J.09 Sample Task Order 3.pdf

PDF 891 KB Posted

Attached to
Environmental IDIQ Federal contract opportunity
Solicitation number
191BWC19R0002
Issued by
International Boundary and Water Commission U.S.-Mexico

View the file

Other files for this federal contract opportunity

Other files attached to Environmental IDIQ, newest first.
File Type Posted
Questions and Answers Received Against 191BWC20R0001.pdf PDF
J.08 Sample Task Order 2 - Revised.pdf PDF
Amendment 0001.pdf PDF
J.01 Performance Work Statement - Revised.pdf PDF
J.08 Sample Task Order 2.pdf PDF
J.03 Wage Determinations - 16 in Total.pdf PDF
J.01 Performance Work Statement.pdf PDF
J.07 Sample Task Order 1.pdf PDF
J.05 Exhibit No 2 Evaluation Sheets.pdf PDF
J.02 QASP.pdf PDF
191BWC20R0001.pdf PDF
J.04 IDIQ Evaluation Plan v2 and Exhibit No 1.pdf PDF
J.06 Exhibit No 3 Technical Scoring Adjectives.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contract #TBD RFP 19-XX Task Order # TBD

IDIQ_Tijuana_Channel_Dredging_EA_SOW_1_May_2019 1

Statement of Work for Preparation of an Environmental Assessment for Proposed Dredging of a portion

Tijuana River in the City of San Ysidro, San Diego County California

I. SUMMARY

This Statement of Work (SOW) is to accomplish National Environmental Policy Act (NEPA) Environmental Assessment (EA) compliance for a United States International Boundary and Water Commission (USIBWC) requirement to increase the flood flow conveyance capacity of an approximately 1.5-mile reach of Tijuana River in San Ysidro, San Diego County California.

Tijuana River is an integral part of the USIBWC Tijuana River Flood Control Project (TRFCP).

The Tijuana River portion of TRFCP conveyance capacity that has been significantly diminished by accumulation of in channel sediment in the Tijuana River between the crossings of International Boundary and Dairy Mart Road in San Ysidro California.

II. BACKGROUND INFORMATION

The project location is shown in Attachment 1. The subject reach of Tijuana River is located in an urban area with limited access to the actual stream channel. The design flood conveyance of Tijuana River is 21,000 cubic feet per second (cfs). By 2012 accumulation of sediment and flood plain vegetation had diminished the conveyance capacity to 9,483 cfs. Selective vegetation removal completed in early 2017 has increased the conveyance capacity to 15,304 cfs.

Hydraulic modeling indicates that removal of an estimated 200,000 cubic yards (cy) will result in an increase of the conveyance capacity to 20,571 cfs or 98% of the original design.

The contractor will develop and evaluate alternative means of accomplishing of restoration design flow and in coordination with USIBWC, prepare the following deliverables in compliance with NEPA.

II.A. Agency Real Property Access and Ownership Real property ownership and easement authority that presently exists for USIBWC to accomplish the work that is the subject of this NEPA analysis is limited to levees and floodplain access from public roads.

II.B. Existing Site Specific Documentation Prior biological surveys and consultations and other site specific work has been completed in this project area. A list of these documents that will be furnished to the contractor are shown in Attachment 2. The information in these documents should be incorporated into the NEPA documents as appropriate.

III. DESCRIPTION OF WORK / SPECIFICATIONS

III.A. Duties and Responsibilities Questions and clarifications regarding this scope of work shall be immediately directed through the Contracting Officer. The Contractor, in coordination with USIBWC, shall achieve NEPA

IDIQ_Tijuana_Channel_Dredging_EA_SOW_1_May_2019 2 compliance through successful completion of the following tasks:

III.A.1. Task 1. – Kickoff Meeting and Project Area Site Visit The Contractor shall perform the following tasks:

Attend morning kickoff to be held at USIBWC San Diego Field Office and participate in afternoon site visit in San Ysidro, California. Contractor shall record and deliver draft and final attendance logs and meeting minutes and provide copies of contractor site visit photos and field notes.

