190068_ATT9_SOW.pdf
PDF 267 KB Posted
- Solicitation number
- FA813725R0035
About this file
This Statement of Work (SOW) details a construction project to repair the fire suppression system at Maintenance Hangar B2280 on Tinker Air Force Base in Oklahoma. The project involves a comprehensive replacement and upgrade of the existing fire protection infrastructure, including removing and replacing under-wing monitors, above-ground piping, deluge valves, and installing new wet sprinkler systems and flame detectors in both the south and north hangar bays.
The project is phased into four distinct stages, with a maximum total performance period of 360 days. Key requirements include submitting detailed preconstruction documentation, maintaining continuous facility occupancy during construction, adhering to strict government review timelines, and completing work in compliance with Tinker AFB facility standards. The contractor must provide comprehensive documentation, including working as-built drawings, operations and maintenance manuals, and must coordinate closely with government project managers throughout the construction process. All work must be performed under controlled/restricted area protocols, with specific safety, environmental, and airfield operation guidelines.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work - 1 of 17 MACB Const Only_v1_10/05/22
STATEMENT OF WORK
Repair Fire Suppression System, Maint Hangar B2280 Project #: WWYK190068
Work Order #: 20435 - Amend
Revision: 0 Issued: 07 Oct 22
1. SCOPE OF WORK
1.1 GENERAL
This Order is classified as a 'Construction Only' Order, as defined in the MAC-BOA Statement of Work, Section 1.3.3 (Construction Only).
The work to be performed under the terms of this contract consists of furnishing all materials, labor, plant, tools, transportation, equipment, testing services, quality control and incidentals required to accomplish the repair/replacement of the fire suppression system and associated fire protection equipment in the Maintenance Hangar, B2280 at Tinker Air Force Base (AFB), Oklahoma (reference the contract drawings for additional location information).
The Contractor shall be responsible for identifying the necessary logistical, architectural and structural work elements required to perform the work as described herein. Assemblies, framework, fixtures or apparatus not readily identified on plans or this Statement of Work (SOW) shall be provided by the Contractor as required for a complete, fully operating and functioning system or systems, ready for use by the Government.
Information such as floor plan layouts, dimensions, structural, mechanical and electrical data, and location of underground utilities provided by the Government for existing and new construction are based on available as-built documentation, field observation, and equipment selected as design basis by the Government. This information is to be considered approximate and shall be field verified by the Contractor.
The Contractor shall perform a site investigation to verify existing conditions. If necessary, additional as-built drawings are available from 72 ABW/CE - Engineering Support, located in B400.
1.2 CONTRACTOR’S PROPOSAL
1.2.1 Proposal Package
The Contractor shall submit a proposal package in accordance with the MAC-BOA Statement of Work, Section 13.4 (Proposal Package).
For purpose of developing the proposal, this Order shall be considered a Routine requirement in accordance with the MAC-BOA Statement of Work, Section 13.3 (Contractor’s Proposal).
1.2.2 Estimated Construction Schedule
Contractor’s proposed schedule must demonstrate a reasonable and realistic sequence of activities which represent all work through the entire contract performance period (reference section PERIOD OF PERFORMANCE below), taking into account the major work elements from the detailed cost proposal, as well as submittal reviews, mobilization, material delivery times, anticipated weather delays, and final inspection/closeout.
16 May 25 Statement of Work - 2 of 17 WWYK190068
In developing the estimated schedule, the Contractor shall account for the following milestones and Government review times in addition to construction activities:
DELIVERY SCHEDULE & SUBMITTALS
Item of Work & Deliverables Government Review Time (calendar days) Remarks
Contract Pre-construction Conference/ Notice to Proceed (NTP) 1 day At Tinker AFB
Baseline Construction Schedule and Schedule of Values 14 days Provide within
10 days of NTP
SD-01 Preconstruction Submittals (except as noted below) 14 days
Provide all preconstruction submittals within 30 days of NTP
Health and Safety Plan 21 days
Internal Combustion Engines Plan 21 days
Entry Access List / Vehicle Entry Access List 14 days
Must be approved prior to obtaining access to controlled/restricted areas
Airfield Construction Waiver 60 days Must be provided by 1st business day of month
Notice of Proposed Construction (FAA Form 7460-1) 60 days
Must be provided by 1st business day of month
Request for Contractor Staging Area 30 days Must be approved prior to mobilization
Storm Water Pollution Prevention Plan (SWPPP) 21 days
Must be approved prior to submitting Tinker Excavation Permit Request
Water System Construction Permits 30 days
Chemical/Hazardous Material Request/Authorization 21 days
Spray Painting Plan 21 days
Abatement Submittals (asbestos, lead based paint) 21 days
Material Submittals
(SD-03, SD-04, SD-07, SD-08)
14 days Provide within 30 days of NTP
Contract Pre-Construction Conference/NTP: Begin Mobilization 1 day At Tinker AFB; may be waived by CO
Outages 21 days
Closures (roadway, parking aisles, etc.) 60 days
16 May 25 Statement of Work - 3 of 17 WWYK190068
DELIVERY SCHEDULE & SUBMITTALS
Item of Work & Deliverables Government Review Time (calendar days) Remarks
Tinker Excavation Permit Request 14 days SWPPP must be approved prior to submittal
Construction Submittals (SD-06, SD-09) 14 days
Final/Closeout Submittals (SD-10, SD-11) 14 days
Must be approved prior to final inspection.
