, metal piping and pipe support shall be grounded to the existing building grounding infrastructure.
1.6 Structural works
1.6.1 The Contractor shall provide a raised platform for the outdoor unit (a concrete pad or other approved support platform);
5 19MK8025Q0009
1.6.2 The contractor shall provide seismic and vibration isolation bracing for all equipment, ducting (if applicable) and piping systems in accordance with the more stringent of ASHRAE, IBC, or other codes/standards specified in this contract. Contractor shall comply with the pertinent building codes for proper mounting and bracing of equipment, duct, and pipes to protect against seismic events.
Mechanical equipment shall have seismic mounts/bracing governed by non-structural seismic requirements of the building code. Surge restrainers shall be installed on all hangers and rod throughout. End of branch lines require seismic restraints. Mains and cross mains require seismic bracing. See OBO-ICS-IBC Chapter 16, Table 1609 -
Design Criteria for Snow, Wind and Seismic.
1.7 BAS connectivity
1.7.1 The new cooling system shall be a standalone installation not connected to the embassy existing HVAC infrastructure.
1.7.2 Controllers shall be BACNET compatible for future integration of the switchgear room cooling system into the embassy compound BAS.
1.8 CONTRACTING OFFICER'S REPRESENTATIVE (COR)
1.8.1 The Contracting Officer may designate in writing one or more
Government employees, by name or position title, to act for the
Contracting Officer under this contract. Each designee shall be identified as a Contracting Officer’s Representative (COR). Such designation(s) shall specify the scope and limitations of the authority so delegated; provided, that the designee shall not change the terms or conditions of the contract, unless the COR is a warranted
Contracting Officer, and this authority is delegated in the designation.
1.8.2 The COR for this contract is Toni Dimitrov, US Embassy’s FAC
Mechanical Engineer.
1.8.3 The Contractor shall give written assurance to the COR that all contractor staff performing work on or for the project have obtained all requisite licenses and permits.
1.8.4 This is a firm fixed price contract and no charges or increases will be made due to contractor oversights, or unanticipated expenditures. All additional claims beyond the terms of the contract will be made in writing and directed to the US Embassy Contracting Officer for reconciliation.
6 19MK8025Q0009
1.8.5 All work shall be performed during 0800 – 1800 hrs., Mondays thru
Fridays. Other hours, if requested by the Contractor, may be approved by the Contracting Officer's Representative (COR). The
Contractor shall give 24 hours in advance to COR who will consider any deviation from the hours identified above. Changes in work hours, initiated by the Contractor, will not be a cause for a price increase.
PHASE 1 – DESIGN SERVICES
1.9 Kick-Off Meeting: Within 5 (five) business days after issuances of the Notice to Proceed (NTP), the Contractor shall assemble a team to participate in a meeting at the embassy premises, with the Contracting Officer (CO), Contracting Officer’s Representative (COR), Work Safety Officer (POSHO) officer. The meeting will include discussions of Project schedule, review of the
SOW and technical aspects of the project.
1.10 Phase 1 – Design Deliverables – 50% CD, 100% CD and IFC Set:
1.10.1 The following deliverables shall be provided for each the 50% CD, 100% CD and IFC submissions.
1.10.1.1 The 50% CD submission is not expected to have all
drawings and specifications completed for each deliverable, however, there should be adequate detail for
OBO/DE to provide timely and sufficient feedback.
1.10.1.2 Emphasis shall be placed on calculations for the 50% CD submission as this will be an important driver in finalizing equipment selections and determining required electrical and structural modifications.
1.10.2 Long-Lead Equipment Procurement: Submittals for long lead items (i.e. chillers, pumps) may be submitted following the completed
50% CD submittal.
1.10.3 Product Literature: Identify all materials and products to be used. The specific manufacturer and model number used as the basis of design shall be listed for each item. Include maintenance and warranty information. Contractor shall provide information on local
Contractors and technicians in the region that can provide service and preventive maintenance support for all major pieces of equipment.
