19-RF-029 SPECS.pdf

PDF 444 KB Posted

Attached to
Horicon Paving and Access Road Rehab
Solicitation number
140F0320R0011
Issued by

About this file

This federal contract solicitation seeks proposals for a paving and access road rehabilitation project at the Horicon National Wildlife Refuge in Wisconsin. The project consists of laying 7-inch thick fiber reinforced concrete paving including mobilization, removing existing parking lot base, placing and compacting embankment fill and aggregate, installing a trench drain system with PVC piping and a reinforced concrete end outlet, miscellaneous grading, and seeding disturbed areas. Work also includes surveying and setting grade stakes. There are two additives that will be detailed in the full solicitation package. The magnitude of this requirement is estimated between $500,000 to $1,000,000. This is a total small business set-aside under NAICS code 237310 for highway, street, and bridge construction. The solicitation package will be available on August 14, 2020 on SAM.gov with proposals due on September 14, 2020 and will include specifications, drawings, and prevailing wage determinations.

View the file

Other files

File Type Posted
Wage Determinations.pdf PDF
Notice to Offerors.pdf PDF
CPARS Notice.pdf PDF
PPQ.pdf PDF
SF 24 Bid Bond.pdf PDF
19-RF-029 DWGS.pdf PDF
19-RF-029 BIDSCH.pdf PDF
Sol_140F0320R0011.pdf PDF
CLAUSES.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DIVISION 1 SECTION 01100

GENERAL REQUIREMENTS SUMMARY OF THE

WORK

01100-1

A. General

1. Project Title: Maintenance Area and Access Road Paving and Rehabilitation.

2. All applicable Sections of the Federal Acquisition

Regulations (FAR) and Division 1 apply to each Section of this Technical Specification (Division 2 through 16).

3. Payment for work done under this contract shall be made in accordance with the lump sum and unit price bid therefore in the Bidding Schedule, and in accordance with subsequent addenda, Change Orders, and/or Extra Work Orders.

B. Work and Payment Under This Contract

1. The work in this contract is listed below. Measurement and payment shall include but not be limited to furnishing materials, labor, and equipment for work defined below.

Base Bid Item

Maintenance Area Paving and Rehabilitation - The work includes but is not limited to laying 7 inch thick fiber reinforced concrete paving including mobilization and demobilization, removing and stockpiling of existing parking lot base, placing, shaping, and compacting of embankment fill and aggregate, installing a trench drain system with PVC piping, installing a reinforced concrete end outlet, miscellaneous grading, and placing topsoil and seeding on disturbed areas not receiving paving. Work also includes surveying and setting grade stakes to ensure positive drainage as shown on the Construction Drawings.

Measurement for payment for Base Bid Item, Maintenance

Area Paving and Rehabilitation shall be lump sum.

01100-2

Schedule - Bid Additives

Item 1A. Access Road Rehabilitation. The work includes but is not limited to: Milling 4 inches of bituminous pavement off a section of road 20’ wide by 524 feet long, adding gravel base to raise the road 1 foot and widen each side of the road by 1 foot, and placing asphalt concrete pavement 3-1/2 inches thick as shown on the plans. Work also includes grubbing, earthwork, excavation, transporting, placing, shaping and compacting of embankment fill and aggregate, and placing topsoil and seeding on all disturbed areas not receiving gravel or asphalt paving.

Measurement for payment for Bid Alternative 1A, Access Road Rehabilitation shall be lump sum.

Item 2A. Maintenance Area Paving and Rehabilitation - The work includes but is not limited to laying 7 inch thick concrete paving including mobilization and demobilization, removing and stockpiling of existing parking lot base, placing, shaping, and compacting of embankment fill and aggregate, installing a manhole and 12” diameter concrete drain pipe and concrete end outlet, and placing topsoil and seeding on disturbed areas not receiving paving. Work also includes surveying and setting grade stakes to ensure positive drainage as shown on the Construction Drawings.

Measurement for payment for Bid Additive 2A, Maintenance

Area Paving and Rehabilitation shall be lump sum.

C. Location And Inspection Of Site

1. The site of the work is located at the Horicon National Wildlife Refuge, near Horicon, Wisconsin. The mailing

01100-3 address is shown on the Solicitation, Offer, and Award (Standard Form 1442) as attached to this Invitation. The Refuge Manager may be contacted for further information at the above referenced address or by telephone at (920) 387-2658.

2. All prospective bidders, contractors, subcontractors, and related persons are encouraged to visit the site of the proposed work and to assess the location and extent of the work prior to submitting bids. Persons may inspect the work site by contacting the Refuge Manager.

D. Specifications and Drawings for Construction

1. The successful bidder will be provided, upon request, 1 set of full size prints of the contract drawings as necessary for execution of this contract. These drawings will be provided at no additional cost to the successful bidder/quoter.

2. Exact location of all affected utilities will be the responsibility of the contractor. Drawings may not completely show all utilities. Site verification is required in addition to contacting any local authorities and utility companies to determine exact locations of utilities.

3. In case of difference between drawings and specifications, the specifications shall govern.

E. Work Not Included In This Contract

1. All items indicated "NIC" on drawings or specifications are items not included in this contract.

2. Work in place is generally shown as "Existing" on the

Contract Drawings.

3. Work to be performed under other contracts and not included as part of this contract is generally shown as "By Others" on the Contract Drawings.

01100-4

F. Items Provided By The Government

1. Work to be accomplished by the Government or manufactured items to be provided by the Government are generally shown as "By Government" on the Contract Drawings.

