About this file
Summary of Town of Greenwich Bid Documents for Project 19-22
This is a Request for Bid (RFB) package issued by the Town of Greenwich, Connecticut, Department of Public Works Engineering Division for maintenance dredging of sediment forebays at Binney Park Pond. The project involves the removal and off-site disposal of approximately 300 cubic yards of sediment initially, with an estimated 150 cubic yards required annually for up to four years, using mechanical dredging methods in two sediment forebays within the upper pond. The dredging work will be performed in accordance with an Inland Wetlands and Watercourses Agency (IWWA) permit with an expiration date of August 22, 2026. Sealed bids consisting of one original and two copies are due on Wednesday, November 26, 2025, at 2:00 p.m. at the DPW Chimblo Conference Room, Town Hall, 101 Field Point Road, Greenwich, Connecticut. The contract includes a Base Bid for non-hazardous material dredging and an Alternative Bid for hazardous material dredging, with the Town determining annually which classification applies based on sediment laboratory testing prior to issuing a Notice to Proceed. The contractor must commence work within ten days of receiving the Notice to Proceed and complete work within 275 calendar days, with a daily time charge of $1,500 assessed for delays beyond this period.
The bid documents specify prevailing wage requirements in accordance with Connecticut General Statutes Section 31-53, with detailed wage schedules provided for various classifications including mechanical dredge operators, maintenance engineers, mates/welders, and deckhands. All contractors must provide proof that employees have completed a 10-hour OSHA construction safety and health course prior to beginning work and must submit certified weekly payrolls documenting compliance with minimum wage rates. A bid bond in the amount of 10 percent of the total bid is required with bid submission, and the successful contractor must furnish a Performance, Maintenance, and Payment Bond in the full amount of the contract within ten days of award. Insurance requirements include General Liability ($2,000,000 aggregate/$1,000,000 per occurrence), Comprehensive Automobile Liability ($1,000,000 combined single limit), Excess Liability ($5,000,000 umbrella form), Workers' Compensation per Connecticut statute, and Professional Liability ($1,000,000). The Town reserves the right to reject any or all bids and to accept the lowest responsible bid based on the average total price of the Base Bid and Alternative 1. Payment will be made monthly based on 75 percent of excavated material with the remaining 25 percent paid upon acceptance of the final hydrographic survey, with a 5 percent retainage held for 30 days after completion and 2 percent retainage held for the remainder of the one-year warranty period.
Text of this file
S
I EW
AR
CH
D R
OUND V
PO
I N T
RO
A D
AutoCAD SHX Text
TOWN OF GREENWICH
AutoCAD SHX Text
CONNECTICUT
AutoCAD SHX Text
PROPOSAL - SPECIFICATIONS
AutoCAD SHX Text
INFORMATION FOR BIDDERS
AutoCAD SHX Text
FOR
AutoCAD SHX Text
DEPARTMENT OF PUBLIC WORKS
AutoCAD SHX Text
ENGINEERING DIVISION
AutoCAD SHX Text
AT BINNEY PARK POND
AutoCAD SHX Text
PROJECT NO. 19-22
AutoCAD SHX Text
MAINTENANCE DREDGING OF SEDIMENT FOREBAYS
AutoCAD SHX Text
NOVEMBER 2025
SECTION 1
INFORMATION FOR BIDDERS
TITLE ARTICLE
RECEIPT AND OPENING OF BIDS 1.1
LOCATION AND DESCRIPTION OF WORK TO BE DONE 1.2
CONTRACT DOCUMENTS 1.3
NON-REFUNDABLE FEE FOR DRAWINGS AND DOCUMENTS 1.4
QUESTIONS REGARDING DRAWINGS AND DOCUMENTS 1.5
BIDDERS TO INVESTIGATE 1.6
INFORMATION NOT GUARANTEED 1.7
BLANK FORM FOR BID 1.8
TIME LIMITS AND TIME CHARGE 1.9
WITHDRAWAL OF BIDS 1.10
CONTRACT BONDS 1.11
ABILITY AND EXPERIENCE OF BIDDER 1.12
BIDS 1.13
RIGHT TO REJECT OR ACCEPT BIDS 1.14
RIGHT TO ALTER FORM, QUANTITY, ETC., OF WORK 1.15
EXECUTION OF AGREEMENT 1.16
INSURANCE CERTIFICATES 1.17
COMPARISON OF BIDS 1.18
BID SECURITY 1.19
ITEMS 1.20
MINIMUM PREVAILING WAGE RATES 1.21
CONSTRUCTION SAFETY AND HEALTH COURSE 1.22
NON-CONNECTICUT CONTRACTORS 1.23
SUPPLIERS AND SUBCONTRACTORS 1.24
PROHIBITION OF WASTES GENERATED FROM OIL AND GAS DRILLING AND EXTRACTION
ACTIVITIES 1.25
INFORMATION FOR BIDDERS
1.1 RECEIPT AND OPENING OF BIDS.
Sealed bids, one (1) original and two (2) copies, will be received in the Office of the Purchasing Department and shall be opened and read aloud in the DPW Chimblo Conference Room, Town Hall, 101 Field Point Road, Greenwich, Connecticut at 2 o'clock p.m. (prevailing time) on Wednesday, November 26, 2025 for the following work:
Maintenance Dredging of Sediment Forebays at Binney Park Pond Town Project No. 19-22
1.2 LOCATION AND DESCRIPTION OF WORK TO BE DONE.
The work herein specified to be done consists of the removal and disposal offsite of approximately 300 cubic yards of sediment initially with approximately 300 cubic yards every other year thereafter up to 4 years, completed by mechanical dredging in two sediment forebays within the upper pond of the Binney Park Pond. Greenwich Connecticut, all as more particularly indicated, shown or described in the drawings, specifications and other contract documents and as described by the Engineer.
The Contractor shall furnish all labor, services, materials, equipment, plant, machinery, apparatus, appliances, tools, supplies and all other things necessary to do all work required for the completion of each item of the work and as herein specified.
The location, general characteristics and principal details of the work are indicated on drawings which are listed as follows:
SHEET NUMBER TITLE
Figure 1 Location Map Figure 2 Existing Conditions Figure 3 Post Dredge Conditions Figure 4 Annual Dredging Plan
The above drawings are the contract drawings, sometimes referred to herein as the "Drawings".
Additional drawings showing details in accordance with which the work is to be done will be furnished from time to time by the Engineer, if found necessary, and shall then become a part of the contract drawings.
1.3 CONTRACT DOCUMENTS.
The 'Drawings', 'Invitation to Bid', 'Information for Bidders', Forms for 'Bid', 'Agreement' and ‘Bonds’, 'General Conditions' and 'Technical and Materials Specifications' become the contract documents and may be obtained on the Town’s website, www.greenwichct.gov/bids.
1.4 NON-REFUNDABLE FEE FOR DRAWINGS AND DOCUMENTS.
Drawings and specifications will be posted to the Town’s website and may be downloaded at no cost.
Drawings taken from the Town’s website and printed on the bidder’s equipment may not be to scale.
1.5 QUESTIONS REGARDING DRAWINGS AND DOCUMENTS.
In general, no answer will be given to prospective bidders in reply to an oral question if the question involves an interpretation of the intent or meaning of the drawings or other contract documents or the equality or use of products or methods other than those designated or described on the drawings or in the specifications.
Any information given to bidders other than by means of the drawings and other contract documents, including addenda, as described below, is given informally, for information and the convenience of the bidder only, and is not guaranteed. The bidder agrees that such information shall not be used as the basis of nor shall the giving of http://www.greenwichct.gov/bids any such information entitle the bidder to assess any claim or demand against the Town or the Engineer on account thereof.
To receive consideration, such questions shall be submitted in writing to the Project Engineer, Finton Sweeney, Civil Engineer II, Town of Greenwich, DPW Engineering Division 101 Field Point Road Greenwich, CT 06830 or by email to finton.sweeney@greenwichct.gov at least five (5) days before the established date for receipt of Bids. If the questions involve the acceptability or use of any unspecified products or methods, it must be accompanied by drawings, specifications or other data in sufficient detail to enable the Engineer to determine the acceptability, equality and suitability of the unspecified product or method. In general, the Engineer will neither approve nor disapprove particular products prior to the opening of Bids; such products will be considered when offered by the Contractor for incorporation into the work.
The Engineer will set forth as addenda, which shall become a part of the contract documents, such questions received as above provided as in their sole judgment are appropriate or necessary and their decision regarding each. It is the responsibility of the prospective bidder to check the Town’s website (www.greenwichct.gov/bids) for any addenda issued up to 48 hours prior to the bid opening.
The Contractor agrees to use the products and methods designated or described in the specifications as amended by the addenda. Any addenda issued shall take precedence over drawings or specifications.
Where there is a conflict between specifications and drawings, the higher standard shall prevail.
1.6 BIDDERS TO INVESTIGATE.
Bidders are required to submit their bids upon the following express conditions which shall apply to and be deemed a part of every bid received.
Bidders must satisfy themselves by personal examination of the site of the work and by such other means as they may wish, as to the actual conditions there existing, the character and requirements of the work, the difficulties attendant upon its execution, and the accuracy of all estimated quantities stated in the Bid.
Any subsurface information furnished is based on an interpretation made at specific locations as indicated and no assurance is given that these conditions are necessarily typical of other locations or that they have remained unchanged since the field data were obtained. Further, no assurance is given that the presence or absence of water and other subsurface conditions at the time of these explorations will be representative of actual conditions at the time of construction. The Contractor shall be solely responsible for any assumptions, deductions, or conclusions they may make or which may be derived from their examination of any available subsurface information.
1.7 INFORMATION NOT GUARANTEED.
All information given on the drawings or in the other contract documents relating to subsurface and other conditions, natural phenomena, existing pipes and other structures is furnished only for the information and convenience of bidders and is not guaranteed.
It is agreed and understood that the Town does not warrant guarantee that the subsurface or other conditions, natural phenomena, existing pipes or other structures encountered during construction will be the same as those indicated on the drawings or in the other contract documents and the bidder or Contractor shall assume all risk with respect to such conditions.
It is agreed further and understood that no bidder or Contractor shall use or be entitled to use any of the information made available to them or obtained in any examination made by them in any manner as a basis of or ground for, any claim or demand against the Town or the Engineer, arising from or by reason of any variance which may exist between the information made available and the actual subsurface or other conditions, natural phenomena, existing pipes or other structures actually encountered during the construction work.
The Contractor shall dig test pits, contact appropriate parties, or do any other necessary work, and at their mailto:finton.sweeney@greenwichct.gov http://www.greenwichct.org/ own expense, to locate subsurface and other structures both shown and not shown on the drawings, in advance to performing work near the structure.
1.8 BLANK FORM FOR BID.
All bids must be upon the blank form for "Bid Sheet", which is given in Section 2, and must state the proposed price of each item of the work, both in words and in figures, and be signed by the bidder with their business address and place of residence.