1.10.4 Project Schedule: The Contractor shall provide a project schedule summary, including all related tasks so the contractor can deliver on time. This schedule should contain all important delivery dates, time restrictions and the expected project duration.
7 19MK8025Q0009
1.11 Phase 1 Milestones / Schedule of Deliverables
PHASE 2 – CONSTRUCTION SERVICES
1.12 Following IFC document review and issuance of OBO building permit, the
Contracting Officer shall provide a NTP (notice to proceed) for Phase 2. No equipment shall be ordered prior to receipt of OBO approval. At the COR’s discretion, long lead equipment may be submitted/approved early in the project to expedite equipment manufacturing.
1.13 Kick-Off Meeting: Within 5 (five) business days after issuances of the Notice to Proceed (NTP), the Contractor shall assemble a team to participate in a meeting at the embassy premises, with the Contracting Officer (CO), Contracting Officer’s Representative (COR), Work Safety Officer (POSHO) officer. The meeting will include discussions of Project construction schedule, review of the SOW and other technical aspects of the project. The meeting shall include discussion of work safety (SHEM) requirements that are
Item Deliver to: Delivery Date
Contract Award Contractor +0
Design Notice to Proceed (NTP) Contractor +5
Site Survey - +5
50% Construction Documents (CD) COR +20
50% CD Integrated Design Review (IDR) COR +35
50% CD Comment Resolution Meeting COR via Video Conference +40
100% Construction Documents COR +60
100% Integrated Design Review COR +75
100% CD Comment Resolution Meeting COR via Video Conference +80
Design Issued for Construction (DIFC) COR via ProjNet +90
8 19MK8025Q0009
mandatory during project completion. Work safety is essential having in mind that the switchgear room is housing the embassy compound main electrical breakers. Both personnel safety and safety of the equipment is a priority.
1.14 Onsite Execution Work Plans: Prior to each and all site mobilizations, the
Contractor shall provide a copy of a detailed execution plan, which includes dates, specific daily tasks, shutdown requirements / lengths, equipment / systems parts to be installed, specific employees lists to be dispatched and their qualifications.
1.15 Progress Reports Requirement: Following award, the Contractor shall submit progress reports (along with project schedule updates – see below) to the COR preferably on a weekly basis.
1.16 Reports shall be either letter or A4 format, either in PDF or Word. Reports shall contain all information relevant to the project, including a description of work accomplished, work in progress, planned activities, arising/occurring issues, proposed solutions,
1.17 Project Schedule Updates: The Contractor shall also provide weekly project schedule updates that record actual work progress versus the approved base lined schedule. These schedules shall have identical formats for clarity.
1.17.1 The Contractor shall plan, estimate, and schedule all work to assure labor, and equipment are available to complete work requirements within the specified time limits and in conformance and quality standards and performance requirements established herein. The
Contractor shall utilize Critical Path methodologies and processes to schedule, plan, monitor and manage this task order. Provide phasing schedule of the work to be done during the construction period
1.17.2 The schedule shall be scaled initially by weeks or at COR request.
1.17.3 All schedule updates and progress recording shall be validated by the
Contractor in writing to be accurate as of the reporting date.
1.17.4 The schedule shall also include an initial base-line date indicating the date which the schedule was base lined and for subsequent schedule submission requirements the data date shall reflect the current and/or revised schedule date.
1.18 Deployment Reports, Checklists, Punchlists & Inspection Records: All deployment reports, checklists, punch-lists, scheduled/performed inspection records, corrective actions taken, cost data, and program economic reports shall be maintained by the Contractor through the term of this contract. The file(s) shall be the property of the Government and made available to the
Contracting Officer’s Representative (COR) during regular working hours.
The file shall be turned over to the Contracting Officer (CO) and Contracting
Officer’s Representative (COR) within three (3) working days following
9 19MK8025Q0009
completion or termination of this contract.