G. Engineering Services

1. None.

H. Temporary Facilities

1. Maintain and restore all government roads, service areas, and utilities used to pre-construction condition.

I. Site Access and Right of Way

1. The construction access limits on Government property will be established by the Government and the Contractor shall be responsible for complying with these limits and governing all work accordingly. All temporary access roads shall be removed following work completion unless directed otherwise by the Contracting Officer.

2. All bidders are reminded that they are responsible for contacting the local entity such as township, county, or state having jurisdiction in the project vicinity to insure bidders/quoters are aware of any requirements of the local entity. These requirements are between the entity and the bidder. Load limits and other restrictions shall be obeyed. If the Contractor proposes to cross private property, permission must be obtained from the owner to use private property or roads in the conduct of the work.

3. Work scheduled on Saturdays, Sundays, Federal Holidays or other than normal working hours will be approved in advance by the Government.

J. Safety - In addition to FAR 52.236-13 Accident Prevention

01100-5

1. Contractor shall fill out and submit the

“Preconstruction Safety Checklist” to the Contraction Officer (CO) prior to beginning construction.

2. The contractor shall designate a safety officer to ensure a safe work site. The safety officer shall perform daily work site inspections to assure compliance with all safety regulations and standards.

3. The Contractor’s Safety Plan shall be available on-site. The Contractor shall provide Material Safety Data Sheets (MSDS) for all hazardous materials brought on-site. MSDS shall be made available in a conspicuous location.

4. All equipment and work activities shall comply with OSHA

Regulations and all accidents incidental to work performed under this contract shall be reported in accordance with OSHA reporting requirements. Additionally a copy of the accident report shall be provided to the Contracting Officer.

5. The Contractor shall provide and install barricades, signs, or other warning devices to delineate the construction area and restrict public access to the construction site. Follow the Manual of Uniform Traffic Control Devices (MUTCD).

6. Provide at least one non-freezing-type fire extinguisher in each workshop and shed used for storage of materials on the premises. Place in location readily accessible to workers.

7. Provide at least on non-freezing type fire extinguisher of the appropriate class for each group of workers performing flammable operations.

8. Provide and maintain a basic first aid kit for use of workers.

01100-6

(a) Provide first aid supply commensurate with size of project and provide items necessary for first aid treatment of all injuries. The first aid supply shall include items identified on the Material Safety Data Sheets (MSDS) and be placed in applicable locations.

(b) Advise all workers of the location of first aid supplies.

(c) Post telephone numbers of nearest hospital or ambulance service and fire station in conspicuous location. Advise all workers of location of telephone numbers.

9. Provide necessary Personnel Protective Equipment (PPE) as identified by MSDS and OSHA regulations. Provide documentation that workers have been trained in use of PPE prior to individual use.

(END OF SECTION 01100)

DIVISION 1 SECTION 01310

GENERAL REQUIREMENTS PROJECT

COORDINATION

01310-1

A. Jobsite Administration - Superintendence, Subcontract administration and Quality Control, is the responsibility of the Contractor.

1. Final decisions relative to items in conflict shall be made by the Contracting Officer.

2. The Government shall have the authority to temporarily suspend the work for such time as necessary because of the failure on the part of the Contractor to perform any of the provisions of the contract, and no extension of contract performance time will be allowed for such suspensions. Resumption of work will not be permitted until the Government determines that the deficiencies in performance, which caused the temporary suspension, have been corrected.

3. The Contractor shall notify the Engineer at least ten

(10) days prior to the anticipated date of completion of all work specified herein. Upon completion of the work, the Engineer shall proceed with the final inspection which shall be completed as promptly as practicable. The time required for such inspection and for performing any corrective work shall be included in the contract performance time.

B. Modification/Change Order procedures

1. In the event of the need for a change order, the Contractor will receive a letter requesting a price quote for proposed changes to the contract.

2. For evaluation purposes, the Contractor's quote shall be broken down to show the costs of labor and materials for each proposed category of work included with the change, along with the total cost for Contractor's overhead, profit, and bond for the proposed changes.

01310-2

3. All contract time extensions required as a result of a proposed change must be justified and supported in detail at the time of the proposal.

C. Preconstruction Conference

1. Soon after award of the Contract and prior to commencing construction, the Contractor and any subcontractors shall attend a preconstruction conference with representatives of the Government. Timely notification of the meeting will be given to the Contractor. Time, date, and place of the conference will be determined by the Contracting Officer. Requirements pertaining to contract administration, construction operations and the project schedule will be discussed. The project schedule shall be in accordance with Section 01330.

2. The Preconstruction Safety Checklist must be submitted for review and completion during the Preconstruction Conference.

D. Progress Meetings

1. Periodic general project meetings will be conducted with a representative of the Contractor at the project site or by telephone by the Government's representative for the purpose of coordinating, expediting, and assessing the work progress.

2. The Contractor shall provide reports of progress on the project, discuss the work schedule for the coming period and present all conflicts, discrepancies or other difficulties for resolution. A record of discussions and decisions will be prepared by the Government and distributed to those attending and others affected.

01310-3

(END OF SECTION 01310)

DIVISION 1 SECTION 01330

GENERAL REQUIREMENTS SUBMITTALS

01310-1

A. General Refer to submittal register or technical specifications for all submittals required.

When specifically requested by the Government representative, the Contractor shall provide copies of manufacturer's literature containing detailed specifications and performance data or shop drawings fully describing the items and written installation instructions and/or recommendations for review and approval prior to accomplishing equipment installation.

B. Submittal Register:

1. A submittal register, listing all items requiring submittals under this solicitation, is provided as an attachment to this document. The Contractor shall provide all required submittals to the Engineer within 21 days of award except for items noted otherwise on the submittal register.