1.9 TIME LIMITS AND TIME CHARGE.
The Contractors shall commence with the work within ten (10) days after receipt of 'Notice to Proceed' from the Town.
Time is of the essence of this contract and as prosecution of the work will inconvenience property owners, vehicular traffic, and pedestrians and adversely affect business in the area, it is essential that the work be pressed vigorously to completion. Also, the cost to the Town of administration of the contract, including engineering, inspection and supervision of construction, will be increased or decreased as the time occupied in the work is lengthened or shortened and the deprivation to the residents of the Town of the needed improvement herein contracted for will cause damages to the Town, the exact amount of which will be difficult to ascertain.
Therefore, in order to avoid the uncertainties and time consuming effort involved, it is hereby estimated that the reasonably probable, foreseeable damages which will arise in the event of the Contractor's delay are hereby expressed in terms of a time charge which will be made against the Contractor, and dates for completion, suspension and/or commencement of work will be established in accordance with the following provisions.
A time charge of One Thousand Five Hundred Dollars ($1,500.00) per day will be made against the Contractor for each and every day (Saturdays, Sundays and legal holidays excluded) that the work is in progress beyond two hundred seventy-five (275) days calendar days (no days excluded) after the Contractor has been notified to commence with the work. The amount of time charge will be deducted from the monthly and final payments due the Contractor as these are made. This time charge will continue, except as provided below, until the work is completed and accepted, but not including retainer, maintenance or repair period, if any. The Engineer's decision concerning whether the work has been completed shall be final, as provided in Article 4.4 of this contract.
Each bidder should include in their estimate of the cost of the work, a sum equal to the amount derived by multiplying said time charge by the number of days which they estimate the time charge will apply. This sum shall not appear as a separate item of the bid, but shall be distributed among the various items on which prices are asked on the bid sheet. The time charge will be suspended during the period of any delay that may be caused by the Town, either through change of plan or through ordering suspension of the work for any reason other than failure on the part of the Contractor to comply with the specifications, said suspension must be certified by engineer.
If any delay is caused to the Contractor by specific orders of the Engineer to stop the work (for reasons other than failure on the part of the Contractor to comply with the requirements of the contract documents), such delay will entitle the Contractor to an equivalent extension of time, and the suspension of the time charge only during such an extension of time. When extra or additional work is ordered by the Engineer, the Contractor will be allowed a suspension of the time charge expressed in days and derived by dividing the cost of such additional work by the time charge factor.
The time charge factor is that number derived by dividing the total amount of the contract on which the award is made by the number of days between date work is started and date of completion and acceptance of the repair and alteration, etc., deducting Saturdays, Sundays and legal holidays.
1.10 WITHDRAWAL OF BID.
Except as hereinafter in this article otherwise expressly provided, once their bid is submitted and received by the Town for consideration and comparison with other bids similarly submitted, the Bidder agrees that they may not and will not withdraw it within one hundred and twenty (120) days consecutive calendar days after the actual date of opening of Bids.
Upon proper written request and identification, Bids may be withdrawn only as follows
1. At any time prior to the designated time for the opening of bids
2. Provided the bid has not theretofore been accepted by the Town, at any time subsequent to the expiration if the period during which the bidder has agreed not to withdraw their bid.
Unless a bid is withdrawn as provided above, the Bidder agrees that it shall be deemed open for acceptance until the 'agreement' has been executed by both parties thereto or until Town notifies a Bidder in writing that their bid is rejected or that the Town does not intend to accept it, or returns their bid deposit. Notice of acceptance of a bid shall not constitute rejection of any other bid.
1.11 CONTRACT BONDS.
The Bidder whose bid is accepted agrees to furnish the 'contract bonds' in the forms which follow in Section 5, entitled ‘Contract Bonds’, each in the sum of the full amount of the bid, including allowance for contingencies and extra work, and/or contract price as determined by the Engineer, and duly executed and acknowledged by the said Bidder as principle and by a surety company qualified to do business under the laws of the State of Connecticut and satisfactory to the Town, as surety, for the faithful performance of the contract and payment for labor and materials. The premiums for such bonds shall be paid by the Contractor. The ‘Contract Bond’ is only required for contracts exceeding $100,000.
For contracts that require a Performance, Maintenance and Payment Bond, the contractor shall maintain all of the specified required insurance coverage and continue to document the specified required insurance coverage for one (1) year after completion of the work of the contract (or other such time as the contractor or other agreement requires).
The Bidder must provide a letter from the bonding company stating that their company is able to receive performance bonding within one weeks’ time after receipt of award on the Town of Greenwich Performance, Maintenance and Payment Bond Form (enclosed herein) for this project in the total amount of the bid. The letter must be on the bonding company’s letterhead with their name address and telephone number and must be submitted with the bid.
1.12 ABILITY AND EXPERIENCE OF BIDDER.
No award will be made to any Bidder who cannot satisfy the Town that they have sufficient ability and experience in this class of work and sufficient capital and plant to enable them to prosecute and complete the work successfully within the time named, or, where such time is not named, within reasonable period of time as is determined by the Engineer. The Town's decision or judgment on these matters shall be final, conclusive and binding.
The Town may make such investigations as it deems necessary, and the Bidder shall furnish to the Town, under oath if so required, all such information and data for this purpose as the Town may request.
The ability of any Bidder to obtain a performance bond will not be regarded as the sole test of such Bidder's competency or responsibility.
1.13 BIDS.
The Town may reject bids which in its sole judgment are either incomplete, conditional, obscure or not responsive or which contain additions not called for, erasures not properly initialed, alterations or similar irregularities, or the Town may waive such omissions, conditions or irregularities.
