This document contains questions and answers related to a solicitation for labor support services for the Department of State's Bureau of International Security and Nonproliferation. The solicitation seeks on-site labor to provide program management and execution support for the Office of Weapons of Mass Destruction Terrorism, Office of the Biological Policy Staff, Office of Nuclear Energy, Safety and Security, and Office of Counterproliferation Initiatives. The answers clarify that the staffing plan and transition plan should be included in the management approach section of the technical proposal, confirm page limits for resumes and past performance profiles, and correct pricing and facility clearance information on forms. No direct information is provided about the required services, response date, or other solicitation details.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 19AQMM24R0027-0005.pdf | ||
| 19AQMM24R0027-0004.pdf | ||
| 19AQMM24R0027-0003.pdf | ||
| 19AQMM24R0027-0001.pdf | ||
| 19AQMM24R0027-0002.pdf | ||
| QUESTIONS AND ANSWERS 2 19AQMM24R0027 RFP.docx | DOCX document | |
| WMDT - PPQ.doc | DOC document | |
| 19AQMM24R0027 POSTED.pdf | ||
| SECTION J Attachment A- Performance Work Statement.pdf | ||
| SECTION J - ATTACHMENT B- Bidders - Approved DD-254.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SBU - CONTRACTING AND ACQUISITIONS
Reference: RFP
Section #
Title: Paragraph(s)
Page(s) # Question
1. L.3.1 Volume I:
Technical
Proposal
VOLUME I:
TECHNICAL
PROPOSAL
top of page Page 21 of 27 "Factor 2: Management Approach 5 page limit in addition to:
Draft Quality Control Plan."
Could the Government please confirm if the Draft Quality
Control Plan is inside the 5 page limit or if it has a page limit?
ANSWER: Corrected
2. L.3.1 Volume I:
Technical
Proposal
SECTION M –
EVALUATION
FACTORS
FOR AWARD
Factor 3: Key
Personnel
M.3.2 Factor 2:
Management
Approach letters c and d letter b
The Staffing plan is referenced in two different sections.
Factor 3: Key Personnel: "c. Propose a staffing plan that describes how it will satisfy contract requirements per section C.4 of the
PWS. Outline an effective strategy as to how it will acquire and retain qualified and experienced personnel with current certifications as identified in the PWS.
d. Provide a Staffing Plan using the format provided in the table below. The staffing plan must identify all personnel, including key personnel and summarize hours, per labor category and offeror proposed WBS Level 3 elements, across the life of the contract.
The staffing plan must identify subcontractor(s), if any, who will be used in performing under the task order, the qualifications of the
Offeror’s subcontractor team, and how they will be managed."
Factor 2: Management Approach: "b. The extent to which the
Offeror’s proposed staffing plan and alignment of hours per labor category per WBS Level 3 element demonstrate its ability to satisfy contract requirements and acquire and retain qualified and experienced personnel."
Could the Government please confirm where the Staffing Plan should go?
ANSWER: Staffing Plan should be included within the
Management Approach
3. L.3.1 Volume I:
SECTION M –
EVALUATION
FACTORS
FOR AWARD
Factor 3: Key
Personnel
M.3.2 Factor 2:
Management
Approach letters a
(under
Sample
Staffing
Matrix) letter c
The Transition plan is referenced in two different sections.
Factor 3: Key Personnel: "a. Propose a draft transition plan which identifies all actions for a successful implementation of this contract."
Factor 2: Management Approach: "c. The Offeror’s proposed draft transition plan will be evaluated for completeness, timeliness of transition process, efficiency, understanding and consideration of the current environment, and risk identification and mitigation strategies that will allow a timely and seamless assumption of services."
Could the Government please confirm where the Transition
Plan should go?
4. L.3.1 Volume I:
Technical
Proposal
VOLUME I:
TECHNICAL
PROPOSAL
top of page Page 21 of 27 "Factor 3: Key Personnel Resumes 20 page limit in addition to:
Work Breakdown Structure (WBS) no page limit for Work
Breakdown Structure; can be provided as Excel or Word format"
2 page limit per resume
15 page limit
Could the Government please confirm if the page limit for
Factor 3 is 15 pages or 20 pages?
ANSWER: 20 page limit as stated
5. L.3.1 Volume I:
L.4.2 Volume
II: Price
Proposal
VOLUME I:
TECHNICAL
PROPOSAL
VOLUME II: Price
PROPOSAL (No
Page Limits) top of page middle of page
"Factor 4: Past Performance Summaries 2 page limit per past performance profile
Assumptions and Exceptions 2 page limit”
After bullets, it lists “Assumptions and Exceptions”
Could the Government please confirm if the Assumptions and
Exceptions section should be in Volume I Technical Proposal
Factor 4 with a 2 page limit? If it should be in Volume II instead, is the page limit still 2 pages?
ANSWER: SHOULD BE INCLUDE IN WITH THE TECHNICAL VOLUME
6. L.4.2 Volume
II: Price
Proposal
VOLUME II: Price
PROPOSAL (No
Page Limits)
"Completed
RFP Sections
B, D thru K, inclusive"
Page 24 of 27 Under Section H, "52.217-8 - Option to Extend Services (Nov
1999)" and "52.217-9 - Option to Extend the Term of the
Contract (Mar 2000)", should we complete the blanks (for time period to extend) in the Volume with the submission, or will that be done following award?
ANSWER: CORRECTED
7. DD254 Form Sections 1a top of page page 1 of 4 Section 1a. Level of Facility Clearance: Should this be Top
Secret (shows Secret)?
ANSWER: SECRET IS CORRECT
8. DD254 Form Sections 8 middle of page page 2 of 4 Section 8. Actual Performance: Should each location should be noted, both Washington, DC and Arlington, VA
ANSWER: YES
9. DD254 Form Sections 10 top of page page 2 of 4 Section 10: Access Requirements: Should the following be checked?
COMSEC
Restricted Data
Alternative Compensatory Control Measures (ACCM)
Information
Critical Nuclear Weapon Design Information
Formerly Restricted Data
SCI – Yes
Non-SCI – Yes
NATO
Sensitive but unclassified information (SBU)
ANSWER: DD 254 WILL BE REVISED
10. DD254 Form Sections 11 middle of page page 3 of 4 Section 11: Should the following also be checked?
Have access to classified information only at another contractor's facility or a government activity
ANSWER: DD 254 WILL BE REVISED
Have access to U.S. Classified information outside the
US, Puerto Rico, US Possessions and Trust territories
ANSWER: DD 254 WILL BE REVISED
11. SF-33
Continuation
Pages
Cost/Pricing Tables Quantity and
Unit columns
Pages 2 -
Should the “Unit” for Line Items 001 - 007 be Hours and not
Each?
ANSWER: CORRECTED
12. SF-33
Continuation
Pages
Cost/Pricing Tables Line Item
X008
Pages 2 -
Line Item 008 is titled Firm Fixed Price; however the type of contract pricing is listed as LH and the quantity is 1,950.00.
Can the Government clarify this Line Item?
ANSWER: CORRECTED