IBWC SBIWTP Expansion and Rehabilitation Industry Day .pdf

PDF 3 MB Posted

Attached to
South Bay International Wastewater Treatment Plant Expansion Project
Solicitation number
191BWC23R0008
Issued by

View the file

Other files

File Type Posted
20 June participants.pdf PDF
SBIWTP SOURCES SOUGHT Addendum 2.pdf PDF
SBIWTP SOURCES SOUGHT Addendum.pdf PDF
SBIWTP SOURCES SOUGHT.docx DOCX document
SBIWTP SOURCES SOUGHT.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

South Bay International WWTP Expansion and Rehabilitation

INDUSTRY DAY PRESENTATION

June 20, 2023

Presentation Overview

• Introductions

• Project Background

• Capabilities Statement

• Procurement Schedule

Introductions

• United States Section, International Boundary and Water Commission

(USIBWC)

• United States Environmental Protection Agency (EPA)

• United States Army Corps of Engineers

(USACE)

• Arcadis U.S., Inc.

Project Background

Project Background – SBIWTP Location

San Ysidro, San Diego County, California Began Operation: 1997 Primary Treatment Secondary Treatment: 2011 Upgrade Additional Secondary Sedimentation Tanks:

Project Background- Tijuana Sanitation

• The SBIWTP treats wastewater from Tijuana, Baja California

• SBIWTP is part of a binational effort to address sanitation in this area through various agreements and multiple agencies

• Cooperative efforts have been implemented since 1920's

• Present: Collection and treatment system in Tijuana needs rehabilitation

• Untreated sewage enters the Tijuana River in Mexico and the Pacific Ocean at Punta Bandera daily

• Efforts are underway in both the United States and Mexico to address this issue

Project Background – Tijuana Sanitation Concerns

• Water quality issues are of great concern to communities in Greater San Diego and Tijuana

• Agreements

• USMCA

• EPA and CONAGUA Statement of Intent

• IBWC Minute 328

Project Background – Ongoing Efforts

• U.S. side infrastructure

• Feasibility study

• Environmental requirements, NEPA (PEIS), Record of Decision (June 2023)

• SBIWTP part of a group of projects to address issue in U.S. and Mexico

• SBIWTP planning

• Phase 1: Predesign Activities started, Sep 2022-Dec 2023

• Binational coordination

• Mexico infrastructure projects

Project Background – SBIWTP Description

• 25 million gallons per day

(mgd) average annual flow

• Designed to achieve secondary effluent discharge limits

• Final effluent is discharged via ocean outfall

• Biosolids are thickened, dewatered, and stabilized before transport to Mexico for disposal

Project Background – Pre-design Work Completed

• Assessment of Existing Facilities

• Physical and Performance Assessment

• Site Survey

• Geotechnical Investigations

• Assessment Report, Conceptual Drawings and Cost Opinions

• Evaluation of the Largest Possible Expansion Report, Conceptual Drawings and Cost Opinions

• Based on 50 mgd annual average flow

• Evaluated anaerobic digestion for solids stabilization

• Evaluation of Contracting Methods Report

Project Background – Additional Information

• Current Available Budget

• Range: $250M-$300M – includes all design and construction

• SBIWTP rehabilitation and expansion may be phased to accommodate available budget

• Initial rehabilitation phase for facilities nearing end of useful life

• Initial expansion phase up to 50 mgd with peaking factor up to 1.5 (75 mgd peak flow)

Capabilities Statement

Capabilities Statement - Requirements

• Firm’s contact information

• Firm’s capabilities

• Include comparable work performed over the last 5-years

• Firm’s Business Size

• Firms Bonding Capacity

Capabilities Statement - Requirements

• Firm’s experience

• Include experience utilizing Progressive Design Build, Design-Bid-Build, Fixed Price Design Build, Fixed Price Incentive- Successive Target, Early Contractor Involvement, Construction Manager as Constructor, Construction Manager-At Risk, or Construction Manager/General Contractor

• Experience with federal projects and compliance with Federal Acquisition Regulations

• Provide input on benefits and risks of using delivery methods

• Ability to meet cost principals and procedures, cost accounting standards, and earned value management

Procurement Schedule

Procurement Schedule

• RFI’s to Industry Day Presentation Due to Contracting Officer – June 23,

• Addendum Issued - June 30, 2023

• Capabilities Statement Responses Due – July 14, 2023, at 16:00

• Delivery Method Confirmed – July/August 2023

• Prepare Scope of Work – July/August 2023

• Issue Scope of Work RFP – Fall 2023

• Selection and Notice to Proceed – Q1/Q2 2024

South Bay International WWTP Expansion and Rehabilitation

END OF PRESENTATION

South Bay International WWTP�Expansion and Rehabilitation�
Presentation Overview
Introductions
Slide Number 4
Project Background – SBIWTP Location
Project Background- Tijuana Sanitation
Project Background – Tijuana Sanitation Concerns
Project Background – Ongoing Efforts
Project Background – SBIWTP Description
Project Background – Pre-design Work Completed
Project Background – Additional Information
Slide Number 12
Capabilities Statement - Requirements
Capabilities Statement - Requirements
Slide Number 15
Procurement Schedule
South Bay International WWTP�Expansion and Rehabilitation