2. Furnish four copies of all required submittals. Three copies will be retained by the Government. One copy will be returned to the Contractor.

3. The approval of submittals shall not relieve the contractor to comply with the terms and conditions of the contract drawings and specifications. The contractor shall be responsible to determine correct dimension, design, connection, detail and satisfactory construction of all work.

C. Project Schedule: Contractor shall provide as required by

Federal Acquisition Regulation (FAR) clauses. *

D. Price Breakdown - Lump Sum Items: Contractor shall provide as required by FAR clauses. *

E. Subcontractor's List

Submit a list of subcontractors who will be working on the project.

DIVISION 1 SECTION 01330

GENERAL REQUIREMENTS SUBMITTALS

01330-2

F. Submittal of Progress Payment Certificate: Contractor shall provide as required by FAR clauses. *

G. Guarantees, Warranties And Certificates -Refer to Section

01770.

H. Operating And Maintenance Instruction - Refer to Section

01770

I. Delivery Tickets

1. The Contractor shall submit to the Government's on site representative, one legible copy of each delivery ticket for all material delivered to the construction site.

2. The delivery ticket shall show brand name, catalog number, and number of items received.

J. Waste Manifests

4. The Contractor shall submit copies of all waste manifests.

5. Manifests shall state type of waste (i.e., construction debris, hazardous asbestos, etc.), location of disposal, landfill designation, EPA registration of landfill, and EPA registration for transportation of any hazardous wastes.

* The applicable FAR clauses will be provided in full text to the resultant contractor at the pre-construction conference.

(END OF SECTION 01330)

DIVISION 1 SECTION 01420

GENERAL REQUIREMENTS DEFINITIONS AND STANDARDS

01420-1

A. Regulatory Requirements

1. All work shall be accomplished in strict accordance with the regulations, codes, and laws in effect at the time the work is performed for the location where it is to be performed.

B. Means and Methods

1. Means and methods used in the performance of this contract must be in accordance with all applicable Federal Acquisition Regulations in addition to OSHA regulations, 29 Code of Federal Regulations, acceptable industry practices as recognized by societies, associations, building codes, manufacturers’ specifications and any applicable state safety and health requirements.

C. Permits

1. All permits required to support construction activities such as road permits for oversize, overweight vehicles and equipment, bridge permits, and utility hookup permits, shall be obtained and paid for by the Contractor.

(END OF SECTION 01420)

DIVISION 1 SECTION 01770

GENERAL REQUIREMENTS PROJECT CLOSEOUT

01770-1

A. Manufacturer's Specifications

1. The installation of manufactured products and equipment, together with all associated parts, shall be in conformance with the manufacturer's recommendations, and code requirements. All installations shall be complete and ready for immediate use, and every essential part required for proper operation of the manufacturer's equipment shall be provided. Following the completion of the work under this contract, all installed equipment shall be tested for proper operation and compliance with the contract.

B. Final Inspection

1. The Contractor shall request a final inspection in writing at least ten (10) days prior to the anticipated date of completion.

2. Work will not be considered ready for final inspection until all the work has been completed and the Contractor has certified that all items are properly operating and in strict compliance with all contract terms and conditions.

3. The Contractor and the Contracting Officer’s

Representative (COR)shall be at the job site during the final inspection.

C. Tests

1. Submit reports of all tests to the Contracting Officer’s Representative prior to final payment.

DIVISION 1 SECTION 01770

GENERAL REQUIREMENTS PROJECT CLOSEOUT

01770-2

D. Record Drawings

The Contractor shall provide and maintain in proper order and in good, clean condition, in the field or the Refuge office or at the project site, one (1) complete set of full size prints of all drawings. On this set, with red pencil or ink, the Contractor will neatly inscribe all changes in work. At time of final acceptance, and prior to final payment, these corrected prints will be presented to the Engineer. The Contractor will note all data and changes on these record drawings in sufficient detail and clarity to provide information necessary for preparation of "as built" drawings by the Government.

E. Guarantees, Warranties and Certificates

1. The Contractor will submit all guarantees, warranties and certificates to the government prior to final payment.

2. The Government requires a 100% warranty for a period of one full year after final acceptance. Items of work found defective during the warranty period will be replaced at no cost to the Government and the warranty for that particular part of the work shall automatically extend for one full year beyond the completion date of repairs.

3. If a manufacturer or supplier offers a guarantee in excess of the one year requirement outlined herein, then the longer guarantee period will apply for those particular items.

(END OF SECTION 01770)

DIVISION 2 SECTION 02200

SITE WORK

EARTHWORK

02200-1

1. The requirements of this section shall govern the earthwork necessary for sub-grade preparation or embankment construction including all excavation, scarifying, surface grading, compaction of fill, and supply or removal of all excavated material.

2. The Contractor shall take reasonable precautions to protect natural plant growth outside of the construction limits against damage from construction operations. The Contractor shall box, pad or fence existing trees which are subject to damage from construction operations.

3. The Contractor shall determine the exact locations of all affected utilities and structures prior to commencing construction and shall govern construction operations in a manner that will prevent damage to them.

4. Submittals: The Contractor shall submit compaction tests for all subgrades. The tests shall be made by an independent testing laboratory and all tests shall be paid for by the Contractor.

a. In-place field density tests of the sub-grade shall be tested for compliance with these specifications in accordance with ASTM Standards. Tests which do not meet the density standards shall be repeated after the material has been re-compacted.