III.A.2. Task 2 – Fact Sheet The contractor shall research and prepare from existing information, a fact sheet suitable for the general public that provides history and context of the present role of Tijuana River in the TRFCP. Fact sheet will address community, environmental, regulatory and municipal concerns and serve as a baseline source of information available to interested parties and the media during the entire NEPA process for this action. Format, content, and distribution of this fact sheet will be coordinated and approved by USIBWC Public Affairs Officer and shall not exceed one (1) full page front and back.

III.A.3. Task 3 – Sediment Sampling and Analysis Plan The Contractor shall plan the collection and analysis of sediment samples from the bed of the perennial Tijuana River at the channel centerline including grab samples for constituent analysis and particle size distribution at up to 3 locations and at depths of up to 5 feet below the existing bed. Develop and deliver draft and final sampling and analysis plan including location and depth, utility clearance, site access, sampling methodology and recording and reporting of sampling locations and analytical methodology and Quality Assurance Quality/Control Plan. The required analytical parameters are provided in Attachment 3. The geotechnical analysis shall meet historic ASTM D422-63 (2007) e2 standard.

III.A.4. Task 4 – Conduct and Report Sediment Sampling and Analysis Report of analysis shall include Chain of Custody documentation and graphical representation of sample locations (geographic coordinate and/or channel centerline station number) and schematic channel cross section representations of geotechnical and chemical parameter results indicating water surface elevation, bed elevation, sample and total depth elevations.

III.A.5. Task 5 – Appropriate Technology Review Contractor shall research, compare and report on commercially available sediment removal, management and disposal methods and technologies that are applicable to this requirement with consideration to the stakeholder and regulatory concerns and site specific conditions. This deliverable is intended to identify and summarize applicable technology and provide a basis for informed stakeholder involvement and later development of alternatives for NEPA analysis and shall not exceed thirty (30) pages.

III.A.6. Task 6 – Stakeholder/Public Involvement Components Significant work has previously been conducted and stakeholders are well known. Contractor will use government furnished information augmented by contractor research to prepare and update stakeholder contact lists for use in all public involvement aspects needed later in this effort (including task 7 scoping meeting). A preliminary list of local stakeholders is shown in

IDIQ_Tijuana_Channel_Dredging_EA_SOW_1_May_2019 3

Attachment 4.

III.A.7. Task 7 – Purpose and Need and Four Alternatives A conceptual draft of the Purpose and Need and four alternatives, including the no action alternative, is required for USIBWC review and concurrence prior to task 7 public scoping meeting. These will be used as basis for materials and presentation used in scoping meeting but may be significantly revised based on stakeholder responses. Alternatives must include all aspects of the action/technology proposed such as site ownership/access, staging areas, disposal areas, transportation and pipeline routes, environmentally sensitive or other areas or resources of special concern. USIBWC anticipates the 3 action alternatives to include two relying on sediment removal solutions and one accomplishing reduction of peak flow by means of off channel storage of a portion of peak discharge at one or more upstream locations adjacent to the Tijuana River.

III.A.8. Task 8 – Costed Option for Wetland, Cultural, and Biological Resource Survey and Reporting Contractor, with coordination and approval of USIBWC shall supply expertise to accomplish additional Wetland, Cultural, or Threatened and Endangered Species Survey and Reporting that may be required to complete evaluation of the alternatives developed under task 7. Costed Option may be provided based on cost per acre for combined resource survey and reporting.

III.A.9. Task 9 – Conduct Scoping Meeting Contractor, with coordination and approval of USIBWC at each step, shall plan, advertise, prepare and send invitations, facilitate, conduct, and report the results of a public scoping meeting. The Contractor shall publish USIBWC-approved public notices in at least two local newspapers prior to the scoping meeting. The meeting will be held in San Ysidro, California.

Contractor will be responsible for production of all meeting materials, displays, presentations, site visits that are required to fully inform and solicit input from stakeholders with respect to the purpose and need for action. This includes providing Word format drafts of all necessary Agency, Tribal and other stakeholder letters to be sent out by USIBWC. Any new stakeholders identified during the scoping meeting process will be included in revision of the task 5 Stakeholder/Public Involvement Components.

III.A.10. Task 10 – Internal Draft EA and Decision Document An internal draft of the full EA document (in accordance with 40 CFR 1500-1508) to include all significant impact, mitigations, figures, tables, maps, photos, agency and stakeholder coordination, and appendices shall be provided to USIBWC for technical and legal review.

