Project Manual Summary: Ben Taub Hospital Level 6 Cardiac Critical Care Unit Renovation
This Project Manual is a comprehensive bidding and construction document for Harris Health System (Harris County Hospital District) for the renovation and reconfiguration of the Level 6 Cardiac Critical Care Unit at Ben Taub Hospital in Houston, Texas. The project, identified as 22-1SCP01622 with HOK Project Number 24.10251.00, encompasses selective structural demolition, asbestos remediation, concrete rehabilitation, cold-formed metal framing installation, and associated mechanical, electrical, plumbing, fire suppression, and communications systems work. The document was issued for bid and permit on February 19, 2026, and includes detailed specifications across 28 divisions of work. A prebid meeting is required for prospective bidders, with attendance mandatory to be considered for award. The contract includes a Notice to Proceed that establishes the contract commencement date, with contract time calculated in calendar days as specified in the supplemental conditions section.
Bid security in the amount of five percent of the bidder's maximum bid price is required, submitted as either a cashier's check or bid bond. The contract requires both Performance and Payment Bonds in amounts equal to 100 percent of the Contract Sum, to be delivered no later than ten days after the date of Notice of Intent to Award. The contractor must comply with Harris Health System's General Conditions, which include liquidated damages provisions for failure to complete work within the specified contract time, insurance requirements with minimum coverage limits including Workers Compensation ($1,000,000 per occurrence), Commercial General Liability ($2,000,000 aggregate), and Automobile Liability ($1,000,000 combined single limit), and prevailing wage rate requirements under Texas Government Code Section 2258. The estimated project budget is $5,400,000, with the work to be performed at the Ben Taub Hospital location in Houston, Texas.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
H E L L M U T H , O B A T A & K A S S A B A U M , I n c
A R C H I T E C T U R E , E N G I N E E R I N G , P L A N N I N G , I N T E R I O R S , G R A P H I C S , C O N S U L T I N G
Project Manual Issue for Bid and Permit
Project
Harris Health - Ben Taub Hospital Level 6
Cardiac Critical Care Unit
Renovation and Reconfiguration 22-1SCP01622
1504 Ben Taub Loop
Houston, TX 77030
Prepared for
Harris Health System Houston Texas
Issue for Bid and Permit – February 19, 2026 Design Architect:
Hellmuth, Obata & Kassabaum, Inc.
Houston, Texas
HOK Project No. 24.10251.00
Dedicated to Design Excellence and the Team Approach
TABLE OF CONTENTS 000110 - 1
© Hellmuth, Obata, & Kassabaum Inc.
Harris Health System – Ben Taub Hospital Level 6 Issue for Bid and Permit
Cardiac Critical Care Unit - Renovation and
Reconfiguration (22-1SCP01622)
February 19, 2026
1504 Ben Taub Loop, Houston, TX 77030 HOK Project No. 24.10251.00
SECTION 000110 – TABLE OF CONTENTS
PROCUREMENT AND CONTRACTING DOCUMENTS GROUP
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
000110 TABLE OF CONTENTS
000111 SEALS PAGE
000112 HARRIS HEALTH SYSTEM GENERAL CONDITIONS, POLICIES, PROCEDURES, ETC.:
HARRIS HEALTH SYSTEM GENERAL CONDITIONS
• SECTION 1. DEFINITION OF TERMS
• SECTION 2. BIDDING AND AWARD
• SECTION 3. INSURANCE
• SECTION 4. REGULATORY REQUIREMENTS
• SECTION 5. EXECUTION OF THE WORK
• SECTION 6. PAYMENT
HARRIS HEALTH SYSTEM FACILITIES ENGINEERING POLICIES AND PROCEDURES
• CONTRACTORS WORK GUIDELINES
• CONSTRUCTION PRE-DEMOLITION CHECKLIST
• FIRE ALARM EVENT - ANALYSIS ACTION PLAN
• HOT WORK PERMIT PROCEDURES
• FIRE WATCH LOG
• FIRE WATCH CHECKLIST
• ABOVE CEILING WORK & FIRE-SMOKE WALL BARRIER MANAGEMENT
• REQUEST FOR UTILITY-OPERATIONAL SYSTEM SHUTDOWN
• ALTERNATIVE LIFE SAFETY MEASURES
• PRE-CONSTRUCTION RISK ASSESSMENT PROCESS
• FIBER OPTIC CABLING PROTECTION PROCEDURE
• VACCINE PREVENTABLE DISEASE POLICY
• ON-BOARDING NON-EMPLOYEES
• IDENTIFICATION-ACCESS CONTROL BADGE POLICY
• ID BADGE REQUEST FORM
001113 ADVERTISEMENT FOR BIDS
001116 INVITATION TO BID
002113 INSTRUCTIONS TO BIDDERS
002213 SUPPLEMENTARY INSTRUCTIONS TO BIDDERS
002513 PREBID MEETINGS
002600 PROCUREMENT SUBSTITUTION PROCEDURES
003119 EXISTING CONDITION INFORMATION
003126 EXISTING HAZARDOUS MATERIAL INFORMATION
003143 PERMIT APPLICATION
SPECIFICATIONS GROUP
General Requirements Subgroup
DIVISION 01 - GENERAL REQUIREMENTS
TABLE OF CONTENTS 000110 - 2
Harris Health System – Ben Taub Hospital Level 6 Issue for Bid and Permit
Cardiac Critical Care Unit - Renovation and
Reconfiguration (22-1SCP01622)
012500.01 REQUEST FOR SUBSTITUTION FORM
013100 PROJECT MANAGEMENT AND COORDINATION
014000 QUALITY REQUIREMENTS
014200 REFERENCES
016000 PRODUCT REQUIREMENTS
017700 CLOSEOUT PROCEDURES
018000 HARRIS HEALTH SYSTEM SUPPEMENTAL CONDITIONS