1.14 RIGHT TO REJECT OR ACCEPT BIDS.
The Town reserves the right to reject any or all bids with or without reason, or to accept any bid even if it is not the low bid, should the Town deem it to be in the public interest or the interest of the Town to do so. The Town's decision on the qualifications of any bid and/or its decision to accept any bid, or reject any or all bids shall be final, conclusive and binding on all Bidders.
1.15 RIGHT TO ALTER FORM, QUANTITY, OF WORK.
The Town further reserves the right to make alterations in the lines, grade, plan, form and quantity of the work herein contemplated, either before award of contract to the successful Bidder and/or before or after the commencement of the work because of priority restrictions, insufficient funds in appropriations, or other cause.
If such alterations diminish the quantity of the work to be done, they shall not constitute a claim for damage or for anticipated profits on the work dispensed with, or affect the prices bid for the various classes of work remaining. If they increase the amount of work, such increase shall be paid for according to the quantity actually done and at the price or prices bid for the various classes of work, or if not susceptible of classification, the price or prices shall be agreed upon in writing in advance, and in case of failure to so agree, the Contractor shall do the work as aforesaid as extra work.
1.16 EXECUTION OF AGREEMENT.
The Bidder whose bid is accepted will be required and agrees to duly execute the 'agreement' and furnish the required contract bonds and insurance certificates within ten (10) days after award of the contract.
1.17 INSURANCE CERTIFICATES.
The Bidder is required to submit with their bid a signed ‘Insurance Procedure Form’, enclosed herein.
By signing this form, the Bidder acknowledges that they will provide the insurance coverage required for the contemplated work at no additional charge to the Town of Greenwich.
The Contractor will not be permitted to start any construction work until they have submitted certificates covering all insurance and in such form called for under that article of the 'agreement', titled 'Insurance', and has obtained approval in writing of such certificates from the Town.
1.18 COMPARISON OF BIDS.
Bids will be compared on the basis of the sum of the quantities multiplied by respective unit prices, added to lump-sum prices, all as stated in the 'Bid Sheet'.
In the event that there is a discrepancy in the Bid Sheet between the Lump-Sum or unit prices written in words and figures, the prices written in words shall govern.
The Town agrees to examine and consider each bid submitted in consideration of the Bidder's agreements, as hereinabove set forth in the Bid Sheet.
1.19 BID SECURITY.
Each bid must be accompanied by a bid bond prepared on the form of bid bond attached hereto duly executed and acknowledged by the Bidders, as principal, and by a surety company qualified to do business in the State of Connecticut and satisfactory to the Town, as surety.
The bid bond shall be in the sum of 10% of the total bid amount and shall be enclosed in the sealed envelope containing the Bid. Each bid bond may be held by the Town as security for the fulfillment of the Bidder's 'agreement' as hereinabove set forth and as set forth in the Bid Sheet. Should the Bidder fail to fulfill such agreements, the Bid Bond shall become payable to the Town, as liquidated damages, otherwise, the Bid Bond shall become null and void.
1.20 ITEMS.
The work to be done under this contract has been divided into parts or items to enable each Bidder to bid on the different portions of the work in accordance with their estimate of their cost and so that the actual quantity of work executed under each item may be paid for at the price bid for that particular item.
1.21 MINIMUM PREVAILING WAGES.
The minimum prevailing wages paid on this project, when applicable, shall be as shown on the State of Connecticut Labor Department, Wage and Workplace Standards Division, 'Schedule of Prevailing Rates' a copy of which is attached to these specifications or, if not attached, shall be issued by addendum. See Section 4.48 of these specifications.
1.22 CONSTRUCTION SAFETY AND HEALTH COURSE.
Pursuant to Connecticut General Statutes Section 31-53b the Bidder awarded a Contract for new construction of $1,000,000 or more or rehabilitation, repair or the like of $100,000 or more must furnish proof with the weekly certified payroll for the first week each employee begins work that any person performing the work of a mechanic, laborer or worker has completed a course of at least ten (10) hours in duration in construction safety and health approved by the federal Occupational Safety and Health Administration in accordance with regulations adopted by the State of Connecticut Labor Commissioner. See Section 4.48 of these specifications.
1.23 NON-CONNECTICUT CONTRACTORS.
Pursuant to Connecticut General Statutes § 12-430(7), as amended by Connecticut Public Act #11-61, Sec.66, a nonresident contractor shall comply with the State of Connecticut’s bonding requirements.
1.24 SUPPLIERS AND SUBCONTRACTORS.
The Town would appreciate it if all bidders would include Greenwich suppliers and subcontractors in solicitation of prices for the proposed work.
1.25 PROHIBITION OF WASTES GENERATED FROM OIL AND GAS DRILLING AND
EXTRACTION ACTIVITIES.
Pursuant to Town of Greenwich, Chapter 15: Utilities, Town Code, Ordinance Prohibiting Waste Associated with Natural Gas and Oil Extraction, the Town prohibits, the application of natural gas waste or oil waste, whether or not such waste has received Beneficial Use Determination or other approval for use from DEEP (Department of Energy & Environmental Protection) or any other regulatory body, on any road or real property located within the Town for any purpose; the introduction of natural gas waste or oil waste into any wastewater treatment facility within or operated by the Town; the introduction of natural gas waste or oil waste into any solid waste management facility within or operated by the Town; the storage, disposal, sale, acquisition, transfer, handling, treatment and/or processing of waste from natural gas or oil extraction.
