19AQMM20R0043.pdf
PDF 193 KB Posted
- Solicitation number
- 19AQMM20R0043
About this file
This is a solicitation for a firm fixed-price construction contract issued by the Department of State to build Building B at the National Foreign Affairs Training Center in Arlington, Virginia. The project scope involves constructing approximately 150,000 square feet of space including classrooms, offices, student support areas, and infrastructure to consolidate training programs and eliminate nearly 100,000 square feet of off-site office space. Interested offerors must submit a letter by December 10th including company information and security clearance level to access the solicitation documents on ProjNet. A pre-proposal conference will be held on December 19th. The contract award is for a not-to-exceed amount of $70-90 million. Prime contractors and designated subcontractor personnel must possess secret security clearances, and the prime contractor must have a secret facility clearance. Joint ventures must each have a secret facility clearance.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 19AQMM20R0043 0007.pdf | ||
| 19AQMM20R0043 0006.pdf | ||
| 19AQMM20R0043 0005.pdf | ||
| 19AQMM20R0043 0004.pdf | ||
| 19AQMM20R0043 0003.pdf | ||
| 19AQMM20R0043 0002.pdf | ||
| 19AQMM20R0043 0001.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
19AQMM20R0043 SEALED BID (IFB)
X NEGOTIATED (RFP)
2. TYPE OF SOLICITATION 3. DATE ISSUED
12/10/2019
RATING
DO-H8
IMPORTANT -The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
CODE LMAQM
OFFICE OF ACQUISITION MANAGEMENT (A/LM/AQM)
PO BOX 9115, ROSSLYN STATION
US DEPARTMENT OF STATE
ARLINGTON, VA 22219
7. ISSUED BY
OFFICE OF ACQUISITION MANAGEMENT
(A/LM/AQM)
PO BOX 9115, ROSSLYN STATION
US DEPARTMENT OF STATE
ARLINGTON, VA 22219
8. ADDRESS OFFER TO
9. FOR INFORMATION EMAIL: a. NAME
Keith Westry
b. TELEPHONE NO. (Include area code)(NO COLLECT CALLS)
703-516-1964
c. EMAIL westryk@state.gov
SOLICITATION
NOTE: In sealed bid solicitations "offer" and "offeror" means "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
Project Title: Design-Bid-Build, National Foreign Affairs Training Center (NFATC); Building B, Arlington, VA
Drawings are included for the sole purpose of illustrating the design intent of the owner.
The entire contract document including Sections C and Section J, List of Attachments as follows:
J.1 ADMINISTRATIVE DOCUMENTS
J.2 STANDARD DESIGN REQUIREMENTS DOCUMENTS
J.3 PROJECT-SPECIFIC REQUIREMENTS DOCUMENTS
52.232-18 -- Availability of Funds. (Apr 1984) Funds are not presently available for this contract. The Government's obligation under this contract is contingent upon the availability of appropriated funds from which payment for contract purposes can be made. No legal liability on the part of the Government for any payment may arise until funds are made available to the Contracting Officer for this contract and until the Contractor receives notice of such availability, to be confirmed in writing by the Contracting Officer.
11. The Contractor shall begin performance within ___15___ calendar days and complete it within ___730___ calendar days after receiving award, X notice to proceed. This performance period is X mandatory negotiable. ( (See _52.211-10_.)
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS? (If "YES," indicate within how many calendar days after award in Item 12b).
X YES NO
12b. CALENDAR DAYS
Sealed offers in original and __2__ copies to perform the work required are due at the place specified in item 8 by __14:00:00__ (hour) local time __02/11/2020 __ (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
a.
b. An offer guarantee X is, is not required.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.c.
d.
Offers providing less than __120__ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
13. ADDITIONAL SOLICITATION REQUIREMENTS:
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA - FAR (48 CFR) 53.236-1(e)
19AQMM20R0043
OFFER (Must be fully completed by offeror)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
CONTACT: DUNS:
CODE FACILITY CODE
The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
17.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM
10 U.S.C. 2304(c) ( ) 41 U.S.C. 253(c) ( )
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY LMAQM
OFFICE OF ACQUISITION MANAGEMENT (A/LM/AQM)
PO BOX 9115, ROSSLYN STATION
US DEPARTMENT OF STATE
ARLINGTON, VA 22219
GLOBAL FIN. SVCS (RM/GFS/ADO/FM) CHARLESTON,
SOUTH CAROLINA
PO BOX 150008
ATTN: PSU INVOICE PROCESSING (RM/GFS/S/PSU)
CHARLESTON, SC 29415-5008
27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return __________ copies to issuing office) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No futher contractual document is necessary.
30a.NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
Keith Westry 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA
BY
12/10/2019
31c. DATE
STANDARD FORM 1442 (REV. 4-85) BACK
Table of Contents
Section Description Page Number
B Supplies or Services and Prices/Costs Section B Pricing
C Descriptions/Specifications/Statement of Work Section C Description/Specifications/Work Statement
D Packaging and Marking Section D Packing and Marking
E Inspection and Acceptance 52.246-12 Inspection of Construction (Aug 1996) Section E Inspection and Acceptance
F Deliveries or Performance Section F Deliveries and Performance
G Contract Administration Data Section G Contract Administration Data
H Special Contract Requirements Section H Special Contract Requirements
I Contract Clauses Section I Contract Clauses
J List of Attachments K Representations, Certifications, and Other Statements of Offerors or Respondents
Section K Representations and Instructions L Instructions, Conditions, and Notices to Offerors and Respondents M Evaluation Factors for Award
Section M Evaluation Factors for Award
001 Construction of National Foreign Affairs Training Center (NFATC)Building B, Arlington, Virginia .
1.00 JB
The contractor shall complete all work to construct the National Foreign Affairs Training Center (NFATC)Building B in Arlington, Virginia including furnishing all professional services, labor, material, equipment and services, unless otherwise specified herein, required under this contract for the following firm fixed price and within the time specified herein.
Doc Ref No:
Delivery Date FOB:
Section B Pricing
B.1 PRICING
B.1.1 As a firm-fixed price contract, the Contract Price includes all labor, materials, equipment and services necessary to accomplish the construction required by the Contract Documents, including applicable customs duties, transportation to the site, storage, premi-ums for insurance and bonds required by the Solicitation Documents and/or the Contract Documents, permits, license and inspection fees, taxes, and all other items called for by the contract or otherwise necessary for performance of the contract. The Contract Price may be adjusted only by a written Contract modification signed by the Contracting Officer (CO).
B.1.2 The contractor shall complete all work, including furnishing all labor, material, equipment and services as called for and re-quired by the terms and conditions of this contract document and all attachments hereto. The maximum time allowable for perform-ance has been identified in Section/Paragraph F.1, clause 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLE- TION OF WORK (APR 1984) (Reference FAR 11.404(b)). The price is firm fixed-price and shall include all labor, materials, equipment, services, overhead, bonds, and cost for insurance.
B.2 CONTRACT PRICE - CONTRACT LINE ITEM NUMBERS (CLIN)
19AQMM-20-R0043: National Foreign Affairs Training Center (NFATC)Building B, Arlington, Virginia
CONTRACTOR COMPLETES CONTRACT LINE ITEM NUMBERS (CLINs): CLINs 0001 and Section/Paragraph B.7.2
CLIN 0001 Construction: The contractor shall complete all work to construct the National Foreign Affairs Training Center (NFATC)Building B in Arlington, Virginia including furnishing all professional services, labor, material, equipment and services, un-less otherwise specified herein, required under this contract for the following firm fixed price and within the time specified herein.
This price shall include all labor, materials, equipment, overhead insurance and fees, bonds, and profit and all costs for project Gen-eral Requirements. See H.4.1 Bid Guarantee
Construction Services: 1 LS $________________ _
See Section L for information on the required Breakdown of the Proposal Price.
B.3 TYPE OF CONTRACT
This contract is Firm Fixed-Price payable entirely in the currency indicated on the SF1442. No additional sums will be payable on ac-count of any escalation in the cost of materials, equipment, services or labor, or because of the contractor’s failure to properly estimate or accurately predict the cost or difficulty of achieving the results required by this contract. Changes in the contract price or time to complete will be made only due to changes made by the Government in the work to be performed, or by delays caused by the Govern-ment.
19AQMM20R0043
Line Item Summary
Solicitation Number:
19AQMM20R0043
Contract Number: Title: National Foreign Affairs Training Center Bldg B
Date of Solicitation:
12/10/2019
Line Item No. Description Quantity Unit Unit Price Total Cost
B.4 COST OF MATERIALS/EQUIPMENT
The cost of any materials or equipment required in conjunction with the services rendered herein shall be included in the proposed firm fixed-price.
B.5 RESERVED
B.6 PROJNET RFP QUESTIONS AND RESPONSES
Request for Proposal questions are entered into ProjNet by the contractor(s) and responded to by the Government (ProjNet Q&A).
ProjNet Q&A does not change the RFP. The Q&A is intended to clarify requirements and to reflect the parties understanding of the specific RFP performance requirements at time of award. The initial RFP as amended shall form the contract between the contracting parties. ProjNet Q&A will be reviewed and utilized during the course of contract execution and performance to ensure the descriptive and instructive clarifications provided and used to assure understanding of the performance requirements and relied on during the RFP and proposal development phase are implemented.
B.7 MODIFICATION PRICING – FIELD OFFICE OVERHEAD COMPUTATION
B.7.1 The contractor shall identify in its proposal the accounting method it will utilize to compute and recover costs incurred at or in the vicinity of the job site incident to performing the work, such as the cost of superintendence, timekeeping and clerical work, engin-eering, utility costs, supplies, material handling, restoration and cleanup, etc. (“Field Office Overhead”), if applicable, in contract modifications. The contractor may choose any acceptable distribution base for allocating its Field Office Overhead pool(s) to particu-lar cost objectives, but not more than one. The identified method of accounting for Field Office Overhead shall be utilized consist-ently throughout the performance of the contract.
Section C- Descriptions/Specifications/Statement of Work
Section C Description/Specifications/Work Statement
See separate document within this electronic RFP package
C.1 PROJECT SCOPE
1. Project Location: National Foreign Affairs Training Center (NFATC), Arlington, Virginia
2. Project consists of the construction of the Foreign Service Institute Building B on the NFATC Campus as described within the scope of the Contract Documents.
3. Work Included: Provide labor, materials, articles, equipment, incidentals, items, tools, services, supplies, methods, operations, skills in such quantities as may be necessary to complete Project within intent of Contract Documents.
4. Partial demolition and restoration of existing civil and landscaped areas for construction of the building addition.
5. Fire alarm and fire suppression service.
6. HVAC, Electrical, and Plumbing service for new space design.
Singular notations shall be considered plural where plural application is reasonably inferable. Mention or indication of extent of work under work Division or Specification Section is done only for convenience of Contractor and shall not be construed as describing all work required under that Division or Sectio
Section D- Packaging and Marking
Section D Packing and Marking
D.1 MATERIALS SHIPPING ADDRESS
D.1.1 Materials delivered to the site shall be marked in accordance with Section 015141, Security Specifications.
D.2 DEPARTMENT OF STATE DELIVERY, MAIL AND COURIER ADDRESSES
D.2.1 Unclassified and SBU hand-carry deliveries from the contractor to DoS shall be made to the following address between the hours 8:00 AM and 4:00 PM. The contractor shall advise the intended recipient of the materials and estimated time of arrival a min-imum of 24 hours prior to dispatching the package by courier.
David Grossweiler Office of Real Property Management (A/OPR/RPM) 2201 C Street, NW Main State, Room 1264 Washington, DC 20520
D.2.2 Unclassified and SBU packages sent via U.S. Mail, Registered or Certified Mail and shall be addressed as follows:
U.S. Department of State Office of Acquisition Management A/OPE/AQM/FDCD – SA-6A, Suite 400 Attn: Michael Howard P. O. Box 9115, Rosslyn Station Arlington VA 22219
D.2.3 Unclassified and SBU packages sent via commercial courier service shall be addressed as follows:
U.S. Department of State Office of Acquisition Management A/OPE/AQM/FDCD - SA-6A Suite 400 Attn: Michael Howard (Other delivery/recipient instructions can be listed here) 1735 N. Lynn Street Suite 400
ARLINGTON, VA 22209
D.3 PACKAGING REQUIREMENTS FOR MAIL AND COURIER SHIPMENT OF DOCUMENTS AND DRAWINGS
D.3.1 Separate packaging of electronic media and hardcopy material Contractor and any associated subcontractors will package all drawings and electronic media (classified, SBU and unclassified) in sep-arate mailing packages. Specifically, electronic media will be transported in electronic media packages that contain no other drawings or hard copies of any kind, beyond that of transfer/receipt documentation. Hardcopy (paper) drawing and documents will be packaged separately.
D.3.2 Double-wrapping and addressing of packages For all shipping methods, the prime contractor and any associated subcontractors will ensure that all project documentation, regardless of classification, is double-wrapped with both layers addressed properly and labeled with the sender’s address. Document tracking re-ceipts should be packaged inside the inner wrapping with the materials the receipt describes. No indication of the classification or sensitivity should appear on the outer wrapper. Unclassified and SBU packages addressed to overseas facilities or sites may not have the words “blueprints” or “drawings” displayed on the outer wrapper.
D.3.3 Packaging heavy materials in appropriate containers In applying the above double-wrapping and addressing procedures, items sent via US mail or commercial carrier weighing more than one (1) pound shall be enclosed within an appropriately sized double-walled box or, for rolled drawings, a manufactured mailing tube.
The cardboard box or mailing tube counts as the second layer of wrap.
Reference:
DOSAR 652.242-71 NOTICE OF SHIPMENTS (JUL 1988) Section/Paragraph I.81 DOSAR 652.242-72 SHIPPING INSTRUCTIONS (DEC 1994) Section/Paragraph I.81a
Section E- Inspection and Acceptance
Clause Title
52.246-12 Inspection of Construction (Aug 1996)
Section E Inspection and Acceptance
E.1 52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)(Reference 46.312)
E.2 SUBSTANTIAL COMPLETION
Definitions.
E.2.1. “Substantial Completion” means the stage in the progress of the work as determined and certified by the Contracting Officer or Contracting Officer’s Representative in writing to the Contractor, on which the work or a portion thereof designated by the Govern-ment is sufficiently complete and satisfactory, in accordance with the requirements of the Contract Documents, that it may be occu-pied or utilized for the purpose for which it is intended, and only minor items such as touch-up, adjustments, and minor replacements or installations remain to be completed or corrected which (1) do not interfere with the intended occupancy or utilization of the work, and (2) can be completed or corrected within the time period required for final completion. (See J.3.4, Specifications, Division 1, Sec-tion 017705 for Substantial Completion procedures).
E.2.2 “Date Of Substantial Completion.” means the date determined by the Contracting Officer or Contracting Officer’s Representat-ive of which substantial completion of the work has been achieved.
E.3 USE OF EQUIPMENT BY THE GOVERNMENT
E.3.1 Right to use. The Government may take over and operate, with Government employees, such equipment as is necessary for heating or cooling such areas of the building as require the service, and other equipment such as elevators, electrical, plumbing and mechanical systems, as soon as the installation is sufficiently complete to permit operation.
E.3.2 Notice. The COR will advise the Contractor in writing, prior to the use of the equipment, which items of equipment will be op-erated, and the date and time such operation shall begin.
E.3.3 Effect on warranties. Government operation of equipment will not relieve the Contractor of any warranty or correction obliga-tions elsewhere provided for in this contract. The applicable correction period, elsewhere provided for in this contract, for each piece of equipment shall be in accordance with the applicable provisions of this contract.
E.4 FINAL COMPLETION AND ACCEPTANCE
E.4.1 Definitions.
E.4.1.1 “Final Completion and Acceptance” means the stage in the progress of the work as determined and certified by the CO or COR in writing to the Contractor, on which all work required under the contract has been completed in an acceptable manner in ac-cordance with the contract requirements, subject to the discovery of latent defects after final completion, and except for items specific-ally excluded in the notice of final acceptance.
E.4.1.2 “Date Of Final Completion And Acceptance” means the date determined by the Contracting Officer as of which final comple-tion of the work has been achieved, as indicated by written notice to the Contractor. (See J.3.4, Specifications, Division 1, Section 017705, Closeout procedures)
E.4.1.2.1 Reserved
E.4.1.2.2 Reserved
E.5 QUALITY ASSURANCE AND QUALITY CONTROL
(Also See J.3.4, Project Specific Division 1, Section 014000 and 014500)
E.5.1 CONSTRUCTION QUALITY ASSURANCE AND QUALITY CONTROL
E.5.1.1 The Contractor shall institute an appropriate inspection system including checklists of duties to be carried out, ensuring these duties are carried out by the supervisory staff and senior employees, and carrying out weekly inspections to determine whether the various services are being performed according to the contract requirements. Copies of the weekly inspection reports shall be provided to the COR seven (7) days after end of weekly period.
E.5.1.2 Any shortcomings and/or substandard conditions noted in such inspections shall be promptly corrected and improved; any conditions beyond the responsibility of the Contractor shall be brought to the attention of the Contracting Officer or COR, for disposi-tion.
E.5.1.3 Monthly Report: The Contractor shall render a monthly progress report, summing up observations resulting from the inspec-tions, progress, difficulties or irregularities encountered, resolution of problems, measures taken to improved conditions, recommenda-tions, and other matters related to this contract. This monthly report shall be submitted to the COR, together with the Contractor’s monthly invoice.
E.5.1.4 Inspection by Government: The services being performed hereunder and the supplies furnished will be inspected from time to time by the COR, or his/her authorized representatives, to determine that all work is being performed in a satisfactory manner, and that all supplies are of acceptable quality and standards.
E.5.1.5 The Contractor shall be responsible for any countermeasures or corrective action, within the scope of this contract, which may be required by the Contracting Officer as a result of such inspection.
E.6 RESERVED
E.7 PROJECT COMMUNICATIONS
E.7.1 General. DoS has an accredited a web-based Extranet that enhances the security associated with the exchange of DOS design/ construction data, and provides business applications that improve the communication between DoS and partner contracting activities.
The service name is ProjNet (Project Extranet). This service is available to support the Project Communication needs of both the Con-tractor and the USG.
E.7.2 System Capabilities. ProjNet has been developed to support web-based USG-to-Business applications related to the DOS’s fa-cility engineering, design, and construction projects worldwide. In general, ProjNet supports four generic types of business processes:
document collaboration, work product evaluation, contract monitoring, and information dissemination. The following applications are available to support the contract. While there are additional applications being developed, current and active applications are described below.
E.7.2.1 FILER: FILER is a collaborative application that allows authorized project participants to exchange documents among a spe-cific work group. ProjNet will support document collaboration among project teams. In FILER, drawings and related documents may be transmitted among business partners. FILER provides permission framework and access designations to files stored on the ProjNet server. As required, audit information may also be tracked. ProjNet’s FILER meets the FPS-140 USG requirement to electronically encrypt SBU data. FILER is currently DOS’s only approved method for transmitting Sensitive But Unclassified (SBU) information across the Internet.
E.7.2.2 DrChecks: Contract deliverables (typically plans and specifications) will be reviewed for contract compliance utilizing a doc-ument review and checking tool called DrChecks. DrChecks assists the team (both contractor and USG) in collecting, organizing, and tracking issues to resolution. DrChecks is the tool that supports the Request for Information (RFI) process.
E.7.2.3 Submittal Register This electronic submittal tool standardizes and organizes construction submittals in a single location on-line. This application automates the workflow for construction submittals including the collection, coordination, technical evaluation, and approval of submittals in pdf format. The application is designed to be used by the General Contractor, his suppliers, the Designer of Record, and by Government Quality Assurance and technical staff. See Division 1 Section 013305 Construction Submittals for re-quirements on usage of the Submittal Register module in ProjNet.
E.7.3 Classification and Sensitivity of Data Processed ProjNet will support Unclassified and Sensitive But Unclassified (SBU) data only. SBU/NOFORN (No Foreign Dissemination) information is not allowed on ProjNet. It is the responsibility of all ProjNet users to understand the Department of State’s classification guidelines, and to limit the distribution of data on the ProjNet site to unclassi-fied and SBU information only. All movement of electronic project files across the web will be limited to ProjNet in order to protect data from interception. The Department of State, Bureau of Diplomatic Security will have complete access to all ProjNet data and logs with the purpose of enforcing classification guidelines. The hosting website and equipment supporting ProjNet are USG owned; all data passing across the website shall be construed as the property of the USG, subject to enforcement of its classification guidelines.
E.7.4 Service Operation. ProjNet uses secure socket layer (SSL) technology to transmit data between client and server. This techno-logy is built into the site so it is accessible from any Internet connection. Access to ProjNet begins with a request from the prime con-tractor to the COR. Each Prime Contractor’s Security Officer will be responsible for validating and approving its sub-contractors and vendors access requests before forwarding them to the COR. The COR will be responsible for the review and approval of all requests, and certifying access as necessary to the Department’s mission.
E.7.4.1 USG’s Role The USG will support the use of the SSL technology to all Contractors and their sub-contractors. The USG will assist users with login, program usage support, and management of server hardware and software. The USG will support the Contract-or’s implementation of ProjNet by providing an online training course, available via the Foreign Service Institute (FSI), at the Con-tractor’s expense. Instructions for completing the training will be provided by the COR.
E.7.4.2 Accounts and Passwords: All new ProjNet users, or those requiring remedial training, will be required to complete the For-eign Service Institute’s (FSI) distance learning course PA526- ProjNetSM (Facilitating Design and Construction Communication Util-izing the ProjNet Extranet Technology) in advance of being issued a new user account. The cost per person is approximately $125.
Once users have a connection to ProjNet, they identify themselves to the application using a unique password. RPM will be respons-ible for creating and setting up all user accounts. A unique password for each user is automatically generated for that user by the sys-tem. Using their unique password, users may login to the appropriate ProjNet application.
E.7.4.3 Contractor’s Role: It will be the Contractor’s responsibility to send the COR a complete list of all required users for the sys-tem from each company, including subcontractors required for the project. Requests for ProjNet access for any subcontracting firms or vendors owned by, or operated in, any country on the Prohibited Countries List, will not be approved. The USG will provide the con-tractor with a registration form requiring the name, telephone number, email address, and verification of US Citizenship for each Pro-jNet user. For requests involving non-US Citizens, the contractor must also provide country of citizenship, passport number, passport issue place and date, passport expiration, birth date and place, birth name and other names used, and name in the local language char-acters for each user. Requests for ProjNet access by citizens of any country on the Prohibited Countries List will not approved. It will be the responsibility of the Contractor’s Facility Security Officer to monitor and ensure their personnel are following the Business Rules associated with ProjNet (See Section E.7.5).
E.7.4.4 Contractor Connection Requirements All Construction project team members are required to have broadband Internet service and a compatible web browser to gain access and use ProjNet. Browser compatibility can be tested and confirmed on the ProjNet web-site.
E.7.5 Business Rules:
E.7.5.1 The Contractor is restricted from transporting unencrypted SBU data electronically across the Internet using email, FTP sites, or commercial web sites. OBO encourages contractors to transmit all contract drawings and documents as if they are SBU, in order to minimize risk.
E.7.5.2 ProjNet supports up to Sensitive but Unclassified (SBU) data only. It is the responsibility of all ProjNet users to understand the Department of State’s classification guidelines, and to limit the distribution of data on the ProjNet site to unclassified and SBU in-formation. SBU/NOFORN information shall not be transmitted via the ProjNet site, or any other electronic transmission using the In-ternet.
E.7.5.3 Contractor personnel with access to ProjNet must be U.S. citizens or may be non-US Citizens that have obtained approval to operate the system from the Department of State (DOS). The contractor cannot grant non-U.S. citizens access to ProjNet without pri-or DOS approval. Contractors wishing to nominate non-US citizens for access must also provide country of citizenship, passport number, passport issue place and date, passport expiration, birth date and place, birth name and other names used, and name in the loc-al language characters, if applicable, for each user to the COR for registration/approval. Requests for ProjNet access by citizens of any country on the Prohibited Countries List will not approved. Government denial of non-U.S. Citizens or subcontractors for security reasons can be made without providing rationale for denial.
E.7.5.4 It shall be the responsibility of the Contractor’s Security Officer to register, maintain, and delete all user accounts to the sys-tem on a need to know basis.
E.7.5.5 Individual users in each office will be provided with a system-generated password that will enable access to that user only.
E.7.5.6 Users shall protect their passwords as SBU information, and refrain from sharing their access into the ProjNet system.
E.7.5.7 ProjNet workstations should not be left unattended while an active ProjNet work session is ongoing. Users should logout of ProjNet after each work session.
E.7.6 ProjNet Connectivity
ProjNet is utilized in a web-based environment and therefore subject to the inherent speed and connectivity problems of the Internet.
The Contractor is responsible for its own connectivity to the Internet. ProjNet response time is dependent on the Contractor's equip-ment, including processor speed, Internet access speed, current traffic on the Internet, bandwidth, and hardware latency. The Govern-ment will not be liable for any delays associated from the usage of ProjNet including, but not limited to: slow response time, down time periods, connectivity problems, or loss of information. The contractor should ensure that connectivity to the ProjNet system is ac-complished through DSL, cable or other broad band connection. Under no circumstances shall ProjNet usage be grounds for a time ex-tension or cost adjustment to the contract.
Section F- Deliveries or Performance
Section F Deliveries and Performance
F.1 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK - Alternate I (Reference 11.404) See full text at end of section.
Complete blanks as follows:
(a) 10
(c) the completion date/period: The period of the contract for substantial completion shall be calculated from date of issuance of NTP(Notice to Proceed) and shall be no more than:
Project Name Project Duration Substantial Completion Final Acceptance
Date
NAFTC - Building B
24 Months * **
*The Date for Substantial Completion shall be the date of NTP + Project Duration (See Section/Paragraph E.2 SUBSTAN-
TIAL COMPLETION)
**The Date for Final Acceptance shall be the Date for Substantial Completion + 60 days or longer period as agreed and au-thorized by the COR.
F.2 RESERVED
F.3 52.211-12 LIQUIDATED DAMAGES—CONSTRUCTION (Reference 11.503)
Complete blank(s) as follows:
Project Name Amount (per day) NAFTC – Building B
$32,113
See Section/Paragraph E.2 SUBSTANTIAL COMPLETION
F.4 52.211-13 TIME EXTENSIONS (Reference 11.503)
F.5 52.242-14 SUSPENSION OF WORK (Reference 42.1305)
F.6 SCHEDULES (See J.3.4, Project Specific Division 1, Section 013205 for detailed Requirements)
F.6.1 CONTRACTOR’S SUBMISSION OF PROJECT EXECUTION SCHEDULES
F.6.1.1 The time for submission of the schedules shall be as required in J.3.4, Project Specific Division 1, Section 013205.
F.6.1.2 These schedules shall include the time design, construction, shop drawings, product data, samples and other submittals re-quired by the contract to be submitted for acceptance.
F.6.1.3 The Contractor shall revise such schedules (1) to account for the actual progress of the work, (2) to reflect approved adjust-ments in the performance schedule, and (3) as required by the COR to achieve coordination with work by the Government and any separate contractors employed by the Government. The Contractor shall submit schedules on the last day of the preceding month for the next months work. The schedule shall sequence work so as to minimize disruption at the jobsite.
F.6.1.3 All deliverables shall be in the English language, unless otherwise provided hereunder, and any system of dimensions (i.e., English or metric) shown shall be consistent with that used in the contract. No extension of time shall be allowed on account of a delay by the Government in approving such deliverables if the Contractor has failed to act promptly and responsively in submitting its deliverables. Each deliverable shall be identified as required by the contract.
F.7 WORKING HOURS (See J.3.4, Project Specific Division 1, Section 011005)
F.8 EXCUSABLE DELAYS
F.8.1 The Contractor will be allowed time, not money, for excusable delays as defined in FAR 52.249-10, Default (see Section/ Paragraph I.153). Examples of such cases include (l) acts of God or of the public enemy; (2) acts of the United States Government in either its sovereign or contractual capacity; (3) acts of the government of the host country in its sovereign capacity; (4) acts of another contractor in the performance of a contract with the Government; (5)fires; (6) floods; (7) epidemics; (8) quarantine restrictions; (9) strikes; (l0) freight embargoes; and (11) unusually severe weather.
F.8.2 In each instance, the failure to perform must be beyond the control and without the fault or negligence of the Contractor, and the failure to perform furthermore (1) must be one that the Contractor could not have reasonably anticipated and taken adequate measures to protect against, (2) cannot be overcome by reasonable efforts to reschedule the work, and (3) directly and materially affects the date of final completion of the project.
F.8.3 In determining whether the Contractor’s failure to perform is beyond the control and without the fault or negligence of the Con-tractor, if the Contractor contends that its inability to perform is due to poor security conditions, the Government will consider, at a minimum, the following: (i) whether the Contractor implemented adequate security resources, in light of the information reasonably available to the Contractor; (ii) whether the Contractor deployed adequate additional security resources in a timely manner and on an expedited basis, once the need for additional security resources became reasonably clear; and (iii) whether the security conditions were directly impacting the Contractor in its performance of its contract (as opposed to generalized assessments of security conditions in an entire country or city). Furthermore, the mere fact that the diplomatic post in the city or country where the contract was being performed changed its operating status (e.g., from Authorized Departure to Ordered Departure) or that a new travel warning, warden message, or similar document or communication was issued by the Department of State, will not establish that the security conditions prevented the Contractor from performing the Contract.
F.9 DELIVERABLES/SUBMITTALS
F.9.1 The contractor shall furnish the following deliverables/submittals listed below as well as all other identified under this contract.
All classified deliverables/submittals will be submitted via ProjNet-C. All Unclassified submittals, except bonds and insurance shall be uploaded to ProjNet, unless waived by the Contracting Officer.
THE BELOW SUBMITTALS ARE ORGANIZED BY DIVISION NUMBER, VERIFY YOUR RFP HAS THE COORESPONDING
DIVISION REFERENCED BELOW – CO REMOVE THIS MESSAGE FOR RFP RELEASE
# Description Reference Delivery Date Deliver to:
1 Bonds, Payment and Perform-ance H.4
30 calendar days after contract award
Contracting Officer
2 Insurance H.1, H.3, Section I, Part 4.2
30 calendar days after award Contracting Officer
3 Reserved 4 Bios on Personnel
H.35, & H.36 Construction - 30 days after contract award
COR
5 Pre-Construction Conference, Contract Section H.45 & Div 1
To Be Determined Contracting Officer
011005 6 Payment Request
Sec/Para I.136 See Section G
Last calendar day of each month COR
7 Reserved 8 Reserved 9 Reserved COR 10 Special Warranty
H.41.2 With request for inspection for Substantial Completion.
COR
11 Reserved
12 Div 1 011005 Construction Exe-cution and Coordination
a. Organization Chart & Staff re-sumes
30 calendar days after contract award
COR
b. Staff Qualifications as required by Contract Sections B-J
30 calendar days prior to site mobilization.
COR
c. Site Utilization Plan 30 calendar days prior to site mobilization.
COR
d. Confirm Property Survey 30 calendar days prior to site mobilization.
COR
e. Monitoring Plan for Historic and Significant Properties
Prior to excavation COR
f. Instrumentation Reports Weekly COR
g. 90 days Look Ahead 30 calendar days prior to site mobilization, and thereafter in 30 calendar day increments
COR
h. Final Property Survey Prior to (SC) Substantial Com-pletion
COR
i. Photographic Video/Survey 45 calendar days after Contract Award
COR
j. Reserved
k. Occurrence Report Within 24 hours of each incident COR
l. Meeting Minutes TBD, 24 hours after Project Pro-gress Meeting
COR
m. Written Certification of Bound-ary Markers from Local Offi-cials, reference Section H.27
Before construction COR
13 Div 1 013114 Coordination Drawings
a. Coordination Drawings prepared by Contractor
120 calendar days from Contract Award, but not less than 30 days prior to date required by Con-tractor
COR
14 Div 1 013205 Project Schedules
a. Initial Project
Execution Schedule (IPES) 15 calendar days after contract award
COR
b. Baseline Project Execution Schedule (BPES)
Conditional Acceptance is pre-requisite for NTP for Construc-tion
COR
c. Project Execution Updates of IPES and BPES, and Monthly Progress Report Clause 52.236-15
Monthly updates starting with the acceptance of the IPES, and with Monthly Payment Requests
COR
15 Div 1 013305 Construction Sub-mittals
a. Submittal Register - Div 1 and Contract Section H.38
30 calendar days prior to con-struction activities
COR
b.
Material Substitution Request Form
As Required COR
c. Procurement Log With PES (Procurement Execu-tion Schedule)
COR
d. Product Data Refer to technical specification sections
COR
16 Reserved
17 Division 1 Sec 013525, Con-struction Safety and Occupa-tional Health
a. Contractor’s Accident Preven-tion Plan (CAPP)
45 calendar days after contract award
COR
b. Activity Hazard Analysis prior to each performance COR
c. Hazardous Activity Permit prior to each performance COR
d. Material Safety Data Sheets 60 calendar days after LNTP for
Construction
COR
e. Minutes of Safety Meetings 24 hours after meeting COR
f. Accident Investigator Report 24 hours after occurrence COR
g. Potable Water Documentation Monthly COR
18 Reserved
19 Div1 014010 Contractor’s Qual-ity Control
a. Quality Management Program (QMP) Plan J.3.4, Div 1, Section 014010
30 calendar days after Contract award
COR
b. Contractor’s Quality Control Plan
30 calendar days from Contract Award
COR
c. Contractor QC Assignments in Resume Format
Ongoing; updated with assign-ment changes
COR
d. Contractor’s Quality Control Re-ports
Daily COR
20 Div 1 Section 015005, Tempor-ary Facilities and Controls
a. Site Utilization Plan 30 calendar days after LNTP for Site Mobilization and/or Con-struction
COR
b. Reserved
c. Layout of Project Signage 30 calendar days after LNTP for
Site Mobilization and/or Con-struction
COR
d. Temporary Lighting and Elec-trical Plan
30 calendar days after LNTP for Site Mobilization and/or Con-struction
COR
e. On-going testing of Potable Wa-ter
Monthly COR
21 Reserved
22 Div 1 017419 Construction Waste Management Plan
a. Waste Management Plan Within 15 working days of NTP or prior to any waste removal
COR
b. Integrated Waste Management Plan
Incorporates USG comments COR
c. Monthly Progress Reports Waste Removal Log with Monthly Payment
COR
23 Div 1 017705 Closeout Proced-ures
a. Request for Certification of Sub-stantial Completion
15 calendar days prior to sched-uled Substantial Completion
COR
b. Request for Final Inspection and Testing, see also Contract Sec-tion E.4
15 calendar days prior to sched-uled Final Acceptance
COR
c. Final Record Documents marked As-Built
With Request for Inspection and Substantial Completion
COR
d. Project Completion Photography Final Acceptance COR
e. Asbestos and Lead Paint Certi-fication Final Acceptance COR
f. Warranty Management Plan, per
FAR 52-246-21
30 calendar days before planned pre-warranty conference
COR
24 Div 1 017825 O+M Data
a. O + M Library 270 calendar days prior to Sub-stantial Completion, prior to equipment training
COR
b. CMMS Template 60 calendar days prior to Sub-stantial Completion
COR
c. Preventive Maintenance Check-list
60 calendar days prior to Sub-stantial Completion
COR
d. Reserved COR
25 Div 1 017905 Demonstration and Training
a. Training Plan 180 calendar days prior to Sub-stantial Completion
COR
b. Training Records With request for inspection for Substantial Completion
COR
c. Training and Demonstration Videos
Prior to Substantial Completion COR
26 Div 1 019115 Commissioning
a. (CCR) Contractor’s Commis-sioning Representative Resume 30 calendar days after contract award
COR
b. Commissioning Execution Plan 30 calendar days after contract award
COR
c. Equipment Start-up and Energiz-ation procedures
NLT 8 weeks after Construction
NTP
COR
d. Equipment Start-up and Energiz-ation procedures and report formats
NLT 8 weeks after acceptance of associated equipment submittals
COR
e. Equipment Start-up and Energiz-ation Reports
NLT 1 week after successful completion of each procedure
COR
f. Quality Control Test procedures NLT 8 weeks after Construction COR
NTP
g. Quality Control Test procedures and documentation formats NLT 8 weeks after acceptance of associated equipment
COR
h. Quality Control Test reports NLT 1 week after successful completion of test
COR
i. Functional Performance Testing schedule
NLT 8 weeks prior to the start of testing
COR
j. Prefunctional Checklist NLT 1 week prior to the Func-tional Performance Test
COR
k. Short Circuit/Coordination/Arc Flash Study
Prior to Functional Performance Testing
COR
l. HVAC Test and Balance Reports NLT 30 calendar days prior to the scheduled request for Sub-stantial Completion
COR
m. Software documentation and discs that can restore all commis-sioned systems to their operating state.