Facility Construction Subgroup
DIVISION 02 - EXISTING CONDITIONS
024119 SELECTIVE STRUCTURE DEMOLITION
028213 ASBESTOS REMEDIATION
DIVISION 03 - CONCRETE
030130.71 REHABILITATION OF CAST-IN-PLACE CONCRETE
DIVISION 05 - METALS
054000 COLD-FORMED METAL FRAMING
055000 METAL FABRICATIONS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
061053 MISCELLANEOUS ROUGH CARPENTRY
064000 ARCHITECTURAL WOODWORK
066113 SOLID SURFACING
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
070150.19 PREPARATION FOR REROOFING
075423 THERMOPLASTIC-POLYEFIN (TPO) ROOFING
078413 PENETRATION FIRESTOPPING
079200 JOINT SEALANTS
DIVISION 08 - OPENINGS
081113 HOLLOW METAL DOORS AND FRAMES
081216 ALUMINUM FRAMES
081416 FLUSH WOOD DOORS
084243 ICU-CCU ENTRANCES
087100 DOOR HARDWARE
087800 FLUSH SLIDING DOOR HARDWARE SYSTEM
088000 GLAZING
088816 VISION CONTROL INSULATING GLASSUNITS WITH INTEGRATED
CORDLESS LOUVERS
DIVISION 09 - FINISHES
092116 GYPSUM BOARD ASSEMBLIES
093000 TILING
095123 ACOUSTICAL TILE CEILINGS
096513 RESILIENT BASE AND ACCESSORIES
096516 RESILIENT SHEET FLOORING
098100 ACOUSTIC INSULATION
TABLE OF CONTENTS 000110 - 3
Harris Health System – Ben Taub Hospital Level 6 Issue for Bid and Permit
Cardiac Critical Care Unit - Renovation and
Reconfiguration (22-1SCP01622)
099123 INTERIOR PAINTING
DIVISION 10 - SPECIALTIES
101400 SIGNAGE
102123 CUBICLE CURTAINS AND TRACKS
102600 WALL AND DOOR PROTECTION
102813 TOILET ACCESSORIES
105113 METAL LOCKERS
DIVISION 11 - EQUIPMENT
115224 FLAT SCREEN TV MOUNTS
DIVISION 13 - SPECIAL CONSTRUCTION
134900 RADIATION PROTECTION
DIVISION 21 FIRE SUPPRESSION
210517 SLEEVES AND SLEEVE SEALS FOR FIRE-SUPPRESSION PIPING
210553 IDENTIFICATION FOR FIRE-SUPPRESSION PIPING AND EQUIPMENT
211313 WET-PIPE SPRINKLER SYSTEMS
211316 DRY-PIPE SPRINKLER SYSTEMS
211319 PRE-ACTION SPRINKLER SYSTEMS
DIVISION 22 – PLUMBING
220517 SLEEVES AND SLEEVE SEALS FOR PLUMBING PIPING
220518 ESCUTCHEONS FOR PLUMBING PIPING
220523 GENERAL-DUTY VALVES FOR PLUMBING PIPING
220529 HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT
220553 IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT
220719 PLUMBING PIPING INSULATION
221116 DOMESTIC WATER PIPING
221119 DOMESTIC-WATER PIPING SPECIALTIES
221316 SANITARY WASTE AND VENT PIPING
221319 SANITARY WASTE PIPING SPECIALTIES
221513 GENERAL-SERVICE COMPRESSED-AIR
224300 HEALTHCARE PLUMBING FIXTURES
226113 COMPRESSED-AIR PIPING FOR HEALTHCARE FACILITIES
226213 VACUUM PIPING FOR HEALTHCARE FACILITIES
226219 VACUUM EQUIPMENT FOR HEALTHCARE FACILITIES
226313 GAS PIPING FOR HEALTHCARE FACILITIES
226400 MEDICAL GAS ALARMS
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING
230513 COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT
230518 ESCUTCHEONS FOR HVAC PIPING
230519 METERS AND GAGES FOR HVAC PIPING
230523 GENERAL-DUTY VALVES FOR HVAC PIPING
230529 HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT
230553 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT
230593 TESTING, ADJUSTING AND BALANCING FOR HVAC
230713 DUCT INSULATION
TABLE OF CONTENTS 000110 - 4
Harris Health System – Ben Taub Hospital Level 6 Issue for Bid and Permit
Cardiac Critical Care Unit - Renovation and
Reconfiguration (22-1SCP01622)
230716 HVAC EQUIPMENT INSULATION
230719 HVAC PIPING INSULATION
230800 COMMISSIONING OF HVAC
230900 INSTRUMENTATION AND CONTROL FOR HVAC
230993 SEQUENCE OF OPERATIONS FOR HVAC CONTROLS
233113 METAL DUCTS
233416 CENTRIFUGAL HVAC FANS
233600 AIR TERMINAL UNITS
233713 DIFFUSERS REGISTERS AND GRILLES
234100 PARTICULATE AIR FILTRATION
DIVISION 26 – ELECTRICAL
260519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
260529 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
260533 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS
260544 SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND CABLING
260553 IDENTIFICATION FOR ELECTRICAL SYSTEMS
260923 LIGHTING CONTROL DEVICES
262726 WIRING DEVICES
265100 LIGHTING
DIVISION 27 – COMMUNICATIONS
270500 COMMON WORK RESULTS FOR COMMUNICATIONS
270526 GROUNDING AND BONDING
270528 COMMUNICATIONS BUILDING PATHWAYS
270553 IDENTIFICATION FOR COMMUNICATIONS SYSTEMS
271100 COMMUNICATIONS EQUIPMENT ROOM FITTINGS
271200 CABLE TELEVISION DISTRIBUTION SYSTEM
271300 COMMUNICATIONS BACKBONE CABLING
271500 COMMUNICATIONS HORIZONTAL CABLING
272000 DATA COMMUNICATIONS EQUIPMENT
273000 VOICE COMMUNICATIONS EQUIPMENT
274000 AUDIO VISUAL SYSTEMS
275117 OVERHEAD PAGING SYSTEMS
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
283111 DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM
END OF TABLE OF CONTENTS
Harris Health System - Ben Taub Hospital Level 6 Issue for Bid and Permit Cardiac Critical Care Unit - Renovation and February 19, 2026 Reconfiguration (22-1SCP01622) 1504 Ben Taub Loop, Houston, TX 77030 HOK Project No. 24.10251.00
SEALS PAGE 000111 - 1
©Hellmuth, Obata, & Kassabaum Inc.
DOCUMENT 00 01 11 - SEALS PAGE
ARCHITECT
Joseph Przybyl Hellmuth, Obata & Kassabaum Architecture 3200 Southwest Freeway, Suite 900 Houston, Texas 77005 License # 19165
MECHANICAL ENGINEER
Ben Willey Teliosity 730 Town and Country Blvd., Suite
Houston, Texas 77024
Firm ID No.: #F-6494
ELECTRICAL ENGINEER
Teliosity 730 Town and Country Blvd., Suite
PLUMBING ENGINEER
Teliosity 730 Town and Country Blvd., Suite
02/18/2026 02/04/2026 02/04/2026
02-19-2026
Harris Health System - Ben Taub Hospital Level 6 Issue for Bid and Permit Cardiac Critical Care Unit - Renovation and February 19, 2026 Reconfiguration (22-1SCP01622) 1504 Ben Taub Loop, Houston, TX 77030 HOK Project No. 24.10251.00
SEALS PAGE 000111 - 2
©Hellmuth, Obata, & Kassabaum Inc.
LOW VOLTAGE ENGINEER
Brian Hancock Teliosity 730 Town and Country Blvd., Suite
02/19/2026
GENERAL CONDITIONS
FOR BUILDING CONSTRUCTION AND RELATED WORK
Facilities Project Management Office (PMO)
July 2021
HARRIS HEALTH SYSTEM
GENERAL CONDITIONS
(FOR BUILDING CONSTRUCTION AND RELATED WORK)
TABLE OF CONTENTS
SECTION 1. DEFINITION OF TERMS
1.1 Architect/Engineer
1.2 Bid
1.3 Bid Bond
1.4 Bidder
1.5 Board of Trustees
1.6 Bonds
1.7 Change Order
1.8 Construction Change Directive or “CCD”
1.9 Contract
1.10 Contract Documents
1.11 Contract Time
1.12 Contractor
1.13 District
1.14 Drawings
1.15 Notice to Proceed
1.16 Owner’s Designated Representative
1.17 Payment Bond
1.18 Performance Bond
1.19 Product Data
1.20 Project Management Information System (PMIS)
1.21 Project Manual
1.22 Punch List
1.23 Purchasing Agent
1.24 Sample
1.25 Shop Drawings
1.26 Specifications
1.27 Subcontractor
1.28 Superintendent
1.29 Surety
1.30 Work
SECTION 2. BIDDING AND AWARD
2.1 Intent of Drawings and Specifications
2.2 Interpretation of Drawings and Specifications
2.3 Reference Specifications
2.4 Special Provisions
2.5 Examination of Drawings, Specifications, Special Provisions and Site of Work
2.6 Bid
2.7 Addenda
2.8 Form of Bid and Signature
2.9 Bid Security
2.10 Tax Exemptions
2.11 Award of Contract
2.12 Competency of Bidders
2.13 Responsible Bidder
2.14 Disqualification for Collusion
2.15 Material Guarantee
2.16 Return of Bid
2.17 Bonds
2.18 Acceptance of Bid and Bonds
2.19 Purchase Order and Notice to Proceed
SECTION 3. INSURANCE
3.1 Indemnification
3.2 Insurance
SECTION 4. REGULATORY REQUIREMENTS
4.1 Laws to be Observed
4.2 Relations with Owner’s Officials and Employees
4.3 Permits and Licenses
4.4 Barricades, Warning Lights and Signs, On Projects Involving Public Roads
4.5 Sanitary Provisions
4.6 Safety and Health Standards
4.7 Environmental Protection
4.8 Use of Explosives
4.9 Project Signs
4.10 Rest Room and Field Office
4.11 Parking
4.12 Storage
4.13 Hours Of Work
4.14 Badging
4.15 Character of Workers
SECTION 5. EXECUTION OF THE WORK
5.1 Execution of Work
5.2 Construction Schedule
5.3 Time of Completion
5.4 Abandonment of Work or Default of Contractor
5.5 Termination for Convenience of the Owner
5.6 Change Orders
5.7 Subcontracting
5.8 Character of Workmen and Equipment
5.9 Protection Against Claims of Subcontractors, Laborers, Materialmen and
Furnishers of Machinery, Equipment and Supplies
5.10 Authority of Architect/Engineer
5.11 Cooperation of Contractor
5.12 Contractor's Drawings
5.13 Submittals
5.14 Daily Reports
5.15 Record Drawings
5.16 Materials and Workmanship
5.17 Patented Devices, Materials and Processes
5.18 Inspection
5.19 Material Testing
5.20 Contractor's Responsibility for Work
5.21 Preservation and Restoration of Property
5.22 Emergencies
5.23 Utility Obstruction
5.24 Guarantee
5.25 Substantial Completion
5.26 Partial Utilization
5.27 Project Delays
SECTION 6. PAYMENT
6.1 Schedule of Values
6.2 Partial Payments
6.3 Wage Rates and Payroll Records
6.4 Adjusting Payment
6.5 Acceptance and Final Payment
6.6 Retainage
6.7 Release of Lien
6.8 Defective Work
6.9 Closeout
ATTACHMENTS
A. Supplemental Conditions
HARRIS HEALTH SYSTEM GENERAL CONDITIONS
(FOR BUILDING CONSTRUCTION AND RELATED WORK)
SECTION 1. DEFINITION OF TERMS
Whenever the following terms are used in these General Conditions, the intent and meaning shall be interpreted as listed below:
1.1 Architect/Engineer (A/E): Architectural or Engineering firm duly licensed in the State of Texas and retained by the Owner to prepare the Plans and Specifications for the work to be prosecuted hereunder and to generally observe and evaluate the quality/quantity and progress of the work, provided that in the event that no such person or firm is retained by the Owner or that the Owner's contract with such person or firm has expired or has been terminated then such other firm as may be designated in writing will be the "A/E".
1.2 Bid: The written offer to the Owner made on the prescribed form by the Bidder to furnish the materials or equipment and/or to perform the Work or services proposed.
1.3 Bid Bond: The Bid Bond, cashier's check, certified check or other deposit designated in the Specifications to be made by the Bidder, which is to accompany the Bid as a guaranty of good faith to enter into a written Contract.
1.4 Bidder: Any individual, firm, joint venture, partnership, corporation or other legal entity submitting a
Bid.
