This is a Questions and Answers document for RFQ 19H08026Q0050 issued by the SBU - Contracting and Acquisitions office.
The document addresses a vendor inquiry regarding delivery timelines for concrete construction materials. The vendor inquired whether a 45 to 60-day lead time for specialized concrete pavers manufactured in Choluteca would be acceptable, noting this option would be the most cost-effective. The vendor also inquired whether the procurement required delivery within a strict 20-day window. The government's response clarified that the delivery period cannot be extended and concrete pavers must be delivered within 20 days. The document indicates the procurement includes both concrete blocks (available for immediate delivery) and concrete pavers (specialized manufactured products), though specific quantities, pricing terms, or other procurement details are not addressed in this Q&A excerpt.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation Document_19H08026Q0050.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SBU - CONTRACTING AND ACQUISITIONS
Questions and Answers
RFQ 19H08026Q0050
Questions
1. Los bloques de hormigón están disponibles para su entrega prácticamente de inmediato. En cuanto a los adoquines de hormigón, se trata de un producto más especializado que requiere fabricación una vez formalizado el pedido; esto conlleva un plazo de entrega aproximado de 45 a 60 días. Se fabrican en Choluteca. Esta sería, por supuesto, la opción más económica. ¿Les parece bien esta alternativa?
¿O el pedido requiere que obtengamos los adoquines en un plazo estricto de 20 días?
Informal Translation:
1. The concrete blocks are available and can be delivered almost immediately. The concrete pavers, however, are a more specialized product that has to be manufactured once the order is confirmed, so the estimated lead time is about 45 to 60 days. They're manufactured in Choluteca, and this would definitely be the most cost-effective option.
Would this timeline work for you, or does the order require us to supply the pavers within a strict 20-day delivery period?
Answer
1. Lastimosamente no es posible extender el periodo de entrega. Por lo tanto, solicitamos que los mismos sean entregados en el plazo de 20 días.
Informal Translation:
1. Unfortunately, we are unable to extend the delivery period. Therefore, we kindly request that the concrete pavers be delivered within 20 days.