SECTION 2
BID
To the Town of Greenwich, Connecticut, herein called the Town, acting by and through its Department of Public Works Maintenance Dredging of Sediment Forebays at Binney Park Pond, Town Project No. 19-22 Greenwich, Connecticut.
The undersigned, as Bidder, herein referred to as singular and masculine, declares as follows
(1) The only parties interested in this bid as principals are named herein
(2) This bid is made without collusion with any other person, firm or corporation
(3) No officer, agent or employee of the owner is directly or indirectly interested in this bid
(4) They have carefully examined the site of the proposed work and fully informed and satisfied themselves as to the conditions there existing, the character and requirements of the proposed work, the difficulties attendant upon its execution and the accuracy of all estimated quantities stated in this bid, and they have carefully read and examined the drawings, the annexed proposed 'agreement' and the specifications and other contract documents therein referred to and knows and understands the terms and provisions thereof
(5) And they understand that the quantities of work tabulated in this bid or indicated on the drawings or in the specifications or other contract documents are only approximate and are subject to increase or decrease as deemed necessary by the Engineer
And they agree that, if this bid is accepted they will contract with the Town, as provided in the copy of the contract documents deposited in the office of the Engineering Division of the Department of Public Works, this bid form being part of said contract documents and that they will perform all the work and furnish all the materials and equipment, and provide all labor, services, plant, machinery, apparatus, tools, appliances, supplies and all within the time therein prescribed and according to the requirements of the contract documents and of the Engineer as therein set forth, and that they will take in full payment therefore the Lump-Sum or unit price applicable to each item of the work as stated in the following Bid Sheets.
Bidders must bid on each item. All entries in the entire bid must be made clearly and in ink. Prices bid must be written in both words and figures. Bidders should insert extended item prices obtained from quantities and unit prices and insert the total price and applicable addenda numbers where indicated.
Materials and supplies purchased for this Contract which are to be physically incorporated in and become a permanent installation in the work will be exempt from the Connecticut Sales and Use Tax under the Connecticut Education, Welfare and Public Health Tax Act. Each bidder shall take this exemption into account in calculating their Bid for the Work.
The undersigned understands that information relative to subsurface and other conditions, natural phenomena, existing pipes and other structures (surface and/or subsurface) has been furnished only for their information and convenience without any warranty or guarantee, express or implied, that the subsurface and/or other conditions, natural phenomena, existing pipes and other structures (surface and/or subsurface) actually encountered will be the same as those shown on the drawings or in any of the other contract documents and they agree that they shall not use or be entitled to use any such information made available to them through the contract documents or otherwise or obtained by them in their own examination of the site, as a basis of or ground for any claim against the Town, arising from or by reason of any variance which may exist between the aforesaid information made available to or acquired by them and the subsurface and/or other conditions, natural phenomena, existing pipes and other structures (surface and/or subsurface) actually encountered during the construction work, and they have made due allowance therefore in this bid.
The undersigned agrees that for extra work, if any, performed in accordance with the terms and provisions of the annexed form of Agreement, they will accept compensation as stipulated therein in full payment for such Extra
Work.
If this bid is accepted by the Town, the undersigned agrees to complete the entire work provided to be done under the contract within the time stipulated in the Information for Bidders, Article 1.9 headed "Time Limits and Time Charge."
As provided in the Information for Bidders, the bidder hereby agrees that they will not withdraw this bid within one hundred and twenty (120) days consecutive calendar days after the actual date of the opening of bids, and that, if the Town shall accept this bid, the bidder will duly execute and acknowledge the Agreement and furnish, duly executed and acknowledged, the required Contract Bonds and Insurance Certificates within ten (10) days after date of the award of the contract.
Should the bidder fail to fulfill any of their agreements as hereinabove set forth, the Town shall have the right to retain as liquidated damages, the amount of the bid check which shall become the Town's property. If a Bid Bond was given, it is agreed that the amount thereof shall be paid as liquidated damages to the Town by surety.
The undersigned has read and agrees to provide the types and required insurance coverage limits, as defined by Article 4.6 "Insurance". The submitted bid includes the cost relating to the insurance requirements for the contract work.
The bidder, by submittal of this bid, agrees with the Town that the amount of the bid security deposited with this bid fairly and reasonably represents the amount of damages the Town will suffer due to the failure of the bidder to fulfill their agreements as above provided.
Bidders shall complete the “Bid Proposal Forms”, “Bid Bond”, “Vendor Information & Signatory Form”, “Prohibition of Wastes Generated from Oil and Gas Drilling and Extraction Activities Certification” for all Contracts. Failure to complete the previously noted, located in Section 2, will cause the contractors bid to be disqualified.
(Name of Bidder) (Signature and Title of Authorized Representative)
(Business Address) (Type or Print Name of Authorized Representative
(City and State) (Affix Corporate Seal)
(Federal Tax Identification Number) (Date)
(Telephone Number) (Fax Number)
(E-Mail Address)
BIDDING SHEETS
FOR
MAINTENANCE DREDGING OF SEDIMENT FOREBAYS
AT BINNEY PARK
GREENWICH, CONNECTICUT
TOWN PROJECT NO. 19-22
TO: James Michel, P.E. Date: , 2025 Commissioner of Public Works From:
Town Hall 101 Field Point Road Greenwich, CT 06836-2540
Dear Sir: Telephone:
shall install and/or furnish all materials and perform all work as required by and as called for by the drawings and specifications for Town Project No.
19-22 Maintenance Dredging of Sediment Forebays at Binney Park in Greenwich, Connecticut.
