19-027_2020_08_24_100 percent - SPECIFICATION FINAL.pdf
PDF 7 MB Posted
- Attached to
- Upgrade ADA for Various Buildings Project 590-19-113 Federal contract opportunity
- Solicitation number
- 36C24622R0010
About this file
This solicitation requests construction services for accessibility upgrades at three buildings at the Hampton VA Medical Center. The contractor will be responsible for demolishing existing structures and installing temporary and permanent ramps, along with associated mechanical, electrical, and plumbing work, per the attached plans and specifications. The upgrades are required at buildings 137C, 114, and 83. The solicitation number is 36C24622R0010 and was issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 6. The response due date is not provided.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C24622R0010 0002.docx | DOCX document | |
| 36C24622R0010 0003.docx | DOCX document | |
| Sign-In Sheet for Upgrade ADA 11-30-2021.pdf | ||
| 36C24622R0010 0001.docx | DOCX document | |
| 19-027_2020_08_24_100 percent - DRAWINGS PRINT.pdf | ||
| 36C24622R0010.docx | DOCX document | |
| Attachment B - Corp Experience Form.docx | DOCX document | |
| Construction Safety Handbook.pdf | ||
| Attachment A - Base Proposal Item Price Breakdown.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIFICATIONS
Prepared for the Final Submittal by:
J&B Hartigan, Inc.
103 Adams Court
Carrollton, VA 23314
Upgrade ADA Various Buildings (137C, 114, and 83)
Project No.: 590-19-113 Hampton VA Medical Center
Hampton, VA
24 August 2020
SPECIFICATIONS Page 2 of 2
UPGRADE ADA VARIOUS BUILDINGS (137C, 114, 83) 590-19-113
HAMPTON VA MEDICAL CENTER
HAMPTON, VA
00 01 10-1
TABLE OF CONTENTS
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build) 01 33 23 Shop Drawings, Product Data, and Samples 01 35 26 Safety Requirements 01 42 19 Reference Standards 01 45 00 Quality Control 01 45 29 Testing Laboratory Services 01 45 35 Special Inspections 01 57 19 Temporary Environmental Controls 01 74 19 Construction Waste Management 01 81 13 Sustainable Construction Requirements 01 91 00 General Commissioning Requirements
DIVISION 02 – EXISTING CONDITIONS
02 21 13 Site Surveys 02 41 00 Demolition
DIVISION 03 – CONCRETE
03 30 53 (Short-Form) Cast-in-Place Concrete
DIVISION 05 – METALS
05 12 00 Structural Steel Framing 05 31 00 Steel Decking
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 22 00 Roof and Deck Insulation 07 53 23 Ethylene-Propylene-Diene-Monomer Roofing 07 60 00 Flashing and Sheet Metal 07 84 00 Firestopping 07 92 00 Joint Sealants
DIVISION 08 - OPENINGS
HAMPTON, VA
00 01 10-2
SECTION NO. DIVISION AND SECTION TITLES
08 41 13 Aluminum-Framed Entrances and Storefronts 08 71 00 Door Hardware 08 71 13 Automatic Door Operators 08 80 00 Glazing
DIVISION 09 - FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 09 06 00 Schedule for Finishes 09 22 16 Non-Structural Metal Framing 09 29 00 Gypsum Board 09 91 00 Painting
DIVISION 21 – FIRE SUPPRESSION
21 13 13 Wet-Pipe Sprinkler Systems
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING
(HVAC)
23 05 11 Common Work Results for HVAC 23 05 41 Noise and Vibration Control for HVAC Piping & Equipment 23 05 93 Testing, Adjusting, and Balancing for HVAC 23 07 11 HVAC and Boiler Plant Insulation 23 08 00 Commissioning of HVAC Systems 23 23 00 Refrigerant Piping 23 81 43 Air-Source Unitary Heat Pumps
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 26 05 19 Low-Voltage Electrical Power Conductors and Cables 26 05 26 Grounding and Bonding for Electrical Systems 26 05 33 Raceway and Boxes for Electrical Systems 26 27 26 Wiring Devices 26 29 21 Enclosed Switches and Circuit Breakers 26 51 00 Interior Lighting
DIVISION 31 – EARTHWORK
31 20 11 Earthwork (Short Form) 31 23 19 Dewatering
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWINGS SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
GENERAL
GI001 COVER SHEET
GI002 ABBREVIATIONS AND SYMBOLS
GI003 CONTRACTOR STAGING PLAN BUILDING 137C
GI004 CONTRACTOR STAGING PLAN BUILDING 114
GI005 CONTRACTOR STAGING PLAN BUILDING 83
GI101 BUILDING 137C TEMPORARY ADA ACCESS RAMP PLAN
GI102 BUILDING 114 TEMPORARY ADA ACCESS RAMP PLAN
GI103 BUILDING 83 TEMPORARY ADA ACCESS RAMP PLAN
IC101 ICRA CLASS III DETAILS AND NOTES
CIVIL
C-001 CIVIL ABBREVIATIONS, SYMBOLS, AND GENERAL NOTES
CD101 BUILDING 137C EROSION CONTROL AND SWPPP PLAN
CD102 BUILDING 114 EROSION CONTROL AND SWPPP PLAN
CD103 BUILDING 83 EROSION CONTROL AND SWPPP PLAN
CD501 CIVIL DEMOLITION AND EROSION CONTROL DETAILS AND NOTES
C-101 BUILDING 137C TOPOGRAPHIC SURVEY PLAN
C-102 BUILDING 114 TOPOGRAPHIC SURVEY PLAN
C-103 BUILDING 83 TOPOGRAPHIC SURVEY PLAN
CS501 CIVIL DETAILS
STRUCTURAL
S-101 STRUCTURAL GENERAL NOTES
S-301 STRUCTURAL DETAILS
ARCHITECTURAL
AD101 PARTIAL BUILDING 137C DEMOLITION PLAN
AD102 PARTIAL BUILDING 114 DEMOLITION PLAN
AD103 PARTIAL BUILDING 83 DEMOLITION PLAN
AE101 PARTIAL BUILDING 137C NEW WORK PLAN
AE102 PARTIAL BUILDING 114 NEW WORK PLAN
AE103 PARTIAL BUILDING 83 NEW WORK PLAN
AE111 PARTIAL BUILDING 137C ROOF AND ROOF FRAMING PLAN
AE121 PARTIAL BUILDING 137C REFLECTED CEILING PLAN
AE201 BUILDING 137C ELEVATIONS
AE301 BUILDING 137C WALL SECTIONS
AE601 BUILDING 137C STOREFRONT ELEVATIONS AND DETAILS
FIRE PROTECTION
F-101 FIRE SPRINKLER BUILDING 137 FIRST FLOOR PLAN – NEW WORK
MECHANICAL
M-001 LEGEND, ABBREVIATIONS, DETAILS AND SCHEDULES
M-101 BUILDING 137C MECHANICAL FLOOR PLAN – NEW WORK
00 01 15 - 2
ELECTRICAL
E-001 LEGEND AND ABBREVIATIONS
ED101 BUILDING 137C ELECTRICAL PARTIAL PLANS – DEMOLITION
ED102 BUILDING 114 ELECTRICAL PARTIAL PLAN – DEMOLITION
ED103 BUILDING 83 ELECTRICAL PARTIAL PLAN – DEMOLITION
E-101 BUILDING 137C ELECTRICAL PARTIAL PLANS – NEW WORK
E-102 BUILDING 114 ELECTRICAL PARTIAL PLAN – NE WORK
E-103 BUILDING 83 ELECTRICAL PARTIAL PLAN – NEW WORK
- - - E N D - - -i
SECTION 01 00 00
GENERAL REQUIREMENTS
TABLE OF CONTENTS
1.1 SAFETY REQUIREMENTS
1.2 GENERAL INTENTION
1.3 STATEMENT OF BID ITEM(S)
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.5 CONSTRUCTION SECURITY REQUIREMENTS
1.6 OPERATIONS AND STORAGE AREAS
1.7 ALTERATIONS
1.8 DISPOSAL AND RETENTION
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
1.10 RESTORATION
1.11 PHYSICAL DATA
1.12 PROFESSIONAL SURVEYING SERVICES
1.13 LAYOUT OF WORK
1.14 AS-BUILT DRAWINGS
1.15 WARRANTY MANAGEMENT
1.16 USE OF ROADWAYS
1.17 TEMPORARY TOILETS
1.18 AVAILABILITY AND USE OF UTILITY SERVICES
1.19 TESTS
1.20 INSTRUCTIONS
1.21 HISTORIC PRESERVATION
HAMPTON, VA
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for Building 137C, 114, and 83 as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the
Medical Center Engineering Officer.
C. Offices of Bowman, Foster and Associates, Inc. 6353 Center Drive, Suite
101, Norfolk, VA 23502 as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
D. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.
E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
F. Prior to commencing work, the general contractor shall provide proof that an OSHA certified “competent person” (CP) (29 CFR 1926.20 (b) (2) will maintain a presence at the work site whenever the general or subcontractors are present. As a minimum, the competent person shall have 30 hours OSHA Certified Construction Safety Course.
HAMPTON, VA
01 00 00 -2
A.BID ITEM 1 (BASE BID): The contractor shall provide all tools, labor, materials (to include two (2) ADA compliant temporary ramps, two (2) new automatic door operators and associated operating accessories), equipment, supervision, and expertise required to perform general construction, alterations, removal of existing structures and construction debris as per contract drawings and specifications at buildings 137C, 114, and 83 located at the DEPARTMENT OF VETERANS
AFFAIRS MEDICAL CENTER HAMPTON, VA 23667.
B.BID ITEM 2 (DEDUCT ALTERNATE 1): Work associated with the awning from building 137C. This shall include all architectural, structural, and electrical work.
G. Training:
1. All employees of the general contractor or subcontractors shall have the 10-hour OSHA certified Construction Safety course and / or other relevant competency training, as determined by the VA CP with input from the ICRA team.
2. Submit training records of all such employees for approval before the start of work.
1.3 STATEMENT OF BID ITEM(S)
01 00 00 -3
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The general contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the general contractor shall give one week’s notice to the contracting officer so that security can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer.
4. VA reserves the right to close down or shut down the project site and order general contractor’s employees off the premises in the event of a national emergency. The general contractor may return to the site only with the written approval of the contracting officer.
C. Key Control:
1. The general contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR)for the purpose of security inspections of every area of project including toolboxes and parked machines and take any emergency action.
HAMPTON, VA
01 00 00 -4
2. The general contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71
00, DOOR HARDWARE and coordinate.
E. Document Control:
1. Before starting any work, the general contractor/subcontractor shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.
2. The general contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the contracting officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of contracting officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify contracting officer and site security officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
a. Security, access, and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
01 00 00 -5
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
F. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. A limited number of (2 to 5) permits shall be issued for general contractor and its employees for parking in designated areas only.
1.6 OPERATIONS AND STORAGE AREAS
A. The contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The contractor shall hold and save the
Government, its officers, and agents, free and harmless from liability of any nature occasioned by the contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the contractor only with the approval of the contracting officer and shall be built with labor and materials furnished by the contractor without expense to the government. The temporary buildings and utilities shall remain the property of the contractor and shall be removed by the contractor at its expense upon completion of the work. With the written consent of the contracting officer, the buildings and utilities may be abandoned and need not be removed.
C. The contractor shall, under regulations prescribed by the contracting officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the contracting officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the contractor shall protect them from damage. The
01 00 00 -6 contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as determined by the COR.
E. Workers are subject to rules of Medical Center applicable to their conduct.
F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
G. Execute work with little interference as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of
Veterans Affairs in quantities sufficient for not more than two workdays. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR or Utility Company involved:
01 00 00 -7
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the contractor.
I. Phasing:
The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.
It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to ramp removal, electrical removal, reinstall ramp and reinstall electrical.
To ensure such executions, contractor shall furnish the COR with a schedule of approximate phasing dates on which the contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to
COR and contractor, as follows:
Phase I:
Demolition and construction shall begin on Building 83. The removal of the existing ramp shall take place and the new ramp installed. The electrical shall coincide with the new construction of the ramp.
Phase II:
Demolition and construction shall begin on Building 114. The removal of the existing ramp and installation of the new ramp shall take place. The electrical shall coincide with the new construction of the ramp.
Phase III:
Demolition and construction of the new vestibule shall take place at Building 137C. The installation of the new mechanical and electrical shall coincide with the vestibule construction.
HAMPTON, VA
01 00 00 -8
J. Building(s) No.(s) 137C, 114, and 83 will be occupied during performance of work; but immediate areas of alterations will be vacated. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of Veterans
Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc.
to facilitate patient and staff access. Coordinate alteration work in areas occupied by Department of Veterans Affairs so that Medical Center operations will continue during the construction period.
1. Immediate areas of alterations not mentioned in preceding
Subparagraph 1 will be temporarily vacated while alterations are performed.
K. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings.
Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm
(one inch) above grade. Remove the fence when directed by COR.
L. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall always maintain a minimum temperature of 4 degrees
C (40 degrees F), except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangement for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs
01 00 00 -9 or municipal) whichever will be required to respond to an alarm from
Contractor's employee or watchman.
M. Utilities Services: always maintain existing utility services for
Medical Center. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR and/or Chief of
Engineering. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center
Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL
INSTALLATIONS, for additional requirements.
2. Contractor shall submit a request to interrupt any such services to
COR, in writing, 15 days in advance of proposed interruption.
Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
01 00 00 -10
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
N. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
O. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. 2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
P. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the contractor shall make a thorough survey with the COR and a representative of VA Supply Service, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by all three, to the contracting officer. This report shall list by rooms and spaces:
01 00 00 -11
1. Existing condition and types of resilient flooring, doors, windows, walls, and other surfaces not required to be altered throughout affected areas of buildings.
2. Shall note any discrepancies between drawings and existing conditions at site.
3. Shall designate areas for working space, materials storage, and routes of access to areas within buildings where alterations occur, and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government.
Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR
52.243-4 and VAAR 852.236-88).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls, and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of
Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled, and equipment moved and/or relocated.
01 00 00 -12
2. Protection of interior of existing structures at all times, from damage, dust, and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
A. The contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the contracting officer.
B. The contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the contractor. The contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the contractor fails or refuses to repair the damage promptly, the contracting officer may have the necessary work performed and charge the cost to the contractor.
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils, and the
01 00 00 -13 environment. Refer to Articles, "Alterations", "Restoration", and
"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
D. Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General Conditions. A National Pollutant Discharge
Elimination System (NPDES) permit is required for this project. The contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the (appropriate medical center) office. The apparent low bidder, contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements.
Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the contractor's method of operations and operations planning and the contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:
- Designating areas for equipment maintenance and repair.
- Providing waste receptacles at convenient locations and provide regular collection of wastes.
- Locating equipment wash down areas on site and provide appropriate control of wash-waters.
- Providing adequately maintained sanitary facilities.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the
COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
HAMPTON, VA
01 00 00 -14
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At contractor's own expense, contractor shall immediately restore to service and repair any damage caused by contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR
52.236-2).
1.11 PHYSICAL DATA
A. Data and information furnished or referred to below is for the contractor's information. The government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the contractor.
1. The indications of physical conditions on the drawings and in the specifications are the result of site investigations by Bowman, Foster & Associates, Inc.
(FAR 52.236-4)
B. Subsurface conditions have been developed by core borings and test pits. Logs of subsurface exploration are shown diagrammatically on drawings.
C. A copy of the soil report will be made available for inspection by bidders upon request to the Engineering Officer at the VA Medical
Center and shall be considered part of the contract documents.
D. Government does not guarantee that other materials will not be encountered, nor that proportions, conditions, or character of several
01 00 00 -15 materials will not vary from those indicated by explorations. Bidders are expected to examine site of work and logs of borings; and, after investigation, decide for themselves character of materials and make their bids accordingly. Upon proper application to Department of
Veterans Affairs, bidders will be permitted to make subsurface explorations of their own at site.
1.12 PROFESSIONAL SURVEYING SERVICES
A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the contractor shall perform services specified herein and in other specification sections.
The contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the contractor, and that the land surveyor or civil engineer has no financial interest in this contract.
1.13 LAYOUT OF WORK
A. The contractor shall lay out the work from government established base lines and benchmarks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The contractor shall furnish, at contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the contracting officer. The contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the contracting officer until authorized to remove them.
If such marks are destroyed by the contractor or through contractor's negligence before their removal is authorized, the contracting officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the contractor.
(FAR 52.236-17)
B. Establish and plainly mark and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each such structure and/or addition, roads, are in accordance with lines and elevations shown on contract drawings.
01 00 00 -16
C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities, and elevations of floor slabs:
1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the COR before any work (such as footings, floor slabs, columns, walls, utilities, and other major controlling features) is placed.
D. During progress of work, and particularly as work progresses from floor to floor, contractor shall have line grades and plumbness of all major form work checked and certified by a registered land surveyor or registered civil engineer as meeting requirements of contract drawings.
Furnish such certification to the COR before any major items of concrete work are placed. In addition, contractor shall also furnish to the COR certificates from a registered land surveyor or registered civil engineer that the following work is complete in every respect as required by contract drawings.
1. Lines of each building and/or addition.
2. Elevations of bottoms of footings and tops of floors of each building and/or addition.
3. Lines and elevations of sewers and of all outside distribution systems.
4. Lines of elevations of all swales and interment areas.
5. Lines and elevations of roads, streets.
E. Whenever changes from contract drawings are made in line or grading requiring certificates, record such changes on a reproducible drawing bearing the registered land surveyor or registered civil engineer seal, and forward these drawings upon completion of work to COR.
01 00 00 -17
F. The contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of
Article "Professional Surveying Services".
1.14 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications, and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR’s review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.15 WARRANTY MANAGEMENT
A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction in at least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the
Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the contracting officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 months and 9 months warranty inspection will be conducted, measured from time of
HAMPTON, VA
01 00 00 -18 acceptance, by the contactor and the contracting officer. Include in the warranty management plan, but not limited to, the following:
1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the contractor, subcontractors, manufacturers, or suppliers involved.
2. Furnish with each warranty the name, address, and telephone number of each of the guarantor’s representatives nearest project location.
3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.
4. A list for each warranted equipment item, feature of construction or system indicating:
a. Name of item.
b. Model and serial numbers.
c. Location where installed.
d. Name and phone numbers of manufacturers and suppliers.
e. Name and phone numbers of manufacturers or suppliers.
f. Names, addresses and phone numbers of sources of spare parts.
g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.
h. Starting point and duration of warranty period.
i. Summary of maintenance procedures required to continue the warranty in force.
j. Cross-reference to specific pertinent Operation and Maintenance manuals.
01 00 00 -19
k. Organizations, names, and phone numbers of persons to call for warranty service.
l. Typical response time and repair time expected for various warranted equipment.
5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.
6. Procedure and status of tagging of all equipment covered by extended warranties.
7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.
B. Performance Bond: The Performance Bond must remain effective throughout the construction period.
1. In the event the contractor fails to commence and diligently pursue any construction warranty work required, the contracting officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.
2. In the event sufficient funds are not available to cover the construction warranty work performed by the government at the contractor’s expenses, the contracting officer will have the right to recoup expenses from the bonding company.
3. Following oral or written notification of required construction warranty repair work, the contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the contracting officer to proceed against the contractor.
C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the contracting officer, the contractor shall meet with the contracting officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for contractor notification of construction warranty defects, priorities
01 00 00 -20 with respect to the type of defect, reasonable time required for contractor response, and other details deemed necessary by the contracting officer for the execution of the construction warranty will be established and reviewed at this meeting. In connection with these requirements and at the time of the contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the contractor.
This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to government inquiry on warranty work action and status. This requirement does not relieve the contractor of any of its responsibilities in conjunction with other portions of this provision.
D. Contractor’s Response to Construction Warranty Service Requirements:
Following oral or written notification by the contracting officer, the contractor shall respond to construction warranty service requirements in accordance with the “Construction Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period.
Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the contractor does not perform the construction warranty within the timeframe specified, the government will perform the work and back charge the construction warranty payment item established.
1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to completion or relief.
2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to completion or relief.
3. Third Priority Code 3. All other work to be initiated within 3 workdays and work continuously to completion or relief.
4. The “Construction Warranty Service Priority List” is as follows:
Code 1-Air Conditioning Systems
01 00 00 -21
a. Air conditioning leak in part of the building, if causing damage.
b. Air conditioning system not cooling properly.
Code 1 Doors
a. Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire, or safety problem.
Code 3-Doors
a. Interior/exterior personnel doors or hardware not functioning properly.
Code 1-Electrical
a. Power failure (entire area or any building operational after 1600 hours).
Code 2-Electrical
a. Power failure (no power to a room or part of building).
Code 1-Heat
a. Power failure affecting heat.
Code 3-Interior
a. Floors damaged.
b. Paint chipping or peeling.
Code 3
a. All work not listed above.
E. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the contracting officer. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.
01 00 00 -22
1.16 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on Medical
Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed, and restoration performed by the contractor at contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
1.17 TEMPORARY TOILETS
A. Provide where directed, (for use of all contractor's workers) ample temporary sanitary toilet accommodations with suitable sewer and water connections; or, when approved by COR, provide suitable dry closets where directed. Keep such places clean and free from flies, and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.
01 00 00 -23
1.18 AVAILABILITY AND USE OF UTILITY SERVICES
A. The government shall make all reasonably required amounts of utilities available to the contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the contractor for chargeable electrical services shall be the prevailing rates charged to the government. The contractor shall carefully conserve any utilities furnished without charge.
B. The contractor, at contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the contracting officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the government, the contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.
C. Contractor shall install meters at contractor's expense and furnish the
Medical Center a monthly record of the contractor's usage of electricity as hereinafter specified.
D. Electricity (for Construction and Testing): Furnish all temporary electric services.
1. Obtain electricity by connecting to the Medical Center electrical distribution system. The contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the contractor.
E. Water (for Construction and Testing): Furnish temporary water service.
1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the contractor.
2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes
01 00 00 -24 will be cause for revocation (at COR discretion) of use of water from Medical Center's system.
1.19 TESTS
A. As per specification section 23 05 93 the contractor shall provide a written testing and commissioning plan complete with component level, equipment level, sub-system level and system level breakdowns. The plan will provide a schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval prior to commencing work. The contractor shall document the results of the approved plan and submit for approval with the as built documentation.
B. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested.
C. Conduct final tests required in various sections of specifications in presence of an authorized representative of the contracting officer.
Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.
D. Mechanical and electrical systems shall be balanced, controlled, and coordinated. A system is defined as the entire system which must be coordinated to work together during normal operation to produce results for which the system is designed. For example, air conditioning supply air is only one part of entire system which provides comfort conditions for a building. Other related components are return air, refrigerant, controls, and electricity, etc.
E. All related components as defined above shall be functioning when any system component is tested.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .