19 CPTS Carpet Performance Work Statement (PWS).pdf

PDF 371 KB Posted

Attached to
19 CPTS Carpet B1255
Solicitation number
FA446026Q0039
Issued by

About this file

This is a Performance Work Statement (PWS) dated 23 April 2026 for the removal, furnishing, and installation of new flooring in Building 1255 at Little Rock Air Force Base. The contractor must remove approximately 4,283 square feet of existing flooring and 1,071 linear feet of cove base, then furnish and install an estimated 474 square yards of commercial-grade modular carpet with no padding and 1,071 linear feet of vinyl or rubber cove base. The work must be completed within 45 days of material reception or 90 days of contract award, whichever is sooner.

The carpet specifications require material from seven manufacturers through the Air Force Carpet II Program as a mandatory source: Mohawk (2OCR-T, Datum, 7948 Granite), Engineered Floors (1OS-T Meadow Modular Tile color 7097 and 2OS-T Fractured Plaid Modular Tile color 2878), Interface Americas (1OS-T Sublet Color 105879), Mannington (Style TERET/TEREB Teres Cashmere), Tarkett (1OS-T Fabricate Beachrock), and Bentley Mills (3OCR-P Shapeshifter II). Cove base shall be 0.080-inch thick, 4-inch-high Johnsonite color 29 Moonrock or equal. The contractor is responsible for all materials, labor, waste disposal (including mandatory recycling), furniture removal and reinstallation, site preparation, cleanup, and providing a room-by-room phasing plan. The facility operates with over 100 personnel daily and requires room-by-room installation with possible weekend work; facility escorts will be provided. The contractor must secure appropriate base passes and comply with all fire, safety, security, and traffic regulations at Little Rock AFB. The work includes a 12-month warranty on workmanship and labor from the acceptance date, with material warranties following manufacturer specifications.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CUI

Performance Work Statement (PWS)

REMOVE, FURNISH AND INSTALL NEW FLOORING

BUILDING 1255

23 APRIL 2026

1. DESCRIPTION OF SERVICES

1.1. The contractor shall provide all qualified personnel, transportation, tools, equipment, materials and services required to remove the existing floor and cove base, furnish and install new flooring and cove base at building 1255 in selected areas. The contractor shall accomplish all the services below to meet the requirements of this Performance Work Statement (PWS).

Work shall comply with all Federal, State and local regulations, codes and license requirements.

Work shall be accomplished within 45 days of the reception of material or 90 days of contract award.

1.2. The Government will neither supervise contractor employees nor control the method by which the contractor performs the required tasks. It shall be the responsibility of the contractor to manage its employees and to guard against any actions that are of the nature of personal services or give the perception of personal services. If the contractor feels that any actions constitute, or are perceived to constitute personal services, it shall be the contractor’s responsibility to notify the Contracting Officer (CO) immediately. These services shall not be used to perform work of a policy/decision making or management nature, (e.g., inherently governmental functions). All decisions relative to programs supported by the contractor shall be the sole responsibility of the Government.

2. SAFETY AND REGULATORY REQUIREMENTS

2.1. Building 1255 is an administrative facility with over 100 personnel daily. This operation shall require the contractor to work with a room-by-room installation and may have to work on weekends to accomplish the task due to operations. The facility user shall provide contractor escorts within the facilities for the duration of the operation.

2.2. Pre-Install Requirements: Before services commence, the contractor shall inspect the work site and ascertain all information for the diligent performance of the service(s). The contractor shall notify the ordering agency of any conditions that prevent the suitable completion of these services to include operations that could endanger Government personnel or property and require appropriate abatement action. If the contractor discovers problems associated with the work after starting, he or she shall immediately notify the Contracting Officer (CO) for their approval if the work is to continue. Coordinate with the Government designated representative to have utilities/fire alarms etc. turned on or off during the competition of the task.

2.3. Disposal of waste: All waste disposals are the responsibility of the contractor to include any fees or permits. Recycling is mandatory at Little Rock AFB and containers shall be provided for the operation to dispose of cardboard, paper or any other recyclable material. Coordinate through your government representative.

2.4. All work shall be accomplished in accordance with all regulations regarding the installation of flooring in commercial structures and flooring manufacturer specifications along with any environmental regulations on disposal.

2.5. Storage of materials shall be the responsibility of the contractor to arrange with the facility manager or to store off site. 19 CES is not responsible for the storage or the acceptance of material deliveries to Little Rock AFB.