Pre-final Inspection 7-day Minimum Notice
Contractor must have completed internal pre-final and resolved all punch list items from this inspection
Final Inspection 7-day Minimum Notice
All final/closeout submittals must be approved.
Contractor must have resolved all punch list items from pre-final inspection
Note: Information provided in this table is provided to assist the Contractor in developing the construction schedule. Review times may vary depending on the complexity of the submittal.
1.2.3 Contractor Personnel Resumes
Provide names of personnel who will be fulfilling key positions defined in MAC-BOA Statement of Work, Section 3.1 (Contractor Personnel). Submitted names must be included in the Contractor's current organizational chart; reference the MAC-BOA Statement of Work, Section 4.2 (Organizational Chart).
1.3 SPECIAL REQUIREMENTS
1.3.1 Government Occupancy of Facilities
The facility will remain occupied throughout construction.
The construction area, a reasonable buffer area, and any approved staging areas will not be cleared of all Government materials and personnel prior to the start of construction.
Contractor shall consult with the Government Project Manager/Construction Inspector and the Using Agency to coordinate procedures; means of access; space for storage of materials and equipment; and use of approaches, corridors, and stairways in such a way that accommodates the continued performance of the User’s mission during construction.
1.3.2 Period of Performance
The Contractor’s period of performance (PoP) shall not exceed 360 days.
16 May 25 Statement of Work - 4 of 17 WWYK190068
(a) All preconstruction and material submittals shall be submitted for approval during the initial 30 days of the contract. Long lead items may be submitted prior to NTP.
(b) Contractor shall mobilize to the site within 30 days of NTP. The government requests a minimum of 30 days’ notice to coordinate dock outages.
(c) Once mobilized, all on-site work shall be substantially complete within 300 days.
(d) Final 30 days of PoP are reserved for submittal of close-out documentation and final acceptance.
It is anticipated that these requirements can be met utilizing normal duty hours (reference the Section Working Hours below); however, the Contractor will be authorized (and expected) to work weekends, holidays, and additional shifts as required to accomplish the work in the allotted timeframe. This is to include all testing, inspection and acceptance actions.
1.3.3 Working Hours
In accordance with the MAC-BOA Statement of Work and Tinker AFB General Specifications, Section 00 70 00, General Requirements for Construction on Tinker Air Force Base, construction shall take place during normal duty hours (0700 – 1600 Monday-Friday); utility outages will be the exception.
Note: In order to meet schedule (reference section PERIOD OF PERFORMANCE above), the Contractor may request additional work hours (in the form of additional shifts, weekends, and/or holiday work) at no additional cost to the Government.
1.3.4 Phasing
There is a Government-required construction phasing for this Order. The maximum allowable downtime for phase (1) one and phase (3) three is (1) one week each. The maximum allowable downtime for phase (2) two and phase (4) four is (6) six weeks. Contractor shall utilize after-hours and weekend labor as needed to meet these maximum downtime requirements.
Construction will be phased as follows:
PHASE 1 DESCRIPTION:
1. CONSISTS GENERALLY OF THE REMOVAL OF THE UNDER-WING MONITORS AND
ASSOCIATED ABOVE GROUND PIPING.
2. REMOVE ALL ABOVE GROUND PIPING BACK TO BUILDING'S RISER WITHIN WEST
MECHANICAL ROOM. PENETRATION FROM DEMOLISHED PIPING WILL BE PATCHED
AS PER PROJECT SPECIFICATION TO MAINTAIN ELECTRICAL CLASSIFICATION.
3. REMOVE UNDER WING MONITORS AFFF FOAM TANKS ASSOCIATED TRIM.
4. REMOVE EXISTING UNDER WING MONITORS DELUGE VALVES.
5. REMOVE EXISTING UNDER WING MONITORS.
6. AFFF TANKS AND ASSOCIATED PIPING UP TO THE PROPORTIONING VALVE TO BE
ACCOMPLISHED UNDER SEPARATE AFCEC CONTRACT.
16 May 25 Statement of Work - 5 of 17 WWYK190068
PHASE 2 DESCRIPTION:
1. CONSISTS GENERALLY OF THE REMOVAL OF THE OVERHEAD FOAM WATER
SPRINKLER SYSTEM.