1.19 Equipment Start-Up:
1.19.1 The COR or COR’s designated representative shall be present during all start-up demonstrations.
1.19.2 The FM (or local designated technical representative) must approve of the start-up report prior to technician demobilization. All equipment must be successfully started up prior to the Contractor proceeding to any commissioning / demonstration phase.
1.20 Testing and Balancing (TAB): The Contractor shall perform adjusting and balancing procedures on the new equipment.
1.20.1 A final TAB report shall also be included in final deliverables at construction completion.
1.21 Operation & Maintenance (O&M) Manual: The contractor shall provide and submit all project specific O&M manuals for all major equipment and all significant appurtenances being provided as a part of the project. The O&M manual must include all recommended preventive maintenance tasks for the estimated life of the equipment. The preventive maintenance plan must include items, such as weekly, monthly, semi-annually, annually, etc. tasks.
1.22 Commissioning/Final Demonstration: The Contractor shall provide a demonstration of equipment function in its entirety at the end of the project, which includes all sequences, alarms, and even simulating power outages, and equipment failures. Equipment and systems shall not be considered accepted and turned over to the Government without a successful commissioning and demonstration.
1.22.1 Contractor shall pressure test all piping work to ensure the integrity of the piping system. Air or inert gas pressure testing is a preferred method. All leaks shall be repaired by the Contractor prior to restoring service.
1.22.2 Leading up to commissioning, the Contractor and subs shall also be required support pre-commissioning preparation activities. The full team shall be required to complete the
Commissioning/Demonstration phase. The Contractor shall be required to support the development of Cx tasks and shall be required to pre-test equipment prior to commissioning to ensure Cx testing is executed as efficiently as possible. Commissioning is not a tool that shall be used to troubleshoot issues that are the responsibility of the
Contractor to resolve.
1.22.3 The COR or COR’s designated representative shall be present during all commissioning demonstrations.
10 19MK8025Q0009
1.22.4 The full team shall be required onsite to complete the
Commissioning/Final Demonstration phase.
1.22.5 Commissioning shall include, but is not limited to:
1.22.5.1 Simulating lead/lag staging and swapping lead components
(i.e. chillers, pumps) following simulated equipment failures.
1.22.5.2 Simulating plant staging through entire sequence.
1.22.5.3 Confirming the PCC chiller remains as true-backup and is offline when the main house plant is in operation.
1.22.5.4 Simulating a house chilled water plant failure (i.e. high water temperature) to ensure the PCC chiller plant energizes when required. Confirm PCC chiller plan auto-shutdown on return of house chiller loop temperatures.
1.22.5.5 Demonstrating the equipment auto-restarts flowing power outages and switching back-and-forth between generator and normal power.
1.23 Post Training: The Contractor shall provide formal training to Post facilities personnel, as selected by the FM, on the proper operation and maintenance of all major systems and equipment being provided as a part of this project.
Training must be conducted by manufacturer’s representatives or by qualified, manufacturer certified personnel. This training shall be formalized and documented in the form of an electronic (pdf format) reports, submitted to the project COR and FM.
1.24 Warranties: The Contractor shall provide fully documented warranties on all equipment, materials and workmanship:
1.24.1 Manufacturer’s Equipment Warranties and Identification of Warranty
Items
1.24.2 Two-Year Workmanship Guarantee: Covers all equipment, materials and labor in the event that any items of work are found defective.
1.25 As-Built Drawings: The Contractor shall modify final drawings to show as-built conditions within 30 days following formal substantial completion. As-built conditions shall be documented and maintained up to date with re-lined copies during execution.
1.25.1 All as-built drawings shall be signed and sealed by a registered professional engineer, registered in a US State, Puerto Rico or the
District of Columbia.
1.25.2 Provide as-built drawings within 30 days following formal substantial
11 19MK8025Q0009
completion.