1.5 Board of Trustees: The appointed governing body of the Owner.
1.6 Bonds: Instruments of Security furnished by the Contractor and its surety, as required by the Contract
Documents, including bid, performance, payment and special Bonds.
1.7 Change Order: A document added after the Contract execution to revise, add to, or delete from the work and to adjust the Contract sum or Contract time.
1.8 Construction Change Directive or “CCD”: A construction change directive is a written order signed by the Owner only, directing a change in the work prior to agreement on adjustment, if any, in the Contract Price or Contract Time, or both.
1.9 Contract (also “Purchase Order”): A Document issued by the Owner (or Purchasing Agent), binding the contractor to complete the work, and which sets forth the Contract Sum and all Contract Documents required to be included within the Project and to which said Contractor must adhere, in performing the work.
1.10 Contract Documents: The Contract, related Addenda, Contractor's Bid (including documentation accompanying the Bid and any post-Bid documentation submitted prior to the Notice to Proceed), the Bonds, these General Conditions, Supplementary Conditions, the Specifications and Drawings, and the Purchase Order, together with all amendments, modifications, and supplements.
1.11 Contract Time: The number of calendar days (computed as provided in paragraph 5.3) or the date stated in the Contract for the completion of the work.
1.12 Contractor: The individual, firm, joint venture, partnership, corporation or other legal entity with whom a Contract is entered into with the Owner.
1.13 District: The Harris County Hospital District dba Harris Health System, will also be known as the Owner within this document.
1.14 Drawings: The Drawings are the graphic and pictorial portions of the Contract Documents officially approved by The Owner, wherever located and whenever issued, showing the design, location and dimensions of the work, generally including plans, elevations, sections, details, schedules and diagrams.
1.15 Notice to Proceed or “NTP”: Written notice from Owner authorizing the Contractor to proceed with the performance of the work.
1.16 Owner’s Designated Representative: An individual named in the Notice to proceed who is the representative of the Owner, who shall act on behalf of the Owner in all matters relating to the work.
Owner’s Designated Representative may be represented by assistants, agents, and Observers as authorized in writing to act for Owner’s Designated Representative on questions concerning the execution of work, conflicts of interests between Contractors and subcontractors performing work, and the determination of the budget. The decision of the Owner’s Designated Representative shall be final on all matters not specifically assigned to other parties by this document. Should the Board choose to authorize a different person to act on its behalf, such other person or entity shall have the same rights and responsibilities as are herein reserved for the Owner.
1.17 Payment Bond: A surety Bond in the amount of the Contract, solely for the protection of all claimants supplying labor and material in the prosecution of the work provided for in the Contract.
1.18 Performance Bond: A surety Bond in the amount of the Contract conditioned upon the faithful performance of the work in accordance with the Drawings, Specifications and Contract Documents.
Said Bond is solely for the protection of the Owner.
1.19 Product Data: Manufacturer's standard schematic Drawings, catalog, sheets, brochures, diagrams, schedules, performance charts, illustrations and other descriptive items.
1.20 Project Management Information System (PMIS): The current project management software platform in use by the Owner Program Management Office. The PMIS shall be utilized by the Contractor, Owner and Architect/Engineer for all required Project Documents and communications.
1.21 Project Manual: The documents containing, but not limited to, Bid, Contract forms, all Specifications, special provisions and these General Conditions.
1.22 Punch List: A list of items within a project, prepared by the Owner or Architect/Engineer and confirmed by the Contractor, which remain to be replaced or completed in accordance with the requirements of completion of the work.
1.23 Purchasing Agent: The Purchasing Agent of Harris County Hospital District.
1.24 Sample: A physical example furnished by the Contractor to illustrate materials, equipment, or workmanship; to establish standards by which the work will be judged.
1.25 Shop Drawings: Original Drawings prepared by the Contractor, supplier or distributor which illustrate some portion of the work and which shows fabrication, layout, setting, or erection details.
1.26 Specifications: Those portions of the Contract Documents consisting of written technical descriptions of materials, equipment, construction systems, standards and workmanship as applied to the work and certain administrative details applicable thereto.
1.27 Subcontractor: An individual, firm, joint venture, partnership, corporation or other legal entity having a contract with the Contractor or with any Subcontractor for performing a part of the work.
1.28 Superintendent: A representative, together with any necessary assistants, hired by the Contractor who shall be in attendance at the Work Site at all times during the progress of the work.
1.29 Surety: The legal entity, which executes the Performance Bond, Payment Bond or Bid Bond, or guarantees the performance of the Bidder or Contractor.
1.30 Work: The entire completed construction or the various separately identifiable parts thereof required to be finished under the Contract Documents. Work is the result of performing services, furnishing labor, and furnishing and incorporating materials and equipment into the construction, all as required by the Contract Documents.
SECTION 2. BIDDING AND AWARD
2.1 Intent of Drawings and Specifications: The intent of Drawings and Specifications is to prescribe definite Work or services to be undertaken, or materials, supplies, or equipment to be furnished by the Bidder if awarded the Contract. The Contract is to be carried out under the observation of the Architect/Engineer and the Owner unless otherwise indicated.
The Contractor shall furnish, unless otherwise provided in the special provisions or in the Contract, all materials, implements, machinery, equipment, tools, supplies, and labor necessary to the prosecution and completion of the Contract.
Where the Contractor is to furnish only material, supplies, or equipment, the intent is to prescribe the qualifications, quantity, and rate of delivery and location of delivery point or points.
2.2 Interpretation of Drawings and Specifications: Drawings and Specifications provide graphic and written descriptions of the character and scope of the work.
Modifications in the form of Addenda or Change Orders become an integral part of the Drawings and Specifications. Drawings and Specifications are considered inseparable documents. The Contractor must rely on both documents and must perform the work according to combined intent. Organization of Drawings and Specifications does not imply any control over the Contractor in dividing the work among Subcontractors or in establishing the extent of the work to be performed by any trade.
The Contractor shall take no advantage of any errors or omissions in the Drawings or Specifications.
In the event of a conflict between the Drawings and the Specifications, the Specifications shall control.
2.2.1 Words which have well known technical or trade meanings have those meanings in relation to materials or work described in the Contract Documents. Where materials or equipment are specified by a trade or brand name, the intention is not to discriminate against an equal product of another manufacturer, but rather to set a definitive standard of quality or performance. The Architect/Engineer and the Owner will be the judge of equivalency. Any substitution of equivalent materials or equipment must be approved in writing by the Architect/Engineer and the Owner. The Architect/Engineer and Owner may require a specifically designated material, equipment or process.
2.2.2 Materials specified by reference to other documents, such as Federal Specifications or other recognized standards, must be provided as described in the latest document in effect on the date Bids are received. Where more than one reference is made for a single material, the material may be furnished according to any one of the referred Specifications, at the Contractor's option.
2.2.3 Unless otherwise specified, all materials shall be the best of their respective kinds and shall be in all cases fully equal to approved samples. All materials furnished shall be new and free from defects and in accordance with the Specifications applying thereto.
2.2.4 Only Drawing dimensions or dimensions calculated from them will be used by the Contractor.
Where the work is affected by finish dimensions, the Contractor will determine and be responsible for those dimensions. On all Drawings, the figured dimensions shall govern in case of a discrepancy between the figured and scaled dimensions.
2.3 Reference Specifications: When Reference is made in the Specifications to the Specifications of other agencies, organizations or departments, such Reference is made for expediency and standardization, and such Specifications referred to are hereby made a part of these Specifications.
2.4 Special Provisions: Should any construction, work or condition which is not covered by standard Specifications be anticipated on any proposed work, special provisions for such work will be attached to, and shall be considered a part of, the Specifications. Should any special provisions conflict with the standard Specifications, the special provisions shall govern.
2.5 Examination of Drawings, Specifications, Special Provisions and Site of Work : When a Bid is submitted, it will be presumed that the Bidder has visited and carefully examined the site of the work and has made a complete study of the Drawings, Specifications, these General Conditions, special provisions and the form of the Contract to be entered into. Information concerning soil boring and water elevations, various surveys taken on the project site, if available, will be furnished upon request.
This information is offered to the Bidder for information purposes only and the Owner will not be responsible for the information contained therein. This provision is not intended to limit any liability which a third party other than an employee or officer of the Owner may have to the Contractor.
2.5.1 In the event the Contract covers materials, supplies or equipment, the Contractor is presumed to fully understand the requirements of the Owner.
2.6 Bid: Blank spaces in the Bid form must be properly filled. The phraseology of the Bid form must not be changed and no additions or deletions shall be made to the items mentioned therein. Unauthorized conditions, limitations or provisions attached to a Bid will render it void. Explanations which are not intended as limitations or changes in the Bid may be attached to the Bid over the signature of the Bidder, but no alterations or qualifications are permitted. The unit prices Bid on any items shall govern.
2.6.1 The unit prices or the specific sums written in words govern over the unit prices or the specific sums written in figures, and errors of extension will be corrected. If the Bidder fails to Bid on any item, the Owner may, reject such Bid as incomplete.
2.6.2 A Bidder may withdraw its Bid before the expiration of the time during which Bids may be submitted, without prejudice to himself, by submitting a written request for its withdrawal to the Purchasing Agent. No Bid received after the time specified in the Notice to Bidders will be considered.
2.6.3 The Owner reserves the right to reject any or all Bids, or to waive technical defects.
2.7 Addenda: The Contractor is responsible for verifying and obtaining all Addenda related to this work.
Failure to include any or all Addenda in the Bid will be considered as a basis for the rejection of a Bid.
2.8 Form of Bid and Signature: The Bid shall be made only on the form provided and shall be enclosed in an envelope correctly marked with the job number and description, sealed, and addressed as required by the Contract documents. The Bidder shall state in words and in figures the unit prices or the specific sums, as the case may be, for which it proposes to furnish the material, supplies, or equipment or to perform the work or services required by the Drawings and Specifications.
2.8.1 If a Bid is to be mailed, this envelope must be placed in another envelope which must be sealed, mailed and delivered to the Purchasing Agent. Bids are received until the designated time and date set for the opening thereof and must be received by the Purchasing Agent's Office by that time. Mailing of Bids is solely at the Bidder's risk, and no Bid received after the time specified in the Contract Documents will be considered.
2.9 Bid Security: Each Bid must be accompanied by Bid security made payable to the Owner in the amount of five percent of the Bidder's maximum Bid price and in the form of a cashier's check or a Bid Bond issued by a surety meeting the requirements of these General Conditions.
2.10 Tax Exemptions: The Bidder obligates himself, if awarded the Contract, to use reasonable diligence to obtain for the Owner any and all exemptions from State or Federal excise or other tax and if required to pay such taxes or if such taxes are paid, to assist the Owner in any necessary way to obtain refund of such taxes so paid and to execute any required documents necessary to obtain refunds or to assert such exemptions.
2.11 Award of Contract: The Award, if made, will be made after the bid is approved by the Board of Trustees, unless otherwise noted in the Bid Documents.
2.12 Competency of Bidders: Each Bidder must be capable of performing the various items of work or services or of furnishing the various items of materials, supplies, or equipment Bid upon. Each Bidder may be required to furnish a statement covering the experience on similar Work and such statements of the Bidder's financial resources as may be deemed necessary.
2.13 Responsible Bidder: Criteria utilized by the Owner for determining the qualified responsible Bid includes, but is not limited to, whether the Bidder meets the Owner's published specifications, the Bidder's experience, skill, ability, business judgement, financial capacity, integrity, honesty; availability of the necessary facilities, equipment, materials and workers; previous performance, reputation, promptness, safety record and any other factors which could reasonably be asserted as being relevant to the Bidder’s successful performance.
2.14 Disqualification for Collusion: Any or all Bids may be rejected if there is reason for believing that collusion exists among the Bidders, and no party in such collusion will be considered in future Bids for the same work.
2.15 Material Guarantee: Before any Contract is Awarded, the Bidder may be required to furnish a complete statement of the names and addresses of suppliers or of the origin, composition and manufacture of any or all materials to be used in the performance of its Bid, together with samples which may be subjected to the tests provided for in the Specifications to determine their quality and fitness.
