This is Amendment 0001 to Solicitation 19KU2026Q0013, issued by the American Embassy Kuwait on August 12, 2026, for requisition PR16110464. The amendment revises the Statement of Work (SOW) based on Questions and Answers received and incorporates updated technical requirements for two specific work items.
Paragraph 3.5.1 regarding installation of an exterior door has been revised to specify that the glass shall be double-glazed, tempered, Low-E glass consisting of 6 mm + 20 mm + 6 mm configuration and must comply with ANSI Z97.1-1984 safety standards. Paragraph 3.5.3 for fabrication and installation of a transaction counter has been clarified to require a Corian countertop finish. The amendment was issued July 26, 2026, and the receipt deadline was not extended from the original solicitation date. Offerors must acknowledge receipt of this amendment prior to the submission deadline through one of three methods: completing and returning copies of the amendment, acknowledging receipt on each copy of the offer submitted, or submitting a separate letter or electronic communication referencing the solicitation and amendment numbers. All other terms and conditions of the original solicitation remain unchanged.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended.
is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this amendment is to revise the Statement of Work (SOW) based on the Questions and Answers (Q&As) and to incorporate the following updated requirements under Paragraphs 3.5.1 and 3.5.3:
1. Paragraph 3.5.1 – Install Exterior Door
Paragraph 3.5.1 is revised to include the following glass specification: The glass shall be double-glazed, tempered, Low-E, consisting of 6 mm + 20 mm + 6 mm. The glass shall comply with ANSI Z97.1-1984 safety standards.
2. Paragraph 3.5.3 – Fabricate and Install Transaction Counter
Paragraph 3.5.3 is revised to clarify the required countertop finish: The transaction counter shall be provided with a Corian countertop.
All other terms and conditions of the solicitation remain unchanged.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
Previous edition unusable STANDAR
D FORM
30 (REV.
11/2016 Prescribed by GSA FAR
(48 CFR) 5
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
2. AMENDMENT/MODIFICATION NUMBER
PAGE OF PAGES
6. ISSUED BY
5. PROJECT NUMBER (If applicable)
CODE 19KU20 7. ADMINISTERED BY (If other than Item 6) CODE
AMERICAN EMBASSY KUWAIT
AL MASJID AL AQSA STREET ATTN: GSO/Procurement
BAYAN,
KUWAIT 13001
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION NUMBER
19KU2026Q0013
9B. DATED (SEE ITEM 11)
July 26/2026
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE
(X)
4. REQUISITION/PURCHASE REQUISITION NUMBER
PR16110464
3. EFFECTIVE DATE
Aug 12, 2026
1. CONTRACT ID CODE
File details come from the government source that posted it. Updated .