The quantities on the Bidding Sheets are estimated and may not reflect the actual quantities that the Town may order. The total bid prices will be calculated by multiplying the estimated quantities by the unit bid prices. The Town reserves the right to increase, decrease or direct the awarded contractor to proceed with the Base Bid or Alternative 1, depending on the most recent sediment laboratory results.
All bid pricing shall remain firm fixed for the duration of the initial one-year contract term.
Pricing may be adjusted at the beginning of each option year and shall then remain firm fixed for the duration of each option year.
Base Bid
Item No.
Estimated Quantity
Brief Description of Item and Bid in Writing and Figures
Total in Figures
02482BB 600 C.Y. Dredging and Dewatering of Dredged Material (Nonhazardous), per Cubic Yard of Dollars and Cents ($ ) $
02901BB 1 L.S. Miscellaneous Work and Cleanup, per Lump Sum of
TOTAL BASE BID PRICE $
TOWN PROJECT NO. 19-22
Alternative 1
Item No.
Estimated Quantity
Brief Description of Item and Bid in Writing and Figures
Total in Figures
02482Alt1 600 C.Y. Dredging and Dewatering of Dredged Material (Hazardous), per Cubic Yard of
02901Alt1 1 L.S. Miscellaneous Work and Cleanup, per Lump Sum of
TOTAL ALTERNATIVE 1 BID PRICE $
PRICING IN OPTIONAL YEARS OF CONTRACT
Pricing shall remain fixed for each year of this contract. The bidder shall indicate below if pricing may either increase or decrease prior to the start of the optional years of the contract:
_____ Yes, pricing may increase or decrease prior to the start of the option years.
_____ No, Pricing will not increase or decrease at the start of the option years.
If pricing may increase or decrease at the start of the option years, the bidder shall indicate below the maximum percentage or the potential increases or decreases for each optional year.
The maximum allowable increase is 2% per year.
Option Year Maximum Labor Price Increase (if any)
Maximum Labor Price Decrease (if any)
1 % % 2 % % 3 % % 4 % % 5 % % 6 % %
TOWN PROJECT NO. 19-22
For informal comparison only and not to be considered as part of this bid, the average total price as described in Note 3 below as well as the Information for Bidders, Article headed “Comparison of Bids” for Project No. 19-22 is:
Dollars and (written words)
Cents ($ ).
(written words)
The Bid(s) include Addenda Number ……………………………………….………………
Notes:
1. Include “Time Charge” in the bid prices (see Article 1.9 of “Information for Bidders”).
2. For “Minimum Wage Schedule”, see Section 9 of these Contract Documents.
3. The basis of award of this Contract will be made to the lowest responsible bidder based on the average total of the Base Bid and Alternative 1 to determine each bidders total bid price.
The Owner shall determine annually whether the Base Bid or Alternative 1 shall be awarded, based on laboratory testing, prior to Notice to Proceed.
The Bidder is - a corporation incorporated in the State of _________________________________
- A partnership - An Individual. (Bidder must add and delete as necessary to make the foregoing sentence read correctly.
If the Bidder is a corporation, Affix corporate seal and give below the names of its President, Treasurer and General Manager. If a partnership, give full names and residential addresses of all general partners and if an individual, give residential address if different from business address.
The required names and addresses of all persons interested in the foregoing bid, as principals, are as follows
PRINCIPAL NAME & TITLE ADDRESS
Affix Corporate Seal
The Bidder is requested to list below five (5) references for similar work of equal size to that included in the proposed contract that they have done within the last three years which will enable the Town to judge their experience, skill and business standing. Please include project date, contact person and phone number.
COMPANY NAME PROJECT
DATE CONTACT PERSON PHONE NUMBER
(ADD SUPPLEMENTARY PAGE IF NECESSARY.)
CERTIFICATE AS TO MINIMUM PREVAILING WAGES
The undersigned, being duly sworn, deposed and says
1. That they are the __________________________________________ of the Contractor, (Title) In the project hereinafter referred to, and is authorized to execute this certification on behalf of the Contractor,
2. In connection with Maintenance Dredging of Sediment Forebays at Binney Park Pond, Town Project No. 19-22, Greenwich, Connecticut, it is hereby certified that the Contractor has read and understands the provisions of Section 4.48, Prevailing Wages, of these specifications and has included in their bid price the cost of compliance with their requirements.
3. This certification is made at the request of the Town of Greenwich for the purpose of inducing the Town to enter into a contract for the project work and knowing that the Town will rely upon the truth of the representation herein made.
Subscribed and sworn to
Before me this _________________ day of _______________________20____.
(SIGNATURE OF PERSON (TYPE OR PRINT NAME OF PERSON
AUTHORIZED TO SIGN) AUTHORIZED TO SIGN)
NOTARY PUBLIC
Vendor Information & Signatory Form For all Contracts Equal to or Greater than $250,000
Vendor Name: _____________________________________________________________________________________
Primary Business Address: ____________________________________________________________________________
Telephone: _______________________________________ Fax: ___________________________________________
Email: ___________________________________________ Web Site: _______________________________________
Secondary Business Location(s)if any:
Business Address: __________________________________________________________________________________
Telephone: _______________________________________ Fax: ___________________________________________
Email: ___________________________________________ Web Site: _______________________________________
Business Address: __________________________________________________________________________________
Telephone: _______________________________________ Fax: ___________________________________________
Email: ___________________________________________ Web Site: _______________________________________
Type of Entity: Corporation: __________ Type of Corp.: __________ LLC: __________ Partnership: __________ Joint Venture: __________ Sole Proprietorship: __________
Other (please describe): _______________________________________________________________
1. CT State Business License Number (if applicable): ____________________________________ State Agency issuing license: ____________________________________________________
2. Number of years in business under entity name: _____________________________________
3. Provide below the full names of entity’s owners (> 20% ownership), officers and managers. (use a separate sheet of paper if necessary)
4. Has the entity changed its name within the past 3 years?
a. YES NO
5. If yes, provide former name(s): ____________________________________________________________________
6. Have there been any recent (within the last three years) changes in control/ownership, > 20% of the entity?
7. If yes, explain. (use a separate sheet of paper if necessary)
8. Have officers or principals of the entity ever had any license suspended or revoked (other than Driver’s License) for any reason?