2.16 Return of Bid Checks: Bid Bonds of the top three Bidders may be retained by the Purchasing Agent until after the Award and approval of the Contract, Payment Bond and Performance Bond. These Bid Bonds shall be returned by the Purchasing Agent immediately after the final approval of the Contract, Performance Bond and Payment Bond, upon execution of the receipt required by the Purchasing
Agent. The Bid Bonds for all other Bidders shall be returned by the Purchasing Agent at any time within seventy-two (72) hours following the opening of Bids upon execution of the receipt required by the Purchasing Agent.
2.17 Bonds: The prescribed form of Performance Bond and Payment Bond are available to the Bidder and it is presumed that the Bidder is familiar with them. The Bidder to whom an Award is made shall, within ten (10) calendar days from the date of the Award, execute and deliver to Purchasing Agent any required Performance Bond and Payment Bond, all in the prescribed form. If the Bidder to whom the Award is made fails to furnish a required Performance Bond or Payment Bond as herein provided, the Owner may rescind its award and acceptance of Bid and make an Award to the next qualified
Bidder who shall fulfill every stipulation embraced herein as if the first Award were made to it. If this should occur, the Bidder to whom the Award was first made shall at the option of the Owner, be required to pay to the Owner the difference between his Bid and that of the next qualified Bidder up to the maximum amount provided in the Bid Bond for the project. The Performance Bond and the
Payment Bond must be accompanied by a valid power of attorney or proper evidence as approved by the Owner, providing evidence that the person signing on behalf of the Surety is authorized to so act.
2.17.1 A corporation to which an Award is made will be required to furnish evidence of the authority of the officers executing the Contract. A firm or partnership to which an Award is made will be required to furnish evidence of the authority of the person executing the Bid satisfactory to the Owner.
2.18 Acceptance of Bid: Should the Board of Trustees be of the opinion that a Contract should be entered into and approved, it shall authorize the Owner and Purchasing Agent to issue the Purchase Order.
2.19 Purchase Order and Notice to Proceed: The Purchasing Agent shall prepare a purchase order, conforming to the terms of the Contract and transmit it to the Owner and Contractor.
2.19.1 The Owner determines the start date of the project, as agreed upon with the Contractor. After the Purchase Order is issued, and Bonds are received (unless otherwise agreed upon), the Owner shall issue the Notice to Proceed. The time fixed for performance of the Contract (Contract Time) shall begin to run from the date set forth in the Construction Notice to Proceed.
SECTION 3. INSURANCE
3.1 INDEMNIFICATION: THE CONTRACTOR SHALL SAVE HARMLESS THE OWNER, ITS OFFICIALS, EMPLOYEES AND REPRESENTATIVES FROM ALL DAMAGES, EXPENSES, SUITS, ACTIONS AND CLAIMS
OF EVERY KIND AND CHARACTER WHATSOEVER WHICH THE OWNER MAY SUFFER DIRECTLY OR
INDIRECTLY AS A RESULT OF THE CONTRACTOR'S NON-PERFORMANCE OF THE CONTRACT.
CONTRACTOR SHALL ALSO SAVE HARMLESS AND INDEMNIFY THE OWNER AND ALL ITS
REPRESENTATIVES FROM ALL DAMAGES, EXPENSES, SUITS, ACTIONS AND CLAIMS OF EVERY KIND AND
CHARACTER WHATSOEVER WHICH THE OWNER MAY SUFFER DIRECTLY OR INDIRECTLY DUE TO ANY BANKRUPTCY, STATE OR FEDERAL TAX LEVIES OR LIENS, OTHER LEGAL PROCEEDINGS OR OTHER
MATTERS, SIMILAR OR DISSIMILAR, AFFECTING THE CONTRACTOR, IN WHICH THE OWNER MAY
BECOME IN ANY WAY INVOLVED, WHETHER RELATED TO THE CONTRACT AND/OR THE
CONTRACTOR'S PERFORMANCE OR NON-PERFORMANCE UNDER THE CONTRACT.
3.2 Insurance: Prior to commencing any work, but no later than ten working days after award of Contract, the Contractor shall submit or cause to be submitted any and all Certificate(s) of Insurance, showing that the Contractor has the required insurance, to the attention of the Purchasing Agent. (Failure to timely comply may cause the Contract to be rescinded and/or cancelled.) Such insurance is to be provided at the sole cost of the Contractor. No work shall be performed until all of the required insurance has been received and approved.
3.2.1 The Contractor shall be the "Named Insured" on ALL policies. At all times during the term of this contract, the Contractor shall maintain insurance coverage of the type and in the amounts which are not less than the minimum amounts shown below. These requirements do not establish limits of the Contractor's liability. No policies shall be cancelled or lapsed on account of any partial occupancy or substantial completion.
3.2.2 All insurance coverage shall be written by companies holding a Certificate of Authority from the Texas State Board of Insurance and comply with the Minimum Requirements as stated below and being otherwise acceptable to the Owner. In the event that coverage is not procurable, after diligent effort has been made to do so, from among the insurers licensed to transact and actually write the type and class of insurance in the State of Texas, the County may consider "Surplus Lines” Insurance" pursuant to the Texas Insurance Code Ann. Art. 1.14- 2.
3.2.3 ENDORSEMENTS
i. Owner must be named "Specific Additional Insured" on the commercial general liability and business automobile liability (with Contractor's insurance policy as primary).
ii. All policies shall "Waive All Rights of Subrogation" against Owner, its officers, employees and agents.
iii. All policies shall provide that a thirty (30) day written notice shall be submitted to Purchasing Agent in the event of cancellation or material change. If the coverage period shown on the Contractor's current certificate ends during the duration of the project, the Contractor must, prior to the end of the coverage period, file a new certificate with the
Purchasing Agent showing that coverage has been extended.
iv. All certificates must contain the work description, all of the above endorsements and shall be submitted in triplicate.
3.2.4 MINIMUM REQUIREMENTS
During the term of the Contract, the Contractor at its sole expense shall provide primary commercial insurance of such type and with such terms and limits as may be reasonably associated with the Contract. As a minimum, the Contractor shall provide and maintain the following coverage and limits:
i. Workers Compensation, as required by the laws of Texas, and Employers’ Liability, as well as All States, USL&H and other endorsements if applicable to the project, and in accordance with state law.