NLT 30 calendar days prior to the scheduled request for Sub-stantial Completion
COR
F.9.2 The following contract paragraphs require submission of various documents concerning project personnel and subcontractors. Submis-sions required by the paragraphs concerning the construction phase shall be provided as indicated in the requiring paragraph.
Section/Paragraph H.6.3, Foreign Subcontractors Section/Paragraph H.35.3, Construction Personnel Security Section/Paragraph H.30, Organization and Direction of the Work
Note that there may be duplications of the above submittal requirements in Division 1 of the contract. Where Division 1 addresses the same or similar submittals as described above, the submission requirements for those documents are hereby changed to the above re-vised submission requirements.
F.10 RESERVED
F.11 PROJECT EXECUTION SCHEDULE
See also J.3.4, Project Specific Division 1, Section 013205
F.11.1 Project Execution Schedules shall be submitted to the COR for acceptance (reference F.9, item 13). The schedule shall show the order in which the Contractor proposes to perform the work, and the dates on and time periods within which the Contractor con-templates starting and completing the various portions of the work, in the form and containing such detail as is required by the Con-tract Documents. The Contractor shall revise such schedules (1) to account for the actual progress of the work, (2) to reflect approved adjustments in the Contract Time, and (3) as required by the COR to achieve coordination with work by the Government and separate contractors. If the Contractor fails to submit any schedule or schedule revision within the time prescribed, the CO may withhold ap-proval of progress payments until the Contractor submits the required schedule or schedule revision.
F.11.2 Acceptance of schedule. When the Government has accepted any time schedule, it shall be binding upon the Contractor. The Contract Time is fixed by the contract, and may be extended only by a written Contract modification, Change Order or Supplemental Agreement signed by the Contracting Officer. Acceptance or approval of any schedule or revision thereof by the Government shall not (1) be effective to extend the Contract Time or obligate the Government to do so, (2) constitute acceptance of any delay, nor (3) excuse the Contractor from or relieve the Contractor of its obligation to maintain the progress of the work and achieve final comple-tion within the Contract Time.
F.11.3 Recording progress. The Contractor shall record the actual progress of the work against the approved schedules in the form and at intervals as may be required by the COR.
F.11.4 Notice of delay. In the event the Contractor receives a notice of any change in the work, or if any other conditions arise which are likely to cause or are actually causing delays which the Contractor believes may result in completion of the project after the Con-tract Time, the Contractor shall notify the COR of the effect, if any, of such change or other conditions upon the accepted schedule, and shall state in what respects, if any, the relevant schedule or the Contract Time should be revised. Such notice shall be given promptly, and not more than 30 calendar days following the first occurrence of event giving rise to the delay or prospective delay. Re-visions to the accepted Progress Schedule shall only be made with the approval of the COR.
F.11.5 Maintenance of progress. If the Contractor falls behind an accepted schedule, the Contractor shall take steps necessary to im-prove its progress or overcome any delays and ensure completion of the work within the Contract Time, without additional cost to the Government. In this circumstance, the contractor shall demonstrate how the approved rate of progress will be regained and shall sub-mit for acceptance a supplementary schedule or schedules. Methods may include: increase of any or all of the number of shifts, over-time operations, days of work, and the amount of construction planned.
F.11.6 Schedule revision and equitable adjustments. Upon the request of the Contractor, the Contracting Officer shall ascertain the facts and the extent of the any failure to adhere to the performance schedule resulting from alleged excusable delay. If the Contracting Officer determines that any failure to perform results from one or more of the causes for an excusable delay, the relevant schedules shall be revised, subject to the rights of the Government under the termination clause of this contract. In addition, if and to the extent considered appropriate in the judgment of the Contracting Officer, an equitable adjustment shall be made in the Contract Time.
F.12 DOCUMENTATION OF REQUESTS FOR EXTENSION
F.12.1 Any request for a time extension must be supported by the following data, and any other relevant data requested by the COR:
F.12.2 For any delays for which an extension of time is requested, (a) the exact date and degree of work stoppage, (b) the date of re-sumption of any or all parts of such work, and (c) a description of the nature of the delay and the degree, if any, to which the Contract-or could have reasonably anticipated and guarded against such delay or damage incidental thereto.
F.12.3 For delays in receipt of Contractor furnished materials, (a) the date the materials were ordered, (b) the dates of anticipated de-livery at the port of entry and at the project site, (c) the date the materials were scheduled for use or installation by the Contractor, (d) the date the materials were shipped, and (e) the dates the materials were actually received at the port of entry, cleared customs, and were delivered to the project site.
F.12.4 For delays in receipt of Government furnished materials, the date the materials were scheduled for use or installation by the Contractor and the date(s) the materials were actually received at the port of entry, cleared customs, and were delivered to the project site.
F.12.5 For delays in receipt of Government approvals of submittals properly prepared, reviewed and approved by the Contractor be-fore their submission as required by the Contract Documents, (a) the date of submission, (b) the date approvals were received by the Contractor, and (c) the date that installation or fabrication indicated by the submittals were begun, compared with the dates indicated by the current approved construction schedule and schedule of submittals.
F.12.6 For weather delays, (a) average weather conditions during a comparable period over the preceding ten years, (b) a daily log re-cording the actual weather conditions during the relevant time period, and (c) the dates work affected by the weather conditions were scheduled to be performed and the actual dates of performance.
F.13 SUSPENSION OF WORK- NONCOMPLIANCE WITH CONTRACT REQUIREMENTS
In the event the Contractor is in non-compliance with any requirement of this contract and fails to promptly initiate such action as may be appropriate to comply with the specified…