1.26 Deliverables to Accompany Construction Completion: The Contractor shall provide final versions of all of the following in electronic (PDF) format, as well as two printed copies to the Embassy and two printed copies to the CO
(except for the O&M manual). See previous sections for further descriptions of each deliverable.
1.26.1 Testing and Balancing (TAB) Report
1.26.2 Operation and Maintenance (O&M) Manual
1.26.3 Warranties
1.26.4 As-Built Drawings: Including Auto-CAD or BIM files
1.26.5 Completion Report: Following the culmination of all successfully work activities, the Contractor shall submit a completion report for
COR review / approval.
CONTRACT ADMINISTRATION
1.27 The Contractor shall NOT conduct any work that is beyond this Statement of
Work unless directed in writing by the Contracting Officer (CO). Any work done by the Contractor beyond this SOW without direction from the CO will be at the Contractor’s own risk and at no cost to the Government.
1.28 The CO shall provide a Notice to Proceed (NTP) to the Contractor for each phase. No work shall be initiated until the CO issues the NTP.
1.29 Decisions by the COR regarding construction quality will be final.
Construction issues recognized by the COR as requiring actions outside the existing Statement of Work will be separately documented and require a contract modification.
1.30 To expedite the construction and minimize disturbance to USG’s operation, the Contractor may be required to work hours than what are considered normal working hours (i.e. evenings and on weekends).
PAYMENTS
1.31 The Design/Build Contractor shall provide a fixed priced lump sum proposal to the Contracting Officer for each phase [note: there may not be a proposal for Phase 1 if it is a competition]. Each Phase shall be invoiced separately.
12 19MK8025Q0009
The Contractor may submit requests for progress payments at monthly intervals to cover the value of labor and materials completed to date. For progress payments, there shall be retained 10% of the amount due until final completion. Each invoice shall also have the Project Site Manager’s monthly
Status Report attached.
1.31.1 Phase 1 – Design Services Fixed Fee
1.31.2 Phase 2 - Construction Services Fixed Fee
1.31.3 DBA Insurance Fixed Fee
1.32 The Contractor shall submit a copy of all payment invoices with substantiating documents to the COR. The COR will determine if the invoice is complete and proper as submitted. The COR will also determine if billed services have been satisfactorily performed and if expenses billed are correct. If it is determined that the amount billed is incorrect, the COR will within seven days, request the
Contractor to submit a revised invoice.
The Contractor shall specifically identify the last invoice as “Final Invoice”. The Final invoice shall include the remaining payment claimed to be due under the basic contract and all modifications issued, if any. The final invoice shall also have the Contractor's Release of Claims Certificate and two-year Workmanship
Guarantee attached.
13 19MK8025Q0009
SECTION C - PACKAGING AND MARKING
Packaging and marking shall follow commercial practice.
Deliverable items other than letter reports shall be three-hole punched and bound with screw-type binders and rubber bands.
The Contractor shall address letters and all deliverables as listed below:
- email skopjeprocurement@state.gov
- address:
American Embassy Skopje
Attn: GSO/Procurement
St. Samoilova 21
1000, Skopje
SECTION D - INSPECTION AND ACCEPTANCE
D.1.0. INSPECTION
The Contractor shall maintain a system of quality assurance and quality control to ensure that the design and documentation of the design meet the requirements of this contract.
The Government reserves the right to inspect the Contractor's work as well as its system of Quality Assurances and Quality Control (QA/QC).
The Contractor's key individual responsible for quality of design is the COR (Contracting
Officer Representative).
The Contractor's key individual responsible for quality of documentation is COR. If a key individual (see D.3 below) needs to be replaced during performance of this contract the contractor shall submit a resume for a replacement to the COR for approval.
D.2.0. ACCEPTANCE
Acceptance of deliverable items shall be by the COR. Acceptance or use of documents developed under this contract shall not relieve the Contractor of responsibility for the design.