9. If yes, please explain. (use a separate sheet of paper if necessary)
10. Is the entity or has the entity, or any of its principals, officers, members or owners ever been a party to or involved in any US civil, criminal, antitrust violation, regulatory action, settlements, lawsuit or other legal action involving the Town of Greenwich or any other municipality in the States of CT or NY related to the vendor’s business activities?
11. If the answer to question number 10 is ‘yes’, please explain below. (use a separate sheet of paper if necessary.)
12. Has any principal, officer, member or owner of the undersigned entity within the last three years been a principal, officer, member or owner of any entity that has filed for bankruptcy or been voluntarily or involuntarily dissolved?
a. YES NO b.
13. Name and title of person completing / responsible for submission of this bid or contract and the responses to this questionnaire: ________________________________________________________________________________
14. Telephone number and email address for person identified in questions #13:
Phone No.: _________________________________ Email Address: __________________________________
15. If requested by the Town during the solicitation process, the vendor hereby agrees to provide the Town with copies of the most recent three (3) years of Loss History Reports for all lines of insurance coverage from its insurance carrier (as named herein) for all contracts and RFPs/RFQs/RFBs equal to or in excess of $250,000.
Name of Insurance Carrier: ________________________________________________________________________
The loss history reports shall include claims data for all fifty US states; detail of each claim for the past three years for AL, GL, WC; and a summary page with the annual total claim amounts for the past three years for AL, GL, and WC.
16. Have any claims been made against the entity’s performance bond? YES NO
17. Please indicate whether your entity is currently debarred from doing business in the State of Connecticut or any other state.
a. YES List of States:________________________________________________ NO
18. Please indicate whether your entity has ever been convicted of OSHA violations.
a. YES (Attach separate page(s) with explanation.) NO
With regard to item No.17 and 18, the vendor understands and agrees that it has a continuing obligation to inform the Town of any OSHA violation and if it is debarred from doing business in the State of Connecticut or any other State after it has submitted this Vendor Information Form. The Vendor understands and agrees that its obligation to keep the Town informed of any change in status continues up to and including the time of award of the contract and if vendor is awarded the contract, its obligation shall continue during the entire duration of the contract.
19. Provide below an inventory list of all major equipment owned by the entity that would be used on this project:
20. Provide a complete list of the entity’s current public customers located in the State of Connecticut:
CUSTOMER ADDRESS CONTRACT ANNUAL AMOUNT
FAILURE TO COMPLETE THIS FORM OR FAILURE TO PROVIDE THE NECESSARY BACK UP INFORMATION FOR
ANY QUESTION ON THIS FORM MAY RESULT IN DISQUALIFICATION.
Signature _____________________________________________ Date:___________________________________
Print Name and Title ____________________________________________________________________________
Vendor Info EX II 6/21/13
TOWN OF GREENWICH CONNECTICUT
CERTIFICATION FOR BIDS, RFQ's, RFB's, RFP's
PROHIBITION OF WASTES GENERATED FROM OIL & GAS DRILLING AND
EXTRACTION ACTIVITIES
Pursuant to Town of Greenwich, Chapter 15: Utilities, Town Code, Ordinance Prohibiting Waste Associated with Natural Gas and Oil Extraction:
“We, hereby submit a bid for materials, equipment and/or labor for the Town of Greenwich. The bid is for bid documents titled
We hereby represent, warrant and agree that no natural gas waste or oil waste will be used by the undersigned bidder or any contractor, sub-contractor, agent or vendor in connection with the bid; nor will the undersigned bidder or any contractor, sub-contractor, agent or vendor thereof apply any natural gas waste or oil waste to any road or real property within the Town of Greenwich as a result of the submittal of this bid if selected."
Date
Signed
Print Name
Company
Address
SECTION 3
BID BOND
INSTRUCTIONS IN USE OF BOND FORM
1. The Bid Bond form given on the following pages shall be used.
2. The surety on the Bond may be any corporation authorized to act as surety in the State of Connecticut.
3. The full name and business or residence address of each individual party to the Bond shall be inserted in the space provided therefore, and each such party shall sign the Bond with their usual signature on the line opposite the scroll seal.
4. If the principals are partners, their individual names appear in the space provided therefore, with the recital that they are partners composing a firm, naming it, and the Bond shall be executed by a general partner who has been authorized to act on behalf of the partnership.
5. If the principal or surety is a corporation, the name of the state in which incorporated shall be inserted in the space provided therefore and said instrument shall be executed and attested under the corporate seal as indicated in the form. If the corporation has no corporate seal, the fact shall be stated, in which case a scroll of adhesive seal shall appear following the corporate name.
6. The official character and authority of the person or persons executing the Bond for a corporation shall be certified by a proper officer, in lieu of such certificate, there may be attached to the Bond, copies of so much of the records of the corporation as will show the official character and authority of the officers signing, duly certified by a proper office, under the corporate seal, to be true copies.