III.A.11. Task 11 – Public Draft EA and Decision Document Upon receipt of all comment via USIBWC, the contractor shall prepare and deliver the Public Draft EA and Decision Document to USIBWC for posting with the USIBWC prepared Notice of Availability in the Federal Register and USIBWC website. Contractor shall include the most recent revision of the task 5 stakeholder contact list in order for USIBWC to conduct the stakeholder letter mailing.

III.A.12. Task 12 – Consolidate and Report Stakeholder Comment

IDIQ_Tijuana_Channel_Dredging_EA_SOW_1_May_2019 4

All public comments received by USIBWC will be furnished to contractor at conclusion of public comment period for analysis, technical response, recording and summary. At a minimum, the Contractor will compile all comments into a comments matrix with appropriate recommended responses to be included in the NEPA document. Substantial comments may require a formal letter response, to be drafted by the Contractor.

III.A.13. Task 13 – Public Final EA and Decision Document for USIBWC Signature Any revisions to the EA and supporting documentation will be completed with coordination and approval of USIBWC and the Public Final EA and Decision Document along with complete administrative record delivered to USIBWC.

III.A.14. Task 14 – Costed Option Consulting Hours for Additional Analysis and Public Involvement Consulting hours for additional analysis and/or public involvement effort under this scope may be required.

III.A.15. Task 15 -- Project Administration Regarding project administration the Contractor shall:

1. Provide monthly progress reports, which should include description of work performed, pending issues or concerns, work to be performed during the next two month period, and detailed financial progress reports with the amount billed by task and percent task complete.

2. Provide monthly progress reports, including photos and field notes and map based depictions of work completed versus planned.

3. Provide spatial data of proposed sampling locations and depths, staging areas, travel routes, and project limits of disturbance associated with each alternative. Delivered geospatial data shall be contained in an ESRI file geodatabase that is compatible with the ArcGIS version currently used by USIBWC, or some other mutually agreed upon format as described by task order. Delivered geospatial data must have complete metadata that meets or exceeds the minimum content required by either the Federal Geographic Data committee's Content Standard for Digital Spatial Metadata (FGDC CDSGM) or the North American Profile of ISO 19115 2003 Standard or as specified in task order, and include detailed definitions of all layer attributes.

4. Provide overall project management and work coordination. Duties include project tracking, schedule oversight and contract administration. The Contractor shall maintain in close coordination and communication with USIBWC COR throughout the period of performance.

III.B. Government Provided Information and Property The Contractor shall furnish all labor, material, supplies, equipment, and personnel, unless otherwise noted. Attachments 2 and 4 are sources of data and stakeholder information known to the USIBWC that should be evaluated and considered by the contractor. Additional relevant information is likely to be identified by the contractor in execution of this effort. The USIBWC will retain ownership of all equipment purchased for and billed through this contract.

III.C. Performance Period

IDIQ_Tijuana_Channel_Dredging_EA_SOW_1_May_2019 5

1. The period of performance for this project will be from the Notice to Proceed (NTP) plus 250 days.

2. The Contractor will provide a draft schedule which identifies the key milestones and project deliverables.

3. Any project or schedule delays or unforeseen issues will be addressed immediately by the Contractor.

III.D. Deliverables and Deliverable Schedule

Table 4. Deliverables and Targeted Schedule Task Deliverable Due Date III.A.1. Task 1. – Kickoff Meeting and Project Area Site Visit

Draft and Final Kickoff Meeting Minutes with list of action items/dates and list of attendees.

30 days from NTP

III.A.2. Task 2 – Fact Sheet

Outline, Draft and Final single page (front and back) fact sheet.

45 days from NTP

III.A.3. Task 3 – Sediment Sampling and Analysis Plan

Draft and Final Sediment Sampling and Analysis Plan

45 days from NTP

III.A.4. Task 4 –Conduct and Report Sediment

Draft and Final Report Sediment

90 days from NTP

III.A.5. Task 5 – Appropriate Technology Review

Draft and Final Applicable Technology Review

60 days from NTP

III.A.6. Task 6 – Draft Stakeholder/Public Involvement Components

Draft Stakeholder/Public Involvement Components

60 days from NTP

III.A.7. Task 7 – Draft Purpose and Need and Four Alternatives

Draft and Final Purpose and Needs and Four Alternatives

90 days from NTP

III.A.8. Task 8 – Costed Option for Wetland, Cultural, and Biological Resource Survey and Reporting

Field Survey and Draft and Final Reporting

To be determined at time of option award

III.A.9. Task 9 – Conduct Scoping Meeting

Facilitate and Report (Draft and Final) on-site Public Scoping Meeting

90 Days from NTP

III.A.10. Task 10 – Internal Internal Draft EA and Decision 120 days from NTP

IDIQ_Tijuana_Channel_Dredging_EA_SOW_1_May_2019 6

Draft EA and Decision Document

III.A.11. Task 11 – Public Draft EA and Decision

Public Draft EA and Decision

150 days from NTP

III.A.12. Task 12 – Consolidate and Report Stakeholder Comment

Report of Public Comment 190 days from NTP

III.A.13. Task 13 – Public Final EA and Decision Document for USIBWC Signature

Public Final EA and Decision Document for USIBWC Signature and Administrative Record

220 days from NTP

III.A.14. Task 14 – Costed Option Consulting Hours for Additional Analysis and Public Involvement

TBD To be determined at time of option award

III.A.15. Task 15 -- Project Administration

Progress reports (Gantt chart) with discussion of obstacles encountered and recommended solutions.

Monthly

IV. TASK ORDER LOGISTICS

IV.A Quality Assurance The Contractor performance and deliverables shall be subject to review by USIBWC technical staff and management to ensure adequacy, accuracy, and completeness. If project performance and deliverables do not meet the USIBWC acceptance criteria, the USIBWC reserves the right to issue corrective action to remedy the deficiencies. Corrective action may include withholding of payment and denial of schedule modifications until project deliverables are met. The USIBWC acceptance criteria may include: timeliness of scheduled deliverables; degree of technical accuracy & coverage of subject; compliance with legal requirements and industry standards; efficacy of design; legibility. In limited circumstances the USIBWC may request that advance copies of specific sections of the Environmental Assessment and Decision Document be provided for review prior to completion of the full deliverable. USIBWC may consult with stakeholders for input prior to acceptance of deliverables.

IV.B Changes

Changes to scope requirements shall be provided in writing to the CO for approval.

IV.C Government Point-of-Contact Information

IDIQ_Tijuana_Channel_Dredging_EA_SOW_1_May_2019 7

Contracting Officer N. E. Daynow

USIBWC

4171 N. Mesa, Suite C-100 El Paso, Texas, 79902

Phone

(915) 832-4171 n.e.daynow@ibwc.gov

COR

M.T. Space

Phone

(915) 832-4171 m.t.space@ibwc.gov

IV.D Data and Information Management

All photos, data and information collected and developed under this contract shall become the sole property of the USIBWC. Under this task order, the Contractor shall furnish all labor, material, supplies, equipment, and personnel. The USIBWC will retain ownership of all equipment purchased for and billed through this contract.

IDIQ_Tijuana_Channel_Dredging_EA_SOW_1_May_2019 8

V. ATTACHMENTS

Attachment 1

IDIQ_Tijuana_Channel_Dredging_EA_SOW_1_May_2019 9

Attachment 2

1. San Diego County Hazard Mitigation Plan, May 2015

2. Final Survey Report Threatened and Endangered Plant Species Surveys within Areas along the Tijuana River Floodway in the Tijuana River Flood Control Project Area San Diego County, California, November 2015

3. Final Vegetation Management Plan Clearing Areas along the Tijuana River Floodway in the Tijuana River Flood Control Project Area San Diego County, California November 2015 Revised 12 January 2016 IBWC

4. Country Club Letter of 16 March 2012

5. Meeting Minutes – Tijuana River Meeting with City of San Ysidro Minutes, 24

September 2014

6. TRSD-1234 San Ysidro Hike and Bike, 14 September 1999

7. Tijuana River - Perpetual Right and Easement.pdf

8. Update to the Tijuana River Watershed Protection Plan 2016 Developed by The Tijuana

River Watershed Partnership

IDIQ_Tijuana_Channel_Dredging_EA_SOW_1_May_2019 10

Attachment 3

Table 2 USIBWC EMD - Sediment Analysis Requirement

Line Item Parameters Units Matrix Analytical

Method Parameter

Code

Ambient Water

Reporting Limit (AWRL)

Quantities QC samples Unit

Total Metals in Sediment 147 Aluminum mg/kg sediment SW846 6010B 01108 50 ea 148 Antimony mg/kg sediment SW846 6010B 01098 12.5 ea 149 Arsenic mg/kg sediment SW846 6010B 01003 16.5 ea 150 Barium mg/kg sediment SW846 6010B 01008 200 ea 151 Cadmium mg/kg sediment SW846 6010B 01028 2.49 ea 152 Chromium mg/kg sediment SW846 6010B 01029 55.5 ea 153 Copper mg/kg sediment SW846 6010B 01043 74.5 ea 154 Lead mg/kg sediment SW846 6010B 01052 64 ea 155 Mercury mg/kg sediment SW846 7471 71921 0.355 ea 156 Nickel mg/kg sediment SW846 6010B 01068 24.3 ea 157 Selenium mg/kg sediment SW846 6010B 01148 1 ea 158 Silver mg/kg sediment SW846 6010B 01078 1.1 ea 159 Zinc mg/kg sediment SW846 6010B 01093 205 ea

160 DDT μg/kg sediment SW848 8081A 39373 23 ea 161 DDD μg/kg sediment SW848 8081A 39363 3.91 ea 162 DDE μg/kg sediment SW848 8081A 39368 15.65 ea 163 Aldrin μg/kg sediment SW846 8081A 39333 40 ea 164 Chlordane μg/kg sediment SW846 8081A 39351 2.4 ea 165 Endrin μg/kg sediment SW846 8081A 39393 103.5 ea 166 Heptachlor μg/kg sediment SW846 8081A 39413 NA ea 167 Methoxychlor μg/kg sediment SW846 8081A 39481 NA ea 168 Mirex μg/kg sediment SW846 8081A 79800 650 ea 169 Dieldrin μg/kg sediment SW846 8081A 39383 2.15 ea 170 Hexachlorobenzene μg/kg sediment SW846 8081A 39701 120 ea 171 Total PCBs μg/kg sediment SW846 8082 39519 90 ea 172 Endosulfan I μg/kg sediment SW846 8081A 34364 n/a ea 173 Demeton μg/kg sediment SW846 8270 82400 n/a ea 174 Guthion μg/kg sediment SW846 8270 39581 n/a ea 175 Malathion μg/kg sediment SW846 8270 39531 n/a ea 176 Parathion ethyl μg/kg sediment SW846 8270 39541 n/a ea 177 2,4-D μg/kg sediment SW846 8151A 39731 n/a ea 178 2,4,5-TP (Silvex) μg/kg sediment SW846 8151A 39741 n/a ea 179 2,4,5-T μg/kg sediment SW846 8151A 39761 n/a ea 180 Fluorene μg/kg sediment SW846 8270 34384 268 ea 181 Fluoranthene μg/kg sediment SW846 8270 34379 1115 ea 182 Benzo(a)pyrene μg/kg sediment SW846 8270 34250 725 ea 183 Napthalene μg/kg sediment SW846 8270 34445 280.5 ea 184 Benzene μg/kg sediment SW846 8260 34237 22505 ea 185 Toluene μg/kg sediment SW846 8260 34483 2830 ea 186 Ethylbenzene μg/kg sediment SW846 8260 34374 1965 ea 187 Xylene μg/kg sediment SW846 8260 45510 n/a ea

IDIQ_Tijuana_Channel_Dredging_EA_SOW_1_May_2019 11

Attachment 4

1. Adjacent property owners

2. Visiting recreational users

3. San Diego County District X and Y Representatives and Engineering Department

4. City of San Ysidro District X Representative, Engineering and Parks and Recreation

Departments

5. Yesway Home Owners Association and any other association to be determined

6. Tijuana River Scenery Society

7. Advocacy Club Local Chapter

8. US Fish and Wildlife Service

9. California Parks and Wildlife

10. Municipal Utility Providers

11. Native Plant Enthusiasts

12. IBWC Citizen’s Forum (quarterly meeting)