Additional Questions Received Against Solicitation# 191BWC18R0002 – Amistad and Falcon

Hydroelectric Power Plants NERC and TRE Compliance Consulting

1. We would like to know if we a S.A.M. Registration is required. On page #1 – Box 9 it states that all offers are subjects to all terms; however in section I (pg 9), where there is a list of contract clauses that shows that 52.204‐7 (System for Award Management) is not included; but Section L (pg 17) has 52.204‐7 listed.

SAM registration is required. Section I are contract clauses and section L includes provisions, 52.204‐7 is a provision which is why it is not included in section I.

2. May we submit a pricing model that is different than Firm Fixed Price (FFP)?

Yes, pursuant to provision 52.204‐22 Alternative Line Item Proposal, the Offeror is invited to propose alternative line items for which bids, proposals, or quotes are requested in this solicitation to ensure that the resulting contract is economically and administratively advantageous to the Government and the Offeror.