7. If the principal or surety is a Limited Liability Company (LLC), the names of the members shall appear in the spaces provided therefore, with the recital that they are members of an LLC, naming it, and the Bond shall be executed by a managing member who has been authorized to act on behalf of the LLC.
The official character and authority of the person or persons executing the Bond for an LLC shall be certified by a proper managing member. In lieu of such certificate, there may be attached to the Bond, copies of so much of the records of the LLC as will show the official character and authority of the members signing, duly certified by a proper member to be true copies.
8. The date of this Bond must not be prior to the date of the instrument in connection with which it is given.
FORM OF BID BOND
*** BID BOND ***
TOWN OF GREENWICH
Date Bond Executed
Principals
Surety
Penal Sum of Bond (Expressed in Words and Figures) Date of Bid
Know all persons by these presents, that we, the principals and surety above named, are held and firmly bound unto the Town of Greenwich, Connecticut, in the penal sum of the amount stated above, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators, and successors, jointly and severally, firmly by these presents. The condition of this obligation is such that whereas the principal has submitted the accompanying Bid, dated as shown above, for:
Project Name
Now, therefore, if the principal shall not withdraw said Bid within the period specified therein after the opening of the same, or if no period be specified, within sixty (60) days after the said opening, and shall within the period specified therefore, or, if no period be specified, within ten (10) days after the prescribed forms are presented to them for signature, execute such further contractual documents, if any, as may be required by the terms of the Bid as accepted, and give bonds with good and sufficient surety or sureties as may be required, for the faithful performance and proper fulfillment of the resulting contract, and for the protection of all persons supplying labor and materials in the prosecution of the work provided for in such contract or in the event of the withdrawal of said Bid within the period specified, or the failure to enter into such contract and give such bonds within the time specified, if the principal shall pay the Town of Greenwich, Connecticut, the difference between the amount specified in said Bid and the amount for which said Town may procure the required work, supplies and services, if the latter amount be in excess of the former, then the above obligation shall be void and of no effect, otherwise to remain in full force and virtue.
In witness whereof, the above-bounden parties have executed this instrument under their several seals on the date indicated above. The name and corporate seal (if applicable) of each corporate party being hereto affixed.
Name of Partnership
_______________________________________________________________________________(SEAL)
Business Address
Partner - (Hereunto Duly Authorized)
IN THE PRESENCE OF
WITNESS INDIVIDUAL PRINCIPAL
1.___________________________________ AS TO _________________________________
(SEAL)
2.___________________________________ AS TO _________________________________
(SEAL)
3.___________________________________ AS TO _________________________________
(SEAL)
4.___________________________________ AS TO _________________________________
(SEAL)
* CORPORATE PRINCIPAL
ATTEST * BUSINESS ADDRESS
* AFFIX
* CORPORATION
* SEAL
* BY-(HEREUNTO DULY AUTHORIZED)
* TITLE
* CORPORATE SURETY
ATTEST * BUSINESS ADDRESS
* AFFIX
* CORPORATION
* SEAL
* BY-(HEREUNTO DULY AUTHORIZED)
* TITLE
CERTIFICATE AS TO CORPORATE PRINCIPAL
I, _______________________, certify that I am the___________________________________ of the Corporation/Limited Liability Company named as Principal in the within Bond, that __________
_____________________________________________________, who signed the said Bond on behalf of the Principal, was then __________________________________ of _____________________________ said Corporation/Limited Liability Company, that I know their signature and their signature thereto is genuine, and that said Bond was duly signed, sealed (if a Corporation) and attested for and in behalf of said Corporation/Limited Liability Company by authority of its governing body.
(CORPORATE SEAL)
(CORPORATE SECRETARY)
SECTION 4
AGREEMENT
DEFINITIONS ........................................................................................................................................ 4.1
THE CONTRACT DOCUMENTS ........................................................................................................ 4.2
OBLIGATIONS AND LIABILITY OF CONTRACT .......................................................................... 4.3
AUTHORITY OF THE ENGINEER ..................................................................................................... 4.4
SUPERVISION OF WORK ................................................................................................................... 4.5
INSURANCE .......................................................................................................................................... 4.6
PATENTS ................................................................................................................................................ 4.7
COMPLIANCE WITH LAWS ............................................................................................................... 4.8
PROVISIONS REQUIRED BY LAW DEEMED INSERTED ............................................................ 4.9
PERMITS ................................................................................................................................................ 4.10
NOT TO SUBLET OR ASSIGN ............................................................................................................ 4.11
TIME FOR COMMENCEMENT AND COMPLETION OF WORK ................................................. 4.12
LIQUIDATED DAMAGES OR TIME CHARGE ................................................................................ 4.13
NIGHT AND SUNDAY WORK ........................................................................................................... 4.14
EMPLOY COMPETENT INDIVIDUALS ............................................................................................ 4.15
EMPLOY SUFFICIENT LABOR AND EQUIPMENT ....................................................................... 4.16
INTOXICATING LIQUORS ................................................................................................................. 4.17
ACCESS TO WORK .............................................................................................................................. 4.18
EXAMINATION OF WORK ................................................................................................................. 4.19
DEFECTIVE WORK .............................................................................................................................. 4.20
PROTECTION AGAINST WATER AND STORM ............................................................................. 4.21
MISTAKES OF CONTRACTOR .......................................................................................................... 4.22
RIGHT TO MATERIALS ......................................................................................................................
This is the start of the file's text. The full file is on GovTribe.
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .