SBIWTP SOURCES SOUGHT Addendum.pdf
PDF 77 KB Posted
- Solicitation number
- 191BWC23R0008
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 20 June participants.pdf | ||
| SBIWTP SOURCES SOUGHT Addendum 2.pdf | ||
| IBWC SBIWTP Expansion and Rehabilitation Industry Day .pdf | ||
| SBIWTP SOURCES SOUGHT.docx | DOCX document | |
| SBIWTP SOURCES SOUGHT.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SAM.gov Notice ID: 191BWC23R0008
SOURCES SOUGHT
For
Facility expansion and rehabilitation of the South Bay International Wastewater Treatment Plant (SBIWTP)
Addendum
Project location: San Ysidro, CA
The following updates are made to the Sources Sought notice and provided as part of the June 20, 2023, Industry Day presentation:
1. Request for Information (RFIs) based on the industry day presentation should be sent to the Contracting Officer, Philip Johnson, via email to philip.johnson@ibwc.gov by Friday, June 23, 2023. Responses will be provided through this announcement by Friday, June 30, 2023.
2. Current Available Budget:
a. Range: $250M-$300M – includes all design and construction
3. Capabilities Statement: The following was added to Question 4, provide information on Firm’s experience:
a. with federal projects and compliance with Federal Acquisition
Regulations, and
b. Provide input on benefits and risks of using delivery methods
4. Also enclosed to this addendum is a copy of the presentation made during the Industry Day on June 20, 2023.
mailto:philip.johnson@ibwc.gov
File details come from the government source that posted it. Updated .