2.6. Carpet and adhesives furnished for this project must be purchased through the Air Force Carpet II Program as a mandatory source. Carpet and adhesives picked below come from the program.

https://usaf.dps.mil/sites/aficc/afcc/aficc/affcc/sitecollectiondocuments/carpet/carpethomepage.as px

3. WORK REQUIREMENTS

3.1. General Installation: The contractor shall furnish and install commercial grade, Texture Appearance Retention (TARR) method heavy duty or greater commercial grade modular carpet as specified. All cove bases shall be in 120 linear feet rolls by the height and material described unless otherwise specified. Manufacturer, style, and color of flooring are listed below. The contractor is responsible for furnishing all manufacturers recommended adhesives, cove base adhesives, track and caps, transitions, stair/stage edging etc. as part of the installation process in colors specified to match cove base. All exact matches or like items shall meet the customer criteria set forth below.

3.1.1. The contractor shall remove and dispose of an estimated 4,283 square feet of flooring and 1,071 linear feet of cove base from the facility. The contractor shall be responsible for professionally removing and installing all furniture to include modular and regular desks, file cabinets, chairs, cubicles, and seating. The facility users shall be responsible for removing all electronics, books, files, personal items and loose objects (Example: personal items, copiers, printers, computers) in the area specified for floor replacement this contract. The contractor shall provide a room by room phasing plan to the CO during the contract solicitation phase as a part of their bid package for a smooth transition of the flooring removal process.

3.1.2. Preparation of Area: The contractor shall remove all old flooring material, cove base and foreign matter from the surface to be covered, such as loose particles, dirt and grease prior to installation of any floor coverings. Depressions, cracks, crevices, torn wall covering etc., shall be properly prepared or attached to provide a level and true installation of the floor covering.

Extensive cleaning of and/or repairs to be covered shall be completely dry and free from moisture prior to the installation. The contractor will ensure that the temperature of the premises is proper to prevent buckling or shrinkage after installation is completed. Adhere to flooring manufacturer’s specifications for installation.

3.1.3. Contractor shall furnish and install an estimated 474 square yards of commercial modular carpet (no padding):

Manufacturer 1: Mohawk, 2OCR-T, Datum, 7948 Granite.

https://usaf.dps.mil/sites/aficc/afcc/aficc/affcc/sitecollectiondocuments/carpet/carpethomepage.aspx https://usaf.dps.mil/sites/aficc/afcc/aficc/affcc/sitecollectiondocuments/carpet/carpethomepage.aspx

Manufacturer 2: Engineered Floors, 1OS-T, Meadow Modular Tile, color 7097.

Manufacturer 3: Engineered Floors, 2OS-T, Fractured Plaid Modular Tile, style 7587, color 2878 cloth.

Manufacturer 4: Interface Americas, 1 OS-T, Sublet, Color 105879 Upper East.

Manufacturer 5: Mannington, Style code TERET/TEREB, Teres, color Cashmere 122220.

Manufacturer 6: Tarkett, 1OS-T, 11498, Style Fabricate, Color Beachrock 36213.

Manufacturer 7: Bentley Mills, 3OCR-P, Color Shapeshifter II.

3.1.4. Contractor shall furnish and install an estimated 1,071 linear feet of .080 thick, 4-inch-high vinyl or rubber cove base (exact color match or like item): Manufacturer Johnsonite, color 29 Moonrock or equal.

3.1.5. Material Approval and Acceptance: Prior to ordering material, contractors must provide material samples of their recommended or equal manufacturer to the COR to ensure the colors suggested are acceptable through our base engineers. The government reserves the right to change color of the material prior to ordering.

3.1.6. Clean up of Work Areas: Spots and smears of adhesives shall be removed immediately.

Upon completion of the installation work, the contractor shall remove all unused materials, containers, wrappings, cuttings, trimmings, and any other debris, which has accumulated because of the services.

3.1.7. Acceptance of Work: Upon completion of work the contractor shall coordinate a walkthrough inspection of the jobsite with the government representative or COR. 100% inspection of the jobsite, installation, workmanship and material shall be completed to the satisfaction of this PWS before work is considered complete.

4. GOVERNMENT FURNISHED EQUIPMENT

4.1. None.

5. GENERAL REQUIREMENTS

5.1. Contractor personnel and vehicles must possess appropriate passes. These shall be obtained from Installation Security Forces Pass and ID at the Vehicle Inspection Center. A state issued REAL-ID or US Government Passport is required for entry to Little Rock AFB. Non-US citizens: Getting authorization to base may take up to 30 days with proper authorization. Email address to start the pass process is: 19sfs.vss.requests@us.af.mil

5.2. The Contractor is subject to all installation fire, safety, security, and traffic regulations.

5.3. The Government contracts on the understanding that the Contractor is complying with applicable laws concerning workplace safety.

mailto:19sfs.vss.requests@us.af.mil

5.4. The Contractor is subject to all citations and penalties for violation of applicable workplace safety laws. The burden of compliance rests with the Contractor. Enforcement of workplace safety laws is the responsibility of the agency specified in the applicable law.

5.5. The Contracting Officer may notify the Contractor of hazards in Contractor operations that endanger Government personnel or property and require appropriate action. This provision does not constitute assumption of liability for Occupational Safety and Health compliance on the part of the Government or negate other agency responsibility for enforcement of applicable laws.

5.6. Accident prevention principles must be thoroughly integrated into all operations. Unsafe conditions and practices, as identified by the designated representative, must be corrected immediately.

5.7. Contractor Employees: While on the installation, the contractor shall not employ persons for work on this contract if such an employee is identified to the contractor by 19 Security Forces or the Contracting Officer as a potential threat to the health, safety, security, general well-being or operational mission of the installation and its population. Contractor personnel shall present a neat appearance and be easily recognized as contractor employees. This may be accomplished by wearing distinctive clothing bearing the name of the organization or by wearing appropriate badges containing the organization's name and the employee's name. Contractor personnel must wear issued base identification cards at all times while on the installation.

5.8. Service contracts shall require contractor employees to identify themselves as contractor personnel by introducing themselves or being introduced as contractor personnel and displaying distinguishing badges or other visible identification for meetings with government personnel. In addition, contracts shall require contractor personnel to appropriately identify themselves as contractor employees in telephone conversations and in formal and informal written correspondence.

6.0. WARRANTY

6.1. Contractor shall guarantee all workmanship and labor from defects for a period of 12 months from the date of acceptance of the work. Material shall follow manufacturer specifications for warranty.

7.0. APPENDIXES

Appendix A: Floor Plan, Building 1255 Appendix B: Commander’s Environmental Policy Letter

AutoCAD SHX Text up

AutoCAD SHX Text up

AutoCAD SHX Text up

AutoCAD SHX Text up

AutoCAD SHX Text up

AutoCAD SHX Text up

AutoCAD SHX Text FLOOR PLAN B-1255 FIRST FLOOR 34001.66 Sq. Ft.

1129053654A Rectangle

1129053654A Rectangle

1129053654A Rectangle

1129053654A Rectangle

1129053654A Rectangle

1129053654A Rectangle

1129053654A Rectangle

1129053654A Rectangle

1129053654A Rectangle

1129053654A Rectangle

1129053654A Rectangle

1129053654A Rectangle

1129053654A Rectangle

1129053654A Rectangle

1129053654A Rectangle

1129053654A Rectangle

1129053654A Rectangle

APPENDIX B: COMMANDER'S ENVIRONMENTAL POLICY LETTER

DEPARTMENT OF THE AIR FORCE

HEADQUARTERS 19TH AIRLIFT WING (AMC)

LITTLE ROCK AIR FORCE BASE, ARKANSAS

01 June 2023

MEMORANDUM FOR ALL LIT1LE ROCK AFB PERSONNEL

FROM: 19 AW/CC

SUBJECT: Commander's Environmental Policy

1. Little Rock AFB is committed to conducting its national security mission in an environmentally responsible manner that will protect human health, natural resources, and the environment. In support of this commitment, it is our objective to ensure the progressive improvement of the Environmental Management System (EMS) aspects and impacts in all operations, facilities and daily activities.

2. Little Rock AFB goal is to provide the best possible environment to safeguard the lives and health of everyone living and working on Little Rock AFB and in our surrounding communities through programs dedicated to continual improvement to support the next generation warfighter in the support of Air Mobility Command and C-130 operations.

3. Little Rock's environmental policy includes a commitment to continual improvement and prevention of pollution. It is appropriate to the nature, scale and environmental impacts of its activities, products and services while complying with applicable legal requirements which relate to the environmental concerns.

4. The environmental policy intent is to be communicated to all personnel working for and on behalf of LRAFB while also being available to the public upon request. Currently public concerns regarding environmental issues on base are nonexistent.

5. Base-wide training venues for EMS awareness are available on eDash at the following link.

https ://usaf.dps.mil/teams/ eD ASH/ edashsupdoc/ edash%20learning%20management%20system%20(lms) %20user°/o20guide. pdf

6. This policy supersedes the EMS Policy dated 18 October 2022 and will be made available on the Little Rock AFB Portal at the following link.

https ://usaf.dps.mil/teams/ 10625/LittleRock/Shared%20Documents/EMS/2023 %20Commanders%20Env ironmental%20Policy%20signed.pdf.

7. If additional assistance is required, please contact 19 CES/CEIE at 987-7700 or 987-8135.

Compliance with the commitments contained within this policy shall be the responsibility of all members of Little Rock AFB, including all military, civilians, and contractors.

DAVIES.DENNY. o;'"'"";,,.aby

0AV1ES.DENNY.R .1186167941

R. 1186167941 D•" 202300D1 15 14,15-0500'

DENNY R. DAVIES, Colonel, USAF Commander

BLACK KNIGHTS