About this file

This document is a Bill of Quantities for the installation of ABA-compliant teller windows at the Consulate building in Rome, Italy. The key details include:

The project scope involves demolition and removal of existing teller windows, counters, walls, and intercom system, disposal of waste materials, creation of a new 15-minute FE/BR temporary wall, modification of existing hardline steel framing wall to install new teller windows, rerouting of electrical and data cables, painting, and final cleaning. The total estimated cost for this work is 108,000 EUR.

This Bill of Quantities is related to Solicitation Number 191T7024Q0024 issued by the U.S. Department of State for the Consulate Teller Windows project in Rome, Italy. The solicitation is for the installation of ABA-compliant teller windows at the consulate building.

View the file

Other files for this federal contract opportunity

Other files attached to Consulate Teller Windows, Rome, Italy, newest first.
File Type Posted
A0001.pdf PDF
SF-1442.docx DOCX document
Prospective Offerors Cover Letter.pdf PDF
RFQ - 191T7024Q0024.docx DOCX document
Attachment 1 - Technical Specifications.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

No. DESCRIPTION UNIT

UNIT

COST €

TOTAL COST €

Set up construction site area. Move all furniture. Protect floor and furniture with heavy plastic sheets to prevent from dust and damages, segregating the area of work from the rest of the space

LS 1 2,000.00 €

Demolition and removal existing teller windows, counters, existing walls (drywall hard line steel wall and partitions) and existing intercom system by teller windows. Remove existing outlets and EMT.

LS 1 8,000.00 €

Demolition of the temporary security hardline wall at the end of the work and refurbish the premises to their original condition

LS 1 5,000.00 €

Load, transport and dispose all the waste material to the authorized dump, releasing disposal certificates

LS 1 4,000.00 €

Create new temporary 15-minute FE/BR. Such wall shall be composed of solid masonry wall, (> 20 cm thickness) to assure temporary new hardline and 3 mm (1/8") thick steel plate on the protected side

LS 1 5,000.00 €

Modify existing hardline steel framing wall with steel plate on both sides to install new FE/BR teller window. Cut existing steel frame to allow the installation of new teller windows and the passage of all existing systems. Create new welded tubes connections. Supply, install and weld new steel tubes 100x100x6mm. Supply, install and weld hard line 6mm steel wall on both sides (1250x1250mm max panel size).

Supply and install two new 15 minute FE/BR interior steel security teller windows STW/1510 w/deal-tray and stainless steel clad, glazing as NG255, to DOS-1123, size 1210mm x 910mm, with 1/2" x 8" embed plate. Supply and install stainless-steel trim for teller windows. Supply and install new wooden laminate counters on both sides.

(On the applicant side maximum depth 305mm maximum height 940mm). Provide a security hole at the bottom of the counters to allow cables passage with pull box cover (see drawing A103 - Teller Window Wall section for further references). Install partitions on both sides. Applicant side from the top to counter to allow ABA turning space. Install 13cm thickness gypsumboard and structure on both sides. All anchors, steel angles, bolts, gaskets, shims, hardware, metal connections and all installation accessories are included. See drawing A103 for further references.

LS 1 72,000.00 €

Pull back the cables feeding the existing outlets and isolate them. Once the new FE/BR wall structure is installed, install new EMT to reach newly installed outlets and reroute existing cables. All existing electrical connections shall be reused. Pull back data and telephone cables feeding the existing outlets at same current height.

Replace outlet covers maintain existing color for each cable (blue, red, green, yellow).

Once the new FE/BR wall structure is installed, install new EMT to reach newly installed outlets and reroute existing cables.

LS 1 4,000.00 €

Painting of the new FE/BR wall and wall reinforcement. Patch up all walls, ceiling and floor opening created by existing teller window demolition. All patching shall match existing conditions in workmanship and material

LS 1 5,000.00 €

9 Professional cleaning of the premises at final completion of the work LS 1 3,000.00 €

108,000.00 € TOTAL

ABA TELLER WINDOWS CONSULATE NIV OFFICE INSTALLATION

SBU - SENSITIVE BUT UNCLASSIFIED

SBU - SENSITIVE BUT UNCLASSIFIED

SENSITIVE BUT UNCLASSIFIED

File details come from the government source that posted it. Updated .