D.3.0. QUALITY PROGRAM REQUIREMENTS FOR DESIGN CONTRACTS
The Contractor shall prepare and implement (based on approval by the Government), a
Quality Assurance and Control Plan. The Contractor shall address the following areas in the plan:
D.3.1. Organizational Structure. Proposed organizational structure for the project, including charts and a description of responsibilities of key persons who will perform the mailto:skopjeprocurement@state.gov
14 19MK8025Q0009
work. The Contractor shall identify persons responsible for interface with the
Government.
D.3.2. Document Control. The program must ensure that documents, including changes, will be reviewed for adequacy, approved for release by authorized personnel, and properly conveyed to the Government. Persons responsible for reviewing, approving, and releasing documents and revisions must be identified.
D.3.3. Verification. The Contractor shall identify the senior person (s) who will be responsible for final review and verification before documents are transmitted to the
Government. Cursory supervisory reviews will not be sufficient. Design verification may vary from spot-checking of calculations to full-scale review of design drawings and specifications, as the situation requires.
D.3.4. Corrective Action. The quality program must clearly define responsibility and procedures for corrective action if deficiencies in the services or resulting deliverables are found.
D.3.5. Quality Assurance Reporting. The Contractor shall prepare a Quality Assurance
(QA) report. This report shall identify the QA procedures used to review drawings and data for these submissions. This report shall also identify steps taken to coordinate all drawings and documents prepared by the Contractor and subcontractors. The report shall include:
1. QA status of the project.
2. Significant program problems and their solutions/corrective actions.
3. Organization and key personnel changes, as required.
D.3.6. Checking, Coordinating, and Integrating Drawings. Quality control procedures shall ensure that individual drawings and other documentation have been checked and that all documentation, including that of the supporting disciplines (such as civil, structural, mechanical, electrical) has been coordinated and integrated. The Contractor shall correct deficiencies, ambiguities, conflicts, and inconsistencies before document submittal.
D.3.7. Design-to Budget. The Contractor shall describe the procedure for meeting the design-to budget target. The procedure shall include a clear understanding of the cost implications during all design phases. The work of all subcontractors is to be included in the procedure.
15 19MK8025Q0009
SECTION E - DELIVERIES AND PERFORMANCE
E.1.0. PERIOD OF PERFORMANCE
The contractor shall complete all work required by this contract within the period indicated in Delivery Schedule. This period includes up to 1 month (30 calendar days) for Government review and approval for each deliverable item required by the contract.
E.2.0. CONTRACTOR DELAYS
The project schedule is a key parameter of this project. Completion of the design and documentation is key to the project as a whole. Liquidated damages are anticipated for construction associated with this project; they are not required for this A/E effort. The
Government will require adequate consideration for any slippage in schedule without excusable delay. The Contractor is required to document any delays and submit justification to the Contracting Officer.
E.3.0. DELIVERY SCHEDULE
The Contractor shall deliver the items listed in Section A on the following delivery schedule:
E.4.0. DELIVERABLES
E.4.1. The Contractor shall deliver design submittals to the COR at the following address: US Embassy Skopje, st. Samoilova21, 1000, Skopje, North Macedonia.
E.4.2. Delivery of monthly reports shall be as follows: Three (3) copies to the COR at the following address: US Embassy Skopje, st. Samoilova21, 1000, Skopje, North
Macedonia.
Item Deliver to: Delivery Date
Contract Award Contractor +0
Design Notice to Proceed (NTP) Contractor +5
Site Survey - +5
50% Construction Documents (CD) COR +20
50% CD Integrated Design Review (IDR) COR +35
50% CD Comment Resolution Meeting COR via Video Conference +40
100% Construction Documents COR +60
100% Integrated Design Review COR +75
100% CD Comment Resolution Meeting COR via Video Conference +80
Design Issued for Construction (DIFC) COR via ProjNet +90
16 19MK8025Q0009
E.4.3. All delivery charges shall be prepaid by the Contractor.
SECTION F - CONTRACT ADMINISTRATION DATA
F.1.0. 652.242-70 CONTRACTING OFFICER'S REPRESENTATIVE (COR)
(AUG 1999)
(a) The Contracting Officer may designate in writing one or more Government employees, by name or position title, to take action for the Contracting Officer under this contract. Each designee shall be identified as a Contracting Officer’s Representative
(COR). Such designation(s) shall specify the scope and limitations of the authority so delegated; provided, that the designee shall not change the terms or conditions of the contract, unless the COR is a warranted Contracting Officer and this authority is delegated in the designation.
(b) The COR for this contract is the Electrical Engineer.
F.1.1. Duties
The COR may provide technical advice, substantive guidance, inspections, invoice approval, and other purposes as deemed necessary under the contract. The COR is designated as the authority to act for the Contracting Officer in matters concerning technical clarification, inspection, and acceptance of the Contractor's performance under this contract. The COR will coordinate all work with the Contractor during the term of this contract. In no instance is the COR authorized to alter the contract's terms or conditions, including the design to budget parameter. Such changes must be authorized by the Contracting Officer in a written modification to the contract. Reference to the project architect within documents incorporated into this contract shall be read to mean
COR.
F.2.0. INVOICING AND PAYING INSTRUCTIONS
F.2.1. The Contractor shall submit invoices in the original and three copies to the designated billing address indicated in this contract. The COR will determine whether the invoice is complete and proper as submitted. The COR also will determine whether billed services have been satisfactorily performed and whether reimbursable expenses billed are correct. If the amount billed is incorrect, the COR will, within seven days, ask the Contractor to submit a revised invoice.
F.2.2. The Contractor shall specifically identify its last invoice as "Final Invoice." The final invoice shall include the remaining payments due under the basic contract and any and all modifications issued. The final invoice shall also attach a "Contractor's Release
Certificate". The Contractor should keep one copy of the certificate for its files and include the others with each copy of the final invoice. If the Contractor has any questions regarding payment status, contact the COR.
F.2.3. Monthly progress payments pursuant to the contract clause FAR 52.232-10 titled
"Payments Under Fixed Price Architect Engineer Contracts” are not authorized.
Payments for deliverable items listed in Section A shall be made in accordance with FAR
17 19MK8025Q0009
52.232-1, "Payments." For reimbursable expenses listed in Section G, payment shall be made after an acceptable invoice has been submitted by the Contractor. The Contractor shall mail invoices to:
- skopjeinvoices@state.gov
- US Embassy Skopje, st. Samoilova21, 1000, Skopje, North Macedonia.
Invoices shall reflect the contract number and the name of the COR.
F.2.4. The Contractor shall not be eligible to receive payments for any subsequent deliverables until the Government has accepted the previous deliverables.
SECTION G - SPECIAL TERMS AND CONDITIONS
G.1.0. SECURITY
The following considerations must be followed by the Contractor and/or must be incorporated into the design documents.
G.1.1. All documents received or generated under the contract are the property of the
U.S. Government.
G.1.2. All documents are to be controlled and disseminated on a need-to-know basis.
Reproduction and distribution is prohibited without express approval of the U.S.
Government. The Contractor shall mark all design and construction documents as follows:
WARNING
This document is the property of the United States Government. Further reproduction and/or distribution is prohibited without the express written approval of:
US Embassy Skopje, st. Samoilova21, 1000, Skopje, North Macedonia.
G.1.3. Proposed and actual contract documents will only be disseminated on a strict need-to-know basis and will not be further disseminated without prior authorization from the Department of State.
G.1.4. Contractor personnel receiving proposed or actual contract documents, to include blueprints, other technical drawings, sketches, photographs, exposed negatives, and/or descriptive narratives pertaining to the project, will be responsible for these materials while in their possession, or that of any of their subcontractors. The Contractor shall return all documents, including all copies, promptly upon demand by the Government.
G.1.5. Photographs of any public areas of any U.S. diplomatic or consular facility overseas must be approved and authorized in advance by the Site Security Manager
(SSM) and/or the Senior Security Officer (SSO). The SSO or SSM will establish any mailto:skopjeinvoices@state.gov
18 19MK8025Q0009
controls, limits, and/or other restrictions as deemed necessary. The Contractor shall submit a written request for authorization for such photography citing the reason(s) and use(s) for the photographs and/or negatives.
G.1.6. The Department of State shall be afforded the opportunity to review all photographs and negatives in advance of any public use and reserves the right to deny such use. No further dissemination, publication, duplication, or other use beyond that which was requested and approved under this contract is authorized without specific advance written approval from the Department of State.
G.1.7. The Department reserves the right to demand retention of all copies of photographs and negatives.
G.2.0. DESIGN-TO-BUDGET
N/A
G.3.0. CONSTRUCTION COST ESTIMATING
G.3.1. The Contractor shall prepare estimates of the cost of construction and these shall be marked as "Source Selection Information". The Contractor shall safeguard the confidentiality and prevent unauthorized distribution of these estimates.
G.3.2. The Contractor shall prepare construction cost estimates with the same attention to detail as if the Contractor were bidding on the project as a construction contractor.
The Contractor shall base estimates on the same construction contract conditions and specifications that will be used by the Government for procurement of the facilities being designed. Attached for reference are the model construction contract documents and procedures used by the Department of State.
G.3.3. The Contractor shall provide estimates of the cost of construction of the facilities described in the Scope of Work with each of the 35%, 60%, and 100% Construction
Documents submittals. These estimates shall indicate the anticipated cost of construction of the facilities in the country and locale where such facilities are to be built at the estimated midpoint of construction in MKD. Approval to proceed with subsequent phases will not be granted until all budgetary issues are resolved. See "Design-to-
Budget" and Section H, clause 52.236-22 titled "Design within Funding Limitations" for the estimated construction contract price and additional information on the use of construction cost estimates.
G.3.4. The Contractor shall allocate the total projected costs among the 16 divisions contained in the Construction Specifications Institute (CSI) format (see model construction solicitation). The Contractor shall furnish price lists comparing available foreign materials to equivalent U.S. materials, if known, that may be used in construction.
The Contractor shall identify any contingencies for each division.
G.3.5. The Contractor shall furnish quantities and pricing data for each section within each division showing labor, materials, overhead, and profit. The Contractor shall
19 19MK8025Q0009
furnish a list of all foreign materials to be used in the facilities with their unit prices compared to prices for comparable U.S. materials. The costs for U.S. materials shall include, as a separate item, the estimated shipping costs to the site of construction. If the
Contractor has specified a foreign material and there is no comparable U.S. material, the
Contractor shall identify the material, and the price of the foreign material used.
G.3.6. The Contractor shall compare these estimates to the design-to-budget amount and confirm that the facilities as designed can be constructed in the designated locale within the budgeted amount. The Contractor shall promptly advise the Contracting Officer whenever it may know, or have reason to believe, that the estimated cost of construction for the facilities being designed will exceed or is likely to exceed the design-to-budget cost.
In addition to the clause of FAR 52.236-22, if at any time it is determined that the estimated cost of construction exceeds the design-to-budget amount, the Contracting
Officer may direct the Contractor to perform redesign and other services as needed to reduce the estimated cost of construction to an amount that is within the design-to-budget amount. The Contractor shall perform redesign and other services no additional cost to the Government. The Contractor shall not be required to perform such redesign and other services at no cost to the Government if the Contracting Officer determines that the estimated cost of construction exceeds the design-to-budget amount for reasons beyond the reasonable control of the Contractor.
