This document appears to be a Statement of Work (SOW) for the repair and modification of an air-cooled packaged chiller system located at the U.S. Embassy Chancery building in Vienna, Austria. The scope of work includes the replacement and modification of the hot gas line between the compressor and condenser, replacement of expansion valves, installation of shut-off valves and sight glasses in the liquid line, and replacement of the data interface cable between the control units. The work also involves system decommissioning, vacuuming, leak testing, evacuation, refrigerant recharging, and commissioning. The SOW provides a detailed list of the specific materials and labor required. The related federal contract opportunity has a solicitation number of 19AU9024Q0024 and is being issued by the U.S. Department of State for the chiller repairs at the Vienna Chancery facility. The contract is a lump-sum award with a net price listed.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 19AU9024Q0024_SF1449_Chiller_Repair.docx | DOCX document | |
| 19AU9024Q0024_Solicitation_Chiller_Repair.docx | DOCX document | |
| 19AU9024Q0024_Cover Letter_Chiller_Repair.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| SOW_Chancery (1090 Vienna, Boltzmanngasse 16) Chiller repairs |
| LV_Chancery_ Boltzmanngasse 16, 1090 Wien- Instandsetzung Kaeltemaschine (Danfoss Turbocor) |
| Item | Scope of work/Leistungsbeschreibung | Lump sum /€ net |
| Air cooled AIRSTACK packaged chiller (2 modules) with Danfoss TT300- twin turbine centrifugal compressor and Beckhoff control unit | ||
| Luftgekühlte AIRSTACK-Paketkältemaschine (2 Module) mit Danfoss TT300-Doppelturbinen-Radialverdichter und Beckhoff-Steuerung |
| 1 (english) | The scope of the offer is the replacement and modification of the hot gas line between compressor and condensor |
| in circuits 1 & 2 and the replacement of the expansion valves, installation of shut- off valves and sight glasses | |
| in the liquid line for circuits 1 & 2 and the data interface cable replacment btw. FlexSys control unit and Turbocor 2. |
| Task list: |
| System decommissioning |
| System vacuuming |
| Installation and replacement of all components listed below |
| Leak test using technical nitrogen |
| Evacuation of the circuits |
| Filling the system using the refrigerant provided |
| Commissioning the system |
| Function & running check |
| Creation of a commissioning report |
| Entry in the test logbook |
| Documentation- R&I diagram in CAD |
| Labor: |
| System decommissioning, system vacuuming, installation 2 sight glasses, 8 Alco filter driers, 2 Danfoss check valves CHV-X 40D, |
| 2 Danfoss shut-off valves SVA-S 40D, 4 Danfoss ball shut-off valves 35mm, leak testing, commissioning and function test together |
| with BAS technician, R&I diagram in CAD |
| Material: |
| 2 liquid sight glasses DN32, 8 Alco filter driers/cores H48006969 for 2 systems, 2 Danfoss check valves CHV-X 40D, |
| 2 Danfoss shut-off valves SVA-S 40D, 2 Danfoss ball shut-off valves 35mm 1-3/8", 2m copper pipes 35mm and 54mm incl. all |
| necessary incidentals and data interface cable Turbocor I/O modul |
| 1(german) | Gegenstand des Angebotes ist der Austausch und die Adaptierung der Heißgasleitung zwischen Verdichter und |
| und Verflüssiger in den Kreisläufen 1 & 2 und der Austausch der Expansionsventile, Einbau von Absperrventilen und Schaugläsern | |
| in der Flüssigkeitsleitung für die Kreisläufe 1 & 2 und das Datenschnittstellenkabel btw. FlexSys-Steuereinheit und Turbocor 2. |
| Aufgabenliste: |
| Außerbetriebnahme der Anlage |
| Absaugen des Systems |
| Einbau und Austausch aller unten aufgeführten Komponenten |
| Dichtheitsprüfung mit technischem Stickstoff |
| Evakuierung der Kreisläufe |
| Befüllung der Anlage mit dem mitgelieferten Kältemittel |
| Inbetriebsetzung der Anlage |
| Funktions- und Laufkontrolle |
| Erstellung eines Inbetriebnahmeprotokolls |
| Eintrag in das Prüfbuch |
| Dokumentation - R&I-Schema in CAD |
| Arbeitsaufwand: |
| Außerbetriebnahme der Anlage, Absaugen der Anlage, Einbau von 2 Schaugläsern, 8 Alco Filtertrocknern, 2 Danfoss Rückschlagventilen |
| CHV-X40D, 2 Danfoss Absperrventile SVA-S 40D, 4 Danfoss Kugelabsperrventile 35mm, Dichtheitspruefung, Inbetriebnahme und |
| und Funktionstest mit MSR Techniker, R&I Schema in CAD |
| Material: |
| 2 Flüssigkeitsschaugläser DN32, 8 Alco Filtertrockner/Kerne H48006969 für 2 Systeme, 2 Danfoss Rückschlagventile CHV-X 40D, |
| 2 Danfoss Absperrventile SVA-S 40D, 2 Danfoss Kugelabsperrventile 35mm 1-3/8“, 2m Kupferrohre 35mm und 54mm inkl. allem |
| notwendigem Zubehör und Datenschnittstellenkabel Turbocor I/O modul |
Lump sum €, net/Gesamtpreis € netto:
&P Facility Management/FAC July 2024