Employers’ Liability
Each Accident: $1,000,000
Disease–Each Employee: $1,000,000
Policy Limit: $1,000,000
ii. Commercial General Liability, including but not limited to the coverage indicated below.
Coverage shall not contain any restrictive endorsements nor exclude or limit Products/Completed Operations, Contractual Liability, or Cross Liability. Where exposure exists, the County may require coverage for watercraft, blasting, collapse, explosions, blowout, cratering, underground damage, pollution, or other coverage. Harris Health System shall be named Additional Insured on primary/non-contributory basis.
Each Occurrence: $1,000,000
Personal and Advertising Injury: $1,000,000
Products/Completed Operations: $1,000,000
General Aggregate (per project): $2,000,000
iii. Automobile Liability, including coverage for all owned, hired, and non-owned vehicles used in connection with the Contract. Harris Health System shall be named Additional Insured on primary/non-contributory basis.
Combined Single Limit-Each Accident: $1,000,000
iv. Umbrella/Excess Liability (Harris Health System shall be named Additional Insured on primary/non-contributory basis)
Each Occurrence/Aggregate: $1,000,000
v. Professional/Errors & Omissions Liability (if applicable)
Each Occurrence/Aggregate: $1,000,000
The County reserves the right to require additional insurance if necessary. Coverage shall be issued by companies licensed (by TDI) to do business in Texas, unless said coverage is not available or economically feasible except through an excess or surplus lines company, in which case the company should be registered to do business in Texas. Companies shall have an A.M. Best rating of at least A-VII. Contractor shall furnish evidence of such insurance to the County in the form of unaltered insurance certificates. If any part of the contract is sublet, insurance shall be provided by or on behalf of any subcontractor, and shall be sufficient to cover their portion of the contract. Contractor shall furnish evidence of such insurance to the County as well.
Policies of insurance required by the contract shall waive all rights of subrogation against the County, its officers, employees and agents. If any applicable insurance policies are cancelled, materially changed, or non-renewed, contractor shall give written notice to the County at least 30 days prior to such effective date and within 30 days thereafter, shall provide evidence of suitable replacement policies. Failure to keep in force the required insurance coverage may result in termination of the contract. Upon request, certified copies of original insurance policies shall be furnished to the County.
The requirements stipulated in this attachment do not establish limits of contractor liability.
i. Builder's Risk (building construction only). Coverage for all risks for physical loss or damage at one hundred percent (100%) of all value as created during construction. If the contract is for the construction of a building only, the amount of the contract shall be deemed to be the insurable value. If the contract is for the construction of a building and other facilities, or if for any other reason the cost of the building to the Owner is not ascertainable, the Owner will determine the insurable value of the building.
In regard to Workers Compensation Coverage, the following special requirements shall apply:
1. Certificate of coverage ("certificate") - A copy of a certificate of insurance, a certificate of authority to self-insure issued by the commission, or a coverage agreement (TWCC-81, TWCC-82, TWCC-83, or TWCC-84), showing statutory workers compensation insurance coverage for the person's or entity's employees providing services on a project, for the duration of the work. The Contractor must provide a certificate of coverage to Owner prior to being awarded the contract.
2. Duration of the work - includes the time from the beginning of the work on the project until the Contractor's work on the project has been completed and accepted by Owner.
3. Persons providing services on the project ("Subcontractor" Texas Labor Code in section
406.096) - includes all persons or entities performing all or part of the services the Contractor has undertaken to perform on the project, regardless of whether that person contracted directly with the Contractor and regardless of whether that person has employees. This includes, without limitation, independent Contractors, Subcontractors, leasing companies, motor carriers, owner-operators, employees of any such entity, or employees of any entity which furnishes persons to provide services on the project.
"Services" include, without limitation, providing, hauling, or delivering equipment or materials, or providing labor, transportation, or other service related to a project.
"Services" does not include activities unrelated to the project, such as food/beverage vendors, office supply deliveries, and delivery of portable toilets.
4. The Contractor shall provide coverage, based on proper reporting of classification codes and payroll amounts and filing of any coverage agreements, which meets the statutory requirements of Texas Labor Code, Section 401.011(44) for all employees of the Contractor providing services on the project, for the duration of the work.
5. If the coverage period shown on the Contractor's current certificate of coverage ends during the duration of the project, the Contractor must, prior to the end of the coverage period, file a new certificate of coverage with Owner showing that coverage has been extended.
6. The Contractor shall obtain from each person providing services on a project, and provide to Owner:
a. a certificate of coverage, prior to that person beginning work on the project, so Owner will have on file certificates of coverage showing coverage for all persons providing services on the project; and
b. no later than seven days after receipt by the Contractor, a new certificate of coverage showing extension of coverage, if the coverage period shown on the current certificate of coverage ends during the duration of the project.
7. The Contractor shall retain all required certificates of coverage for the duration of the work and for one year thereafter.
8. The Contractor shall notify Owner in writing by certified mail or personal delivery, within 10 days after the Contractor knows or should know, of any change that materially affects the provision of coverage of any person providing services on the project.
9. The Contractor shall post on each project site a notice, in the text, form and manner prescribed by the Texas Workers Compensation Commission, informing all persons providing services on the project that they are required to be covered, and stating how a person may verify coverage and report lack of coverage. (This notice must be printed with a title in at least 30-point bold type and text in at least 19 point normal type, and shall be in both English and Spanish and any other language common to the worker population.)
SECTION 4. REGULATORY REQUIREMENTS
4.1 Laws to be Observed: THE CONTRACTOR IS ASSUMED TO BE FAMILIAR WITH AND AT ALL TIMES SHALL OBSERVE AND COMPLY WITH ALL FEDERAL, STATE, DISTRICT AND CITY LAWS, ORDINANCES AND
REGULATIONS IN ANY MANNER AFFECTING THE CONDUCT OF THE WORK, AND SHALL INDEMNIFY
AND SAVE HARMLESS THE OWNER AND ITS REPRESENTATIVES AGAINST ANY CLAIM ARISING FROM
THE VIOLATION OF, OR FAILURE TO COMPLY WITH ANY SUCH LAWS, ORDINANCES, OR REGULATIONS, BY THE CONTRACTOR OR ITS EMPLOYEES.