G.4.0. REIMBURSABLE EXPENSES
N/A
G.5.0. ORGANIZATIONAL CONFLICTS OF INTEREST
Neither the Contractor nor any of its employees, affiliates, or related entities may propose on the construction effort envisioned by this contract. The Contractor, its employees, affiliates, or related entities may not provide consulting or subcontract services related to the construction to any offeror or prospective offeror on the construction contract.
The Contractor shall include this clause in all subcontracts, purchase orders, and consulting agreements for service.
G.6.0. RELEASE OF INFORMATION
All data furnished to the Contractor and data developed in connection with the project shall be considered privileged. The Contractor shall not make public announcements, including news and press releases; these are the prerogative of the Contracting Officer.
G.7.0. NOTIFICATION OF CHANGES
G.7.1. This clause applies to changes other than changes directed by the Government pursuant to the contract clause titled "Changes - Fixed Price (AUG 87) Alternate III
(APR 1984)."
20 19MK8025Q0009
G.7.2. Definitions. "Contracting Officer," as used in this clause, does not include representatives of the Contracting Officer.
G.7.3. Notice. The primary purpose of this clause is to obtain prompt reporting of
Government conduct that the Contractor considers to be a change to this contract. Except for changes identified in writing and signed by the Contracting Officer, the Contractor shall notify the Contracting Officer in writing within ten (10) days from the date the
Contractor identified any Government conduct (including actions, inactions, and written or oral communications) that the Contractor regards as a change to the contract terms and conditions. Any notification received after 10 days will not be considered. Based on the most accurate information available to the Contractor, the notice shall state -
(i) The date, nature and circumstances of the conduct regarded as a change.
(ii) The name, function, and activity of each Government individual and
Contractor official or employee involved in or knowledgeable about such conduct.
(iii) The identification of any documents and the substance of any oral communication involved in such conduct.
(iv) In the instance of alleged acceleration of scheduled performance or delivery, the basis upon which it arose.
(v) The elements of contract performance that the Contractor may seek an equitable adjustment under this clause, including –
• What contract line items have been or may be affected by the alleged change.
• What labor or materials or both have been or may be added, deleted, or wasted by the alleged change.
• To the extent practicable, what delay and disruption in the manner and sequence of performance and effect on continued performance have been or may be caused by the alleged change.
• What adjustments to contract price, delivery schedule, and other provisions affected by the alleged change are estimated; and
(vi) The Contractor's estimate of the time by which the Government must respond to the Contractor's notice to minimize cost, delay, or disruption of performance.
G.7.4. Continued Performance. Following submission of the notice required above, the
Contractor shall diligently continue performance of this contract to the maximum extent possible in accordance with its terms and conditions as construed by the Contractor.
Unless the notice reports a direction of the Contracting Officer or a communication from a representative of the Contracting Officer, the Contractor shall continue performance.
However, if the Contractor regards the direction or communication as a change as described above, notice shall be given in the manner provided.
21 19MK8025Q0009
G.7.5. Government Response. The Contracting Officer shall, within thirty (30) days after receipt of notice, respond to the notice in writing. In responding, the Contracting
Officer shall -
(1) Confirm that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance.
(2) Countermand any communication regarded as a change.
(3) Deny that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance; or
(4) Advise the Contractor what additional information is required and when and establish the date by which it should be furnished and the date the
Government will respond.
G.7.6. Equitable Adjustments.
If the Contracting Officer confirms that the Government conduct effected a change as alleged by the Contractor, and the conduct causes an increase or decrease in the
Contractor's cost of, or the time required for, performance of any part of the work under this contract, the Government will modify the contract to make an equitable adjustment -
(1) In the contract price or delivery schedule or both; and
(2) Any other term of the contract affected.
In the case of drawings, designs, or specifications that are defective, and the Government is responsible, an equitable adjustment shall include the cost and time extension for the delay reasonably incurred by the Contractor in attempting to comply with the defective drawings, designs, or specifications before the Contractor identified, or reasonably should have…
This is the start of the file's text. The full file is on GovTribe.