2. DEMOLISH EXISTING DET-TRONICS RELEASING PANEL SERVING THE SOUTH DOCK.
3. DEMOLISH EXISTING FLAME DETECTOR AND ASSOCIATED CONDUIT WITHIN SOUTH
DOCK.
4. INSTALL NEW WET SPRINKLER SYSTEM WITHIN THE SOUTH HANGER BAY.
5. INSTALL NEW X3301 MULTISPECTRUM IR FLAME DETECTOR WITHIN SOUTH HANGAR
BAY.
6. FOLLOWING THE SUCCESSFUL FINAL INSPECTION OF THE OVERHEAD WET
SPRINKLER SYSTEM WITH THE BASE FIRE PROTECTION ENGINEER, BASE FIRE
DEPARTMENT, AND PROJECT COR CONTRACTOR MAY PROCEED TO PHASE 3.
7. AFFF TANKS AND ASSOCIATED PIPING UP TO THE PROPORTIONING VALVE TO BE
ACCOMPLISHED UNDER SEPARATE AFCEC CONTRACT.
PHASE 3 DESCRIPTION:
1. CONSISTS GENERALLY OF THE REMOVAL OF THE UNDER-WING MONITORS AND
ASSOCIATED ABOVE GROUND PIPING.
2. REMOVE ALL ABOVE GROUND PIPING BACK TO BUILDING'S RISER WITHIN WEST
MECHANICAL ROOM. PENETRATION FROM DEMOLISHED PIPING WILL BE PATCHED AS
PER PROJECT SPECIFICATION TO MAINTAIN ELECTRICAL CLASSIFICATION.
3. REMOVE EXISTING UNDER WING MONITORS DELUGE VALVES.
4. REMOVE EXISTING UNDER WING MONITORS.
5. AFFF TANKS AND ASSOCIATED PIPING UP TO THE PROPORTIONING VALVE TO BE
ACCOMPLISHED UNDER SEPARATE AFCEC CONTRACT.
PHASE 4 DESCRIPTION:
1. CONSISTS GENERALLY OF THE REMOVAL OF THE OVERHEAD FOAM WATER
SPRINKLER SYSTEM.
2. DEMOLISH EXISTING DET-TRONICS RELEASING PANEL SERVING NORTH
HANGAR BAY.
3. DEMOLISH EXISTING FLAME DETECTOR AND ASSOCIATED CONDUIT WITHIN
DOCK ONE.
4. INSTALL NEW WET SPRINKLER SYSTEM WITHIN THE NORTH HANGER BAY.
5. INSTALL NEW X3301 MULTISPECTRUM IR FLAME DETECTOR WITHIN THE NORTH
HANGAR BAY.
6. AFFF TANKS AND ASSOCIATED PIPING UP TO THE PROPORTIONING VALVE TO
BE ACCOMPLISHED AFCEC CONTRACT.
16 May 25 Statement of Work - 6 of 17 WWYK190068
Phases 1, 2, 3, and 4 may be accomplished concurrently to reduce overall construction time if allowed by the government.
Phasing discussed above shall be reflected in the Contractor's estimated construction schedule (provided with the proposal).
1.3.5 FOD Awareness and Prevention Training
In accordance with Tinker AFB General Specifications, Section 00 71 00, General Safety Requirements for Construction on Tinker Air Force Base, all Contractor personnel working on this Order will be required to complete Foreign Object Debris (FOD) awareness and prevention training.
The work to be performed for this Order will require the Contractor to work in or travel through areas near operational and/or production aircraft or related components.
The work to be performed requires that special attention be given to tools when working in and around the flight line. The Contractor shall utilize a means of tracking tools for the duration of this project. A list of tools signed by the Contractor's Quality Control Manager shall be provided to the Construction Inspector prior to construction start with periodic updates submitted during construction and final list at completion. All tools shall be accounted for at the end of each day and at the completion of the project.
1.3.6 Air Field Operations
The work to be performed under this contract is located in an Air Field Operations area.
All Contractor activities on the airfield shall be pre-coordinated with the CO in conjunction with the Airfield Manager prior to the Contractor proceeding on the airdrome. The Contractor shall adhere to the provisions of TAFBI 13-204, Airfield Operations; and Tinker AFB General Specifications, Sections 00 71 00 and 00 80 05, Special Provisions for Working on or Near the Airfield.
This Order will require the Contractor to obtain and 'Airfield Construction Waiver' in accordance with Tinker AFB General Specifications, Section 00 71 00. No construction may start on any part of the airfield until the Base Commander (72ABW/CC) has approved the waiver.
1.3.7 Controlled/Restricted Area(s)
Work to be performed under this Order is located in a controlled area.