4.2 Relations with Officials and Employees of Owner: All Contractors, Subcontractors and their employees are prohibited to give or lend money, services or any other thing of value, to any official, employee or representative of Owner, and should it appear that this provision has been violated, then Owner, in its discretion, may terminate any and all Contracts that may exist between the Contractor and Owner.
4.3 Permits and Licenses: The Contractor shall procure all permits and licenses, pay all charges and fees, and give all notices necessary and incidental to the due and lawful prosecution of the work unless otherwise noted in the Contract Documents. No additional compensation will be made for time associated with the permit process.
4.4 Barricades, Warning Lights and Signs, On Projects Involving Public Roads: Unless provided otherwise in the Contract Documents, the Contractor is solely responsible for furnishing, erecting and maintaining, suitable barricades, warning signs, flares, barriers, cones, lights, flags, signals, flagmen and other traffic control devices as are or may be necessary to adequately protect the work and shall warn, advise and safeguard the public over the entire project, including, but not limited to, sections of the project which the Contractor closes to traffic.
4.4.1 The Contractor's responsibility in this regard extends for the entire duration of the work, from the start of construction until acceptance by the Owner. All barricades, signs and other types of devices necessary for traffic control and to protect the work shall be in accordance with the "Texas Manual on Uniform Traffic Control Devices".
4.5 Sanitary Provisions: The Contractor shall provide and maintain in a neat, sanitary condition, such accommodations for the use of its employees as may be necessary to comply with the requirements of any Federal, State, Owner, or City laws, ordinances or regulations.
4.6 Safety and Health Standards: The Contractor shall observe and comply with all safety and health standards and to all legislation and amendments enacted for the safety and health of Contractor's employees. Such safety and health standards shall apply to all Subcontractors, and the Contractor shall be responsible for initiating, maintaining, supervising and inspecting safety programs, safety systems and safety precautions. The Contractor shall take all reasonable precautions for the safety of, and shall provide protection to prevent damage, injury, loss, or obstruction of access to:
A. The General Public;
B. All employees on the Work Site and all visitors, invitee, and other persons who come onto the Owner's property and may be affected thereby:
C. All patients using Hospital District facilities;
D. All the Work and all materials and equipment to be incorporated therein, whether in storage on or off the Site, under the care and custody or control of the Contractor and/or Subcontractors; and
E. Other property at the Site or adjacent thereto, including but not limited to trees, shrubs, lawns, walks, pavements, structures and utilities not designated for removal and/or replacement during construction.
4.7 Environmental Protection: The Contractor shall be responsible for compliance with all applicable environmental protection requirements, codes, regulations, laws, and ordinances.
4.7.1 The Contractor shall recognize the environmental requirements of the project. Disturbed areas shall be strictly limited to boundaries established by the Architect/Engineer and Owner.
Particular attention is drawn to the avoidance of any pollution of any "on-site" streams, sewers, wells or other water sources.
4.7.2 Contractor shall prevent erosion of soil and excess runoff of surface or subsurface water from the construction site during the construction period. To retain existing drainage patterns external to the construction site, the Contractor shall construct temporary ground cover as needed to control conditions.
4.7.3 The Contractor shall legally dispose of all solid waste materials and other materials to be removed from the site by transporting to disposal areas that are approved by State and local authorities. No burning shall be permitted unless otherwise noted. All work shall be performed in such a manner as may be required to avoid pollution of the air by dust or other contaminants.
4.7.4 The Contractor shall control excessive noise at the job site.
4.8 Use of Explosives: When the use of explosives is necessary for the prosecution of the work, the Contractor shall use the utmost care not to endanger life or property. All explosives shall be stored in a secure manner and all such storage places shall be marked clearly "Dangerous", "Explosives" and shall be in the care of competent watchmen. The Contractor shall be solely responsible for damage caused by explosives.
4.9 Project Signs: When required, the Contractor shall provide, install, and maintain a project sign at the construction site. The borders and block style letters will be black, while the sign background and other exposed surfaces shall be white, or as stipulated in the specifications.
4.10 Rest Room and Field Office: Unless otherwise noted in the specifications or in Notice to Proceed, the Contractor shall provide and maintain at its own expense an office and a rest room for the exclusive use of the Architect/Engineer and the Owner for all projects over one hundred (100) calendar days in duration. The office will be approximately 200 square feet in size, mounted on skids, wheels or other approved mobility with 7 feet minimum ceiling height and shall be of weather-tight construction. The inside walls of the office shall be lined with paneling or other material approved by the Architect/Engineer or the Owner, and the office shall have no fewer than six double-hung windows, a door with hasp for padlock and a floor a minimum of 8 inches above the ground covered in tile or other material approved by the Architect/Engineer or the Owner. The office shall have a closet at least
3 feet wide, l-1/2 feet deep and 7 feet in height, a sloped top stand-up height table and stool, a desk, 3 chairs, and a lockable two-drawer legal size file cabinet. The Contractor shall also provide two racks for holding Drawings and an office sign 24" X 36", painted as directed by the Owner. All exterior openings shall be screened. The rest room and field office shall be placed at a location satisfactory to the Owner. The office shall be wired and furnished with electricity, shall be air-conditioned, heated and shall have WiFi and/or wireless internet service and contain a working telephone with a separate line and an outside bell for the exclusive use of the Architect/Engineer and the Owner.
4.10.1 This building, and the items furnished with the building, shall remain the Contractor's property and shall be removed by the Contractor at the end of the project. No direct payment will be made for the structure or the furnishings. On projects that require a field office, the
Contractor shall have the office complete in place and fully furnished and operational within 45 calendar days from the receipt of the purchase order. Failure to have fully furnished and operational field office within the allotted 45 calendar days will result in liquidated damages being assessed against the contract in the amount of one thousand dollars ($1,000.00) per day for each day that the field office is not fully operational. The term fully operational shall include but not be limited to: all required utility connections, required furnishings and climate control.
4.11 Parking: The Contractor shall be responsible for the parking of his vehicles in a legal manner at no additional expense or inconvenience to Owner.
4.12 Storage:
4.12.1 General – The Contractor shall be fully responsible for the security and safe keeping of any stored materials.
4.12.2 In addition to manufacturer’s recommendations, Contractor shall…