Compaction shall not be less than 100% Standard Proctor for subgrades and 95% for embankments.

b. All density tests shall be in accordance with ASTM Standards for standard proctor maximum dry density specified and within -1 to +3 percent of the soils optimum moisture content.

c. Density Tests Quantities:

SITEWORK

1. Base Bid Item Testing - A minimum of 10 tests shall be taken and the locations of those test shall be at the discretion of the Government Inspector.

2. Bid Additive 1A Testing - A minimum of 10 tests shall be taken and the locations of those tests shall be at the discretion of the Government Inspector.

3. Bid Additive 2A Testing - A minimum of 10 tests shall be taken and the locations of those tests shall be at the discretion of the Government Inspector.

C. Execution

1. Existing topsoil to the extent it is encountered shall be stockpiled at the site to be used for later re-spread.

Vegetation to the extent it is encountered shall be scarified and removed from the site. Grading of the sub-grade shall be smoothed and trimmed and shall be free of depressions or lumps, to a tolerance of 0.1 foot. Grades and drainage shall be sloped as shown on the contract drawings.

2. Existing gravel base and soil materials shall be removed to a depth necessary to allow placement of the aggregate base and concrete or bituminous paving to the depths required as shown on the contract drawings and as described herein. Gravel and soil materials removed shall be stockpilied for later reuse if they meet base course or embankment requirements.

3. All waste materials encountered or excavated from designated areas shall be removed from the site at the Contractor's expense and disposed of according to local and state code requirements.

4. Following excavation of existing soil and/or road shoulder and base material, the sub-grade shall be tested

SITEWORK

for density. Areas not meeting the required density requirements shall be re-compacted. Compaction shall not be less than 100% Standard Proctor for subgrades under bituminous or concrete pavement and 95% for road shoulders and embankments.

4. Grading of the sub-grade shall be smoothed and trimmed and shall be free of depressions or lumps, to a tolerance of 0.1 foot. Sub-grade shall be sloped as shown on the contract drawings. The sub-grade shall be maintained in a smooth condition until the aggregate or fill has been placed.

(END OF SECTION 02200)

DIVISION 2 SECTION 02224

SITEWORK AGGREGATE BASE COURSE

02224-1

1. Work under this section includes the furnishing, spreading and compaction of the aggregate base courses under all concrete and bituminous pavements, under PVC and concrete pipes and manhole, and along the Access Road shoulder edge.

2. The Contractor shall provide all labor, tools, materials and equipment necessary to install the base course as shown on the contract drawings and as specified herein.

3. All work performed under this section shall be accompanied by personnel experienced in this type of work and with equipment suitable for the work being done.

Unless otherwise specified herein, work under this section shall meet the requirements of Division 3 conforming to the State of Wisconsin DOT Standard Specifications for Highway and Structure Construction, 2013 edition.

4. All work specified herein shall be accomplished only when, in the opinion of the Engineer, weather and site conditions are suitable for this type of work.

5. Submittals:

a. Certification that the gravel material meets these specifications shall be submitted for approval prior to delivery of any materials to the job site.

Weight tickets shall be collected by the Government Inspector at the jobsite.

b. The Contractor shall submit compaction tests made by an independent testing laboratory. All tests shall be paid for by the Contractor.

1. Aggregate density tests shall be in accordance with Method C of AASHTO T 99 with a minimum of 10 tests being taken for the Base Bid, 10 tests for Bid Additive 1A, and 10 tests for

02224-2

Bid Additive 2A. Testing locations shall be at the discretion of the Government Inspector.

2. Subgrade density tests shall be in accordance with Section 02200, paragraph A.4.

B. Materials

The aggregate used for the base course under bituminous and concrete pavement shall conform to the following gradation:

Sieve Size % Passing By Weight

1-1/4 95 - 100

1" - 3/4" 70 - 93% 3/8" 42 - 80% No. 4 25 - 63% No. 10 16 - 48% No. 40 8 - 28% No. 200 2 - 12%

The aggregate used for all road shoulder areas, under pre-cast and PVC pipe and under the manhole structure shall conform to the following gradation:

Sieve Size % Passing By Weight

1" 100% 3/4" 95 -100% 3/8" 50 - 90% No. 4 35 - 70% No. 10 15 - 55% No. 40 10 - 35% No. 200 5 - 15%

Crushed rock for the base course shall consist of clean, sound durable fragments of stone, free from an excess of flat, elongated soft or disintegrated pieces, dust, dirt or other objectionable matter.

02224-3

C. Equipment

1. The equipment used in the work shall be of sufficient size and in such mechanical condition as to meet the requirements specified herein and shall be capable of providing a satisfactory quality of work. All equipment shall be ready for immediate use when required or directed by the Engineer. The Engineer may order the immediate removal and replacement of any unsatisfactory piece of equipment which will not, in his opinion, produce finished work of acceptable quality.

2. Any equipment which drips fuel, grease, oil or any other substance which, in the opinion of the Engineer, is detrimental to the quality of the finished product shall not be permitted on the jobsite until such drips are adequately repaired.

D. Execution

1. Subbase construction: Refer to Section 02200, Paragraph A.4.

2. Aggregate Base Under Bituminous: The aggregate base under all bituminous paving shall be constructed in a total compacted thickness of twelve (12) inches placed in layers of not more than six (6) inches when using vibratory rolling equipment. Compaction shall be no less than 100% standard proctor. Water shall be added if required to obtain specified density.

2. Aggregate Base Under Concrete: The aggregate base under all concrete paving shall be constructed in a total compacted thickness of six (6) inches placed in layers of not more than six (6) inches when using vibratory rolling equipment. Compaction shall be no less than 100% standard proctor. Water shall be added if required to obtain specified density.

02224-4

3. Aggregate Base Under Fiber Reinforced Concrete Paving, PVC and Pre-Cast Pipes, and under the Manhole and Outlet Structures and for Access Road Shoulder shall be constructed in a total compacted thickness of six (6) inches placed in layers of not more than six (6) inches when using vibratory rolling equipment. Compaction shall be no less than 100% standard proctor. Water shall be added if required to obtain specified density.

5. Aggregate surfaces shall be smooth and uniform and free from abrupt changes in grade. They shall be sloped to provide drainage and shall contain no depressions which would pocket water. Drainage for the shoulder sections of the Access Road will be graded at 2%.

(END OF SECTION 02224)

DIVISION 2 SECTION 02270

SITEWORK GEOTEXTILE FABRIC

02270-1

1. The requirements of this section shall govern the work necessary to place the geotextile fabric. Geotextile fabric shall be used in conjunction with riprap for erosion protection at pre-cast concrete end section outlets.

2. Submittal: The brand geotextile fabric to be used shall be accepted on the following basis: The Contractor shall furnish the Engineer a mill certificate or affidavit signed by a legally authorized official from the company manufacturing the fabric. The mill certificate or affidavit shall attest that the fabric meets the requirements stated in these specifications.

B. Material

The filter fabric shall be pervious sheet, woven or non-woven, resistant to deterioration in soil construction applications. The filter fabric shall contain stabilizers and/or inhibitors to make the filaments resistant to deterioration due to ultra-violet and heat exposure. The filter fabric shall provide an Equivalent Opening Size (EOS) no finer than U.S. Standard Sieve No. 100 and no coarser than U.S. Standard Sieve No. 70. EOS shall be measured in accordance with CW-02215 (Corps of Engineers, November, 1977). The fabric Grab Tensile Strength (ASTM D- 1682) shall exceed 250 pounds in any principal direction.

The fabric puncture Strength (ASTM D-751) shall exceed 120 psi. The burst strength (ASTM D-751) shall exceed 400 psi.

1. The Contractor shall provide that during all periods of shipment and storage the filter fabric material shall be protected from the direct sunlight, ultra-violet rays, temperature greater than 140ΕF and any mud, debris, or damaging material. The fabric shall remain in a heavy duty protective covering prior to

DIVISION 2 SECTION 02270

SITEWORK GEOTEXTILE FABRIC

02270-2 installation.

2. Fabric strips shall be placed so as to provide a minimum overlap of three (3) feet. The fabric shall be protected at all times during installation and construction. Damaged fabric shall be replaced, except that holes or tears of not larger than two (2) feet in any direction and not closer than two (2) feet to an edge may be covered with a patch two (2) feet larger than the hole. The fabric shall be covered within 3 days of placement.

(END OF SECTION 02270)

DIVISION 2 SECTION 02271

SITEWORK RIPRAP

02271-1

1. The Contractor shall furnish and place riprap protection to the prescribed outlines and thickness as shown on the drawings. Riprap shall be used in conjunction with geo-textile fabric for erosion protection on outlet end sections.

2. Quality Control

a. The Government may require testing to assure that the riprap meets the requirements specified herein.

All costs of tests of density and gradation shall be borne by the Contractor. One (1) performance of each type of test may be required. However, should the riprap be shown to be inadequate in any test, additional testing under the direction of the Engineer and at no cost to the Government, will be required. The Engineer will designate the riprap samples to be used in the test.

b. This gradation test shall be performed by the

Contractor on site and in the presence of the Engi-neer. Location of the test area will be selected by the Engineer. The test will involve removing all riprap in place from the predetermined location, weighing and grading approximately one

(1) cubic yard of material, and replacement of material to the original location. It is the Contractor's responsibility to assure that the riprap meets the gradation and tolerances specified in these specifications at the source of supply.

c. Riprap found to be deficient in any respect shall be re-graded or replaced at no additional cost to the Government.

3. Submittal Certification:

a. The source of the riprap material shall be

DIVISION 2 SECTION 02271

SITEWORK RIPRAP

02271-2 approved, in writing, by the Engineer prior to the start of riprap operations.

1. Riprap stone shall be natural stone and shall be sound, non-stratified, durable, and free of defects. The riprap shall be graded between 2 and 6 inches in diameter.

Recycled concrete shall not be used.

2. All riprap material shall be compact in shape, and the greatest dimension of any individual rock shall be no greater than three (3) times its least dimension.

3. The riprap shall have a minimum density of 157 pounds per solid cubic foot and shall be reasonably well graded.

1. Geotextile fabric material shall be placed under all riprap. The riprap shall be placed in such a manner so as to avoid dislocating or damaging the geotextile fabric.

The Contractor shall demonstrate to the Engineer prior to placement the method he will use.

2. Riprap shall be placed in such a manner that the completed riprap is stable and the larger stones are uniformly distributed throughout the mass so that no small rock concentrations or voids occur. The finished surface shall be uniform meeting the slope and depth requirements shown. The Contractor shall remove substandard riprap as directed, and replace with riprap material meeting the requirements of this paragraph. The material which is removed shall be removed from the Refuge and disposed of in a legally constituted disposal site at no additional cost to the Government.

(END OF SECTION 02271)

DIVISION 2 SECTION 02533

SITE WORK BITUMINOUS

SURFACING

02533-1

1. Work under this Section includes all surface preparation, leveling, bituminous placement, compaction, finishing and related operations necessary to install bituminous base course and bituminous surface course. This work shall include all areas where installation of a 1-3/4 inch bitunimous base course lift and a 1-3/4-inch bituminous surface course lift is required.

2. All work performed under this Section shall be accomplished by mechanics experienced in this type of work and with equipment suitable for the type of work being done.

3. All work specified herein shall be accomplished only when in the opinion of the Engineer, weather and site conditions are suitable for this type of work.

4. Where not specifically covered herein, all work shall be accomplished in accordance with applicable provisions of Wisconsin Department of Transportation Standard Specifications for Highway and Structure Construction (WI/DOT), 2013 edition, Sections 450, 455, and 460.

5. Flagmen and barricades shall be used as necessary to control and direct traffic in a safe manner.

6. Submittals:

a. All materials utilized in the work shall be subject to review and approval by the Engineer prior to commencement work. Certified laboratory analysis of all bituminous materials proposed for use shall be submitted to the Engineer for review and approval prior to delivery of any such materials to the jobsite.

02533-2

b. The Contractor shall submit to the Engineer a statement giving the sources of all paving materials proposed for the work.

c. At least 15 days prior to preparation of any asphaltic concrete material to be used on the project, the Contractor shall submit to the Engineer for review and approval, a job-mix formula to be supplied for the project. The job-mix formula shall contain a gradation curve for the combined aggregate, relative quantity of each ingredient and shall state a definite percentage for each sieve fraction of aggregate and for the bituminous material. No material will be accepted for use until the job-mix formula has been reviewed and approved, in writing, by the Engineer

d. The Engineer reserves the right to make such changes in the proportions of asphalt cement and aggregate as he considers necessary within the limits of the specifications.

e. Testing: The contractor shall engage a qualified independent testing agency to perform field quality control testing. In-place density of compacted pavement will be determined by testing 4 samples according to ASTM D 1188 or ASTM D 2726. Core sample locations will be at the discretion of the COR. Minimum required density will conform to Section 460.3.3.1, Table 460-3.

1. Bituminous Asphalt materials:

a. Bituminous asphalt material shall be WI/DOT LV Mix, with liquid asphalt cement PG58-28.

b. Aggregate size used in the mixture shall conform to paragraph 460.3.2 and the following:

02533-3

Lower Layer: 12.5 mm Upper Layer: 12.5 mm

c. Tack coat shall be MS-2, SS-1, SS-1h, CSS-1 or CSS-

1h emulsified asphalt.

C. Equipment

1. General:

a. The equipment used in the work shall be of sufficient size and in such mechanical condition as to meet the requirements specified herein and shall be capable of providing a satisfactory quality of work. All equipment shall be ready for immediate use when required or directed by the Engineer. The Engineer may order the immediate removal and replacement of any unsatisfactory piece of equipment which will not, in his opinion, produce finished work of acceptable quality.

b. Any equipment which drips fuel, grease, oil or any other substance which, in the opinion of the Engineer, is detrimental to the quality of the finished product shall not be permitted on the jobsite until such drips are adequately repaired.

D. Execution

1. General:

a. Bituminous materials shall be applied only when surface and weather conditions are favorable.

b. Bituminous materials shall be placed only during daylight hours when the base and air temperatures are 50 F. or higher, when the relative humidity is 75% or less, and when the base surface is dry.

Moisture content of the upper 2 inches of base

02533-4 material shall be not more than 65% optimum moisture content.

c. All bituminous pavement work shall be accomplished between June 1 through October 15.

d. The Contractor shall notify the Contracting Officer at least 72 hours in advance of paving operations.

All paving shall be conducted in the presence of the Government Inspector.

2. The bituminous surfacing shall be constructed in two (2) separate compacted lifts to the depth described in the specifications and shown on the drawings.

3. Surface Preparation:

a. Areas which are to receive paving shall be true to line and grade and shall be free of loose or foreign materials, which in the opinion of the Engineer, would impede proper bonding.

b. All vertical surfaces and existing asphalt with which the mixture will come in contact shall be given a tack coat. Apply tack coat as specified in WI/DOT Section 455.3.2.

c. Any existing bituminous or concrete surface abutting the new bituminous shall have a straight, cut joint made.

d. The operation of equipment on tack coated surfaces shall be prohibited unless specifically authorized by the Engineer. If the base lift is dirtied by the Contractor, another tack coat will be required at the Contractor's expense.

4. Transportation of the Mix:

02533-5

a. The mix shall be transported to the jobsite in vehicles cleaned of all foreign material which may affect the mix.

b. Transport vehicles shall be dispatched such that the mix is delivered at a uniform rate which does not exceed the paving machine capacity.

c. The paving mix shall be delivered to the jobsite at a temperature as specified by the batch plant but in no case shall the temperature of the mix at the jobsite be less than 230 F. The transport vehicles will be covered and/or insulated as required by the Engineer.

5. Spreading and Finishing:

a. The temperature of the surface on which the mix is to be placed shall not be less than 50F.

b. The mix shall be spread and struck off with a mechanical paving machine meeting the requirements of WI/DOT.

c. The paving machine shall produce a uniform textured layer prior to rolling.

d. In areas not accessible by the paving machine, the mix may be spread and finished by alternate equipment or hand as approved by the COR.

e. Placing by hand shall be done carefully. The mix shall be spread uniformly to avoid segregation of the aggregates. Prior to rolling, the surface shall be checked with a straight edge and all irregularities shall be corrected.

6. Compaction:

a. Minimum compaction density shall be as shown in

Section 460.3.3.1.

02533-6

b. During rolling, roller wheels shall be kept moist with only enough water used to prevent picking up the material.

c. Following compaction of longitudinal joints and edges, rolling shall start longitudinally at the sides and gradually progress toward the center of the parking lot. The rollers shall move at a uniform speed with the drive wheels nearest the paver.

d. If rolling causes displacement of the material, the affected areas shall be loosened at once with lutes or shovels and restored to the original grade of the loose material before being re-rolled.

e. Heavy equipment and/or rollers will not be permitted to stand on the pavement until it has been thoroughly compacted and cooled.

f. Breakdown rolling shall immediately follow rolling of the longitudinal joints and edges. Rollers shall be operated as close to the paver as necessary to obtain the required density without undue placement.

g. The second rolling shall be accomplished with pneumatic tire or tandem rollers as specified herein. The second rolling shall follow the breakdown rolling as closely as possible and while the mix is still at a temperature which will allow for proper compaction.

h. Finish rolling shall be accomplished while the material is still warm enough to allow for removal of the roller marks.

i. Areas which are not accessible by the rollers shall be compacted with a trench roller or by hand.

02533-7

7. Surface Requirements:

a. The surface shall be tested with a 10 foot straight edge. Any irregularities which vary more than 1/4 inch shall be corrected by the Contractor at no additional cost to the Government.

b. Drainage slopes shall conform to those shown on the construction drawings, with a minimum of 2% being required.

8. Traffic Control:

When working, the Contractor shall provide appropriate barricades, warning devices, and/or flagmen as necessary to protect workers, equipment, and construction areas.

Follow the Manual of Uniform Traffic Control Devices

(MUTCD).

(END OF SECTION 02533)

DIVISION 3 SECTION 02570

CONCRETE PRE-CAST CONCRETE MANHOLE AND

ACCESSORIES

02570-1

1. The requirements of this section pertain to the installation of the pre-fabricated reinforced concrete manhole and outlet sgtructures, slot trench drain, and PVC and pre-cast pipes installed in the Maintenance Area under Bid Alternative 2A and Base Bid Items.

2. The reinforced concrete manhole will be designed to meet HS-20 Loadings.

3. The work shall include the furnishing of all labor, tools, equipment, materials and performing all required operations to provide a complete item in accordance with the project plans and these specifications.

4. All concrete work not specifically covered by these specifications shall conform to ACI Standard Building Code Requirements for Reinforced Concrete (ACI 318-77) and the Wisconsin Department of Transportation Standard Specifications.

B. Quality Assurance

1. Perform Work according to ASTM and AASHTO standards and manufacturer’s instructions and to Referenced Standards below:

a. ASTM C478 – Standard Specification for Circular

Precast Reinforced Concrete Manhole Sections.

b. ASTM C497 – Standard Test Methods for Concrete Pipe, Manhole Sections, or Tile.

c. ASTM C990 – Standard Specification for Joints for

Concrete Pipe and Manholes using Preformed Flexible Joint Sealants.

d. ASTM C913 – Instructions for unloading and moving precast concrete manholes and drainage structures.

e. ASTM A36 Structural Steel for Frames and Grates

02570-2

C. Submittals:

1. Product Data: Submit manufacturer’s information for pre-cast manhole, pipe and outlet components including materials, features, configuration, and dimensions.

Manufacturer shall have a minimum 5 years of successful experience in providing pre-cast structures.

2. Manufacturer’s Instructions: Submit detailed instructions on installation requirements, including storage and handling procedures.

3. Quality Control Submittals: Provide results of factory and onsite tests and inspections.

4. Warranty: Furnish a minimum one-year manufacturer’s warranty for all components listed in this Section. Follow the Standards listed below.

1. Precast Concrete Base – AASHTO M 259, ASTM C478, Type V cement, minimum 28 day compressive strength 4,000 psi, minimum 6” of concrete between invert and exterior of the base, reinforced as required. All reinforcing designed for 1” minimum cover. Interior manhole steps shall be steel, plastic coated, and 16” on center if required.

2. Precast Concrete Barrel System – AASHTO, M 259, ASTM C478, Type V cement, 48” inside diameter. Eccentric cones with the same wall thickness and reinforcement, sized for minimum 24”frame and grate cover.

3. Manhole Extension - ASTM C478, Type V cement, minimum 24” inside diameter of similar quality as manhole sections.

4. Manhole and Base Coatings – PPC coating as manufactured by the Polymorphic Polymers Corporation or approved equal.

Applied to all interior manhole surfaces.

5. Preformed Joint Material – Plastic or mastic as recommended by the barrel section manufacturer. Resistant to sewer environment to provide water tight seal between

02570-3 concrete sections. Preformed joint material shall be Ram- Nek, Kent Seal, or equal.

6. Non Shrink Grout – ASTM C1107, prepackaged.

7. Frame and Grate - Type V cement, minimum 24” inside diameter of similar quality as manhole sections.

8. 12”Diameter Pre-Cast Reinforced Concrete Pipe – Furnish

12” diameter pipe conforming to ATSM C76, AASHTO M170, Class III, with bell and spigot joint configuration.

Joints will be sealed with an elastomeric rubber gasket and joint lubricant supplied by the manufacturer. The lubricant shall be applied to the gasket and bell during assembly and the joint shall be watertight. All pipe requirements and assembly will meet WISDOT Standard Specifications.

9. Pre-Cast Reinforced Concrete Outlet Structure - ASTM C478, Type V cement, minimum 28 day compressive strength 4,000 psi, minimum 6” of concrete between invert and exterior of the base, reinforced as required. All reinforcing designed for 1” minimum cover. Interior manhole steps shall be steel, plastic coated, and 16” on center if required.

Outlet sections will meet WISDOT Standard Specifications.

10. Manhole Grate Cover – Standard 24-inch diameter steel with hot dipped galvanized finish. Contractor to submit drain grate manufacturer and grate opening styles for approval.

1. Verify that the excavation base is ready to receive Work and excavation dimensions and elevations are as indicated on the Drawings. Remove any ground water if present.

Ensure the bedding and backfill for the manhole, pipe trench and outlet are compacted as required. Correct over excavation by adding base aggregate specified.

2. Inspect precast concrete manhole, pipe, and outlet sections prior to placement to verify that they are

02570-4 internally clean and free from damage. Remove and replace damaged units.

3. Lift precast components at lifting points designated by the manufacturer and place precast manhole base on firm dense bedding. Set level and firmly position base section before adding additional sections. Join base to pipe per manufacturer’s recommendations. Coat with Polymorphic Polymer coating.

4. Place each section and extension plumb. Join sections with a full bed of preformed joint material. Cut off excess joint material to provide space for at least ¼ inch depth of grout. Verify that all surfaces are free of dirt, oil, grease or other contaminants. Roughen surface to ensure sufficient bond and grout smooth the interior and exterior of the joint after the mastic has set. Refer to Manufacturer’s instructions for proper grouting application.

5. Adjust and set frame and grate cover. Verify that the installed manhole meets required alignment and grade to allow surface drainage off concrete pavement.

6. Leakage Testing – Testing in accordance to ASTM C497.

a. Perform leakage testing prior to backfilling.

b. Conduct a visual inspection of concrete manhole structure. Repair all visible and detectable leaks.

c. Temporarily plug all wall sleeves, piping entrances and other openings during test period.

d. Fill Structure to overflow level. Allow to stand for 4 hours. Refill to overflow level. Allow to stand for 24 hours.

e. Examine exterior surfaces and joints for leakage.

Measure drop in surface water. Allowable leakage is a drop of ½ inch or less during the test period and no visible signs of leakage.

02570-5

f. Acceptance: Contractor shall repair or replace components failing to perform as specifies and rerun test at no cost to the government.

7. Lay pre-cast pipe along trench to precast outlet location connecting pipe sections to the outlet in conformance with manufacturer’s installation recommendations. Sectionsulet

8. Backfill manhole, pipes and outlet structures according to Specification Section 02200, Earthwork.

End of Section

DIVISION 3 SECTION 02950

CONCRETE SITE

RESTORATION

02950-1

1. Work covered in this Section includes providing all materials, equipment and labor to seed and establish grass cover on all disturbed areas not receiving aggregate or bituminous or concrete paving. Work will include final grading, topsoil preparation and placement, seeding, mulching and other work as may be necessary.

2. All work in this Section shall conform to Wisconsin

Department of Transportation Standard Specification for Highway and Structure Construction (WI/DOT), 2013 Edition, Section 625, Topsoil and Salvaged Topsoil.

3. Submittals: Seed Certification.

1. Seed shall be Prarie Nursery of Westfield, WI seed mix #50012 and shall be applied at a rate of 10 pounds per acre. The mix shall be supplemented with annual oats and shall be applied at a rate of 30 pounds per acre.

2. Mulch materials shall meet the requirements of WI/DOT

Standard Specification 627.

1. Areas requiring seeding shall be final graded as shown on the Drawings. Grading shall be performed in manner that will minimize erosion. After final grading, all disturbed areas shall be covered with topsoil, seeded and mulched.

Turf restoration shall be in accordance with WI/DOT Standard Specificatons 625, 627, and 630.

2. A minimum of 4 inches of topsoil depth shall be placed in all areas requiring seeding.

(END OF SECTION 02950)

DIVISION 3 SECTION 02950

CONCRETE SITE

RESTORATION

02950-2

DIVISION 3 SECTION 03210

CONCRETE REINFORCING STEEL

03210-1

1. All concrete reinforcing steel will be fabricated and placed in accordance with the "Manual of Standard Practice" by the Concrete Reinforcing Steel Institute (CRSI), latest edition. Fabrication and placement will also be in accordance with these specifications and as shown on the contract drawings.

2. Submittal: The Contractor shall furnish mill certificates and shop drawings for the reinforcing steel used. The mill certificate shall include all descriptive material information pertaining to the reinforcing steel.

The shop drawings shall show all dimensions and connection details.

1. Reinforcing steel shall conform to the requirements of ASTM A-615, latest revision.

a. All bars No. 4 or larger shall be Grade 60.

b. Submit non-shrink structural grout.

1. Store steel reinforcement in protected area before use.

2. Drill holes of appropriate diameter to allow reinforcing bars to be securely set in grout.

3. All reinforcing steel shall be securely supported so they will not be displaced while placing fiber reinforced concrete.

4. Subject to the approval of the Engineer, reinforcement bar placement may be modified from spacing shown in the drawings to avoid embedded items and other obstructions

DIVISION 3 SECTION 03210

CONCRETE REINFORCING STEEL

03210-2 in the existing Vehicle Storage Building floor slab.

7. Prior to fiber reinforced concrete paving, the Contractor will notify the designated Government Inspector when the reinforcing bars have been grouted in the floor slab so that reinforcing can be inspected.

(END OF SECTION 03210)

DIVISION 3 SECTION 03310

CONCRETE FIBER REINFORCED

CONCRETE

03300-1

1. The requirements of this section pertain to the installation of the fiber reinforced concrete pavement in the Maintenance Area.

2. All concrete work not specifically covered by these specifications shall conform to Wisconsin Department of Transportation Standard Specification for Highway and Structure Construction (WI/DOT), 2013 Edition.

3. Testing. The Contractor shall:

a. Perform appropriate laboratory tests including compression tests of cylinders, air content and slump tests to substantiate mix designs.