AF Form 1199C, USAF Entry Control Card (i.e., Secure Area Badge) is required for Contractor personnel to access the controlled area/work site.
Contractor must provide an Entry Access List (EAL) for all personnel and a Vehicle Entry Access List (VEAL) for approval prior to construction. EAL/VEAL must be submitted to the COR a minimum of fourteen (14) days prior to when access will be required to the work site. Work may not commence until the EAL/VEAL is approved.
Note that any change to contractor personnel or vehicles being brought into the controlled area will require a resubmission of the EAL/VEAL; timelines for approval will be the same as for the initial submission. New personnel or vehicles may not be brought onto the worksite until the revised EAL/VEAL is approved.
1.3.8 Contracting Officer’s Representative
16 May 25 Statement of Work - 7 of 17 WWYK190068
The Contracting Officer’s Representative (COR) is an individual designated by the Contracting Officer upon award of the Task Order and authorized to perform specific technical or administrative functions.
The COR is not authorized to make any commitments or changes that will affect price, quality, quantity, delivery, or any other term or condition of the contract. It shall be the Contractor’s responsibility to contact the CO concerning any matters where the Contractor believes that the direction received from the COR may affect price, quality, quantity, delivery, or any other term or condition of the contract prior to performing work or purchase of material.
1.4 BADGE(S)
AFMC Form 387, Air Force Material Command Identification Cards (i.e., contractor badges) are required for Contractor personnel to access/work on Tinker AFB. The Contractor must have all personnel badged prior to commencing work.
Contractor shall designate an employee to act as Certifying Official for all personnel requiring badges. The designated Certifying Official shall complete DD Form 577, Appointment/ Termination Record – Authorized Signature and submit to the COR upon award of the contract.
Upon approval, Contractor’s Certifying Official will be responsible for completing an AFMC Form 496, Application for AFMC Identification Card, for all personnel requiring a contractor badge.
Badges are issued at B6611, Pass and ID.
Badges shall be displayed on the outer clothing, on the front of the body between the neck and waist and must be visible at all times.
1.5 OUTAGES AND CLOSURES
Request utility outages and/or closures in accordance with TAFB Standard Operating Procedure Planned and Emergency Outages. Outage may be required to be performed outside of normal duty hours. The Contractor shall provide temporary lighting and power that may be required for continued performance of User's mission during outages.
1.6 RECOVERED MATERIAL DETERMINATION FORM (RMDF)
No products listed in the Comprehensive Procurement Guideline (CPG), Biobased, Energy Star, or Federal Energy Management Program (FEMP) Low Standby Power programs have been included in this Order.
1.7 ENVIRONMENTAL MANAGEMENT (EM) SURVEY
An EM survey indicates there are no asbestos containing materials (ACM) or heavy metals (HM) concerns for area(s) where work is to be performed. If at any time the Contractor encounters suspect environmental conditions, they shall notify the CO.
An EM survey indicates there are lead based paint (LBP) concerns for area(s) listed below, however, this area does not have plans to receive any work. The following have been identified:
(a) On the steel structural beam of the storage room
(b) On part of the south cement wall
Removal of this paint can only be performed by a competent trained worker and practices that would create dust hazards should be avoided.
16 May 25 Statement of Work - 8 of 17 WWYK190068
If at any time the Contractor encounters suspect environmental conditions not identified above, they shall notify the CO.
1.8 HEALTH AND SAFETY
Commander’s Statement of Safety Intent – The safety of everyone on Tinker AFB is our top priority. All individuals must accept personal responsibility for safety and seek opportunities for improving the safety of our work environment. Everyone working on Tinker AFB is challenged to find, fix (if able) and report all hazards and near-misses. It is our shared duty to take every reasonable step and precaution to prevent accidents and preserve the health/safety of each contractor and government employee.
Reference the MAC-BOA Statement of Work and Tinker AFB General Specifications, Section 00 71 00 for additional information.
1.9 BIOENVIRONMENTAL REGULATIONS
(a) To assist in the evaluation of health hazards & to provide emergency medical treatment, Contractor must have Material Data Sheets (MDS) for hazardous materials reviewed and exchange of HAZCOM information accomplished prior to use. Process hazardous material in accordance with Tinker AFB General Specifications, Section 00 72 00, Environmental Requirements for Construction on Tinker AFB.
(b) Ventilation measurements must be in accordance with current edition of ACGIH Ventilation Manual and 29 CFR 1910.94.
(c) Welding, cutting, or brazing operations must be in accordance with 29 CFR 1910.252.
The Contractor shall not operate welders near chlorinated hydrocarbons.
(d) Hazardous noise levels in the vicinity of DoD Active Duty and Civilians must be in accordance with OSHA 29 CFR 1910.95 and AFI 48-127, Occupational Noise and Hearing Conservation Program.
(e) Where confined spaces may be involved, ensure confined space entry permits are acquired prior to entering a confined space. Personal Protective Equipment (PPE) must be in accordance with 29 CFR 1910.146 and AFOSH Std 91-25.
2. PRECONSTRUCTION & CONSTRUCTION SERVICES BY CONTRACTOR
2.1 CONTRACT SCHEDULE AND PROGRESS REPORTING
Contract Schedule and Progress Reports shall be developed and submitted in accordance with the MAC-BOA Statement of Work, Sections 14.4 (Contract Schedule) and 14.5 (Contract Progress Reporting).
For the purposes of this contract, the Contractor shall submit contract schedules in the 'Network Analysis Schedule (NAS)' format.
2.2 CONSTRUCTION
The Contractor shall execute the work as indicated in the attached drawings and specifications.
All construction shall fully comply with the Government's drawings and specifications (reference paragraph GOVERNMENT FURNISHED DRAWINGS, SPECIFICATIONS & REFERENCES below); the most current editions of Tinker AFB Facility Standards; and any approved Contractor generated shop drawings or ‘delegated’ design.
16 May 25 Statement of Work - 9 of 17 WWYK190068
All construction shall comply with the most current versions of codes/standards/regulations referenced by the above publications.
The term 'most current' is to be understood to mean, “Most current as of date of contract award.”
In case of conflict between the contract documents, governing codes or standards, and the Tinker AFB facility standards, Contractor shall submit a request for information (RFI) to the Government for resolution.
2.3 ORDER OF PRECEDENCE
In the event of a conflict or inconsistency between any of the provisions of this contract, precedence shall be applied in the following order:
• Any portions of the accepted proposal which both conform to and exceed the provisions of the solicitation.
• The provisions of the solicitation, including:
- The Solicitation, Offer and Award
- Specifications
- Drawings
- SOW
• All other provisions of the accepted proposal.
• Any contractor generated ‘delegated’ design products including, but not limited to:
plans, specifications, engineering studies and analyses, shop drawings, and equipment installation drawings.
2.4 RECORD DRAWINGS
2.4.1 Working As-Built Drawings ('Redline' Set)
The Contractor shall keep a careful record at the job site of all changes and corrections from the layouts shown on the Construction drawings. The working as-built drawings shall clearly indicate authorized field changes, updates based on existing conditions and corrections to the drawings.
After substantial completion and prior to final inspection, the Contractor shall submit working as-built drawings for Government use during the inspection walkthroughs; at the end of the inspection, the Government and Contractor will identify any additional redlines that need to be added. Reference Tinker AFB General Specifications, Section 01 78 00 for additional information.
2.4.2 As-Built Drawings
After the final inspection, and after all Punch List Items have been completed, the Contractor shall incorporate the redlines into the CAD files, making any necessary changes from the inspections, and submit this final set as the Final As-built drawings. These drawings shall be labeled 'AS-BUILT' and submitted for Government approval. Reference Tinker AFB General Specifications, Section 01 78 00 for additional information.
Shop drawings shall be in accordance with the 'additional record drawings' requirements of Tinker AFB General Specifications, Section 01 78 00.
2.5 OPERATIONS & MAINTENANCE (O&M) MANUALS AND TRAINING
16 May 25 Statement of Work - 10 of 17 WWYK190068
The Contractor shall provide O&M manuals for Government approval a minimum of 30 calendar days prior to the final inspection. Reference Tinker AFB General Specifications, Sections 01 78 00 and 01 78 23, Operation and Maintenance Data, for additional information.
The Contractor shall provide training for Government operations and maintenance personnel.
Provide a training plan for Government approval a minimum of 30 calendar days prior to the final inspection. Reference Tinker AFB General Specifications, Sections 01 78 00 and 01 78 23 for additional information.
2.6 DD FORM 1354 REQUIREMENT
The Contractor shall submit a DD Form 1354, Transfer and Acceptance of Military Real Property, for Government approval a minimum of 14 calendar days prior to the final inspection. Reference Tinker AFB General Specifications, Section 01 78 00 for additional information.
3. GOVERNMENT FURNISHED DRAWINGS, SPECIFICATIONS & REFERENCES
3.1 DRAWINGS
Refer to Appendix A, Project Drawing Index. Drawing files, in PDF format, are included on the attached CD.
3.2 SPECIFICATIONS
Refer to Appendix B, Project Specification Table of Contents. Specification files, in PDF format, are included on the attached CD.
3.3 BASE STANDARDS / REFERENCE DOCUMENTS / FORMS
Refer to Appendix C, Tinker AFB Facility Standards and Reference Documents. Tinker AFB facility standards and reference files, in PDF format, are included on the attached CD.
4. GOVERNMENT FURNISHED PROPERTY:
There is no Government Furnished Property included in this contract.
5. STAGING/STORAGE AREA(S):
Contractor shall limit all applicable storage of materials, equipment, and incidentals to the immediate construction site while work is being performed. If the Contractor requires additional storage area(s) other than the project site, a request shall be submitted in accordance with Tinker AFB General Specifications, Section 01 50 00, Contractor Facilities.
It is recommended that the Contractor make arrangements for storage of equipment between its delivery and its installation, as availability of space and security during non-working hours cannot be guaranteed.
6. 'OR EQUAL' CLAUSE:
16 May 25 Statement of Work - 11 of 17 WWYK190068
Where reference is made in the specification or on the drawings to specific manufacturers and/or model numbers of equipment or materials, the information is provided to indicate design intent and to establish the minimum quality standards, physical attributes, and performance characteristics which are required for the referenced item. The use of specific names and/or model number is not intended to limit selection of other manufacturers;
equipment or materials meeting these criteria may be submitted to the COR for consideration and shall be clearly identified, in writing, as a substitution.
The burden of proving equality for proposed substitutions shall be the responsibility of the Contractor and submittals for said substitutions shall include detailed manufacturer’s specifications, dimensioned drawings, performance data and any other information necessary to clearly indicate that the proposed item meets or exceeds the quality standards, physical characteristics, and performance criteria established by the contract documents. Submittals, which do not provide proof of equality, will be rejected.
Approval of a substitute by the COR shall not result in a change to contract price or schedule;
such changes can only be approved by the CO.
End of SOW
16 May 25 Statement of Work - 12 of 17 WWYK190068
Appendix A Project Drawing Index
General
G-001 General Notes & Vicinity Map G-002 General Phasing Plan G-100A Code Analysis G-100B General Life Safety Overall Hangar Plan G-101 Life Safety First Floor Plan - Area A G-102 Life Safety First Floor Plan - Area B G-103 Life Safety First Floor Plan - Area C G-104 Life Safety First Floor Plan - Area D G-105 General Life Safety Second Floor Plan - Area A G-106 Life Safety Second Floor Area B G-107 Life Safety Mezzanine Plan G-108 Life Safety Third Floor G-109 Code Compliant Site Plan
Fire Protection
F-001 Fire Suppression General Notes F-002 Fire Alarm and Mass Notification - General Notes FD101 Fire Alarm First Floor Plan Area A - Demolition FD102 Fire Alarm First Floor Plan Area B – Demolition FD103 Fire Alarm First Floor Plan Area C – Demolition FD104 Fire Alarm First Floor Plan Area D – Demolition FD105 Fire Alarm Second Floor Plan – Demolition FD106 Fire Alarm Third Floor Plan – Demolition FD107 Fire Suppression First Floor Plan Area A – Demolition FD108 Fire Suppression First Floor Plan Area B – Demolition FD109 Fire Suppression First Floor Plan Area C – Demolition FD110 Fire Suppression First Floor Plan Area D – Demolition FD501 Fire Protection Demolition Photos FA101 Fire Alarm and Mass Notification Partial First Floor Plan Area A - New Work FA102 Fire Alarm and Mass Notification Partial First Floor Plan Area B - New Work FA103 Fire Alarm and Mass Notification Partial First Floor Plan Area C - New Work FA104 Fire Alarm and Mass Notification Partial First Floor Plan Area D - New Work FA105 Fire Alarm and Mass Notification Second Floor East & West - New Work FA106 Fire Alarm and Mass Notification Mezzanine Plan East & West - New Work FA107 Fire Alarm and Mass Notification Third Floor Plan East & West - New Work FA501 Fire Alarm and Mass Notification Details FA502 Fire Alarm Detail - Monaco Antenna Detail FA601 Fire Alarm and Mass Notification Sequence of Operations FA602 Fire Alarm and Mass Notification Riser Diagram FX101 Fire Suppression First Floor Plan Area A - New Work FX102 Fire Suppression First Floor Plan Area B - New Work FX103 Fire Suppression First Floor Plan Area C - New Work FX104 Fire Suppression First Floor Plan Area D - New Work FX501 Fire Suppression Details
16 May 25 Statement of Work - 13 of 17 WWYK190068
Appendix A (Continued) Project Drawing Index
Architecture
AD-101 Architectural Floor Plan – Demolition A-101 Architectural Floor Plan – New Work A-401 Architectural Enlarged Floor Plan - New Work A-501 Architectural Details and Schedules
Structural
S-001 Structural General Notes S-002 Structural Standard Details S-100 Structural First Floor Plan - New Work S-401 Structural Enlarged Intermediate Roof Plan - New Work
Mechanical
M-001 Mechanical Symbols, Legend and Abbreviations M-101 Mechanical Overall Plan M-401 Mechanical Enlarged Plan - New Work M-501 Mechanical Details
Electrical
E-001 Electrical Symbols, Legend, and Abbreviations E-100 Electrical Overall Plan – New Work ED-101 Electrical Overall Plan - Demolition ED-601 One-Line Diagram - Demolition E-401 First Floor Enlarged Plans E-402 Electrical Second Floor Enlarged Plans - Demolition & New Work E-601 Electrical One Line Diagram E-602 Electrical Schedules
16 May 25 Statement of Work - 14 of 17 WWYK190068
Appendix B Project Specification Table of Contents
Division 00 – Procurement and Contracting Requirements
00 70 00 General Requirements for Construction on Tinker AFB 00 71 00 General Safety Requirements for Construction on Tinker AFB 00 72 00 Environmental Requirements for Construction on Tinker AFB 00 80 00 Special Provisions for Working on Tinker AFB 00 80 05 Special Provisions for Working on or Near the Airfield on Tinker AFB
Division 01 - General Requirements
01 32 16.00 20 Small Project Construction Progress Schedules 01 33 00 Submittal Procedures 01 42 00 Sources for Reference Publications 01 45 00.00 10 Quality Control 01 50 00 Contractor Facilities 01 78 00 Closeout Submittals 01 78 23 Operation and Maintenance Data
Division 02 – Existing Conditions
02 41 00 Demolition
Division 05 - Metals 05 40 00 Cold-Formed Metal Framing
Division 07 - Thermal and Moisture Protection
07 21 16 Mineral Fiber Blanket Insulation 07 84 00 Firestopping 07 92 00 Joint Sealants
Division 08 - Openings
08 11 13 Steel Doors and Frames 08 71 00 Door Hardware
Division 09 - Finishes
09 22 00 Supports for Gypsum Board 09 29 00 Gypsum Board 09 65 00 Resilient Flooring 09 90 00 Paints and Coatings
Division 10 - Specialties
10 14 00.20 Interior Signage 10 26 00 Wall and Door Protection 10 44 16 Fire Extinguishers
16 May 25 Statement of Work - 15 of 17 WWYK190068
Appendix B (Continued) Project Specification Table of Contents
Division 21 - Fire Suppression
21 13 13 Wet Pipe Sprinkler Systems, Fire Protection
Division 23 - Heating, Ventilating, and Air Conditioning (HVAC)
23 09 00 Instrumentation and Control for HVAC 23 09 13 Instrumentation and Control Devices for HVAC 23 09 23.02 BACnet Direct Digital Control for HVAC and Other Building Control Systems 23 81 00 Decentralized Unitary HVAC Equipment
Division 26 - Electrical
26 20 00 Interior Distribution System 26 28 01.00 10 Coordinated Power System Protection
Division 28 - Electronic Safety and Security
28 31 76 Interior Fire Alarm and Mass Notification System, Addressable
16 May 25 Statement of Work - 16 of 17 WWYK190068
Appendix C Tinker AFB Facility Standards and Reference Documents
Base Facility Standards
2020 Tinker Air Force Base Facility Standard 2020 Tinker Air Force Base Mechanical Standard 2021 Tinker Air Force Base Electrical Standard
Tinker AFB General Specifications (Div 00 and Div 01) Reference Documents
Sections 00 7x 00 DoDOP-2000.16V1 AFI 10-245-0 Antiterrorism (AT) Program Implementation AFI 13-213 Airfield Driving AFI 13-213 TINKERAFBSUP Airfield Driving (Tinker AFB Supplement to AFI 13-213) AFI 21-101 Aircraft and Equipment Maintenance Management AFI 21-101 AFMCSUP Aircraft and Equipment Maintenance Management (AFMC
Supplement to AFI 21-101) AFI 48-104 Tobacco Free Living AFI 91-202 The US Air Force Mishap Prevention Program AFI 91-202 AFMCSUP The US Air Force Mishap Prevention Program (AFMC
Supplement to AFI 91-202) AFMAN 32-7003 Environmental Conservation AFMAN 40-201 Radioactive Material (RAM) Management AFMAN 48-148 Ionizing Radiation Protection AFMAN 91-203 Air Force Occupational Safety, Fire, and Health Standards AFMAN 91-203 OC-ALCSUP Air Force Occupational Safety, Fire, and Health Standards (OC-
ALC Supplement to AFMAN 91-203) TINKERAFBI 13-204 Airfield Operations TINKERAFBI 21-100 Foreign Object Damage (FOD) and Dropped Object Prevention
(DOP) Programs TINKERAFB_SOP_Outages Planned and Emergency Outages Standard Operating
Procedures TINKERAFB HWMP Tinker AFB Hazardous Waste Management Plan TINKERAFB INRMP Tinker AFB Integrated Natural Resources Management Plan TINKERAFB INRMP_APP E Tinker AFB Integrated Natural Resources Management Plan –
Appendix E, Native Landscaping Plant Materials TINKERAFB INRMP_APP G Tinker AFB Integrated Natural Resources Management Plan –
Appendix G, Urban Forestry Management Procedures EM 385-1-1 Safety -- Safety and Health Requirements Manual UFC 3-260-01 Airfield and Heliport Planning and Design UFC 3-260-04 Airfield and Heliport Marking UFC 3-535-01 Visual Air Navigation Facilities
16 May 25 Statement of Work - 17 of 17 WWYK190068
Appendix C (Continued) Base Standards and Reference Documents
UFC 3-600-01 Fire Protection Engineering for Facilities UFC 3-601-02 Fire Protection Systems Inspection, Testing, and Maintenance
Section 00 78 00 ERDC/ITL TR-12-1 A/E/C Graphics Standard ERDC/ITL TR-12-6 A/E/C CAD Standard
URML Unified Master Reference List
Tinker AFB General Requirements Specifications Attachments/Forms
00 70 00, Attachment 1 Tinker AFB Outage Request Form 00 71 00, Attachment 1 Airfield Construction Waiver 00 71 00, Attachment 2 EAL Template 00 71 00, Attachment 3 VEAL Template 00 72 00, Attachment 7a AF3952, Chemical/Hazardous Material Request Authorization
Form 00 72 00, Attachment 7b Monthly Hazardous Material Usage Report 00 72 00, Attachment 8 Recovered Materials Determination Form 00 72 00, Attachment 9 EMS Awareness Training 00 72 00, Attachment 13 AF487, Generator Operating Log 00 72 00, Attachment 14 Information for New Boilers 01 33 00, Attachment 1 AF3000, Material Approval Submittal 00 15 00, Attachment 1 Staging Request Form 01 78 00, Attachment 1 DD1354, Transfer and Acceptance of Military Real Property 01 78 00, Attachment 2 DD1354 Checklist
Tinker AFB General Requirements Specifications Required Training Materials
EMS General Awareness Training for Contractors AFMC FOD/DOP Program
| 1. SCOPE OF WORK |
| 1.1 GENERAL |
| 1.2 CONTRACTOR’S PROPOSAL |
| 1.2.1 Proposal Package |
| 1.2.2 Estimated Construction Schedule |
| 1.2.3 Contractor Personnel Resumes |
| 1.3 SPECIAL REQUIREMENTS |
| 1.3.1 Government Occupancy of Facilities |
| 1.3.2 Period of Performance |
| 1.3.3 Working Hours |
| 1.3.4 Phasing |
| There is a Government-required construction phasing for this Order. The maximum allowable downtime for phase (1) one and phase (3) three is (1) one week each. The maximum allowable downtime for phase (2) two and phase (4) four is (6) six weeks. Contr... |
| Phases 1, 2, 3, and 4 may be accomplished concurrently to reduce overall construction time if allowed by the government. |
| 1.3.5 FOD Awareness and Prevention Training |
| 1.3.6 Air Field Operations |
| 1.3.7 Controlled/Restricted Area(s) |
| Work to be performed under this Order is located in a controlled area. |
| 1.3.8 Contracting Officer’s Representative |
| 1.4 BADGE(S) |
| 1.5 OUTAGES AND CLOSURES |
| 1.6 RECOVERED MATERIAL DETERMINATION FORM (RMDF) |
| 1.7 ENVIRONMENTAL MANAGEMENT (EM) SURVEY |
| Removal of this paint can only be performed by a competent trained worker and practices that would create dust hazards should be avoided. |
| If at any time the Contractor encounters suspect environmental conditions not identified above, they shall notify the CO. |
| 1.8 HEALTH AND SAFETY |
| 1.9 BIOENVIRONMENTAL Regulations |
| 2. PRECONSTRUCTION & CONSTRUCTION SERVICES BY CONTRACTOR |
| 2.1 CONTRACT SCHEDULE AND PROGRESS REPORTING |
| 2.2 CONSTRUCTION |
| 2.3 ORDER OF PRECEDENCE |
| 2.4 RECORD DRAWINGS |
| 2.4.1 Working As-Built Drawings ('Redline' Set) |
| 2.4.2 As-Built Drawings |
| 2.5 OPERATIONS & MAINTENANCE (O&M) MANUALS AND TRAINING |
| 2.6 DD FORM 1354 REQUIREMENT |
| 3. GOVERNMENT FURNISHED DRAWINGS, SPECIFICATIONS & REFERENCES |
| 3.1 DRAWINGS |
| 3.2 SPECIFICATIONS |
| 3.3 BASE STANDARDS / REFERENCE DOCUMENTS / FORMS |
| 4. GOVERNMENT FURNISHED PROPERTY: |
| 5. STAGING/STORAGE AREA(S): |
| 6. 'OR EQUAL' CLAUSE: |