IBWC SBIWTP Expansion and Rehabilitation Industry Day .pdf
PDF 3 MB Posted
- Solicitation number
- 191BWC23R0008
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 20 June participants.pdf | ||
| SBIWTP SOURCES SOUGHT Addendum 2.pdf | ||
| SBIWTP SOURCES SOUGHT Addendum.pdf | ||
| SBIWTP SOURCES SOUGHT.docx | DOCX document | |
| SBIWTP SOURCES SOUGHT.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
South Bay International WWTP Expansion and Rehabilitation
INDUSTRY DAY PRESENTATION
June 20, 2023
Presentation Overview
• Introductions
• Project Background
• Capabilities Statement
• Procurement Schedule
Introductions
• United States Section, International Boundary and Water Commission
(USIBWC)
• United States Environmental Protection Agency (EPA)
• United States Army Corps of Engineers
(USACE)
• Arcadis U.S., Inc.
Project Background
Project Background – SBIWTP Location
San Ysidro, San Diego County, California Began Operation: 1997 Primary Treatment Secondary Treatment: 2011 Upgrade Additional Secondary Sedimentation Tanks:
Project Background- Tijuana Sanitation
• The SBIWTP treats wastewater from Tijuana, Baja California
• SBIWTP is part of a binational effort to address sanitation in this area through various agreements and multiple agencies
• Cooperative efforts have been implemented since 1920's
• Present: Collection and treatment system in Tijuana needs rehabilitation
• Untreated sewage enters the Tijuana River in Mexico and the Pacific Ocean at Punta Bandera daily
• Efforts are underway in both the United States and Mexico to address this issue
Project Background – Tijuana Sanitation Concerns
• Water quality issues are of great concern to communities in Greater San Diego and Tijuana
• Agreements
• USMCA
• EPA and CONAGUA Statement of Intent
• IBWC Minute 328
Project Background – Ongoing Efforts
• U.S. side infrastructure
• Feasibility study
• Environmental requirements, NEPA (PEIS), Record of Decision (June 2023)
• SBIWTP part of a group of projects to address issue in U.S. and Mexico
• SBIWTP planning
• Phase 1: Predesign Activities started, Sep 2022-Dec 2023
• Binational coordination
• Mexico infrastructure projects
Project Background – SBIWTP Description
• 25 million gallons per day
(mgd) average annual flow
• Designed to achieve secondary effluent discharge limits
• Final effluent is discharged via ocean outfall
• Biosolids are thickened, dewatered, and stabilized before transport to Mexico for disposal
Project Background – Pre-design Work Completed
• Assessment of Existing Facilities
• Physical and Performance Assessment
• Site Survey
• Geotechnical Investigations
• Assessment Report, Conceptual Drawings and Cost Opinions
• Evaluation of the Largest Possible Expansion Report, Conceptual Drawings and Cost Opinions
• Based on 50 mgd annual average flow
• Evaluated anaerobic digestion for solids stabilization
• Evaluation of Contracting Methods Report
Project Background – Additional Information
• Current Available Budget
• Range: $250M-$300M – includes all design and construction
• SBIWTP rehabilitation and expansion may be phased to accommodate available budget
• Initial rehabilitation phase for facilities nearing end of useful life
• Initial expansion phase up to 50 mgd with peaking factor up to 1.5 (75 mgd peak flow)
Capabilities Statement
Capabilities Statement - Requirements
• Firm’s contact information
• Firm’s capabilities
• Include comparable work performed over the last 5-years
• Firm’s Business Size
• Firms Bonding Capacity
Capabilities Statement - Requirements
• Firm’s experience
• Include experience utilizing Progressive Design Build, Design-Bid-Build, Fixed Price Design Build, Fixed Price Incentive- Successive Target, Early Contractor Involvement, Construction Manager as Constructor, Construction Manager-At Risk, or Construction Manager/General Contractor
• Experience with federal projects and compliance with Federal Acquisition Regulations
• Provide input on benefits and risks of using delivery methods
• Ability to meet cost principals and procedures, cost accounting standards, and earned value management
Procurement Schedule
Procurement Schedule
• RFI’s to Industry Day Presentation Due to Contracting Officer – June 23,
• Addendum Issued - June 30, 2023
• Capabilities Statement Responses Due – July 14, 2023, at 16:00
• Delivery Method Confirmed – July/August 2023
• Prepare Scope of Work – July/August 2023
• Issue Scope of Work RFP – Fall 2023
• Selection and Notice to Proceed – Q1/Q2 2024
South Bay International WWTP Expansion and Rehabilitation
END OF PRESENTATION
| South Bay International WWTP�Expansion and Rehabilitation� |
| Presentation Overview |
| Introductions |
| Slide Number 4 |
| Project Background – SBIWTP Location |
| Project Background- Tijuana Sanitation |
| Project Background – Tijuana Sanitation Concerns |
| Project Background – Ongoing Efforts |
| Project Background – SBIWTP Description |
| Project Background – Pre-design Work Completed |
| Project Background – Additional Information |
| Slide Number 12 |
| Capabilities Statement - Requirements |
| Capabilities Statement - Requirements |
| Slide Number 15 |
| Procurement Schedule |
| South Bay International WWTP�Expansion and Rehabilitation� |
File details come from the government source that posted it. Updated .